Push rod platform embedded part

Through the adoption of the embedded parts of the push rod platform, the installation work is divided and pre-processed or synchronized processing is carried out in advance, the problems of long construction cycles and high labor costs in the existing technology are solved, and construction efficiency and cost reduction are achieved.

CN222445327UActive Publication Date: 2025-02-11SHENZHEN GREENJOY TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420869224.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-24
Publication Date
2025-02-11
Estimated Expiration
2034-04-24

AI Technical Summary

Technical Problem

The construction period of the existing indoor golf simulator push rod platform is relatively long, the staff has a heavy labor burden and high labor costs.

Method used

The push rod platform embedded parts are used, including the platform body, ball-up device and simulated push rod cup. By pre-completed part of the work or synchronized construction with the support platform, the on-site construction cycle is shortened.

Benefits of technology

Through split installation work, pre-processing or synchronous processing is pre-processed in advance, the construction cycle is significantly shortened and the labor burden and labor costs of staff are reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222445327U_ABST
    Figure CN222445327U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of indoor golf simulators, in particular to a push rod platform embedded part which comprises a platform body, a ball feeding device and a simulation push rod hole cup, the ball feeding device and the simulation push rod hole cup are mounted on the platform body, a mounting hole is formed in a supporting platform of a golf simulation system, and the platform body can be embedded into the mounting hole. The method has the effect of shortening the on-site construction period.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of indoor golf simulators, and in particular to putter platform embedded parts. Background Art

[0002] Putting platform embedded parts are an indoor sport that simulates outdoor golf. It uses various equipment to achieve the simulation effect of real scenes.

[0003] Common indoor simulation systems include support platforms, simulated audio, simulated curtains and other devices. The support platform is set on the ground and is mainly used for people to step on, which is equivalent to the function of the floor. The support platform is equipped with a ball loading device and a simulated putting hole cup for athletes to perform putting hole cup simulation training.

[0004] The support platform is usually formed by wooden bars or plates fixed on site by iron nails. During the construction process, the ball loading device and the simulated putting hole cup need to be installed together. The construction period is long, the labor burden of the staff is heavy, and the labor cost is high. Utility Model Content

[0005] In order to shorten the construction period and reduce the labor burden of the staff, this application provides push rod platform embedded parts.

[0006] The push rod platform embedded parts provided in this application adopt the following technical solutions:

[0007] The putter platform embedded part comprises a platform body, a ball loading device and a simulated putter hole cup installed on the platform body. The support platform of the golf simulation system is provided with a mounting hole, and the platform body can be embedded in the mounting hole.

[0008] By adopting the above technical solution, the supporting platform is divided into two parts as a whole, so that part of the work can be completed in advance, or the construction can be carried out simultaneously with the supporting platform, or the assembly of part of the push rod platform can be completed in advance, and part of the work can be completed simultaneously at the construction site, which can be determined according to the actual construction situation. After the push rod platform is spliced, it is installed in the installation hole, so as to quickly complete the construction of the supporting platform and shorten the on-site construction period.

[0009] Optionally, the platform body includes a first platform and a second platform, the simulated putting hole cup is installed on the first platform, and the ball loading device is installed on the second platform.

[0010] By adopting the above technical solution, the first platform and the second platform are respectively installed with a simulated putting hole cup and a ball loading device, so that they can be separated and spliced ​​at the same time, further improving the construction efficiency.

[0011] Optionally, the first platform includes a frame and a panel arranged outside the frame.

[0012] By adopting the above technical solution, the enclosure is supported by the frame, and the enclosure is wrapped outside the bracket to form the first platform. A cavity exists inside the first platform, which reduces the overall mass of the first platform and facilitates the transportation of the first platform from the pre-assembled site to the on-site construction site.

[0013] Optionally, the skeleton is formed by a plurality of crisscross keels fixed to each other, and the keels are a shell structure with a hollow interior.

[0014] By adopting the above technical solution, the interior of the keel is hollow, so as to further reduce the mass of the first platform.

[0015] Optionally, the enclosure includes side panels and panel panels, the side panels are perpendicular to the first platform, the panel panels are parallel to the first platform, and adjacent side panels are rotatably connected.

[0016] By adopting the above technical solution, the side panels are rotatably connected, which facilitates the synchronous taking and placing of multiple side panels. At the same time, the rotatable connection of multiple side panels facilitates the folding of the side panels, which facilitates the separate storage or transportation of the side panels.

[0017] Optionally, the panel is equally divided into a plurality of sections.

[0018] By adopting the above technical solution, multiple panels are divided equally, the size of a single panel is controlled, packaging and transportation are convenient, and it is convenient for workers to take, place and assemble.

[0019] Optionally, a slope simulation component is provided on the first platform, and the slope simulation component includes a simulation plate and a lifting member, the simulation plate is arranged in close contact with the panel, and the lifting member is located inside the bracket for applying a force perpendicular to the panel to the simulation plate.

[0020] By adopting the above technical solution, when the simulation plate is subjected to force, the angle between it and the panel changes, so that different slopes can be generated on the first platform, simulating the slope in the real environment.

[0021] Optionally, a side of the simulation board close to the second platform is fixedly connected to the panel, and the simulation board can be deformed.

[0022] By adopting the above technical solution, the side of the simulation board close to the second platform is fixedly connected to the panel, so that the golf ball can roll smoothly onto the simulation board, reducing the situation where the golf ball is blocked due to the steps between the simulation board and the second platform.

[0023] In summary, the present application includes at least one of the following beneficial technical effects:

[0024] 1. Separate the installation work of the ball loading device and the simulated putting hole cup from the support platform so that part of the work can be pre-processed in advance, or the two can be processed simultaneously, thereby shortening the on-site construction period.

[0025] 2. The adjacent side panels are rotatably connected to facilitate the simultaneous placement of multiple side panels. At the same time, multiple side panels can be folded to facilitate transportation of the side panels. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application.

[0027] Figure 2 It is a structural diagram of the first platform of an embodiment of the present application.

[0028] Figure numerals: 1. platform body; 2. first platform; 21. frame; 22. enclosure; 221. side panel; 222. panel; 3. ball loading device; 4. simulated putting hole cup; 5. slope simulation component; 51. simulation board; 52. lifting part; 53. connecting plate; 6. second platform; 7. support platform; 71. mounting hole. DETAILED DESCRIPTION

[0029] The following is combined with Figure 1-2 This application is described in further detail.

[0030] The embodiment of the present application discloses a push rod platform embedded part.

[0031] Reference Figure 1 and Figure 2 The putter platform embedded parts include a platform body 1, a ball loading device 3 and a simulated putter hole cup 4 installed on the platform body 1, and the platform body 1 is formed by splicing steel structures. The support platform 7 of the golf simulation system is provided with a mounting hole 71 corresponding to the platform body 1, and the platform body 1 can be embedded in the mounting hole 71. Before construction, the platform body 1 is pre-assembled and the ball loading device 3 and the simulated putter hole cup 4 are installed. During the construction process, the putter platform embedded parts are installed in the mounting hole 71 to complete the construction of the support platform 7, thereby shortening the construction period.

[0032] Reference Figure 1 and Figure 2 The platform body 1 includes a first platform 2 and a second platform 6, the simulated putting hole cup 4 is installed on the first platform 2, and the ball loading device 3 is installed on the second platform 6. The first platform 2 and the second platform 6 are fixedly connected by screws. It is convenient for the staff to synchronously build the two platforms and install the ball loading device 3 and the simulated putting hole cup 4.

[0033] Reference Figure 1 and Figure 2The first platform 2 includes a frame 21 and a panel 22 arranged outside the frame 21. The frame 21 is a square disc-shaped structure. The frame 21 is formed by a plurality of crisscross keels connected by screws. The panel 22 is provided in plurality, and is respectively arranged on different sides of the frame 21, and is fixedly connected to the keel in the frame 21 by screws. In this embodiment, the keel is a hollow shell structure, which reduces the overall mass of the first platform 2 and facilitates transportation.

[0034] Reference Figure 1 and Figure 2 The enclosure 22 includes a side panel 221 and a panel 222. The side panel 221 is arranged perpendicular to the ground, and the panel 222 is arranged parallel to the ground. Multiple side panels 221 are arranged corresponding to the side of the frame 21 perpendicular to the ground, and two adjacent side panels 221 are rotatably connected by hinges. The multiple side panels 221 can be folded to facilitate transportation, and the multiple side panels 221 can be transported conveniently. During assembly, the side panels 221 are unfolded and arranged outside the frame 21, and fixed by screws. The side panel 221 includes a bracket and a thin plate. The bracket has a mesh structure, and the thin plate is fitted and fixedly connected to the bracket to form a side panel 221 with an overall plate-like structure.

[0035] Reference Figure 1 and Figure 2 In this embodiment, the panel 222 is equally divided into a plurality of plates to control the size of the panel 222 and facilitate the placement and installation of the panel 222. In this embodiment, the overall length of the first platform 2 is 2.2 m, and the panel 222 is divided into two plates along its length direction.

[0036] Reference Figure 1 and Figure 2 , a slope simulation component 5 is also provided on the first platform 2, and the slope simulation component 5 includes a simulation board 51 and a lifting member 52. The simulation board 51 has a certain elasticity, and the simulation board 51 is arranged on the side of the panel 222 away from the frame 21, and the lifting member 52 is located in the gap of the keel of the frame 21, and is fixedly connected to the keel. The lifting member 52 is used to apply a force perpendicular to the direction of the panel 222 to the simulation board 51, so that the simulation board 51 can be deformed, tilted, or bulged to simulate various ground conditions in an actual golf course; such as slopes, bulges, etc. In this embodiment, the lifting member 52 is an electric push rod, and the telescopic rod of the electric push rod can abut against the simulation board 51 when it is extended and retracted, so as to move the simulation board 51.

[0037] Reference Figure 1 and Figure 2The side of the simulation board 51 close to the ball loading device 3 is fixedly connected to the panel 222 by screws to reduce the situation in which a step structure is formed between the simulation board 51 and the second platform 6 when the lifting member 52 applies force to the simulation board 51, resulting in the golf ball being unable to roll onto the first platform 2.

[0038] Reference Figure 1 and Figure 2 , two simulation boards 51 are also provided to facilitate packaging and transportation. A connecting plate 53 is provided on one side of the simulation board 51 close to the frame 21, and the connecting plate 53 is located at the intersection of the two simulation boards 51. Two groups of threaded holes are provided on the connecting plate 53, and the two groups of threaded holes correspond to the two simulation boards 51 respectively. The two simulation boards 51 are fixedly connected to the connecting plate 53 by screws respectively, so as to realize the connection between the two simulation boards 51.

[0039] Reference Figure 1 and Figure 2 The second platform 6 includes a frame 21 and a panel 222. The frame 21 of the panel 222 of the second platform 6 is similar to that of the first platform 2, and will not be described in detail. In this embodiment, the overall length and width of the second platform 6 are both 1.1 m, so the panel 222 does not need to be divided.

[0040] The implementation principle of the push rod platform embedded parts of the embodiment of the present application is: the more difficult area of ​​the support platform 7 is separated, which can be pre-processed on the one hand, and can also be processed synchronously with the support platform 7, thereby improving the overall construction efficiency. After the push rod platform embedded parts are set and spliced, they are embedded in the installation hole 71 to complete the construction of the support platform 7.

[0041] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. The push rod platform embedded part is characterized by: The golf simulation system comprises a platform body (1), a ball loading device (3) and a simulated putting hole cup (4) mounted on the platform body (1); a mounting hole (71) is provided on a support platform (7) of the golf simulation system, and the platform body (1) can be embedded in the mounting hole (71).

2. The push rod platform embedded part according to claim 1, characterized in that: The platform body (1) comprises a first platform (2) and a second platform (6), the simulated putting hole cup (4) is mounted on the first platform (2), and the ball loading device (3) is mounted on the second platform (6).

3. The push rod platform embedded part according to claim 2, characterized in that: The first platform (2) comprises a frame (21) and a panel (22) arranged outside the frame (21).

4. The push rod platform embedded part according to claim 3, characterized in that: The skeleton (21) is formed by a plurality of crisscross keels fixed to each other, and the keels are a shell structure with a hollow interior.

5. The push rod platform embedded part according to claim 4, characterized in that: The enclosure (22) comprises a side plate (221) and a panel (222), wherein the side plate (221) is perpendicular to the first platform (2), and the panel (222) is parallel to the first platform (2), and adjacent side plates (221) are rotatably connected.

6. The push rod platform embedded part according to claim 5, characterized in that: The panel (222) is equally divided into a plurality of panels.

7. The push rod platform embedded part according to claim 4, characterized in that: A slope simulation component (5) is arranged on the first platform (2), and the slope simulation component (5) comprises a simulation plate (51) and a lifting member (52), wherein the simulation plate (51) is arranged in contact with the panel (222), and the lifting member (52) is located inside the bracket and is used to apply a force to the simulation plate (51) in a direction perpendicular to the panel (222).

8. The push rod platform embedded part according to claim 7, characterized in that: A side of the simulation board (51) close to the second platform (6) is fixedly connected to the panel (222), and the simulation board (51) is capable of deformation.