Bridge cable bent tower concrete distributing device

By designing a bridge Sota concrete fabric device, the combination of sub -components and support components is used to realize the symmetry, layered, and continuous pouring of concrete, solving the problem of difficulty guarantee and safety risks in traditional construction methods, which has improved it. Construction efficiency and safety.

CN222390271UActive Publication Date: 2025-01-24THE 4TH ENG CO LTD OF CHINA RAILWAY 17TH BUREAU GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421151718.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-24
Publication Date
2025-01-24
Estimated Expiration
2034-05-24

AI Technical Summary

Technical Problem

In high-rise structure construction, the traditional single-point feeding method of pumping concrete is difficult to ensure the symmetry, layering and continuous pouring of concrete, resulting in difficult to ensure construction quality and high safety risks and high economic costs.

Method used

A bridge is designed with a bridge tower concrete fabric device, including the base, the material component, and the support component. The combination of the vertical rod, the collecting warehouse and the sliding of the material can be used to achieve the symmetry, layered, and continuous pouring of the concrete.

Benefits of technology

This device improves the quality of concrete construction, guarantees structural security, reduces human investment and safety risks, and reduces construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222390271U_ABST
    Figure CN222390271U_ABST
Patent Text Reader

Abstract

The utility model discloses a concrete distributing device for a bridge cable bent tower, which relates to the technical field of constructional engineering and comprises a base and a distributing component arranged on the base. The material distributing assembly comprises a vertical rod arranged on the supporting beam, a material collecting bin arranged on the vertical rod and a material distributing sliding groove formed in the bottom of the material collecting bin and used for distributing materials, the vertical rod can be arranged on the supporting beam in an up-down moving mode, and the material collecting bin is rotationally arranged on the vertical rod; a traditional construction method of high-rise concrete single-point distribution is changed, the construction technology of concrete symmetry, layering and continuous pouring is applied, the construction quality of a reinforced concrete structure is fully improved, structural safety is guaranteed, and the problems that in a traditional narrow space, the multi-person operation space is limited, and the safety risk is high are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction engineering, in particular to a bridge cable tower concrete placing device. Background Art

[0002] At present, there are more and more special bridges such as long-span cable-stayed bridges and suspension bridges across the country, and the design of cable towers is getting higher and higher, which makes concrete pouring more and more difficult and makes it difficult to ensure the construction quality. Concrete pouring has always been an important part of the entire project construction. The physical quality of the concrete structure directly determines the service life of the entire project. The method of concrete pouring is particularly important. Under the existing construction technology conditions, the concrete of bridge cable towers is generally poured by pumping concrete at a single point. Although the concrete pouring task is completed, it is difficult to ensure the physical quality of the concrete during construction. The main problems that need to be solved urgently are as follows: ① During the construction of most high-rise structures, due to the limited height of the sky pump, it is necessary to pre-embed the surface of the cable tower and pump it into the mold for pouring; because the discharge port of the cable tower is fixed, it is impossible to achieve symmetrical, layered, and continuous pouring construction technology, and it is difficult to ensure the construction quality; ② The cross-sectional size of the cable tower is small, and the working platform is usually erected in the form of installing embedded parts and the platform space is small. Traditional pumping The concrete pouring process requires the assistance of multiple people to complete the construction, which has the following two disadvantages: First, there are many people on the working platform, the embedded parts bear a large load, are prone to instability, and have a high safety risk; second, during the construction of the traditional process, a large amount of manpower is required to shovel the concrete to ensure the continuous flow of concrete, which is not economical; ③ Traditional concrete pouring is a single-point distribution process. Due to the dense structural steel bars, it is difficult for concrete to flow by itself. It relies on the vibration of the vibrator to flow, and aggregate separation or segregation is common, resulting in a series of serious consequences such as reduced concrete strength at the construction joint, reduced concrete impermeability and frost resistance, and easy cracking and deformation.

[0003] Therefore, in order to change the traditional construction method of high-rise structure concrete, improve the quality of concrete pouring, implement the continuous, layered and symmetrical concrete pouring construction process, and eliminate the separation and segregation of concrete aggregates, it is necessary to propose a bridge pylon concrete placing device. Utility Model Content

[0004] In view of this, the purpose of the utility model is to provide a bridge pylon concrete placing device, which can not only reduce the input of manpower, but also achieve the effect of continuous, layered and symmetrical pouring of concrete, and speed up the construction progress while ensuring the construction quality. The device is simple to process, low in cost, has little working limitation and a wide range of application.

[0005] The utility model provides a bridge pylon concrete placing device adopting the following technical solutions:

[0006] A bridge pylon concrete placing device comprises a base and a material distribution assembly arranged on the base, wherein a support beam is vertically arranged on the base, and the material distribution assembly comprises a vertical pole arranged on the support beam, a material collection bin arranged on the vertical pole, and a material distribution chute arranged at the bottom of the material collection bin for material distribution, wherein the vertical pole is movably arranged on the support beam, and the material collection bin is rotatably arranged on the vertical pole.

[0007] Furthermore, a plurality of fixing holes for fixing the vertical poles are evenly arranged on the support beam in the vertical direction.

[0008] Furthermore, a first rotating member is provided at the bottom of the material collecting bin, and the material collecting bin is rotatably arranged on the vertical pole through the first rotating member.

[0009] Furthermore, it also includes a support assembly for supporting the material distribution chute, the support assembly includes a support rod, one end of the support rod is arranged near the end of the material distribution chute for discharging materials, and the other end of the support rod is rotatably arranged on the vertical rod.

[0010] Furthermore, the support assembly also includes a second rotating member arranged on the vertical pole, and the end of the support pole away from the material distribution chute is fixed on the second rotating member. When the bottom end of the vertical pole is located at the bottom of the support beam, the second rotating member is located near the top of the support beam.

[0011] Furthermore, the base is provided with an oblique support rod for supporting the support beam.

[0012] Furthermore, the base is provided with reinforcement rods for reinforcing the support beams and the diagonal braces.

[0013] In summary, the utility model has at least one of the following beneficial effects: the concrete distribution device for bridge pylons of the utility model not only changes the traditional high-rise concrete single-point distribution construction method, but also uses the construction process of symmetrical, layered and continuous pouring of concrete, fully improving the construction quality of reinforced concrete structures and ensuring structural safety, and also changes the problem of limited working space for multiple people and high safety risks in traditional narrow spaces; and the device is made of ordinary materials, convenient to make, simple to operate, easy to use, with small working limitations and a wide range of applications, which greatly improves the quality of concrete construction. On the premise of ensuring construction quality, it reduces manpower input and reduces safety risks. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a structural schematic diagram of an embodiment of the utility model.

[0015] Description of reference numerals:

[0016] 1. Base; 11. Support beam; 12. Fixing hole; 13. Diagonal support rod; 14. Reinforcement rod; 2. Material distribution assembly; 21. Aggregate bin; 22. Material distribution chute; 23. First selection rotating part; 3. Support assembly; 31. Support rod; 32. Second rotating part. DETAILED DESCRIPTION

[0017] The following is an explanation of the implementation of the present invention through specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific implementations, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention.

[0018] The following is combined with Figure 1 The utility model is described in further detail.

[0019] The utility model embodiment discloses a bridge pylon concrete placing device. Figure 1 The concrete placing device of the bridge pylon includes a base 1 and a material distribution component 2 arranged on the base 1. A support beam 11 is vertically arranged on the base 1. The base 1 and the support beam 1 are both made of channel steel. The material distribution component 2 includes a vertical pole 21 arranged on the support beam 11, a collection bin 22 arranged on the vertical pole 21, and a material distribution chute 23 for material distribution arranged at the bottom of the collection bin 22. The collection bin 22 is arranged in a funnel shape, and the material distribution chute 23 is arranged to be inclined downward. The vertical pole 21 can be moved up and down on the support beam 11, and the collection bin 22 is rotatably arranged on the vertical pole 21. By moving the vertical pole 21 up and down, the vertical pole 21 is moved on the support beam 11 according to the height of the construction site. The rod 21 is used to change the height of the aggregate bin 22. When the height of the aggregate bin 22 is appropriate, the vertical rod 21 is fixed. When the material is divided, the aggregate bin 22 is rotated on the vertical rod 21 to achieve a symmetrical, layered, and continuous construction process of concrete. It not only changes the traditional high-rise concrete single-point material distribution construction method, but also uses the symmetrical, layered, and continuous pouring of concrete. The construction quality of reinforced concrete structures is fully improved, the structural safety is guaranteed, and the problem of limited space for multiple people to work in a small space and high safety risks is changed. Moreover, the device is made of ordinary materials, is easy to make, simple to operate, easy to use, has small working limitations, and has a wide range of applications, which greatly improves the quality of concrete construction. On the premise of ensuring construction quality, it reduces manpower investment and reduces safety risks.

[0020] In this embodiment, a plurality of fixing holes 12 for fixing the vertical poles 21 are evenly arranged on the support beam 11 in the vertical direction, and corresponding holes are also opened on the vertical poles 21. After the vertical poles 21 are moved to a suitable position, the vertical poles 21 are fixed with bolts through the fixing holes 12.

[0021] In this embodiment, a first rotating member 24 is provided at the bottom of the material collection bin 22, and the material collection bin 22 is rotatably arranged on the vertical pole 21 through the first rotating member 24. The first rotating member 24 is a bearing, and the inner ring of the first rotating member 24 is sleeved on the vertical pole 21 and fixed by welding, and the top of the outer ring is fixed to the bottom of the material collection bin 22.

[0022] In this embodiment, a support assembly 3 for supporting the material distribution chute 23 is also included. The support assembly 3 includes a support rod 31. One end of the support rod 31 is arranged at an end close to the material discharge end of the material distribution chute 23, and the other end of the support rod 31 is rotatably arranged on the vertical rod 21.

[0023] In this embodiment, the support assembly 3 also includes a second rotating member 32 arranged on the vertical pole 21, and one end of the support rod 31 away from the material distribution chute 23 is fixed on the second rotating member 32. When the bottom end of the vertical pole 21 is located at the bottom of the support beam 11, the second rotating member 32 is located close to the top of the support beam 11. The second rotating member 32 is a bearing, and the inner ring of the second rotating member 32 is sleeved on the vertical pole 21 and fixed by welding, and the end of the support rod 31 is fixed on the outer ring.

[0024] In this embodiment, the base 1 is provided with an oblique support rod 13 for supporting the support beam 11 . The oblique support rod 13 can support the support beam 11 and increase the overall strength of the support beam 11 .

[0025] In this embodiment, a reinforcement rod 14 for reinforcing the support beam 11 and the diagonal support rod 13 is provided on the base 1. One end of the reinforcement rod 14 is fixed at the middle position of the diagonal support rod 13, and the other end is fixed at the bottom of the support beam 11 to reinforce the diagonal support rod 13 and the support beam 11.

[0026] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the technical solution of the utility model can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution of the utility model, which should be included in the scope of the claims of the utility model.

Claims

1. A bridge pylon concrete placing device, characterized in that: The invention comprises a base (1) and a material distribution component (2) arranged on the base (1); a support beam (11) is arranged vertically on the base (1); the material distribution component (2) comprises a vertical rod (21) arranged on the support beam (11), a material collection bin (22) arranged on the vertical rod (21), and a material distribution chute (23) arranged at the bottom of the material collection bin (22) for material distribution; the vertical rod (21) is arranged on the support beam (11) so as to be movable up and down; and the material collection bin (22) is rotatably arranged on the vertical rod (21).

2. The bridge pylon concrete placing device according to claim 1, characterized in that: A plurality of fixing holes (12) for fixing the vertical poles (21) are evenly arranged on the support beam (11) in the vertical direction.

3. The bridge pylon concrete placing device according to claim 1, characterized in that: A first rotating member (24) is arranged at the bottom of the material collecting bin (22), and the material collecting bin (22) is rotatably arranged on the vertical pole (21) through the first rotating member (24).

4. The bridge pylon concrete placing device according to claim 3, characterized in that: It also includes a support assembly (3) for supporting the material distribution chute (23), the support assembly (3) including a support rod (31), one end of the support rod (31) is arranged near the end of the material distribution chute (23) where the material is discharged, and the other end of the support rod (31) is rotatably arranged on the vertical rod (21).

5. The bridge pylon concrete placing device according to claim 4, characterized in that: The support assembly (3) also includes a second rotating member (32) arranged on the vertical rod (21), and one end of the support rod (31) away from the material distribution chute (23) is fixed on the second rotating member (32), and when the bottom end of the vertical rod (21) is located at the bottom of the support beam (11), the second rotating member (32) is located near the top of the support beam (11).

6. The bridge pylon concrete placing device according to claim 1, characterized in that: The base (1) is provided with an oblique support rod (13) for supporting the support beam (11).