Hanging basket for building construction
By designing U-shaped plates, rotating wheels and multi-layer buffer components in the hanging basket for construction, the problem of hard collision between the hanging basket and the wall under strong windy weather or external force is solved, and the flexible offset between the hanging basket and the wall is achieved, reducing vibration force and improving safety.
Patent Information
- Application Number
- CN202421395027.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-18
- Publication Date
- 2025-03-11
- Estimated Expiration
- 2034-06-18
AI Technical Summary
The hanging basket is prone to shake under strong windy weather or external force, resulting in hard collision with the wall, causing damage to the hanging basket and walls, and affecting the safety of the staff.
A hanging basket for construction is designed, adopting a combined structure of U-shaped plate and a rotating wheel, and providing multi-layer cushion protection through the first buffer assembly and the second buffer assembly to prevent the hanging basket body from directly opposing the wall.
Through the design of the rotating wheel and buffer assembly, flexible offset between the hanging basket body and the wall is achieved, reducing vibration force, reducing damage to the hanging basket and wall, and improving staff safety.
Smart Images

Figure CN222595490U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of building construction tools, and specifically relates to a hanging basket for building construction. Background Art
[0002] During the use of the hanging basket, if it is affected by strong winds or external forces, it is easy to cause the hanging basket to shake, and the shaking hanging basket will collide hard with the wall. Under the action of the hard collision, not only the hanging basket and the wall will be damaged, but also the personnel working in the hanging basket will be vibrated, thus affecting the safety of the personnel in the hanging basket.
[0003] In view of this, the present utility model is proposed. Utility Model Content
[0004] In order to solve the above technical problems, the basic concept of the technical solution adopted by the utility model is:
[0005] A hanging basket for construction includes a hanging basket body and a U-shaped plate arranged on the side of the hanging basket body close to the wall, wherein the U-shaped plate is connected to a rotating wheel via a rotating shaft, and the hanging basket body is provided with a first buffer component and a second buffer component for performing multi-level buffering on the rotating wheel.
[0006] There are four rotating wheels, and the four rotating wheels are symmetrically arranged in pairs.
[0007] The first buffer assembly includes two groups of fixed plates fixedly connected to one side of the hanging basket body close to the rotating wheel, each of which is symmetrically arranged. A fixed rod is fixedly connected between the two fixed plates on the same side. The two fixed rods are slidably connected to sliding plates. The two sliding plates are rotatably connected to rotating plates on the side close to the rotating wheel. The other ends of the two rotating plates are rotatably connected to the U-shaped plate. Two first springs are provided on the side walls of the two fixed rods.
[0008] One opposite end of the two first springs located on the same side is connected to the sliding plate, and the other end is connected to the fixed plate.
[0009] The second buffer assembly includes a fixed tube fixedly connected to the side of the hanging basket body close to the rotating wheel, the fixed tube is slidably connected with a buffer rod, one end of the buffer rod is connected to the U-shaped plate, the other end of the buffer rod is located in the fixed tube and fixedly connected to a buffer plate, the side of the buffer plate away from the buffer rod is fixedly connected to a second spring, and the other end of the second spring is connected to the bottom wall of the fixed tube.
[0010] The fixed tube is filled with damping fluid, and the buffer plate is provided with a plurality of buffer holes, through which the damping fluid passes.
[0011] Compared with the prior art, the utility model has the following beneficial effects:
[0012] The utility model avoids direct impact between the hanging basket body and the wall by setting the rotating wheel. At the same time, under the action of the first buffer component and the second buffer component, a multi-layer buffer protection is formed for the hanging basket body, so that the hanging basket body and the wall are flexibly impacted, thereby reducing the vibration force generated when the hanging basket body collides with the wall when affected by strong winds or external forces, thereby reducing damage to the hanging basket body and the wall and improving the safety of the staff in the hanging basket body.
[0013] The specific implementation of the utility model is further described in detail below with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] In the attached picture:
[0015] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0016] Figure 2 This is a schematic diagram of the internal structure of the second buffer component of the utility model;
[0017] Figure 3 for Figure 2 Enlarged view of point A in the middle.
[0018] In the figure: 1, hanging basket body; 2, U-shaped plate; 3, rotating shaft; 4, rotating wheel; 501, fixed plate; 502, fixed rod; 503, sliding plate; 504, rotating plate; 505, first spring; 601, fixed tube; 602, buffer rod; 603, buffer plate; 604, second spring; 605, buffer hole. DETAILED DESCRIPTION
[0019] In order to make the purpose, technical scheme and advantages of the embodiments of the utility model clearer, the technical scheme in the embodiments will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. The following embodiments are used to illustrate the utility model.
[0020] See also Figure 1-Figure 3 A construction hanging basket shown in the figure includes a hanging basket body 1, and also includes a U-shaped plate 2 arranged on the side of the hanging basket body 1 close to the wall, the U-shaped plate 2 is connected to a rotating wheel 4 through a rotating shaft 3, and the hanging basket body 1 is provided with a first buffer component and a second buffer component for performing multi-level buffering on the rotating wheel 4;
[0021] It should be noted here that: by setting the rotating wheel 4, the direct impact between the hanging basket body 1 and the wall is avoided. At the same time, under the action of the first buffer component and the second buffer component, a multi-layer buffer protection is formed for the hanging basket body 1, so that the hanging basket body 1 and the wall are flexibly impacted, thereby reducing the vibration force generated when the hanging basket body 1 collides with the wall when affected by strong winds or external forces, thereby reducing damage to the hanging basket body 1 and the wall and improving the safety of the staff in the hanging basket body 1.
[0022] See also Figure 2 , there are four rotating wheels 4 in the figure, and the four rotating wheels 4 are symmetrically arranged in pairs;
[0023] It should be noted here that: a more stable and balanced buffering force is provided for the hanging basket body 1 by means of four rotating wheels 4 which are symmetrically arranged in pairs.
[0024] See also Figure 2 and Figure 3 The first buffer assembly shown in the figure includes two groups of fixed plates 501 that are symmetrically arranged in pairs and fixedly connected to the side of the hanging basket body 1 close to the rotating wheel 4, a fixed rod 502 is fixedly connected between the two fixed plates 501 on the same side, the two fixed rods 502 are slidably connected to the sliding plate 503, the two sliding plates 503 are rotatably connected to the side close to the rotating wheel 4 with the rotating plate 504, the other ends of the two rotating plates 504 are rotatably connected to the U-shaped plate 2, and two first springs 505 are sleeved on the side walls of the two fixed rods 502;
[0025] It should be noted here that: through the provision of the first buffer assembly, the elastic force of the first spring 505 is utilized to form a first layer of buffer protection for the hanging basket body 1.
[0026] See also Figure 2 and Figure 3 , the two first springs 505 located on the same side in the figure have opposite ends connected to the sliding plate 503, and the other ends connected to the fixed plate 501;
[0027] It should be noted here that by limiting the positions of the two ends of the first spring 505 , the first spring 505 is easily deformed by force, thereby forming an elastic force.
[0028] See also Figure 2 and Figure 3The second buffer assembly shown in the figure includes a fixed tube 601 fixedly connected to the side of the hanging basket body 1 close to the rotating wheel 4, the fixed tube 601 is slidably connected with a buffer rod 602, one end of the buffer rod 602 is connected to the U-shaped plate 2, the other end of the buffer rod 602 is located in the fixed tube 601 and is fixedly connected with a buffer plate 603, the side of the buffer plate 603 away from the buffer rod 602 is fixedly connected with a second spring 604, and the other end of the second spring 604 is connected to the bottom wall of the fixed tube 601;
[0029] It should be noted that: through the provision of the second buffer assembly, under the elastic action of the second spring 604, a second layer of buffer protection is formed for the hanging basket body 1.
[0030] See also Figure 2 and Figure 3 The fixed tube 601 shown in the figure is filled with damping fluid, and the buffer plate 603 is provided with a plurality of buffer holes 605, the number of which does not exceed five, and the damping fluid passes through each buffer hole 605;
[0031] It should be noted here that: by setting the buffer hole 605 and the damping fluid, a third layer of buffering protection is formed for the hanging basket body 1 by utilizing the damping buffer mechanism.
[0032] Working principle: When the hanging basket body 1 is in use, when the hanging basket body 1 is affected by strong winds or external forces, the hanging basket body 1 will collide with the wall. In the process of the hanging basket body 1 moving close to the wall, the rotating wheel 4 will first abut against the wall. In the process of the rotating wheel 4 abutting against the wall, the rotating wheel 4 will be pushed to move close to the hanging basket body 1. In the process of the rotating wheel 4 moving close to the hanging basket body 1, the rotating plate 504 will be driven to rotate. In the process of the rotating plate 504 rotating, the sliding plate 503 will be pushed to slide on the side wall of the fixed rod 502, thereby further compressing or stretching the first spring 505, so that the first spring 505 is deformed by force to form an elastic force, thereby using the elastic force of the first spring 505 to form a first layer of buffer protection for the hanging basket body 1;
[0033] When the rotating wheel 4 moves closer to the hanging basket body 1, the buffer plate 603 will be pushed to slide in the fixed tube 601, thereby compressing the second spring 604, so that the second spring 604 is deformed by force to form an elastic force, so that under the elastic action of the second spring 604, a second layer of buffer protection is formed for the hanging basket body 1;
[0034] At the same time, during the sliding of the buffer plate 603 in the fixed tube 601, the damping liquid in the fixed tube 601 will be squeezed, so that the damping liquid can only pass through the buffer hole 605 on the buffer plate 603, thereby forming a damping buffer mechanism, further forming a third layer of buffer protection for the hanging basket body 1, and thus through the setting of the first buffer component and the second buffer component, a multi-layer buffer protection effect is formed for the hanging basket body 1, so that the hanging basket body 1 and the wall are flexibly offset, thereby reducing the vibration force generated when the hanging basket body 1 collides with the wall when affected by strong winds or external forces, thereby reducing damage to the hanging basket body 1 and the wall and improving the safety of the staff in the hanging basket body 1.
Claims
1. A hanging basket for construction, comprising: Basket body (1); It is characterized by further comprising: A U-shaped plate (2) is arranged on a side of the hanging basket body (1) close to the wall, the U-shaped plate (2) is connected to a rotating wheel (4) via a rotating shaft (3), and the hanging basket body (1) is provided with a first buffer component and a second buffer component for performing multi-stage buffering on the rotating wheel (4).
2. A construction hanging basket according to claim 1, characterized in that: Four rotating wheels (4) are provided, and the four rotating wheels (4) are arranged symmetrically in pairs.
3. A construction hanging basket according to claim 1, characterized in that: The first buffer assembly comprises two groups of fixed plates (501) fixedly connected to a side of the hanging basket body (1) close to the rotating wheel (4) and symmetrically arranged in pairs, a fixed rod (502) is fixedly connected between the two fixed plates (501) located on the same side, the two fixed rods (502) are slidably connected to a sliding plate (503), the two sliding plates (503) are rotatably connected to a rotating plate (504) on a side close to the rotating wheel (4), the other ends of the two rotating plates (504) are rotatably connected to the U-shaped plate (2), and two first springs (505) are sleeved on the side walls of the two fixed rods (502).
4. A construction hanging basket according to claim 3, characterized in that: One opposite end of the two first springs (505) located on the same side is connected to the sliding plate (503), and the other end is connected to the fixed plate (501).
5. A construction hanging basket according to claim 1, characterized in that: The second buffer assembly comprises a fixed tube (601) fixedly connected to a side of the hanging basket body (1) close to the rotating wheel (4); the fixed tube (601) is slidably connected to a buffer rod (602); one end of the buffer rod (602) is connected to the U-shaped plate (2); the other end of the buffer rod (602) is located in the fixed tube (601) and is fixedly connected to a buffer plate (603); a side of the buffer plate (603) away from the buffer rod (602) is fixedly connected to a second spring (604); the other end of the second spring (604) is connected to the bottom wall of the fixed tube (601).
6. A construction hanging basket according to claim 5, characterized in that: The fixed tube (601) is filled with damping fluid, and the buffer plate (603) is provided with a plurality of buffer holes (605), through which the damping fluid passes.