Detachable overhanging connecting piece mechanism capable of adjusting position of scaffold
By designing a detachable cantilever connector mechanism, using the combination of screw sleeves and cantilever outer frames, flexible adjustment of scaffolding position and reuse of connectors are achieved, and the problem of position adjustment difficulties and removal risks caused by fixed connections in the prior art is solved.
Patent Information
- Application Number
- CN202421020764.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-11
- Publication Date
- 2025-03-18
- Estimated Expiration
- 2034-05-11
AI Technical Summary
The existing wall connecting parts are fixedly connected to the scaffolding, which makes it impossible to adjust the front and rear position of the scaffolding. At the same time, the pre-embedded method of wall connecting parts increases construction costs and leaves hidden dangers when demolished.
A detachable cantilever connection mechanism is designed. By setting up a supporting riser and screw sleeve on the floor board, combining the cantilever outer frame and the external cantilever steel pipe, the horizontal direction adjustment of the cantilever outer frame is achieved by rotating the screw sleeve, and the height of the external cantilever steel pipe is adjusted through the first fastener to achieve up and down direction adjustment.
It realizes flexible adjustment of the scaffolding position to meet the stability and safety requirements during construction. At the same time, the entire connector mechanism can be removed and reused, reducing construction costs and avoiding hidden dangers.
Smart Images

Figure CN222632798U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a connecting piece mechanism of a scaffold, in particular to a cantilever connecting piece mechanism which can adjust the position of a scaffold. Background Art
[0002] A wall tie refers to a component that strengthens the stability of other structures by connecting to a reliable fixed end. In construction projects, wall ties are often used to connect a scaffolding frame to the main structure of the building. Wall ties can stably transmit tension and pressure. Existing wall ties use pre-buried short steel pipes to fix the pre-buried short steel pipes to the structural scaffolding. However, during the main construction, in order to ensure the overall stability and safety of the scaffolding, the front and rear positions of the installed scaffolding need to be adjusted. Since the existing wall ties are fixedly connected to the scaffolding, the adjustment of the front and rear positions of the scaffolding cannot be achieved. In addition, when the scaffolding is dismantled after the main structure construction is completed, the wall ties also need to be dismantled. Since the wall ties are pre-buried parts, the only option is to cut off the exposed wall ties, which not only increases the construction cost, but also leaves hidden dangers in the wall panels or floor panels. Summary of the invention
[0003] The utility model provides a detachable cantilever connector mechanism capable of adjusting the position of a scaffold, thereby realizing the detachability and reuse of the entire connector mechanism.
[0004] The utility model solves the above technical problems through the following technical solutions:
[0005] A detachable cantilever connector mechanism capable of adjusting the position of a scaffold comprises a floor plate and a cantilever outer frame, a support riser is fixedly arranged on the floor plate, a first fastener is arranged on the support riser, a horizontal external cantilever steel pipe is connected to the first fastener, a first external thread is arranged at the outer end of the first horizontal external cantilever steel pipe, a second horizontal external cantilever steel pipe is connected to the cantilever outer frame, the cantilever outer frame and the second horizontal external cantilever steel pipe are connected together by a second fastener, and a second horizontal external cantilever steel pipe is connected to the second horizontal external cantilever steel pipe. A second external thread is provided at the inner end of the cantilever steel pipe, and a screw sleeve is provided between the outer end of the first horizontal external cantilever steel pipe and the inner end of the second horizontal external cantilever steel pipe, the outer end of the first horizontal external cantilever steel pipe is screwed into the inner port of the screw sleeve, and the inner end of the second horizontal external cantilever steel pipe is screwed into the outer port of the screw sleeve, and the first external thread provided on the outer end of the first horizontal external cantilever steel pipe and the second external thread provided on the inner end of the second horizontal external cantilever steel pipe are provided in opposite directions.
[0006] A support riser through-hole and a bolt through-hole are respectively reserved on the floor slab, the lower end of the support riser is welded and connected to the upper top surface of the lower prefabricated pad, an upper prefabricated pad is arranged on the support riser through-hole, a center hole is arranged on the upper prefabricated pad, the upper end of the support riser passes through the support riser through-hole and the center hole arranged on the upper prefabricated pad in turn, and is arranged above the floor slab, a fixing bolt is arranged between the lower prefabricated pad and the upper prefabricated pad; a rotating handle is arranged on the outer side of the screw sleeve.
[0007] The utility model adjusts the front and rear positions of the cantilevered outer frame in the horizontal direction by rotating the screw sleeve, and adjusts the height of the external cantilevered steel pipe by the first fastener to adjust the cantilevered outer frame in the up and down directions; the entire connecting member mechanism can be dismantled and reused. BRIEF DESCRIPTION OF THE DRAWINGS
[0008] Figure 1 It is a structural schematic diagram of the utility model;
[0009] Figure 2 This is a diagram showing the matching relationship between the upper prefabricated pad 2 and the support riser 5 of the utility model;
[0010] Figure 3 It is a diagram showing the matching relationship between the spiral sleeve 6 of the utility model and two externally connected cantilevered steel pipes. DETAILED DESCRIPTION
[0011] The utility model is described in detail below with reference to the accompanying drawings:
[0012] A detachable cantilever connector mechanism capable of adjusting the position of a scaffold comprises a floor plate and a cantilever outer frame 10, a support riser 5 is fixedly arranged on the floor plate, a first fastener 4 is arranged on the support riser 5, a horizontal external cantilever steel pipe 7 is connected to the first fastener 4, the first fastener 4 connects the cross-shaped support riser 5 with the horizontal external cantilever steel pipe 7, and the height adjustment of the cantilever outer frame 10 can be achieved by adjusting the position of the first fastener 4; a first external thread is arranged on the outer side end of the first horizontal external cantilever steel pipe 7, a second horizontal external cantilever steel pipe 8 is connected to the cantilever outer frame 10, the cantilever outer frame 10 and the second horizontal external cantilever steel pipe 8 are connected together through a second fastener 9, a second external thread is arranged on the inner side end of the second horizontal external cantilever steel pipe 8, and the outer side end of the first horizontal external cantilever steel pipe 7 is connected to the second horizontal external cantilever steel pipe 8. A screw sleeve 6 is arranged between the inner ends of the cantilever steel pipe 8, the outer end of the first horizontal external cantilever steel pipe 7 is screwed into the inner port of the screw sleeve 6, and the inner end of the second horizontal external cantilever steel pipe 8 is screwed into the outer port of the screw sleeve 6, and the first external thread arranged on the outer end of the first horizontal external cantilever steel pipe 7 and the second external thread arranged on the inner end of the second horizontal external cantilever steel pipe 8 are arranged in opposite directions; when the screw sleeve 6 is rotated forward, the length of the first horizontal external cantilever steel pipe 7 and the second horizontal external cantilever steel pipe 8 connected together by the screw sleeve 6 will become longer, thereby achieving the purpose of moving the cantilever outer frame 10 outward; conversely, the screw sleeve 6 is rotated backward, so that the length of the first horizontal external cantilever steel pipe 7 and the second horizontal external cantilever steel pipe 8 connected together by the screw sleeve 6 will become shorter, thereby achieving the purpose of moving the cantilever outer frame 10 inward.
[0013] The floor slab is respectively provided with supporting riser through-holes and bolt through-holes, the lower end of the supporting riser 5 is welded and connected to the upper top surface of the lower prefabricated pad 1, the upper prefabricated pad 2 is arranged on the supporting riser through-hole, the upper prefabricated pad 2 is provided with a center hole, the upper end of the supporting riser 5 passes through the supporting riser through-hole and the center hole provided on the upper prefabricated pad 2 in turn, and is arranged above the floor slab, a fixing bolt 3 is provided between the lower prefabricated pad 1 and the upper prefabricated pad 2, the supporting riser through-holes and the bolt through-holes can be achieved by pre-burying PVC pipes when casting the floor slab; a rotating handle is provided on the outer side of the screw sleeve 6 to facilitate the rotation of the screw sleeve 6.
Claims
1. A detachable cantilever connector mechanism capable of adjusting the position of a scaffold, comprising a floor plate and a cantilever outer frame (10), characterized in that: A support riser (5) is fixedly arranged on the floor slab, a first fastener (4) is arranged on the support riser (5), a horizontal external cantilever steel pipe (7) is connected to the first fastener (4), a first external thread is arranged on the outer side end of the first horizontal external cantilever steel pipe (7), a second horizontal external cantilever steel pipe (8) is connected to the cantilever external frame (10), the cantilever external frame (10) and the second horizontal external cantilever steel pipe (8) are connected together via a second fastener (9), a second thread is arranged on the inner side end of the second horizontal external cantilever steel pipe (8) An external thread is provided between the outer end of a first horizontal external cantilever steel pipe (7) and the inner end of a second horizontal external cantilever steel pipe (8), the outer end of the first horizontal external cantilever steel pipe (7) is screwed into the inner port of the screw sleeve (6), and the inner end of the second horizontal external cantilever steel pipe (8) is screwed into the outer port of the screw sleeve (6), and the first external thread provided on the outer end of the first horizontal external cantilever steel pipe (7) and the second external thread provided on the inner end of the second horizontal external cantilever steel pipe (8) are provided in opposite directions.
2. A detachable cantilever connector mechanism capable of adjusting the position of a scaffold according to claim 1, characterized in that: A support riser through hole and a bolt through hole are respectively reserved on the floor slab, the lower end of the support riser (5) is welded to the upper top surface of the lower prefabricated pad (1), an upper prefabricated pad (2) is arranged on the support riser through hole, a center hole is arranged on the upper prefabricated pad (2), the upper end of the support riser (5) passes through the support riser through hole and the center hole arranged on the upper prefabricated pad (2) in sequence, and is arranged above the floor slab, a fixing bolt (3) is arranged between the lower prefabricated pad (1) and the upper prefabricated pad (2); a rotating handle is arranged on the outer side of the screw sleeve (6).