Recyclable concrete precast slab foundation for building entrance exit passageway

By designing a turnaroundable concrete prefabricated slab foundation, using the combination of multiple prefabricated slabs and detachable connecting components, the problems of extended opening time and inability to turnover and use caused by on-site casting are solved, and the effects of cost saving and time reduction are achieved.

CN222557369UActive Publication Date: 2025-03-04CHINA CONSTRUCTION THIRD BUREAU URBAN CONSTRUCTION CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421233118.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-31
Publication Date
2025-03-04
Estimated Expiration
2034-05-31

AI Technical Summary

Technical Problem

In the prior art, the method of on-site casting is used to produce concrete prefabricated slab foundations, resulting in the extended opening time and the inability to turnover and use of concrete prefabricated slab foundations.

Method used

A turnover concrete prefabricated plate foundation for safety passage into the building was designed. Through the assembly of multiple prefabricated plates and the use of detachable connecting components, multiple turnover and use of prefabricated plates are achieved.

Benefits of technology

The problem of extended opening time and inability to use prefabricated board foundations is solved, cost savings, shortening the time for on-site opening, and simplifying the structure and reducing manufacturing costs through the dual functions of the second connecting component.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222557369U_ABST
    Figure CN222557369U_ABST
Patent Text Reader

Abstract

The utility model provides a turnover concrete precast slab foundation for a building entrance exit passageway. Comprising a plurality of precast slabs which are respectively distributed along a first direction and a second direction; the first connecting assembly is arranged between the two adjacent prefabricated slabs in the first direction and used for detachably connecting the two adjacent prefabricated slabs in the first direction; the second connecting assembly is arranged between the two adjacent prefabricated slabs in the second direction and used for detachably connecting the two adjacent prefabricated slabs in the second direction; wherein the second connecting assembly serves as a hoisting piece and is used for hoisting a single prefabricated slab. The turnover concrete precast slab foundation is formed by assembling a plurality of precast slabs. In this way, repeated turnover use is facilitated, the problems that in the prior art, due to the fact that concrete prefabricated slab foundations are manufactured in a cast-in-place mode, the traffic time is prolonged, and turnover use cannot be achieved are solved, cost is saved, and the on-site traffic time is shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building processing equipment, in particular to a rotatable prefabricated concrete slab foundation for a building safety passage. Background Art

[0002] With the development of modern construction industry, various places and enterprises have put forward higher and higher requirements and standards for safe and civilized construction. As an indispensable part of on-site safety and civilization, the importance of building safety passage is self-evident. Building safety passage is not only a safety guarantee passage for construction site workers to enter and exit the building, but also an important way for small working vehicles, machinery and materials to enter the building. In the past construction process, the foundation of the safety passage often adopts on-site concrete construction. This method has two main disadvantages. First, cast-in-place concrete construction requires manual formwork, steel bar binding, concrete pouring and other processes. After pouring, it usually takes more than a few days for the concrete to be strong enough to allow vehicles to pass, so the efficiency is low; second, at the end of construction, the foundation of the on-site safety passage can only be used once, and it needs to be broken after the construction is completed. Not only can it not be turned over, but it will also generate a lot of demolition and construction waste removal costs, which is relatively wasteful and not economical.

[0003] That is to say, the existing technology of using on-site casting to make the concrete precast slab foundation easily leads to the problem of prolonged traffic time and the inability to recycle the concrete precast slab foundation. Utility Model Content

[0004] In order to solve the above technical problems, the utility model provides a rotatable precast concrete slab foundation for a safe passage into a building, which solves the problems of prolonged traffic time and inability to rotatably use the precast concrete slab foundation caused by on-site casting of the precast concrete slab foundation.

[0005] The utility model provides a turnable prefabricated concrete slab foundation for a building safety passage, comprising: a plurality of prefabricated slabs, which are respectively distributed along a first direction and a second direction; and

[0006] a first connecting assembly, which is disposed between two adjacent prefabricated panels along a first direction and is used to detachably connect the two adjacent prefabricated panels in the first direction; and

[0007] A second connecting assembly is disposed between two adjacent prefabricated panels along a second direction and is used to detachably connect the two adjacent prefabricated panels in the second direction;

[0008] The second connecting assembly is used as a lifting component for lifting a single prefabricated panel.

[0009] In one embodiment, the first connection component includes:

[0010] A first PVC sleeve, which is pre-buried in one of the two adjacent prefabricated panels; and

[0011] A second PVC sleeve, which is embedded in another prefabricated panel; and

[0012] One end of the first connecting piece is inserted into the first PVC sleeve, and the other end of the first connecting piece is inserted into the second PVC sleeve.

[0013] In one embodiment, the first connecting member is a U-shaped steel pipe, and two open ends of the U-shaped steel pipe are respectively inserted into the first PVC sleeve and the second PVC sleeve.

[0014] In one embodiment, the number of the first connecting components is one or more. When the number of the first connecting components is plural, the plurality of first connecting components are spaced apart along the second direction.

[0015] In one embodiment, a portion of the second connection assembly is embedded in one of two adjacent prefabricated panels, and another portion of the second connection assembly is plug-fitted with the other prefabricated panel.

[0016] In one embodiment, the second connection component includes:

[0017] A first connecting section, one end of which is embedded in one of two adjacent prefabricated panels, and the other end of which extends out of the prefabricated panel; and

[0018] A second connecting section, one end of which is embedded in one of two adjacent prefabricated panels, and the other end of which extends out of the prefabricated panel; and

[0019] a convex section, one end of which is connected to the other end of the first connecting section, and the other end of the convex section is connected to the other end of the second connecting section;

[0020] The raised section protrudes in a direction away from one of the two adjacent prefabricated panels, the other prefabricated panel is provided with a hanging ring groove, and the other end of the first connecting section, the other end of the second connecting section and the raised section are inserted into the hanging ring groove of the other prefabricated panel.

[0021] In one embodiment, the first connecting section and the second connecting section have the same structure and are arranged opposite to each other in the first direction.

[0022] In one embodiment, the first connecting section and the second connecting section are L-shaped.

[0023] In one embodiment, the raised section is a U-shaped ring, and two open ends of the U-shaped ring are respectively connected to the first connecting section and the second connecting section.

[0024] In one embodiment, the second connecting component is configured as an integral bent tube formed by bending a round tube, and / or the first connecting component is configured as an integral bent tube formed by bending a round tube.

[0025] Compared with the prior art, the beneficial effects of the utility model are as follows: the rotatable concrete precast panel foundation is assembled from a plurality of precast panels. This facilitates its multiple turnover use, and avoids the problem of prolonged traffic time and inability to be rotatable caused by the on-site casting method used in the prior art to make the concrete precast panel foundation, thereby saving costs and shortening the time for on-site traffic. In addition, the second connecting component has a dual function, which can detachably connect two adjacent precast panels in the first direction. It can also serve as a lifting piece for a single precast panel, thus avoiding the need to set up a separate component as a lifting piece for the precast panel, thereby simplifying the structure of the rotatable concrete precast panel foundation and saving its manufacturing cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a schematic diagram of the three-dimensional structure of the turnaround precast concrete slab foundation in the embodiment of the utility model;

[0027] Figure 2 for Figure 1 Positioning drawing of embedded parts of precast panels;

[0028] Figure 3 for Figure 1 Reinforcement diagram of precast slab;

[0029] Figure 4 yes Figure 1 Main section view of the turnaround precast concrete slab foundation;

[0030] Figure 5 yes Figure 1 A schematic diagram of a second connected component in ;

[0031] Figure 6 yes Figure 1 Schematic diagram of the first connected component in .

[0032] In the figure: 10, prefabricated board; 11, lifting ring groove; 20, first connecting component; 21, first PVC sleeve; 22, second PVC sleeve; 23, first connecting piece; 30, second connecting component; 31, first connecting section; 32, second connecting section; 33, raised section. DETAILED DESCRIPTION

[0033] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0034] It should be noted that the first direction and the second direction in the present application refer to the length and width directions of the prefabricated board 10 .

[0035] like Figures 1 to 6 As shown, the utility model provides a recyclable concrete precast panel foundation for a building safety passage, and the recyclable concrete precast panel foundation includes a plurality of precast panels 10, a first connecting assembly 20, and a second connecting assembly 30. The plurality of precast panels 10 are distributed along a first direction and a second direction respectively; the first connecting assembly 20 is arranged between two adjacent precast panels 10 along the first direction, and is used to detachably connect the two adjacent precast panels 10 in the first direction; and the second connecting assembly 30 is arranged between two adjacent precast panels 10 along the second direction, and is used to detachably connect the two adjacent precast panels 10 in the second direction; the second connecting assembly 30 is used as a lifting member for lifting a single precast panel 10.

[0036] In the above arrangement, the recyclable concrete precast panel foundation is assembled from a plurality of precast panels 10. This facilitates its multiple recyclable use, and avoids the problem of prolonged traffic time and inability to recycle caused by the on-site pouring method used in the prior art to make the concrete precast panel foundation, thereby saving costs and shortening the time for on-site traffic. In addition, the second connecting assembly 30 has a dual function, which can detachably connect two adjacent precast panels 10 in the first direction. It can also serve as a lifting member for a single precast panel 10, thus avoiding the need to set up a separate component as a lifting member for the precast panel 10, thereby simplifying the structure of the recyclable concrete precast panel foundation and saving its manufacturing cost.

[0037] Specifically, Figures 1 to 6 As shown, in one embodiment, the first connection assembly 20 includes a first PVC sleeve 21, a second PVC sleeve 22 and a first connector 23. The first PVC sleeve 21 is pre-buried in one of the two adjacent precast panels 10; the second PVC sleeve 22 is pre-buried in the other precast panel 10; one end of the first connector 23 is plugged into the first PVC sleeve 21, and the other end of the first connector 23 is plugged into the second PVC sleeve 22. Thus, the detachable connection of the turnover concrete precast panel foundation in the first direction is realized.

[0038] Specifically, Figures 1 to 6 As shown, in one embodiment, the first connecting member 23 is a U-shaped steel pipe, and two open ends of the U-shaped steel pipe are respectively inserted into the first PVC sleeve 21 and the second PVC sleeve 22.

[0039] Specifically, Figures 1 to 6 As shown, in one embodiment, there are multiple first connection assemblies 20, and the multiple first connection assemblies 20 are arranged at intervals along the second direction. This enhances the overall connection strength of the turnaround precast concrete slab foundation.

[0040] Specifically, Figures 1 to 6 As shown, in one embodiment, the number of the first connecting components 20 is two, and the two first connecting components 20 are arranged at intervals along the second direction.

[0041] Of course, the specific number of the first connecting components 20 can be adjusted according to actual conditions.

[0042] Specifically, Figures 1 to 6 As shown, in one embodiment, a portion of the second connection assembly 30 is embedded in one of two adjacent prefabricated panels 10 , and another portion of the second connection assembly 30 is plug-fitted with the other prefabricated panel 10 .

[0043] Specifically, Figures 1 to 6 As shown, in one embodiment, the second connection assembly 30 includes a first connection section 31, a second connection section 32 and a protruding section 33. Among them, the first connection section 31, one end of which is pre-buried in one of the two adjacent prefabricated panels 10, and the other end of the first connection section 31 extends out of the prefabricated panel 10; the second connection section 32, one end of which is pre-buried in one of the two adjacent prefabricated panels 10, and the other end of the second connection section 32 extends out of the prefabricated panel 10; the protruding section 33, one end of which is connected to the other end of the first connection section 31, and the other end of the protruding section 33 is connected to the other end of the second connection section 32; the protruding section 33 protrudes in a direction away from one of the two adjacent prefabricated panels 10, and the other prefabricated panel 10 is provided with a hanging ring groove 11, and the other end of the first connection section 31, the other end of the second connection section 32 and the protruding section 33 are inserted into the hanging ring groove 11 of the other prefabricated panel 10.

[0044] Specifically, Figures 1 to 6 As shown, in one embodiment, the first connecting section 31 and the second connecting section 32 have the same structure and are arranged opposite to each other in the first direction.

[0045] Specifically, Figures 1 to 6 As shown, in one embodiment, the first connecting section 31 and the second connecting section 32 are L-shaped.

[0046] Specifically, Figures 1 to 6 As shown, in one embodiment, the raised section 33 is a U-shaped ring, and two open ends of the U-shaped ring are respectively connected to the first connecting section 31 and the second connecting section 32 .

[0047] Specifically, Figures 1 to 6 As shown, in one embodiment, the second connecting assembly 30 is constructed as an integral bent tube formed by bending a round tube.

[0048] Specifically, Figures 1 to 6 As shown, in one embodiment, the first connecting assembly 20 is constructed as an integral bent tube formed by bending a round tube.

[0049] It should be noted that the prefabricated main body foundation plate (prefabricated plate 10), as the main body of the safety channel concrete prefabricated plate foundation, has a rectangular cross-section and mainly bears the upper load of the safety channel; the special lifting ring (second connecting component) is embedded in the prefabricated main body foundation plate and is used for lifting work during the turnover process; the U-shaped plate connector (first connecting component) cooperates with the reserved PVC sleeve on the prefabricated main body foundation plate as a detachable and turnover temporary fixing device, which is used to connect and fix adjacent safety channel concrete prefabricated plate foundations; the protruding part of the special lifting ring can penetrate into the groove of the lifting ring to ensure a tight connection, and at the same time play a role in fixing adjacent plates.

[0050] Specifically, the foundation of the recyclable concrete precast slab is prefabricated in a factory or construction site. After completion, it is transported to the designated location through a safe passage by vehicles and assembled in place using a lifting and hoisting machine. The process is: leveling the ground of the prefabrication site → supporting the formwork → tying the steel bars → installing the embedded parts → pouring the concrete → curing → removing the formwork.

[0051] Before installing the rotatable precast concrete slab foundation for the safe entrance to the building in this application, the foundation must be leveled and compacted, and the overall drainage design slope on site must be verified. The ring knife method must be used to test the foundation bearing capacity to ensure that the foundation elastic modulus is ≥40Mpa.

[0052] The recyclable precast concrete slab foundation of the building entrance safety passage of this application should be used in combination of multiple pieces, which can be combined according to the actual length and width of the safety passage required on site. The modulus of a single recyclable precast concrete slab foundation of the building entrance safety passage is 2m long and 1.5m wide, which can be spliced ​​and combined into safety passages of different sizes such as 2m×3m, 4m×6m, 7.5m×10m, etc. The specific size of the anti-smashing shed of the upper safety passage can also be combined as its column foundation, and the anti-smashing shed of the safety passage can be fixed to the foundation with expansion bolts, etc.

[0053] During installation, first locate and lay out the position of the prefabricated main body foundation plate, and then hoist and secure each prefabricated main body foundation plate from one side to the other. The special hoisting ring and the hoisting ring groove are interlocked in sequence. After all the plates are hoisted into place, install the U-shaped plate connector to connect the prefabricated main body foundation plates into a whole.

[0054] When dismantling, first remove the U-shaped plate connector, and then lift and remove the prefabricated main foundation plate from one side to the other.

[0055] In the present invention, the terms "first", "second", and "third" are used for descriptive purposes only and should not be understood as indicating or implying relative importance; the term "plurality" refers to two or more, unless otherwise clearly defined. The terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; "connected" can be a direct connection or an indirect connection through an intermediate medium. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.

[0056] In the description of the present invention, it is necessary to understand that the directions or positional relationships indicated by terms such as "up", "down", "left", "right", "front" and "back" are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or unit referred to must have a specific direction, be constructed and operated in a specific orientation, and therefore, cannot be understood as a limitation on the present invention.

[0057] In the description of this specification, the description of the terms "one embodiment", "some embodiments", "specific embodiments", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0058] The above are only preferred implementations of the utility model. The protection scope of the utility model is not limited to the above embodiments. All technical solutions under the idea of ​​the utility model belong to the protection scope of the utility model. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the utility model should also be regarded as the protection scope of the utility model.

Claims

1. A recyclable prefabricated concrete slab foundation for a building safety passage, characterized in that: include: A plurality of prefabricated panels (10), which are distributed along a first direction and a second direction respectively; as well as A first connecting assembly (20) is arranged between two adjacent prefabricated panels (10) along a first direction and is used to detachably connect the two adjacent prefabricated panels (10) in the first direction; as well as A second connecting assembly (30) is arranged between two adjacent prefabricated panels (10) along a second direction and is used to detachably connect the two adjacent prefabricated panels (10) in the second direction; The second connecting assembly (30) is used as a lifting component for lifting a single prefabricated panel (10).

2. The recyclable prefabricated concrete slab foundation for a building safety passage according to claim 1 is characterized in that: The first connecting component (20) comprises: a first PVC sleeve (21), which is pre-buried in one of the two adjacent prefabricated panels (10); and A second PVC sleeve (22) pre-buried in another of the prefabricated panels (10); and One end of the first connecting piece (23) is inserted into the first PVC sleeve (21), and the other end of the first connecting piece (23) is inserted into the second PVC sleeve (22).

3. The recyclable prefabricated concrete slab foundation for a building safety passage according to claim 2 is characterized in that: The first connecting member (23) is a U-shaped steel pipe, and the two open ends of the U-shaped steel pipe are respectively inserted into the first PVC sleeve (21) and the second PVC sleeve (22).

4. The recyclable prefabricated concrete slab foundation for a building safety passage according to claim 1 is characterized in that: The number of the first connecting components (20) is one or more. When the number of the first connecting components (20) is plural, the plurality of first connecting components (20) are arranged at intervals along the second direction.

5. The recyclable prefabricated concrete slab foundation for a building safety passage according to any one of claims 1 to 4, characterized in that: A portion of the second connection component (30) is pre-buried in one of the two adjacent prefabricated panels (10), and another portion of the second connection component (30) is plug-fitted into the other prefabricated panel (10).

6. The recyclable prefabricated concrete slab foundation for a building safety passage according to claim 5, characterized in that: The second connecting component (30) comprises: A first connecting section (31), one end of which is embedded in one of the two adjacent prefabricated panels (10), and the other end of the first connecting section (31) extends out of the prefabricated panel (10); and A second connecting section (32), one end of which is embedded in one of the two adjacent prefabricated panels (10), and the other end of the second connecting section (32) extends out of the prefabricated panel (10); and a convex section (33), one end of which is connected to the other end of the first connecting section (31), and the other end of the convex section (33) is connected to the other end of the second connecting section (32); The raised section (33) is raised in a direction away from one of the two adjacent prefabricated panels (10), the other prefabricated panel (10) is provided with a hanging ring groove (11), and the other end of the first connecting section (31), the other end of the second connecting section (32) and the raised section (33) are inserted into the hanging ring groove (11) of the other prefabricated panel (10).

7. The recyclable prefabricated concrete slab foundation for a building safety passage according to claim 6, characterized in that: The first connecting section (31) and the second connecting section (32) have the same structure and are arranged opposite to each other in a first direction.

8. The recyclable prefabricated concrete slab foundation for a building safety passage according to claim 7, characterized in that: The first connecting section (31) and the second connecting section (32) are L-shaped.

9. The recyclable prefabricated concrete slab foundation for a building safety passage according to claim 8, characterized in that: The raised section (33) is a U-shaped ring, and two open ends of the U-shaped ring are respectively connected to the first connecting section (31) and the second connecting section (32).

10. The recyclable prefabricated concrete slab foundation for a building safety passage according to claim 6, characterized in that: The second connection component (30) is constructed as an integral bent tube formed by bending a round tube, and / or the first connection component (20) is constructed as an integral bent tube formed by bending a round tube.