By welding the ring plate and cow legs on the outer surface of the column empty steel pipe in bridge construction, and setting an oblique support ramp on the cow legs, the problems of operation difficulties, waste of materials and difficulty in controlling the accuracy at the docking of the column empty steel pipes in the column are solved, and a more efficient and safe construction process is achieved.

CN222557456UActive Publication Date: 2025-03-04ROAD & BRIDGE SOUTH CHINA ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421217572.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-30
Publication Date
2025-03-04
Estimated Expiration
2034-05-30

AI Technical Summary

Technical Problem

In bridge construction, there are problems such as operational difficulties, waste of materials and difficulty in controlling accuracy at the docking of the inclined braces and column empty steel pipes.

Method used

By welding the ring plate and the cow leg on the outer surface of the column empty steel pipe and setting an oblique support ramp on the cow leg, the docking between the oblique support and the column empty steel pipe is achieved, and concrete is avoided in the steel pipe.

Benefits of technology

This solution improves the safety and efficiency of the docking of the oblique braces with column empty steel pipes, reduces construction costs, simplifies operations, reduces material waste, and reduces the requirements for accuracy control.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222557456U_ABST
    Figure CN222557456U_ABST
Patent Text Reader

Abstract

The utility model provides an inclined strut and stand column empty steel pipe butt joint structure which comprises an inclined strut and a stand column empty steel pipe which are in butt joint with each other, an annular plate is arranged at the position, in butt joint with the inclined strut, of the stand column empty steel pipe, a bracket used for being connected with the inclined strut is arranged on the annular plate, and the end face, connected with the bracket, of the inclined strut is a flush section. The annular plate and the bracket are welded to the outer surface of the stand column hollow steel pipe to achieve connection with the inclined strut, the bearing capacity is good, operation is easy, concrete does not need to be poured in the stand column hollow steel pipe, turnover of the stand column hollow steel pipe is not affected, the mass of the stand column hollow steel pipe increased by the welded annular plate and bracket can be ignored, and the cost is low. The structure loss of the hollow steel pipe of the stand column is small, the requirement for on-site precision control is low, and the on-site butt joint quality and efficiency are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of bridge construction, and in particular to a structure for butting diagonal braces and column hollow steel pipes. Background Art

[0002] During the construction of bridges, it is usually necessary to connect the diagonal brace with the empty steel pipe of the column to meet the construction requirements. At the local joint between the diagonal brace and the empty steel pipe of the column, in order to prevent the deformation and damage of the steel pipe in the column hole, concrete is usually poured in the empty steel pipe of the column, but there are the following defects:

[0003] (1) The joint between the diagonal brace and the column empty steel pipe is usually located in the middle of the steel pipe, so it is necessary to pour about 1-2m of concrete in the middle of the steel pipe, which is difficult to operate;

[0004] (2) Pouring concrete on a part of the steel pipe increases the weight of the steel, making it inconvenient to turn around and resulting in a waste of materials;

[0005] (3) In order to adapt to the connection with the column, the connecting end of the diagonal brace and the column needs to be cut into a groove to dock with the column, which requires high precision and is difficult to operate on site. Utility Model Content

[0006] The purpose of the present application is to provide a diagonal brace and column hollow steel pipe docking structure which has a simple structure and is convenient to construct.

[0007] In order to achieve the above objectives, this application provides the following technical solutions:

[0008] A diagonal brace and column empty steel pipe docking structure, comprising a diagonal brace and a column empty steel pipe docked with each other, wherein the column empty steel pipe is provided with a ring plate at the docking position with the diagonal brace, and the ring plate is provided with a corbel for connecting with the diagonal brace, and the end surface of the diagonal brace connected with the corbel is a flush section.

[0009] It is further arranged that: two ring plates are arranged along the axial direction of the hollow steel pipe of the column, and the corbel is fixed between the two ring plates.

[0010] It is further arranged that the corbel comprises at least two corbel plates arranged in parallel, and the corbel plates are fully welded to the ring plate.

[0011] It is further arranged that: the corbel is provided with a diagonal brace groove for connecting with the diagonal brace, and the slope of the diagonal brace groove is the tangent value of the angle between the diagonal brace and the hollow steel pipe of the column.

[0012] It is further arranged that a stiffening plate is provided between the diagonal brace and the diagonal brace groove of the corbel.

[0013] It is further arranged that the stiffening plate is located on the outer side of the diagonal brace away from the hollow steel pipe of the column.

[0014] Further configuration: the thickness of the stiffening plate is in the range of 1-2 cm.

[0015] Further configuration: the inner side of the ring plate and the outer side wall of the column hollow steel pipe are fully welded.

[0016] It is further configured that the thickness of the ring plate ranges from 1 to 2 cm.

[0017] Compared with the prior art, the solution of this application has the following advantages:

[0018] 1. The butt joint structure of the diagonal brace and the column empty steel pipe involved in the present application realizes the connection with the diagonal brace by welding ring plates and corbels on the outer surface of the column empty steel pipe. It has good bearing capacity and simple operation. There is no need to pour concrete in the column empty steel pipe, which does not affect the turnover of the column empty steel pipe. The mass added to the column empty steel pipe by the welded ring plates and corbels can be ignored, the structural loss of the column empty steel pipe is small, the requirements for on-site precision control are low, and the on-site butt joint quality and efficiency are improved.

[0019] 2. In the diagonal brace and column hollow steel pipe docking structure involved in the present application, by setting the diagonal brace bevel on the corbel, the end face of the diagonal brace can be set to a flush section to connect with the corbel, which is easy to operate, can reduce the cutting accuracy of the diagonal brace, and improve construction efficiency.

[0020] 3. In the diagonal brace and column empty steel pipe docking structure involved in the present application, by arranging a stiffening plate between the diagonal brace groove of the corbel and the diagonal brace, the connection strength between the corbel and the diagonal brace is improved, thereby improving the connection stability between the diagonal brace and the column empty steel pipe.

[0021] Additional aspects and advantages of the present application will be partially given in the following description, which will become apparent from the following description, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:

[0023] Figure 1 This is an elevation view of an embodiment of the diagonal brace and column hollow steel pipe docking structure of the present application;

[0024] Figure 2 This is a cross-sectional view of an embodiment of the hollow steel pipe docking structure of the diagonal brace and the column of the present application.

[0025] In the figure, 1. Empty steel pipe for column; 2. Diagonal brace; 3. Ring plate; 4. Corbel; 5. Stiffening plate. DETAILED DESCRIPTION

[0026] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present application, and cannot be interpreted as limiting the present application.

[0027] Those skilled in the art will appreciate that, unless specifically stated, the "said" and "the" used herein may also include plural forms. It should be further understood that the term "including" used in the specification of the present application refers to the presence of the features, parts and / or components, but does not exclude the implementation of other features, parts, components and / or their combinations supported by the technical field. The term "and / or" used herein refers to at least one of the items defined by the term, for example, "A and / or B" can be implemented as "A", or as "B", or as "A and B".

[0028] In the description of the present application, the directions or positional relationships indicated by words such as "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" are based on the exemplary directions or positional relationships shown in the accompanying drawings. They are for the convenience of describing or simplifying the description of the embodiments of the present application, and do not indicate or imply that the referred device or component must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be understood as limitations on the present application.

[0029] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, unless otherwise specified, "plurality" means two or more.

[0030] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0031] In the description of this specification, specific features, structures, materials or characteristics may be combined in any one or more embodiments or examples in a suitable manner. To make the purpose, technical solution and advantages of this application clearer, the implementation mode of this application will be further described in detail below in conjunction with the accompanying drawings.

[0032] Aiming at the problem that the joint between the diagonal brace 2 and the column hollow steel pipe 1 is prone to deformation, the present application discloses a joint structure between the diagonal brace 2 and the column hollow steel pipe 1. Figure 1 and Figure 2 , which can improve the safety of the joint between the diagonal brace 2 and the column empty steel pipe 1, reduce construction costs and improve construction efficiency.

[0033] The diagonal brace 2 and the column hollow steel pipe 1 docking structure of the present application includes a diagonal brace 2 and a column hollow steel pipe 1 docked with each other, the column hollow steel pipe 1 is provided with a ring plate 3 at the docking place with the diagonal brace 2, and a corbel 4 extending outward away from the column hollow steel pipe 1 is provided on one side of the ring plate 3, and the corbel 4 is used to connect with the diagonal brace 2, so as to achieve the docking between the diagonal brace 2 and the column hollow steel pipe 1, and there is no need to pour concrete inside the column hollow steel pipe 1 to prevent the deformation of the steel pipe, and the operation is simple. In addition, the end face of the diagonal brace 2 connected with the corbel 4 is a flush section, and the diagonal brace 2 is directly connected to the corbel 4 through its flush section, and there is no need to cut the end face of the diagonal brace 2 into a groove matching the column hollow steel pipe 1, which reduces the cutting accuracy of the diagonal brace 2 and makes the on-site construction quality easy to control.

[0034] It should be noted that the flush section is usually the cross-section of the steel pipe. The end face of the steel pipe is usually set as a flush end face when it leaves the factory for easy construction. However, the connection method between the conventional diagonal brace and the column requires that the end of the diagonal brace be set to a bevel section that fits the surface of the column, which requires further processing of the end of the steel pipe, and the required precision is high and difficult to control.

[0035] The ring plate 3 can be directly sleeved on the column empty steel pipe 1, or the ring plate 3 adopts a petal structure, and the workers can directly splice the ring plate 3 on the column empty steel pipe 1 to adapt to different construction scenes. The inner side of the ring plate 3 and the outer side wall of the column empty steel pipe 1 are fully welded. The inner diameter of the ring plate 3 in this embodiment is equal to or slightly larger than the outer diameter of the column empty steel pipe 1 to be constructed, and the thickness of the ring plate 3 ranges from 1 to 2 cm, so that the ring plate 3 can strengthen the local bearing capacity of the column empty steel pipe 1 while avoiding adding too much weight to the column empty steel pipe 1.

[0036] The ring plate 3 of the present application is provided with two upper and lower pieces along the axial direction of the column hollow steel tube 1, and the corbel 4 is fixed between the upper and lower ring plates 3. The corbel 4 includes at least two parallel corbel plates, which are provided in the vertical direction, and the upper and lower sides of the corbel plates are fully welded to the upper and lower ring plates 3 respectively. In this embodiment, three corbel plates are provided in parallel, and the diagonal brace 2 is supported by the three corbel plates, which can meet the support requirements for the diagonal brace 2.

[0037] The corbel 4 is provided with a diagonal brace groove for connecting with the diagonal brace 2. The slope of the diagonal brace groove is the tangent value of the angle between the diagonal brace 2 and the empty steel pipe 1 of the column. The slope of the diagonal brace groove can be adjusted to achieve the diagonal brace 2 and the empty steel pipe 1 of the column through the flush section, thereby reducing the cutting accuracy requirements of the diagonal brace 2 and making it easy to control the on-site construction quality.

[0038] Furthermore, a stiffening plate 5 is provided between the diagonal brace 2 and the diagonal brace groove of the corbel 4. The stiffening plate 5 is located on the outer side of the diagonal brace 2 away from the column hollow steel tube 1. The stiffening plate 5 enhances the connection strength between the diagonal brace 2 and the corbel 4, and improves the connection stability between the diagonal brace 2 and the column hollow steel tube 1. In this embodiment, the thickness of the stiffening plate 5 ranges from 1 to 2 cm. While the diagonal brace 2 and the corbel 4 are connected by the stiffening plate 5 to improve the connection strength, it also avoids adding too much weight to the column hollow steel tube 1 by providing the stiffening plate 5.

[0039] During the construction of the butt joint structure of the diagonal brace 2 and the column empty steel pipe 1 of the present embodiment, the column empty steel pipe 1 is installed first, and then the upper and lower ring plates 3 are welded at the joint position where the column empty steel pipe 1 needs to be butt jointed with the diagonal brace 2, the corbel 4 is welded between the two ring plates 3, and the slope of the diagonal brace groove of the corbel 4 is adjusted, the diagonal brace 2 profile is cut, and welded to the diagonal brace groove of the installed corbel 4, thereby completing the butt joint of the diagonal brace 2 and the column empty steel pipe 1.

[0040] Alternatively, in other embodiments, the ring plate 3 and the corbel 4 may be pre-spliced ​​first, and then the column hollow steel pipe 1 and the diagonal brace 2 may be installed according to the structure formed by the spliced ​​ring plate 3 and the corbel 4 .

[0041] In summary, the butt joint structure of the diagonal brace 2 and the column empty steel pipe 1 of the present application realizes the connection with the diagonal brace 2 by welding the ring plate 3 and the corbel 4 on the outer surface of the column empty steel pipe 1. It has good bearing capacity and simple operation. There is no need to pour concrete in the column empty steel pipe 1, and the turnover of the column empty steel pipe 1 is not affected. The added mass of the column empty steel pipe 1 by the welded ring plate 3 and the corbel 4 can be ignored, the structural loss of the column empty steel pipe 1 is small, the requirements for on-site precision control are low, and the on-site docking quality and efficiency are improved.

[0042] The above description is only a partial implementation method of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present application. These improvements and modifications should also be regarded as the scope of protection of the present application.

Claims

1. A diagonal brace and column empty steel pipe docking structure, comprising a diagonal brace and a column empty steel pipe docking with each other, characterized in that: The hollow steel pipe of the column is provided with a ring plate at the joint between it and the diagonal brace, and the ring plate is provided with a corbel for connecting with the diagonal brace, and the end surface of the diagonal brace connecting with the corbel is a flush section.

2. The diagonal brace and column hollow steel pipe docking structure according to claim 1 is characterized in that: Two ring plates are arranged along the axial direction of the hollow steel pipe of the column, and the corbel is fixed between the two ring plates.

3. The hollow steel pipe docking structure of the diagonal brace and column according to claim 2 is characterized in that: The corbel comprises at least two corbel plates arranged in parallel, and the corbel plates are fully welded to the ring plate.

4. The diagonal brace and column hollow steel pipe docking structure according to claim 2 is characterized in that: The corbel is provided with a diagonal brace groove for connecting with the diagonal brace, and the slope of the diagonal brace groove is the tangent value of the angle between the diagonal brace and the hollow steel pipe of the column.

5. The diagonal brace and column hollow steel pipe docking structure according to claim 4 is characterized in that: A stiffening plate is provided between the diagonal brace and the diagonal brace groove of the corbel.

6. The hollow steel pipe docking structure of diagonal braces and columns according to claim 5 is characterized in that: The stiffening plate is located on the outer side of the diagonal brace away from the hollow steel pipe of the column.

7. The hollow steel pipe docking structure of the diagonal brace and the column according to claim 6 is characterized in that: The thickness of the stiffening plate ranges from 1 to 2 cm.

8. The diagonal brace and column hollow steel pipe docking structure according to claim 1 is characterized in that: The inner side of the ring plate and the outer side wall of the column hollow steel pipe are fully welded.

9. The hollow steel pipe docking structure of diagonal braces and columns according to claim 1 is characterized in that: The thickness of the ring plate ranges from 1 to 2 cm.