Tool for measuring over-pouring elevation of pile foundation

By designing a measuring tool for pile foundation construction, using the water storage cover and drainage pipe system to collect and measure the volume of mud water, the problem of difficulty and error in judging the over-filling elevation of pile foundation is solved, and more accurate Elevation measurement and higher quality construction.

CN222505360UActive Publication Date: 2025-02-18HUBEI HAINEIWUSHUANG CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421064520.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-16
Publication Date
2025-02-18
Estimated Expiration
2034-05-16

AI Technical Summary

Technical Problem

During pile foundation construction, due to the obstruction of mud and water, it is difficult for workers to accurately judge the over-filling elevation of the pile foundation, resulting in a large over-filling error, which affects the construction quality.

Method used

A measuring tool for super-filling elevation of pile foundation is designed, including a semicircular first water storage cover and a second water storage cover, which is fixed to the steel casing through a connecting piece, and the overflowing mud water is used to use a drain pipe and a ball valve to control the overflowing mud water. Collect it into the water storage tank, and calculate the elevation of concrete pouring by recording the number of times the mud water is drained.

Benefits of technology

Through the use of measurement tools, the elevation of pile foundation super tanks can be accurately calculated, reducing overfilling errors and improving construction quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222505360U_ABST
    Figure CN222505360U_ABST
Patent Text Reader

Abstract

The utility model provides a measuring tool for pile foundation overfilling elevation, which comprises a semicircular first water storage cover and a semicircular second water storage cover which are sleeved at the upper end of a steel casing, the cross section of the first water storage cover and the cross section of the second water storage cover are L-shaped, the first water storage cover is fixedly connected with the second water storage cover through a connecting piece, and the second water storage cover is fixedly connected with the steel casing through a connecting piece. A drainage pipe is installed on the lower portion of the face, away from the first water storage cover, of the second water storage cover, a ball valve is installed at the end, away from the second water storage cover, of the drainage pipe and arranged on the upper side of a water storage tank used for storing muddy water overflowing from the steel casing, and the upper end of the water storage tank is open. And a drain valve is mounted at the lower part of one surface of the water storage tank. The device has the following beneficial effects that the elevation of the pile foundation overloading tank is measured through the volume of discharged muddy water.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model is a measuring tool for the overfilling height of a pile foundation, belonging to the technical field of construction. Background Art

[0002] Cast-in-place piles are a type of pile foundation. First, a hole is drilled on the construction site. When the required depth is reached, the steel bars are placed and poured with concrete. For unstable soil, it is very difficult to construct reinforced concrete retaining walls, so steel casings are used to protect the bored piles to prevent the hole from collapsing and avoid affecting the construction progress and safety. Muddy water is poured into the steel casing to provide balanced support for the steel casing. When pouring concrete, it is necessary to insert a spigot into the pile hole where muddy water exists, so that the concrete flows to the bottom of the pile hole under the action of the spigot. Then the muddy water is squeezed out by the concrete. Affected by the obstruction of the muddy water, the over-filling elevation of the pile foundation is judged by the workers based on their experience, resulting in a large over-filling error, which affects the construction quality of the pile foundation. Utility Model Content

[0003] In view of the deficiencies in the prior art, the utility model aims to provide a pile foundation overfilling elevation measurement tool to solve the problems raised in the above-mentioned background technology. The utility model measures the elevation of the pile foundation overfilling tank by discharging the volume of muddy water.

[0004] In order to achieve the above-mentioned purpose, the utility model is implemented through the following technical scheme: a pile foundation over-filling elevation measuring tool, including a semicircular first water storage cover and a semicircular second water storage cover for being sleeved on the upper end of a steel casing, the cross-section of the first water storage cover and the cross-section of the second water storage cover are both L-shaped, the first water storage cover is connected and fixed to the second water storage cover through a connecting piece, a drainage pipe is installed at the lower position of a side of the second water storage cover away from the first water storage cover, a ball valve is installed at one end of the drainage pipe away from the second water storage cover, the ball valve is arranged on the upper side of a water tank for storing mud water overflowing from the steel casing, the upper end of the water storage tank is open, and a drain valve is installed at the lower position of one side of the water storage tank.

[0005] Furthermore, the connecting member includes a first connecting ear, both ends of the first water storage cover are connected and fixed with the first connecting ears, the two first connecting ears are respectively fitted with two second connecting ears, the second connecting ears are connected and fixed to the second water storage cover, and the first connecting ear is connected and fixed to the second connecting ears by a connecting bolt.

[0006] Furthermore, the first connecting ear and the first water storage cover are an integrally formed structure, and the second connecting ear and the second water storage cover are an integrally formed structure.

[0007] Furthermore, two symmetrically arranged supports are connected and fixed to the lower positions of two parallel sides of the water tank, the upper surfaces of the supports are provided with vertical holes, pillars are inserted in the vertical holes, and the supports are provided with threaded holes on the side facing away from the water tank, and positioning screws for limiting the relative position of the pillars and the supports are threadedly connected in the threaded holes.

[0008] Furthermore, a chassis is connected and fixed to the lower end of the column, the outer diameter of the chassis is larger than the outer diameter of the column, and the chassis and the column are an integrally formed structure.

[0009] Furthermore, a side surface of the support is connected and fixed with a reinforcing rib, the reinforcing rib is a triangular structure, and the reinforcing rib is connected and fixed to the water tank.

[0010] Furthermore, a screw hole is provided at a lower position of the outer surface of the second water storage cover, an outer surface of one end of the drain pipe away from the ball valve is processed with an external thread, and one end of the drain pipe processed with the external thread is threadedly connected in the screw hole.

[0011] Beneficial effects of the utility model:

[0012] 1. The semicircular first water storage cover and the second water storage cover are sleeved on the upper end of the steel casing, and then the first water storage cover and the second water storage cover are connected by connecting screws, so that the cylindrical structure formed by the first water storage cover and the second water storage cover is restricted on the steel casing. When the concrete flows into the bottom of the pile hole by means of inserting a pipe to guide the concrete, the muddy water in the pile hole overflows from the upper edge of the steel casing under the pressure of the concrete, and the overflowed muddy water flows into the space formed by the first water storage cover, the second water storage cover and the steel casing. After opening the ball valve, the muddy water flows into the space formed by the first water storage cover, the second water storage cover and the steel casing. Water flows into the water tank through the drainage pipe. When a certain amount of muddy water is collected in the water tank, close the ball valve and open the drain valve to drain the muddy water in the water tank. Repeat the above operation and record the number of times the muddy water in the water tank is drained. Since the inner diameter of the pile hole is constant, the volume of the muddy water discharged through the water tank is calculated. According to volume = bottom area * height, the elevation of the concrete pouring in the pile hole is calculated. The elevation of the pile foundation over-tank is measured by the volume of the discharged muddy water to avoid large over-pouring errors.

[0013] 2. Insert poles into the vertical holes on the four supports, and then adjust the relative positions of the four poles and the supports so that the chassis at the lower ends of the four poles are in contact with the ground and the water tank is in a horizontal state. At this time, the four poles can achieve balanced support for the water tank. On the one hand, the water tank can be placed on an uneven ground, and on the other hand, there is no need to level the ground where the water tank is placed. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Other features, objects and advantages of the present invention will become more apparent by reading the detailed description of non-limiting embodiments with reference to the following drawings:

[0015] Figure 1 It is a structural schematic diagram of a pile foundation overfilling height measuring tool of the utility model;

[0016] Figure 2 for Figure 1 Enlarged view of point A in the middle;

[0017] Figure 3 It is a schematic diagram of the assembly of a column, a support, a drainage valve and a water storage tank in a pile foundation overfilling height measuring tool of the utility model;

[0018] Figure 4 It is a schematic diagram of the assembly of the support and the water tank in a pile foundation overfilling height measuring tool of the utility model;

[0019] Figure 5 for Figure 4 Enlarged view of point B in the middle;

[0020] Figure 6 It is a schematic diagram of the assembly of the first connecting ear and the first water storage cover in a pile foundation overfilling height measuring tool of the utility model;

[0021] Figure 7 It is a schematic diagram of assembling the second connecting ear and the second water storage cover in a pile foundation overfilling height measuring tool of the utility model;

[0022] In the figure: 1-first water storage cover, 2-second water storage cover, 3-drain pipe, 4-ball valve, 5-water storage tank, 6-connecting bolts, 7-support, 8-column, 9-chassis, 10-positioning screws, 11-drain valve, 12-vertical hole, 13-threaded hole, 14-screw hole, 15-first connecting ear, 16-second connecting ear. DETAILED DESCRIPTION

[0023] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.

[0024] See also Figure 1 , Figure 6 and Figure 7The utility model provides a technical solution: a measuring tool for the over-filling elevation of a pile foundation, comprising a semicircular first water storage cover 1 and a semicircular second water storage cover 2 for being sleeved on the upper end of a steel casing, the cross-sections of the first water storage cover 1 and the second water storage cover 2 are both L-shaped, and first connecting ears 15 are connected and fixed at both ends of the first water storage cover 1, wherein the first connecting ear 15 and the first water storage cover 1 are an integrally formed structure, the two first connecting ears 15 are respectively fitted with two second connecting ears 16, the second connecting ear 16 is connected and fixed to the second water storage cover 2, and the second connecting ear 16 and the second water storage cover 2 are an integrally formed structure, the first connecting ear 15 is connected and fixed to the second connecting ear 16 by a connecting bolt 6, the semicircular first water storage cover 1 and the second water storage cover 2 are sleeved on the upper end of the steel casing, and then the first water storage cover 1 and the second water storage cover 2 are connected by connecting screws, so that the cylindrical structure formed by the first water storage cover 1 and the second water storage cover 2 is restricted on the steel casing.

[0025] See also Figure 1 and Figure 7 A drain pipe 3 is installed at the lower position of one side of the second water storage cover 2 away from the first water storage cover 1, and a ball valve 4 is installed at the end of the drain pipe 3 away from the second water storage cover 2, wherein a screw hole 14 is opened at the lower position of the outer surface of the second water storage cover 2, and an outer surface of the end of the drain pipe 3 away from the ball valve 4 is processed with an external thread, so that the end of the drain pipe 3 processed with the external thread is threadedly connected to the screw hole 14, completing the assembly of the drain pipe 3 and the second water storage cover 2, which is convenient for the disassembly of the drain pipe 3 and the second water storage cover 2.

[0026] See also Figure 1-Figure 7 The ball valve 4 is arranged on the upper side of the water storage tank 5 for storing the muddy water overflowing from the steel casing. The upper end of the water storage tank 5 is open. A drainage valve 11 is installed at the lower part of one side of the water storage tank 5. When the concrete is guided to flow into the bottom of the pile hole by inserting a pipe, the muddy water in the pile hole overflows from the upper edge of the steel casing under the pressure of the concrete. The overflowed muddy water flows into the space formed by the first water storage cover 1, the second water storage cover 2 and the steel casing. After the ball valve 4 is opened, the muddy water flows into the water storage tank through the drainage pipe 3. In the water tank 5, when a certain amount of muddy water is collected in the water tank 5, close the ball valve 4 and open the drain valve 11 to drain the muddy water in the water tank 5. Repeat the above operation and record the number of times the muddy water in the water tank 5 is drained. Since the inner diameter of the pile hole is constant, the volume of the muddy water discharged through the water tank 5 is calculated. According to volume = bottom area * height, the elevation of the concrete pouring in the pile hole is calculated, and the elevation of the pile foundation over-tank is measured by the volume of the discharged muddy water to avoid large over-pouring errors.

[0027] See also Figure 1-Figure 5, the lower parts of the two parallel sides of the water tank 5 are connected and fixed with two symmetrically arranged supports 7, wherein one side of the support 7 is connected and fixed with a reinforcing rib, and the reinforcing rib is a triangular structure, so that the reinforcing rib is connected and fixed with the water tank 5, and the mechanical strength of the connection between the support 7 and the water tank 5 is improved. A vertical hole 12 is opened on the upper surface of the support 7, and a column 8 is inserted in the vertical hole 12. A threaded hole 13 is opened on the side of the support 7 away from the water tank 5, and a positioning screw 10 for limiting the relative position of the column 8 and the support 7 is threadedly connected in the threaded hole 13. The lower end of the column 8 is connected and fixed There is a chassis 9, the outer diameter of the chassis 9 is larger than the outer diameter of the column 8, the chassis 9 and the column 8 are an integrally formed structure, the chassis 9 increases the contact range of the column 8 with the ground, the column 8 is inserted into the vertical holes 12 on the four supports 7, and then the relative positions of the four columns 8 and the supports 7 are adjusted so that the chassis 9 at the lower ends of the four columns 8 are in contact with the ground, and the water tank 5 is in a horizontal state. At this time, the four columns 8 realize balanced support for the water tank 5. On the one hand, the water tank 5 is placed on an uneven ground, and on the other hand, there is no need to level the ground on which the water tank 5 is placed.

[0028] Although this specification is described according to implementation modes, not every implementation mode includes only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A pile foundation overfilling height measuring tool, comprising a semicircular first water storage cover (1) and a semicircular second water storage cover (2) for sleeved on the upper end of a steel casing, characterized in that: The cross-sections of the first water storage cover (1) and the second water storage cover (2) are both L-shaped. The first water storage cover (1) is connected and fixed to the second water storage cover (2) via a connecting piece. A drainage pipe (3) is installed at the lower part of a side of the second water storage cover (2) away from the first water storage cover (1). A ball valve (4) is installed at one end of the drainage pipe (3) away from the second water storage cover (2). The ball valve (4) is arranged on the upper side of a water storage tank (5) for storing muddy water overflowing from the steel casing. The upper end of the water storage tank (5) is open, and a drainage valve (11) is installed at the lower part of one side of the water storage tank (5).

2. A pile foundation overfilling height measuring tool according to claim 1, characterized in that: The connecting member comprises a first connecting ear (15), both ends of the first water storage cover (1) are connected and fixed with the first connecting ear (15), the two first connecting ears (15) are respectively fitted with two second connecting ears (16), the second connecting ears (16) are connected and fixed to the second water storage cover (2), and the first connecting ear (15) is connected and fixed to the second connecting ears (16) via a connecting bolt (6).

3. A pile foundation overfilling height measuring tool according to claim 2, characterized in that: The first connecting ear (15) and the first water storage cover (1) are an integrally formed structure, and the second connecting ear (16) and the second water storage cover (2) are an integrally formed structure.

4. A pile foundation overfilling height measuring tool according to claim 1, characterized in that: Two symmetrically arranged supports (7) are connected and fixed to the lower positions of two parallel sides of the water storage tank (5); a vertical hole (12) is provided on the upper surface of the support (7); a column (8) is inserted into the vertical hole (12); a threaded hole (13) is provided on the side of the support (7) facing away from the water storage tank (5); a positioning screw (10) for limiting the relative position of the column (8) and the support (7) is threadedly connected to the threaded hole (13).

5. A pile foundation overfilling height measuring tool according to claim 4, characterized in that: The lower end of the column (8) is connected and fixed with a chassis (9); the outer diameter of the chassis (9) is larger than the outer diameter of the column (8); the chassis (9) and the column (8) are an integrally formed structure.

6. A pile foundation overfilling height measuring tool according to claim 4, characterized in that: A reinforcing rib is connected and fixed to one side of the support (7), the reinforcing rib is a triangular structure, and the reinforcing rib is connected and fixed to the water tank (5).

7. A pile foundation overfilling height measuring tool according to claim 1, characterized in that: A screw hole (14) is provided at the lower portion of the outer surface of the second water storage cover (2); an outer surface of one end of the discharge pipe (3) away from the ball valve (4) is processed with an external thread; and the end of the discharge pipe (3) processed with the external thread is threadedly connected in the screw hole (14).