Assembly type road bridge pier column structure

By adopting prefabricated design in the bridge pier structure, components such as splicing bridge pier and top support seats are used to achieve convenient disassembly and connection, solving the lack of stability of the bridge pier structure of the existing technology in the existing technology under overload bias load The problem and improve the convenience of equipment transportation and installation.

CN222412600UActive Publication Date: 2025-01-28GUANGDONG PROVINCE COMM PLANNING & DESIGN INST
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421141810.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-23
Publication Date
2025-01-28
Estimated Expiration
2034-05-23

AI Technical Summary

Technical Problem

Under the action of overload eccentric load, the existing road bridge pier column structure has weak lateral constraints and insufficient stability, which can easily lead to the overall lateral instability of the bridge pier column body, and the overall equipment is large, which is inconvenient for transportation and connection between multiple bridge piers. convenient installation.

Method used

Adopting the structure of the bridge pier column of the prefabricated road, through the setting of the first splicing bridge pier and the second splicing bridge pier, combined with components such as the top support seat, installation rod, installation card ring, and positioning rod to achieve convenient disassembly and connection, improve the transportation of equipment and the transportation of equipment and the transportation of the equipment and the transportation and the transportation of the equipment and the transportation and the transportation and the transportation and the transportation and the transportation of the equipment and the transportation and the transportation of the equipment and Convenient installation.

Benefits of technology

Effectively improve the horizontal stability of the bridge pier pillar, facilitate the convenient transportation of the equipment and the convenient connection of multiple bridge pier, and solve the problem of large equipment overall and inconvenient transportation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222412600U_ABST
    Figure CN222412600U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of road bridges, and discloses an assembly type road bridge pier column structure which comprises a mounting base, a first splicing pier is inserted into the top end of the mounting base, a second splicing pier is inserted into the top of the first splicing pier, and a top end supporting seat is inserted into the top of the second splicing pier; a connecting hole is formed in the top of the top end supporting seat, a supporting frame is welded to the bottom end of the top end supporting seat, connecting plates are fixedly connected to the left end and the right end of the supporting frame, fixing rods are welded to the tops of the connecting plates, and a mounting clamping ring is fixedly connected to the bottom of the top end supporting seat. The connecting groove and the positioning groove in the top end of the first splicing pier can be matched with the positioning rod and the mounting clamping block at the bottom end of the second splicing pier, and the connecting stability between the mounting rod and the mounting clamping ring at the bottom end of the top end supporting seat is achieved through the annular clamping groove and the mounting groove in the top of the first splicing pier.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of roads and bridges, in particular to an assembled road and bridge pier structure. Background Art

[0002] Road bridges are generally composed of several major parts, including roadbed, pavement, bridges, tunnel projects and traffic engineering facilities.

[0003] In contrast to publication number 202023259748.3, a road bridge pier structure is disclosed. A connecting assembly is provided, and workers place the connecting assembly between the lower surface of the bridge body and the outer surface of the pier body. A plurality of I-shaped grooves 1 are provided on the upper surface of the L-shaped connecting plate and a side surface close to the pier body, and an I-shaped groove 2 is provided on the lower surface of the bridge body and the outer surface of the pier body at the position corresponding to the I-shaped groove 1. An I-shaped piece 1 is used in conjunction with the I-shaped grooves 1 and 2, and concrete is injected into the interior of the installation shell through the grouting hole, so that the interior of the installation shell is filled with concrete, so that the connecting assembly can be strengthened and fixed. The I-shaped groove 4 provided inside the fixing ring and the I-shaped groove 3 provided on the outer surface of the pier body are used, and the fixing ring is fixed to the outer surface of the pier body through the I-shaped piece 2, and fits with the lower surface of the installation shell, thereby strengthening and fixing the installation shell and the connecting assembly, so as to solve the problem that the lateral constraint on the main beam is weak and the stability is weak in the above-mentioned background technology, and the pier body may suffer from lateral overall instability under the action of overload eccentric load. Under the condition of large eccentric load vehicles or earthquakes, the bearings may become empty, causing major accidents such as lateral overturning of the main beam. It effectively improves the stability, has a simple structure, and is easy to operate. It solves the problem of weak lateral restraint and stability of the main beam. Under the action of overload eccentric load, the pier column body may suffer from lateral overall instability.

[0004] This road bridge pier column structure is effectively improved in stability with a simple structure and easy operation. It solves the problem of weak lateral constraint on the main beam, weak stability, and the pier column body possibly experiencing lateral overall instability under the action of overload eccentric load. However, the overall length of the equipment is relatively long, which makes it inconvenient for transport vehicles to disassemble the equipment for transportation, and affects convenient and stable installation when multiple piers are connected. Utility Model Content

[0005] In order to solve the above-mentioned technical problems, the utility model provides an assembled road bridge pier structure.

[0006] The utility model is implemented by the following technical scheme: an assembled road bridge pier column structure, comprising a mounting base, a first spliced ​​bridge pier is plugged into the top of the mounting base, a second spliced ​​bridge pier is plugged into the top of the first spliced ​​bridge pier, and a top support seat is plugged into the top of the second spliced ​​bridge pier;

[0007] The top of the top support seat is provided with a connecting hole, the bottom end of the top support seat is welded with a supporting frame, the left and right ends of the supporting frame are fixedly connected with connecting plates, the top of the connecting plate is welded with a fixing rod, the bottom of the top support seat is fixedly connected with a mounting clamp ring, the bottom end of the top support seat is welded with a mounting rod, the top of the second spliced ​​bridge pier is provided with a mounting groove, the top of the second spliced ​​bridge pier is provided with an annular clamping groove, the top of the second spliced ​​bridge pier is welded with a connecting column, the bottom end of the second spliced ​​bridge pier is welded with a connecting clamp ring, the bottom of the second spliced ​​bridge pier is welded with a positioning rod, the top of the first spliced ​​bridge pier is provided with a connecting groove, the top of the first spliced ​​bridge pier is provided with a connecting groove, the top of the first spliced ​​bridge pier is provided with a positioning groove, the inside of the positioning groove is provided with a positioning hole, and the bottom end of the second spliced ​​bridge pier is welded with a mounting block.

[0008] Through the above technical solution, the number of installation rods is set to four, which can ensure the convenience of installation and connection between the top support seat and the second spliced ​​bridge pier.

[0009] As a further improvement of the above solution, a mounting rod is inserted into the interior of the mounting groove, a mounting clamp ring is inserted into the interior of the annular groove, and a connecting column is inserted into the interior of the top support seat.

[0010] Through the above technical solution, the number of mounting slots is set to four, which facilitates the connection and fixation of the mounting rod at the top.

[0011] As a further improvement of the above solution, a mounting block is inserted into the interior of the positioning groove, the positioning rod is inserted into the interior of the positioning hole, and a connecting clamp ring is inserted into the interior of the connecting groove.

[0012] As a further improvement of the above solution, the mounting clamps are symmetrically distributed with the top support seat as the center, and the mounting rods are symmetrically distributed with the top support seat as the center.

[0013] As a further improvement of the above solution, a mounting block is inserted into the interior of the first spliced ​​bridge pier, and a positioning rod is inserted into the interior of the first spliced ​​bridge pier.

[0014] Through the above technical solution, the installation of the clamping block can ensure the stability of the connection between the first spliced ​​bridge pier and the second spliced ​​bridge pier.

[0015] As a further improvement of the above solution, the positioning rods are symmetrically distributed with the second spliced ​​bridge pier as the center, and the positioning holes are symmetrically distributed with the first spliced ​​bridge pier as the center.

[0016] As a further improvement of the above solution, the installation grooves are symmetrically distributed with the second spliced ​​bridge pier as the center, and a connecting clamp is inserted into the interior of the connecting groove.

[0017] Compared with the prior art, the beneficial effects of the present invention are:

[0018] The utility model can cooperate with the positioning rod and the installation block at the bottom end of the second spliced ​​bridge pier by setting the connecting groove and the positioning groove at the top end of the first spliced ​​bridge pier, and then connect the connection stability between the installation rod and the installation clamp ring at the bottom end of the top support seat by setting the annular clamp groove and the installation groove at the top end of the first spliced ​​bridge pier. It is also convenient for workers to conveniently disassemble and stabilize the connection between the installation base, the first spliced ​​bridge pier, the second spliced ​​bridge pier and the top support seat during installation, and it is also convenient for workers to transport the equipment as a whole in batches, which brings convenience to the use of the workers.

[0019] The utility model can be installed to the bottom end of the bridge by setting a connecting hole at the top end of the top support seat in conjunction with external parts, and can ensure the connection stability between the top support seat and the fixing ring by setting a fixing rod and a supporting frame at the bottom end of the top support seat. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0021] Figure 2 This is a schematic diagram of the anatomical structure of the utility model;

[0022] Figure 3 This is a schematic diagram of the disassembly structure of the utility model;

[0023] Figure 4 This is a schematic diagram of the disassembled structure of the utility model when viewed from above;

[0024] Figure 5 It is a schematic diagram of the structure of the utility model when viewed from above.

[0025] Description of main symbols:

[0026] 1. Installation base; 2. First spliced ​​bridge pier; 3. Second spliced ​​bridge pier; 4. Fixed ring; 5. Connecting plate; 6. Support frame; 7. Fixed rod; 8. Top support seat; 9. Connecting hole; 10. Mounting clamp; 11. Mounting rod; 12. Mounting groove; 13. Annular groove; 14. Connecting column; 15. Connecting clamp; 16. Positioning rod; 17. Connecting groove; 18. Positioning groove; 19. Positioning hole; 20. Mounting block. DETAILED DESCRIPTION

[0027] The present invention is further described below in conjunction with the accompanying drawings and specific implementation methods. It should be noted that, under the premise of no conflict, the various embodiments or technical features described below can be arbitrarily combined to form a new embodiment.

[0028] Example:

[0029] Please combine Figure 1-5 The present embodiment is a prefabricated road bridge pier structure, comprising a mounting base 1, a first spliced ​​bridge pier 2 is plugged into the top of the mounting base 1, a second spliced ​​bridge pier 3 is plugged into the top of the first spliced ​​bridge pier 2, and a top support seat 8 is plugged into the top of the second spliced ​​bridge pier 3;

[0030] A connecting hole 9 is provided at the top of the top support seat 8, a supporting frame 6 is welded to the bottom end of the top support seat 8, a connecting plate 5 is fixedly connected to the left and right ends of the supporting frame 6, a fixing rod 7 is welded to the top of the connecting plate 5, a mounting clamp 10 is fixedly connected to the bottom of the top support seat 8, a mounting rod 11 is welded to the bottom end of the top support seat 8, a mounting groove 12 is provided at the top of the second spliced ​​bridge pier 3, an annular clamping groove 13 is provided at the top of the second spliced ​​bridge pier 3, a connecting column 14 is welded at the top of the second spliced ​​bridge pier 3, a connecting clamp 15 is welded to the bottom end of the second spliced ​​bridge pier 3, a positioning rod 16 is welded to the bottom of the second spliced ​​bridge pier 3, a connecting groove 17 is provided at the top of the first spliced ​​bridge pier 2, a connecting groove 17 is provided at the top of the first spliced ​​bridge pier 2, and a mounting groove 17 is provided at the top of the first spliced ​​bridge pier 2. A positioning groove 18 is provided at the end, and a positioning hole 19 is provided inside the positioning groove 18. A mounting block 20 is welded at the bottom end of the second spliced ​​pier 3. By setting the connecting groove 17 and the positioning groove 18 at the top of the first spliced ​​pier 2, the positioning rod 16 and the mounting block 20 at the bottom end of the second spliced ​​pier 3 can be matched. Then, by setting the annular groove 13 and the mounting groove 12 at the top of the first spliced ​​pier 2, the connection stability between the mounting rod 11 and the mounting clamp 10 connected to the bottom end of the top support seat 8 is improved, which is convenient for the staff to install and disassemble the installation base 1, the first spliced ​​pier 2, the second spliced ​​pier 3 and the top support seat 8, and the stability during connection is also convenient for the staff to transport the equipment as a whole in batches, which brings convenience to the staff's use.

[0031] The number of the mounting rods 11 is set to four, which can ensure the convenience of installation and connection between the top support seat 8 and the second spliced ​​bridge pier 3.

[0032] The mounting rod 11 is inserted into the mounting groove 12 , the mounting clamp ring 10 is inserted into the annular clamping groove 13 , and the connecting column 14 is inserted into the top support seat 8 .

[0033] The number of the mounting grooves 12 is set to four, so as to facilitate the connection and fixation of the mounting rod 11 at the top.

[0034] The interior of the positioning groove 18 is plugged with a mounting block 20 , the positioning rod 16 is plugged with the interior of the positioning hole 19 , and the interior of the connecting groove 17 is plugged with a connecting clamp ring 15 .

[0035] The mounting clamp 10 is symmetrically distributed with the top support seat 8 as the center, and the mounting rod 11 is symmetrically distributed with the top support seat 8 as the center. By setting the connecting hole 9 at the top of the top support seat 8, it can be installed to the bottom end of the bridge in coordination with external parts, and by setting the fixing rod 7 and the supporting frame 6 at the bottom end of the top support seat 8, the connection stability between the top support seat 8 and the fixing ring 4 can be ensured.

[0036] An installation block 20 is inserted into the interior of the first spliced ​​bridge pier 2 , and a positioning rod 16 is inserted into the interior of the first spliced ​​bridge pier 2 .

[0037] The installation block 20 can ensure the stability of the connection between the first spliced ​​bridge pier 2 and the second spliced ​​bridge pier 3 .

[0038] The positioning rods 16 are symmetrically distributed with the second spliced ​​bridge pier 3 as the center, and the positioning holes 19 are symmetrically distributed with the first spliced ​​bridge pier 2 as the center.

[0039] The installation grooves 12 are symmetrically distributed with the second splicing bridge pier 3 as the center, and a connecting clamp ring 15 is inserted into the interior of the connecting groove 17 .

[0040] The implementation principle of an assembled road bridge pier structure in the embodiment of the present application is: place the equipment in a suitable position, and by setting the connecting groove 17 and the positioning groove 18 at the top of the first spliced ​​pier 2, it can cooperate with the positioning rod 16 and the mounting block 20 at the bottom of the second spliced ​​pier 3, and then by setting the annular groove 13 and the mounting groove 12 at the top of the first spliced ​​pier 2 to connect to the connection stability between the mounting rod 11 and the mounting clamp ring 10 at the bottom of the top support seat 8, it is also convenient for the staff to conveniently disassemble and connect the mounting base 1, the first spliced ​​pier 2, the second spliced ​​pier 3 and the top support seat 8 during installation, and it is also convenient for the staff to transport the equipment as a whole in batches, which brings convenience to the staff's use. By setting the connecting hole 9 at the top of the top support seat 8, it can be installed to the bottom end of the bridge in cooperation with external parts, and by setting the fixing rod 7 and the support frame 6 at the bottom of the top support seat 8, the connection stability between the top support seat 8 and the fixing ring 4 can be guaranteed.

[0041] The above-mentioned implementation modes are only preferred implementation modes of the present invention, and cannot be used to limit the protection scope of the present invention. Any non-substantial changes and substitutions made by technicians in this field on the basis of the present invention shall fall within the scope of protection required by the present invention.

Claims

1. An assembled road bridge pier structure, comprising a mounting base (1), a first spliced ​​bridge pier (2) being inserted at the top of the mounting base (1), a second spliced ​​bridge pier (3) being inserted at the top of the first spliced ​​bridge pier (2), and a top support seat (8) being inserted at the top of the second spliced ​​bridge pier (3); It is characterized in that The top of the top support seat (8) is provided with a connection hole (9), the bottom of the top support seat (8) is welded with a support frame (6), the left and right ends of the support frame (6) are fixedly connected with a connection plate (5), the top of the connection plate (5) is welded with a fixing rod (7), the bottom of the top support seat (8) is fixedly connected with a mounting clamp ring (10), the bottom of the top support seat (8) is welded with a mounting rod (11), the top of the second spliced ​​bridge pier (3) is provided with a mounting groove (12), the top of the second spliced ​​bridge pier (3) is provided with an annular clamping groove (13), the A connecting column (14) is welded to the top of the second spliced ​​bridge pier (3), a connecting clamp (15) is welded to the bottom of the second spliced ​​bridge pier (3), a positioning rod (16) is welded to the bottom of the second spliced ​​bridge pier (3), a connecting groove (17) is provided at the top of the first spliced ​​bridge pier (2), a connecting groove (17) is provided at the top of the first spliced ​​bridge pier (2), a positioning groove (18) is provided at the top of the first spliced ​​bridge pier (2), a positioning hole (19) is provided inside the positioning groove (18), and a mounting block (20) is welded to the bottom of the second spliced ​​bridge pier (3).

2. The assembled road bridge pier structure according to claim 1, characterized in that: A mounting rod (11) is inserted into the interior of the mounting groove (12), a mounting snap ring (10) is inserted into the interior of the annular clamping groove (13), and a connecting column (14) is inserted into the interior of the top support seat (8).

3. The assembled road bridge pier structure according to claim 1, characterized in that: The interior of the positioning groove (18) is plugged with a mounting block (20), the positioning rod (16) is plugged into the interior of the positioning hole (19), and the interior of the connecting groove (17) is plugged with a connecting clamp ring (15).

4. The assembled road bridge pier structure according to claim 3, characterized in that: The mounting clamp (10) is symmetrically distributed with the top support seat (8) as the center, and the mounting rod (11) is symmetrically distributed with the top support seat (8) as the center.

5. The assembled road bridge pier structure according to claim 1, characterized in that: A mounting block (20) is inserted into the interior of the first spliced ​​bridge pier (2), and a positioning rod (16) is inserted into the interior of the first spliced ​​bridge pier (2).

6. The assembled road bridge pier structure according to claim 5, characterized in that: The positioning rods (16) are symmetrically distributed with the second spliced ​​bridge pier (3) as the center, and the positioning holes (19) are symmetrically distributed with the first spliced ​​bridge pier (2) as the center.

7. The assembled road bridge pier structure according to claim 6, characterized in that: The installation grooves (12) are symmetrically distributed with the second spliced ​​bridge pier (3) as the center, and a connecting clamp ring (15) is inserted into the interior of the connecting groove (17).

Citation Information

Patent Citations

  • Road bridge pier column structure

    CN214530168U