By using a double locking mechanism in the pipeline steel card, using the combination of the card block, guide post and tensile spring, the problem of insufficient locking caused by loose bolts and nuts in the prior art is solved, and a higher locking is achieved Tightening and stability.
Patent Information
- Application Number
- CN202421327798.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-12
- Publication Date
- 2025-02-21
- Estimated Expiration
- 2034-06-12
AI Technical Summary
When existing pipe steel clamps are subjected to vibration, temperature changes or long-term load, the bolt and nut connections are easily loosened, resulting in insufficient locking and affecting the stability of the pipe connection.
A double locking mechanism is adopted. The original locking mechanism is composed of bolts and nuts. The new locking mechanism is composed of a clamp, a guide post and a tensile spring. Before installing the bolts and nuts, the clamp block can pre-lock the joints and steel cards through the action of the tension spring, ensuring that the pipes obtain good stability in the initial stage.
By pre-locking, the pipe connection has higher locking force, thereby improving the stability and safety of the pipe system.
Smart Images

Figure CN222513782U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pipeline steel clamps, in particular to a steel clamp with good locking degree. Background Art
[0002] Pipeline steel clamp is a fixture used to fix and connect pipes and their accessories, also known as clamp or steel clamp. The following is a detailed introduction to pipeline steel clamp:
[0003] Pipeline steel clamps are usually made of steel or stainless steel and are strong and durable.
[0004] For conventional steel clamps, after clamping the two half hoops on the outside of the pipe connection, thread the bolts and then tighten the nuts to complete the installation of the pipe steel clamp.
[0005] However, bolt and nut connections are prone to loosening under vibration, temperature changes or long-term loads. This loosening will reduce the locking degree of the steel clamp and affect the stability of the pipeline connection. During the installation process, if sufficient pre-tightening force is not properly applied, the friction between the bolt and nut will not be enough to maintain the stability of the connection. Insufficient pre-tightening force is one of the common causes of locking defects.
[0006] Therefore, a new steel clip with good locking degree is proposed to solve the above problems. Utility Model Content
[0007] The purpose of the present invention is to solve at least one of the above technical deficiencies.
[0008] Therefore, one purpose of the present invention is to provide a steel clip with good locking performance to solve the problems mentioned in the background technology and overcome the deficiencies in the prior art.
[0009] In order to achieve the above-mentioned purpose, an embodiment of one aspect of the utility model provides a steel clip with good locking degree, comprising a male half ring and a female half ring, wherein the female half ring is connected to the lower part of the male half ring;
[0010] Both ends of the male half ring and the female half ring are fixedly connected with joints, bolts are passed through the joints, and nuts are threadedly connected to the ends of the bolts;
[0011] A positioning block is fixedly connected below the joint of the male half ring, and the positioning block is plugged into the corresponding position of the joint of the female half ring;
[0012] The inner sides of the male half ring and the female half ring are fastened with rubber rings;
[0013] The joints of the male half ring and the female half ring are both provided with a slot and a block is connected to the slot. The block is bent and has a guide column movably connected inside.
[0014] A tension spring is connected between the blocks, and the tension spring is in a tensioned state.
[0015] Preferably, any of the above schemes is that the male half ring and the female half ring are connected by a joint, bolts and nuts, and the male half ring and the female half ring form a single steel ring structure.
[0016] The above technical solution is adopted: the device is a steel clamp for connecting pipes, mainly a rubber ring is put on the connection of the pipe, and then the male half ring and the female half ring are put on, and the positioning block on the male half ring joint is plugged into the female half ring joint;
[0017] Install the clamping block structure, and clamp the clamping block on the surface of the male half ring and the female half ring joints. The tension spring is in the tension state at this time, so that the joints are locked and tightly held together. The male half ring and the female half ring hold the rubber ring together and hold and lock the connection of the pipe;
[0018] Then install the bolts and nuts and tighten the nuts.
[0019] Preferably, any of the above schemes is that the male half ring and the female half ring are made of stainless steel, and the positioning block is welded to the corresponding male half ring joint.
[0020] Preferably, in any of the above schemes, the bending angle of the clamping block is ninety degrees, and the material of the clamping block is stainless steel.
[0021] Adopting the above technical scheme: the core structure of the device is: bolts, nuts, blocks, guide pillars and tension springs. The core advantages of the device are: adopting a double locking mechanism, the original locking mechanism is composed of bolts and nuts, and the newly added locking mechanism is composed of blocks, guide pillars and tension springs. Before installing the bolts and nuts, install the block structure, the block is stuck on the surface of the male half ring and the female half ring joint, and the tension spring is in a stretched state at this time, so that the joints are locked and tightened with each other, the male half ring and the female half ring jointly hold the rubber ring and the connection of the locked pipe. Before installing the bolts and nuts, the block can pre-lock the joint and the steel clamp through the action of the tension spring. This pre-locking method can ensure that the pipeline obtains good stability in the initial stage. When the bolts and nuts are installed for further locking, since the joint and the steel clamp have been pre-locked by the block, the bolts and nuts can more easily reach the expected locking force. This design can ensure that the pipeline connection has a higher locking force, thereby improving the stability and safety of the pipeline system.
[0022] Preferably, any of the above solutions comprises that the clamping block holds the joint of the male half ring and the female half ring.
[0023] Preferably, any of the above schemes is that the stretch spring is located on both sides of the guide column, and the material of the stretch spring is stainless steel and the diameter of the material is 0.3-0.4 cm.
[0024] Compared with the prior art, the advantages and beneficial effects of the utility model are:
[0025] The steel clamp with good locking degree adopts a double locking mechanism through the coordination of bolts, nuts, clamping blocks, guide pillars and tension springs. The original locking mechanism is composed of bolts and nuts, and the newly added locking mechanism is composed of clamping blocks, guide pillars and tension springs. Before installing the bolts and nuts, the clamping block structure is installed, and the clamping block is clamped on the surface of the male half ring and the female half ring joint. The tension spring is in a stretched state at this time, so that the joints are locked and tightened with each other. The male half ring and the female half ring jointly hold the rubber ring and the connection of the locked pipe. Before installing the bolts and nuts, the clamping block can pre-lock the joint and the steel clamp through the action of the tension spring. This pre-locking method can ensure that the pipeline obtains good stability in the initial stage. When the bolts and nuts are installed for further locking, since the joint and the steel clamp have been pre-locked by the clamping block, the bolts and nuts can more easily reach the expected locking force. This design can ensure that the pipeline connection has a higher locking force, thereby improving the stability and safety of the pipeline system.
[0026] Additional aspects and advantages of the present invention will be given in part in the following description and in part will become apparent from the following description or will be learned through the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:
[0028] Figure 1 It is a three-dimensional structural schematic diagram of the utility model;
[0029] Figure 2 This is a front view structural schematic diagram of the utility model;
[0030] Figure 3 This is a schematic diagram of the structure of the utility model when the rubber ring is not installed;
[0031] Figure 4 For this utility model Figure 3 Schematic diagram of the enlarged structure at point A in the middle.
[0032] In the figure: 1-male half ring, 2-female half ring, 3-connector, 4-bolt, 5-nut, 6-positioning block, 7-rubber ring, 8-block, 9-guide column, 10-tension spring. DETAILED DESCRIPTION
[0033] The embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.
[0034] In the present invention, unless otherwise clearly specified and limited, the terms "install", "connect", "connect", "fix" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0035] like Figure 1-4 As shown, the steel clamp with good locking performance comprises a male half ring 1 and a female half ring 2, wherein the female half ring 2 is connected to the lower part of the male half ring 1;
[0036] Joints 3 are fixedly connected at both ends of the male half ring 1 and the female half ring 2, bolts 4 are passed through the joints 3, and nuts 5 are threadedly connected at the ends of the bolts 4;
[0037] A positioning block 6 is fixedly connected below the joint 3 of the male half ring 1, and the positioning block 6 is plugged into the corresponding position of the joint 3 of the female half ring 2;
[0038] The inner sides of the male half ring 1 and the female half ring 2 are fastened with a rubber ring 7;
[0039] The joints 3 of the male half ring 1 and the female half ring 2 are provided with a slot and a block 8 is connected to the slot. The block 8 is bent and a guide column 9 is movably connected inside the block 8.
[0040] A tension spring 10 is connected between the blocks 8 and is in a tensioned state.
[0041] Embodiment 1: The male half ring 1 and the female half ring 2 are connected by a joint 3, a bolt 4 and a nut 5, and the male half ring 1 and the female half ring 2 form a single steel ring structure. The material of the male half ring 1 and the female half ring 2 is stainless steel, and the positioning block 6 is welded to the corresponding male half ring 1 joint 3. The bending angle of the clamping block 8 is 90 degrees, and the material of the clamping block 8 is stainless steel.
[0042] Embodiment 2: The clamping block 8 holds the joint 3 of the male half ring 1 and the female half ring 2. The tension spring 10 is located on both sides of the guide column 9. The material of the tension spring 10 is stainless steel and the diameter of this material is 0.3-0.4 cm. The tension spring 10 has high strength and locking force. Before installing the bolts 4 and nuts 5, the clamping block can pre-lock the joint 3 and the steel clamp through the action of the tension spring 10. This pre-locking method can ensure that the pipeline has good stability in the initial stage. When the bolts 4 and nuts 5 are installed for further locking, since the joint 3 and the steel clamp have been pre-locked by the clamping block 8, the bolts 4 and nuts 5 can more easily achieve the expected locking force. This design can ensure that the pipeline connection has a higher locking force, thereby improving the stability and safety of the pipeline system.
[0043] The working principle of the utility model is as follows:
[0044] The rubber ring 7 is put on the connection of the pipe, and then the male half ring 1 and the female half ring 2 are put on. The positioning block 6 on the joint 3 of the male half ring 1 is inserted into the joint of the female half ring 2;
[0045] Install the clamping block 8 structure, the clamping block 8 is clamped on the surface of the male half ring 1 and the female half ring 2 joint 3, the tension spring 10 is in the tension state at this time, so that the joints 3 are locked and tightly embraced with each other, and the male half ring 1 and the female half ring 2 jointly embrace the rubber ring 7 and the connection of the locking pipe;
[0046] Then install bolt 4 and nut 5, and tighten nut 5.
[0047] Compared with the prior art, the present invention has the following beneficial effects:
[0048] The steel clamp with good locking degree adopts a double locking mechanism through the matching arrangement of bolts 4, nuts 5, clamping blocks 8, guide pillars 9 and tension springs 10. The original locking mechanism is composed of bolts 4 and nuts 5, and the newly added locking mechanism is composed of clamping blocks 8, guide pillars 9 and tension springs 10. Before installing bolts 4 and nuts 5, the clamping block 8 structure is installed, and the clamping block 8 is clamped on the surface of the male half ring 1 and the female half ring 2 joint 3. The tension spring 10 is in a stretched state at this time, so that the joints 3 are locked and held tightly together. The male half ring 1 and the female half ring 2 jointly hold the rubber ring 7 and the connection of the locked pipe. Before installing bolts 4 and nuts 5, the clamping block can pre-lock the joint 3 and the steel clamp through the action of the tension spring 10. This pre-locking method can ensure that the pipeline obtains good stability in the initial stage. When the bolts 4 and nuts 5 are installed for further locking, since the joint 3 and the steel clamp have been pre-locked by the clamping block 8, the bolts 4 and nuts 5 can more easily reach the expected locking force. This design can ensure that the pipe joints have a higher locking force, thereby improving the stability and safety of the pipe system.
Claims
1. A steel card with good locking performance, characterized in that: It comprises a male half ring (1) and a female half ring (2), wherein the female half ring (2) is connected below the male half ring (1); The male half ring (1) and the female half ring (2) are both fixedly connected with joints (3), the joints (3) are penetrated by bolts (4), and the ends of the bolts (4) are threadedly connected with nuts (5); A positioning block (6) is fixedly connected below the joint (3) of the male half ring (1), and the positioning block (6) is plugged into a corresponding position of the joint (3) of the female half ring (2); A rubber ring (7) is fastened to the inner side of the male half ring (1) and the female half ring (2); The joints (3) of the male half ring (1) and the female half ring (2) are both provided with a slot, and a block (8) is connected to the slot, the block (8) is bent, and a guide column (9) is movably connected inside the block (8); A tension spring (10) is connected between the clamping blocks (8), and the tension spring (10) is in a tensioned state.
2. A steel clip with good locking performance as claimed in claim 1, characterized in that: The male half ring (1) and the female half ring (2) are connected via a joint (3), a bolt (4) and a nut (5), and the male half ring (1) and the female half ring (2) form a single steel ring structure.
3. A steel clip with good locking performance as claimed in claim 2, characterized in that: The male half ring (1) and the female half ring (2) are made of stainless steel, and the positioning block (6) is welded to the corresponding joint (3) of the male half ring (1).
4. A steel clip with good locking performance as claimed in claim 3, characterized in that: The bending angle of the clamping block (8) is ninety degrees, and the material of the clamping block (8) is stainless steel.
5. A steel clip with good locking performance as claimed in claim 4, characterized in that: The clamping block (8) tightly holds the joint (3) of the male half ring (1) and the female half ring (2).
6. A steel clip with good locking performance as claimed in claim 5, characterized in that: The stretch spring (10) is located on both sides of the guide column (9). The material of the stretch spring (10) is stainless steel and the diameter of the material is 0.3-0.4 cm.