Hoop part for bridge construction

By designing a ferrule for bridge construction including connecting adjustment components and tilt prompt components, the problems of position offset of embedded steel plates and adaptation of different bridge pier diameters in the prior art are solved, and the adaptation of bridge piers of different diameters and the rapid adjustment of transverse connecting beams is achieved, and construction efficiency and structural stability are improved.

CN222541302UActive Publication Date: 2025-02-28SICHUAN ROAD & BRIDGE CONSTRUCTION GROUP CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421246188.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-03
Publication Date
2025-02-28
Estimated Expiration
2034-06-03

AI Technical Summary

Technical Problem

During construction, the existing bridge construction ferrule parts are offset or misaligned, affecting the lateral connection mount between the bridge pier and the steel pipe support piers and the installation of the ferrule parts, resulting in structural instability. In addition, bridge piers of different thicknesses need to be replaced with corresponding ferrules, and the transverse connecting beams need to be processed according to the actual length. The scope of application is small, which affects the construction progress and is not easy to maintain the horizontal direction of the transverse connecting beams.

Method used

A ferrule for bridge construction is designed, including a pier main body, a first ferrule, a second ferrule, a transverse connecting beam, an adjustment beam, a prompter, a connection adjustment assembly and an inclined reminder assembly. By adjusting the second bolt and the first bolt, the diameters of the first and second bolts are changed to adapt to the pier main body of different diameters; the limit is quickly clamped and the third bolt is prevented from sliding, and ensuring that the pier main body is unstable; the inclination detection lead sinker and trigger switch are used to prompt the staff to incline the inclination of the transverse connecting beam through sound to ensure the stability of the connection structure.

Benefits of technology

The ferrule can adapt to the main body of the bridge pier of different diameters, and quickly adjust the length of the transverse connecting beam, improving the installation and erection efficiency; by tilting the components, avoiding the inclination of the transverse connecting beam, ensuring the stability of the overall structure, and improving the safety and efficiency of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 00000000_0000_ABST
    Figure 00000000_0000_ABST
Patent Text Reader

Abstract

The utility model provides a hoop piece for bridge construction, belongs to the technical field of bridge construction, and aims to solve the problems that when an existing hoop piece for bridge construction is constructed, the position of an embedded steel plate deviates or is staggered, transverse connecting erection and hoop piece installation can be affected, and the horizontal direction of a transverse connecting beam is not easy to keep in the construction process. Comprising a pier body; the first hoop piece is arranged on the outer side of the bridge pier main body; the second hoop piece is arranged on the outer side of the bridge pier main body; the transverse connecting beam is welded to the right side of the second hoop piece; the adjusting beam is connected to the interior of the transverse connecting beam in a sliding mode; the prompter is fixedly connected to the bottom of the adjusting beam; the connecting and adjusting assembly is arranged in the first hoop piece; and the inclination prompting assembly is arranged in the prompter. The utility model has the advantages of high applicability, quick installation, inclination prompt and the like.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of bridge construction, and more specifically, particularly relates to a sleeve hoop for bridge construction. Background Art

[0002] When constructing a bridge using a beam-column support, it is necessary to ensure the stability of the steel pipe piers. The stability of the steel pipe piers is related to the safety of the entire support structure. Therefore, it is necessary to set up a transverse connection between the steel pipe piers or between the steel pipe piers and the permanent bridge piers. When setting up the connection, a hoop for bridge construction is required. The existing hoop for bridge construction requires pre-embedded steel plates on the piers before the hoop, and the brackets and hoop are erected using the pre-embedded steel plates.

[0003] Existing application number CN202020637394.2 The utility model discloses a hoop for bridge construction and a bridge construction device, the hoop for bridge construction includes at least one hoop, a support plate, a first bolt and a second bolt, the hoop is a circular ring structure with an opening, each hoop has protrusions at both ends, the protrusions extend outward from the outer circumference of the hoop along the diameter of the hoop, and the protrusions are provided with a first through hole connected to the first bolt; the connection between the protrusion and the hoop is a chamfered structure, and the chamfered structure is provided with a second through hole connected to the second bolt; the support plate is fixed on the outer circumference of the hoop. When the hoop for bridge construction is used, it is only necessary to put the hoop on the pier, and use the second bolt to adjust the tightness of the hoop, so as to achieve the fixation of the hoop and the pier, effectively solving the problem of lateral connection between different piers caused by forgetting to embed steel plates or embedding them in the wrong position during bridge construction, improving the stability of the lateral connection between different piers, and improving the safety during bridge construction.

[0004] Based on the above, during the construction of the existing bridge construction, the embedded steel plate position is offset or misaligned, which will affect the transverse connection between the pier and the steel pipe pier and the installation of the hoop, affecting the stability of the structure. In addition, during use, piers of different thicknesses need to replace the corresponding hoop, and the transverse connecting beam between the two piers also needs to be processed according to the actual length. The scope of application is small. In the absence of matching transverse connecting beams and hoop, the construction progress is affected. In addition, it is not easy to maintain the horizontal direction of the transverse connecting beam during the construction process. If the transverse connecting beam is horizontally offset, it will cause a height difference between the two sets of hoop, making the transverse connection structure unstable. Utility Model Content

[0005] In order to solve the above technical problems, the utility model provides a hoop for bridge construction to solve the problem that the position of the embedded steel plate of the existing hoop for bridge construction is offset or misplaced during construction, which will affect the transverse connection erection and installation of the hoop between the pier and the steel pipe pier, and affect the stability of the structure. In addition, during use, piers of different thicknesses need to replace the corresponding hoop, and the transverse connecting beam between the two piers also needs to be processed according to the actual length. The scope of application is small. In the absence of matching transverse connecting beams and hoop, the construction progress is affected. In addition, it is not easy to maintain the horizontal direction of the transverse connecting beam during construction. If the transverse connecting beam is offset horizontally, it will cause a height difference between the two sets of hoop, making the transverse connection structure unstable.

[0006] The purpose and effect of the hoop for bridge construction of the utility model are achieved by the following specific technical means:

[0007] A hoop for bridge construction, comprising a pier body;

[0008] a first set of hoop members, the first set of hoop members being arranged outside the pier body;

[0009] a second hoop member, the second hoop member being arranged outside the pier body;

[0010] A transverse connecting beam, the transverse connecting beam being welded to the right side of the second hoop;

[0011] An adjusting beam, wherein the adjusting beam is slidably connected inside the transverse connecting beam;

[0012] A reminder device, the reminder device is fixedly connected to the bottom of the adjustment beam;

[0013] A connection adjustment component, wherein the connection adjustment component is disposed inside the first hoop member;

[0014] A tilt prompting component is arranged inside the prompter.

[0015] Furthermore, the connection adjustment component includes:

[0016] Adjustment blocks, wherein the adjustment blocks are provided in two groups, and the two groups of adjustment blocks are respectively hinged at the ends of the first hoop member and the second hoop member;

[0017] A second bolt is fixedly installed inside the adjusting block.

[0018] Furthermore, the connection adjustment component also includes:

[0019] First bolts, wherein four groups of the first bolts are provided, two groups of the first bolts are fixedly installed inside the first hoop member, and two groups of the first bolts are fixedly installed inside the second hoop member;

[0020] A third bolt, wherein an end of the third bolt is hinged inside the second hoop.

[0021] Furthermore, the connection adjustment component also includes:

[0022] A limit block, the limit block is slidably connected inside the first hoop;

[0023] A pull rod, the pull rod is fixedly connected inside the limit block and slidably connected inside the first hoop;

[0024] A first spring is fixedly mounted on the outside of the pull rod.

[0025] Furthermore, the connection adjustment component also includes:

[0026] An adjustment hole, wherein the adjustment hole is provided inside the adjustment beam;

[0027] A fourth bolt is fixedly installed inside the transverse connecting beam, and the fourth bolt is fixedly installed inside the adjustment hole.

[0028] Furthermore, the tilt prompt component includes:

[0029] A tilt detection plumb sinker, the tilt detection plumb sinker swinging at the bottom of the adjustment beam;

[0030] a second spring, the second spring being fixedly mounted inside the prompter;

[0031] A trigger plate is fixedly mounted on one end of the second spring.

[0032] Furthermore, the tilt prompt component also includes:

[0033] A trigger switch, wherein the trigger switch is fixedly installed inside the prompter;

[0034] A speaker box, the speaker box is fixedly mounted on both sides of the prompter;

[0035] The prompt mechanism is fixedly installed inside the speaker box. The prompt mechanism and the trigger switch are connected in series through wires to form a switch circuit.

[0036] Compared with the prior art, the utility model has the following beneficial effects:

[0037] Firstly, the utility model has a connection adjustment component, by adjusting the second bolt and the first bolt, the diameters of the first hoop member and the second hoop member are changed, so that the first hoop member and the second hoop member can fix pier bodies of different diameters, which greatly improves the applicability of the device, and the third bolt can be quickly clamped and limited by the inclined structure of the limit block, effectively preventing the third bolt from sliding and making the pier body unstable, and the length of the transverse connecting beam can be quickly adjusted through the two groups of pier bodies for rapid installation, which greatly improves the installation and erection efficiency.

[0038] Secondly, the utility model has a tilt prompt component, which detects the swing of the lead weight through the tilting so that the trigger plate squeezes the trigger switch, so that the prompt mechanism makes a sound to remind the staff that the transverse connecting beam is tilted, effectively avoiding the tilt of the transverse connecting beam that makes the overall transverse connection unstable, and conveniently and quickly judges whether the transverse connecting beam is tilted, which is convenient for the staff to make timely adjustments, and effectively improves the installation efficiency.

[0039] The utility model has the advantages of high applicability, quick installation, tilt prompt, etc. It can fix bridge pier bodies of different diameters and quickly adjust bridge piers at different distances, which greatly improves the applicability and installation efficiency of the device. It can quickly prompt the tilt of the device, which is convenient for staff to make timely adjustments, and effectively improves the installation efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] Figure 1 It is a schematic diagram of the main structure of the utility model.

[0041] Figure 2 It is a schematic structural diagram of the first set of hoop components of the utility model.

[0042] Figure 3 It is a schematic structural diagram of the second set of hoop components of the utility model.

[0043] Figure 4 This is a schematic diagram of the third bolt structure of the utility model.

[0044] Figure 5 It is a schematic diagram of the transverse connecting beam structure of the utility model.

[0045] Figure 6 It is a schematic diagram of the structure of the prompter of the utility model.

[0046] Figure 7 It is a schematic diagram of the structure of the tilt detection plumb bob of the utility model.

[0047] In the figure, the corresponding relationship between the component names and the figure numbers is as follows:

[0048] 1. Bridge pier body; 2. First set of hoops; 201. First bolt; 202. Adjustment block; 203. Second bolt; 204. Limit block; 205. Pull rod; 206. First spring; 3. Second set of hoops; 301. Third bolt; 4. Transverse connecting beam; 401. Fourth bolt; 5. Adjustment beam; 501. Adjustment hole; 6. Prompt device; 601. Speaker box; 602. Prompt mechanism; 603. Tilt detection plumb bob; 604. Trigger plate; 605. Second spring; 606. Trigger switch. DETAILED DESCRIPTION

[0049] The following is a further detailed description of the implementation of the present utility model in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present utility model, but cannot be used to limit the scope of the present utility model.

[0050] Embodiment 1:

[0051] As attached Figure 1 To Attachment Figure 7 As shown:

[0052] The utility model provides a sleeve hoop for bridge construction, comprising a pier body 1;

[0053] A first set of hoop members 2, which are arranged outside the pier body 1;

[0054] A second set of hoops 3, which are arranged outside the pier body 1;

[0055] A transverse connecting beam 4, which is welded to the right side of the second hoop member 3;

[0056] An adjusting beam 5, the adjusting beam 5 is slidably connected inside the transverse connecting beam 4;

[0057] A prompter 6, which is fixedly connected to the bottom of the adjusting beam 5;

[0058] A connection adjustment component is arranged inside the first hoop member 2 .

[0059] The connection adjustment components include:

[0060] Adjustment blocks 202, which are provided in two groups, and the two groups of adjustment blocks 202 are respectively hinged at the ends of the first hoop member 2 and the second hoop member 3;

[0061] The second bolt 203 is fixedly installed inside the adjusting block 202; the second bolt 203 plays a role in adjusting the position between the two groups of adjusting blocks 202 by adjusting the second bolt 203, thereby adjusting the distance between the first hoop member 2 and the second hoop member 3, and opening and closing the first hoop member 2 and the second hoop member 3 by swinging the first hoop member 2 and the second hoop member 3 along the two groups of adjusting blocks 202.

[0062] The connection adjustment component also includes:

[0063] First bolts 201, the first bolts 201 are provided in four groups, two groups of the first bolts 201 are fixedly installed inside the first hoop member 2, and two groups of the first bolts 201 are fixedly installed inside the second hoop member 3;

[0064] The third bolt 301, the end of which is hinged inside the second hoop member 3; its function is to change the length of the first hoop member 2 and the second hoop member 3 by adjusting the first bolt 201, to clamp the third bolt 301 into the first hoop member 2 by swinging it, and to fix the first hoop member 2 and the second hoop member 3 together by twisting the third bolt 301.

[0065] The connection adjustment component also includes:

[0066] A limit block 204, the limit block 204 is slidably connected inside the first hoop member 2;

[0067] A pull rod 205, the pull rod 205 is fixedly connected inside the limit block 204, and the pull rod 205 is slidably connected inside the first hoop member 2;

[0068] The first spring 206 is fixedly mounted on the outside of the pull rod 205; the function is that the inclined structure of the limit block 204 facilitates the insertion of the third bolt 301, and the planar structure of the limit block 204 prevents the third bolt 301 from detaching from one side of the plane. When the pull rod 205 is pulled, the pull rod 205 drives the limit block 204 to move, so that the third bolt 301 can move away from one side of the plane of the limit block 204, and the pull rod 205 is released. The first spring 206 drives the limit block 204 to reset under the elastic action.

[0069] The connection adjustment component also includes:

[0070] An adjustment hole 501, the adjustment hole 501 is provided inside the adjustment beam 5;

[0071] The fourth bolt 401 is fixedly installed inside the transverse connecting beam 4, and the fourth bolt 401 is fixedly installed inside the adjusting hole 501; its function is to pull the transverse connecting beam 4, and the transverse connecting beam 4 slides on the outside of the adjusting beam 5, so that the transverse connecting beam 4 is stretched to a suitable length, and then the fourth bolt 401 is inserted into the adjusting hole 501 to fix the transverse connecting beam 4 and the adjusting beam 5.

[0072] The specific usage and function of this embodiment are as follows:

[0073] When it is necessary to hoop and transversely connect two groups of pier bodies 1, pull the transverse connecting beam 4, slide the transverse connecting beam 4 outside the adjusting beam 5, and after the transverse connecting beam 4 is stretched to a suitable length, insert the fourth bolt 401 into the adjusting hole 501 to fix the transverse connecting beam 4 and the adjusting beam 5. By swinging the first hoop member 2 and the second hoop member 3 to swing along the two groups of adjusting blocks 202, the first hoop member 2 and the second hoop member 3 are opened, and the pier body 1 is clamped into the two groups of the first hoop member 2 and the second hoop member 3. According to the diameter of the pier body 1, the second bolt 203 is adjusted to adjust the two groups of adjusting blocks 202 to a suitable position, the first bolt 201 is adjusted to adjust the length of the first hoop member 2 and the second hoop member 3 to a suitable position, the first hoop member 2 is swung to close the first hoop member 2 and the second hoop member 3, the third bolt 301 is swung to clamp into the first hoop member 2, and the third bolt 301 is screwed to fix the first hoop member 2 and the second hoop member 3 together and clamp the pier body 1.

[0074] Embodiment 2:

[0075] Based on the first embodiment, Figures 1 to 7 As shown, it also includes:

[0076] The tilt prompting component is arranged inside the prompter 6.

[0077] Among them, the tilt prompt component includes:

[0078] A tilt detection plumb bob 603, which swings at the bottom of the adjustment beam 5;

[0079] A second spring 605, the second spring 605 is fixedly installed inside the prompter 6;

[0080] The trigger plate 604 is fixedly mounted on one end of the second spring 605; its function is that the tilt detection plumb 603 always points downward under the action of gravity. When the adjustment beam 5 tilts, the tilt detection plumb 603 squeezes the trigger plate 604 and moves the trigger plate 604, and the trigger plate 604 moves to compress the second spring 605.

[0081] Among them, the tilt prompt component also includes:

[0082] A trigger switch 606, the trigger switch 606 is fixedly installed inside the prompter 6;

[0083] A speaker box 601, which is fixedly mounted on both sides of the prompter 6;

[0084] The prompt mechanism 602 is fixedly installed inside the speaker box 601. The prompt mechanism 602 and the trigger switch 606 are connected in series through wires to form a switch circuit. The trigger plate 604 moves and squeezes the trigger switch 606. The trigger switch 606 makes the prompt mechanism 602 emit a sound through the switch circuit and warns the staff that the adjustment beam 5 is tilted. The speaker box 601 protects the prompt mechanism 602.

[0085] The specific usage and function of this embodiment are as follows:

[0086] When the first hoop 2 is installed to tilt the transverse connecting beam 4, the tilt detection plumb bob 603 swings and squeezes the trigger plate 604 to move the trigger plate 604, and the trigger plate 604 moves to compress the second spring 605, and the trigger plate 604 moves to squeeze the trigger switch 606. The trigger switch 606 makes the prompt mechanism 602 emit a sound through the switch circuit and warns the staff that the adjustment beam 5 is tilted, and the speaker box 601 protects the prompt mechanism 602. After the staff adjusts the horizontal direction of the transverse connecting beam 4, the second spring 605 drives the trigger plate 604 to reset under the elastic action, so that the trigger switch 606 loses its squeezing, so that the switch circuit is closed and the prompt mechanism 602 is powered off. The second spring 605 also provides a certain supporting force for the trigger plate 604 to prevent the tilt detection plumb bob 603 from swinging when the prompter 6 vibrates or shakes slightly, so that the trigger plate 604 squeezes the trigger switch 606.

Claims

1. A hoop for bridge construction, characterized in that: The hoop member for bridge construction comprises a pier body (1); a first hoop member (2), the first hoop member (2) being arranged outside the pier body (1); a second hoop member (3), the second hoop member (3) being arranged outside the pier body (1); a transverse connecting beam (4), the transverse connecting beam (4) being welded to the right side of the second hoop member (3); an adjusting beam (5), the adjusting beam (5) being slidably connected inside the transverse connecting beam (4); a prompter (6), the prompter (6) being fixedly connected to the bottom of the adjusting beam (5); a connection adjustment component, the connection adjustment component being arranged inside the first hoop member (2); and a tilt prompting component, the tilt prompting component being arranged inside the prompter (6).

2. A hoop for bridge construction as claimed in claim 1, characterized in that: The connection adjustment assembly comprises: an adjustment block (202) and a second bolt (203); the adjustment block (202) is provided in two groups, and the two groups of adjustment blocks (202) are respectively hinged to the ends of the first hoop member (2) and the second hoop member (3); and the second bolt (203) is fixedly installed inside the adjustment block (202).

3. A hoop for bridge construction as claimed in claim 2, characterized in that: The connection adjustment assembly further comprises: a first bolt (201) and a third bolt (301); the first bolt (201) is provided in four groups, two groups of the first bolts (201) are fixedly mounted inside the first hoop member (2), and two groups of the first bolts (201) are fixedly mounted inside the second hoop member (3); and the end of the third bolt (301) is hinged inside the second hoop member (3).

4. A hoop for bridge construction as claimed in claim 2, characterized in that: The connection adjustment component further comprises: a limit block (204), a pull rod (205) and a first spring (206); the limit block (204) is slidably connected inside the first hoop member (2); the pull rod (205) is fixedly connected inside the limit block (204); the pull rod (205) is slidably connected inside the first hoop member (2); and the first spring (206) is fixedly mounted on the outside of the pull rod (205).

5. A hoop for bridge construction as claimed in claim 2, characterized in that: The connection adjustment assembly further comprises: an adjustment hole (501) and a fourth bolt (401); the adjustment hole (501) is opened inside the adjustment beam (5); and the fourth bolt (401) is fixedly installed inside the transverse connection beam (4).

6. A hoop for bridge construction as claimed in claim 1, characterized in that: The tilt prompting assembly comprises: a tilt detection plumb (603), a second spring (605) and a trigger plate (604); the tilt detection plumb (603) swings at the bottom of the adjustment beam (5); the second spring (605) is fixedly mounted inside the prompter (6); and the trigger plate (604) is fixedly mounted on one end of the second spring (605).

7. A hoop for bridge construction as claimed in claim 6, characterized in that: The tilt prompting assembly further comprises: a trigger switch (606), a speaker box (601) and a prompting mechanism (602); the trigger switch (606) is fixedly mounted inside the prompter (6); the speaker box (601) is fixedly mounted on both sides of the prompter (6); the prompting mechanism (602) is fixedly mounted inside the speaker box (601); the prompting mechanism (602) and the trigger switch (606) are connected in series via an electric wire to form a switch circuit.

Citation Information

Patent Citations

  • Hoop piece for bridge construction and bridge construction device

    CN212294370U