By designing a silicon monene exterior wall insulation integrated casting vibration device including a base, a load-bearing seat, a connecting plate, a rotating assembly, an electric push rod and a vibration assembly, the problems of inconvenience and inefficiency caused by frequent position adjustment in the prior art are solved, and a more efficient casting and vibration process is achieved.

CN222632837UActive Publication Date: 2025-03-18THE SECOND CONSTRUCTION ENGINEERING CO LTD CCSEB
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421410979.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-20
Publication Date
2025-03-18
Estimated Expiration
2034-06-20

AI Technical Summary

Technical Problem

The existing silicon monene exterior wall insulation integrated casting and vibration device needs to be frequently adjusted during use, which leads to inconvenient operation and affects processing efficiency.

Method used

A device including a base, a load-bearing seat, a connecting plate, a rotating assembly, an electric push rod and a vibration assembly is designed. Through the cooperation of these components, the casting and vibration positions can be adjusted and the adjustable range can be expanded.

Benefits of technology

The device can support a large range of pouring and vibration at a certain position, reduce the number of position adjustments, improve processing efficiency, and solve the problem of inefficiency caused by frequent position adjustments in the prior art.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222632837U_ABST
    Figure CN222632837U_ABST
Patent Text Reader

Abstract

The utility model provides a silicon graphene external wall insulation integrated pouring and vibrating device, which relates to the technical field of silicon graphene external wall insulation concrete pouring, and comprises a base, a bearing seat is arranged above the base, a connecting plate is arranged above the bearing seat, the connecting plate is connected with the bearing seat through a rotating component, a connecting port is arranged on the connecting plate, and the connecting port is connected with the bearing seat through the rotating component. A connecting opening is formed in the upper portion of the base, an extending plate is arranged on the inner side of the connecting opening, a first electric push rod is installed on the inner side of the connecting plate, the telescopic end of the first electric push rod is connected with the extending plate, a bearing frame is installed on the extending plate, a casting pipe is installed on the bearing frame, and a vibrating assembly is further installed on the bearing frame. The position of the bearing frame can be adjusted, the adjusting range is wide, so that pouring and vibrating in a large range can be supported at a certain position, meanwhile, the horizontal angle of the connecting plate can be adjusted, the adjustable range of the device is further expanded, and the efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of silicon-graphene external wall thermal insulation concrete pouring, and in particular to a silicon-graphene external wall thermal insulation integrated pouring and vibrating device. Background Art

[0002] In order to enhance the effect of the thermal insulation exterior wall, a cast-in-place concrete composite thermal insulation exterior wall system is generally used. The thermal insulation board is made of silicon graphene board, and then combined with poured concrete as the thermal insulation exterior wall. Concrete pouring refers to the process of pouring concrete into a mold until it is plasticized. After the concrete is poured, the poured concrete needs to be vibrated. For example, the prior art (publication number CN215520013U) discloses an integrated floor slab concrete pouring, vibration and leveling equipment, which can vibrate and level the poured concrete while pouring concrete on the floor decking with tied steel bars, thereby preventing the problem of later manual vibration, which not only has cumbersome operating steps but also increases labor.

[0003] Based on the prior art, it is found that for the integrated pouring and vibrating device, although it has the effect of integrated pouring and vibrating, during use, since the pouring range usually has a certain area, it is necessary to adjust its position frequently, which leads to great inconvenience in the pouring and vibrating process and affects the processing efficiency. Therefore, the utility model proposes a silicon-graphene exterior wall insulation integrated pouring and vibrating device to solve the problems existing in the prior art. Utility Model Content

[0004] In view of the above problems, the purpose of the utility model is to propose a silicon-graphene exterior wall thermal insulation integrated casting and vibration device. This silicon-graphene exterior wall thermal insulation integrated casting and vibration device has the advantages of a wide adjustable range, reduces the need for position adjustment, and can solve the problems in the prior art.

[0005] To achieve the purpose of the utility model, the utility model is implemented through the following technical solutions: a silicon-graphene exterior wall insulation integrated pouring and vibrating device, comprising a base, a load-bearing seat is installed above the base, and a connecting plate is provided above the load-bearing seat, the connecting plate is connected to the load-bearing seat through a rotating assembly, and a connecting port is provided on the connecting plate, an extension plate is provided on the inner side of the connecting port, a first electric push rod is installed on the inner side of the connecting plate, and the telescopic end of the first electric push rod is connected to the extension plate, a load-bearing frame is installed on the extension plate, a casting pipe is installed on the load-bearing frame, and the casting pipe is provided in several groups, and a vibration assembly is also installed on the load-bearing frame.

[0006] Further improvement is that: the rotating assembly includes a lower support seat, an annular slide rail is installed above the lower support seat, a connecting disk is provided above the annular slide rail, and the connecting disk is connected to the connecting plate, the annular slide rail is connected to the connecting disk through a slider, an electric reducer is installed on the inner side of the lower support seat, and the output end of the electric reducer is connected to the connecting plate.

[0007] A further improvement is that the vibrating assembly includes a lower mounting plate, two groups of symmetrically arranged second electric push rods are installed on the load-bearing frame, the telescopic ends of the second electric push rods are connected to the lower mounting plate, and concrete vibrating rods are installed on the lower mounting plate, and several groups of concrete vibrating rods are provided.

[0008] A further improvement is that a cavity is provided inside the load-bearing seat, a partition is installed inside the load-bearing seat, a battery pack is installed above the partition, and the partition is connected to the load-bearing seat by bolts.

[0009] A further improvement is that a protective door is installed on the load-bearing seat, one end of the protective door is hinged to the load-bearing seat, and the protective door is connected to the cavity.

[0010] A further improvement is that a limiting slide bar is installed on the connecting plate, the limiting slide bar passes through the connecting plate, and the limiting slide bar is connected to the extension plate.

[0011] A further improvement is that the width of the load-bearing frame is greater than the width of the extension plate.

[0012] The beneficial effects of the utility model are as follows: the integrated silicon-graphene exterior wall insulation pouring and vibrating device can adjust the position of the load-bearing frame through the cooperation of the first electric push rod, the connecting plate and the extension plate, and the adjustment range is relatively wide, so that at a certain position, it can support pouring and vibration in a larger range, and at the same time, the horizontal angle of the connecting plate can be adjusted, further expanding the adjustable range of the device, thereby reducing the number of position adjustments of the device during the silicon-graphene exterior wall insulation pouring process, improving efficiency, and solving the problem of processing efficiency being affected in the prior art. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0014] Figure 1 It is a front view structural schematic diagram of the utility model.

[0015] Figure 2 It is a side view structural schematic diagram of the pouring pipe distribution of the utility model.

[0016] Figure 3 It is a side view structural schematic diagram of the concrete vibrating rod distribution of the utility model.

[0017] Figure 4 It is a top view schematic diagram of the connection between the extension plate and the load-bearing frame of the utility model.

[0018] Figure 5 It is a front view structural schematic diagram of the connection between the lower support seat and the connecting plate of the utility model.

[0019] Figure 6 It is a front view structural schematic diagram of the extension plate of the utility model after being extended.

[0020] Among them: 1. Base; 2. Load-bearing seat; 3. Connecting plate; 4. Connecting port; 5. Extension plate; 6. First electric push rod; 7. Load-bearing frame; 8. Casting pipe; 9. Lower support seat; 10. Annular slide rail; 11. Connecting plate; 12. Electric reducer; 13. Lower mounting plate; 14. Second electric push rod; 15. Cavity; 16. Partition; 17. Battery pack; 18. Protective door; 19. Limiting slide rod; 20. Concrete vibrator; 21. Three-way pipe. DETAILED DESCRIPTION

[0021] In order to deepen the understanding of the present invention, the present invention will be further described in detail below in conjunction with an embodiment. The embodiment is only used to explain the present invention and does not constitute a limitation on the protection scope of the present invention.

[0022] according to Figure 1-Figure 6 As shown, this embodiment proposes a silicon-graphene exterior wall insulation integrated pouring and vibrating device, including a base 1, a universal wheel is installed at the lower end of the base 1, and the universal wheel is evenly arranged in four groups, and a bearing seat 2 is installed above the base 1, as shown in FIG. Figure 1 As shown, a cavity 15 is provided on the inner side of the load-bearing seat 2, a partition 16 is installed on the inner side of the load-bearing seat 2, a battery pack 17 is installed above the partition 16, the partition 16 is connected to the load-bearing seat 2 by bolts, and then the cavity 15 is divided by the partition 16, the upper part of which is used to install the battery pack 17, and the battery pack 17 is connected to other electronic equipment of the device as a power source for power supply, and the lower part is used for storage, correspondingly, a protective door 18 is installed on the load-bearing seat 2, one end of the protective door 18 is hinged to the load-bearing seat 2, and the protective door 18 is connected to the cavity 15, and the protective door 18 can be opened.

[0023] A connecting plate 3 is provided above the load-bearing seat 2, and the connecting plate 3 is connected to the load-bearing seat 2 through a rotating assembly. Figure 1 and Figure 5As shown, the rotating assembly includes a lower support seat 9, which is fixedly connected to the load-bearing seat 2. An annular slide rail 10 is installed above the lower support seat 9. A connecting disk 11 is provided above the annular slide rail 10, and the connecting disk 11 is connected to the connecting plate 3. At the same time, the annular slide rail 10 is connected to the connecting disk 11 through a slider, and the slider is evenly distributed in four groups. An electric reducer 12 is installed on the inner side of the lower support seat 9, and the output end of the electric reducer 12 is connected to the connecting plate 3. Therefore, when working, the staff controls the start of the electric reducer 12 through a controller (the device has a master controller for controlling all electronic components of the device). The power source of the electric reducer 12 is a battery pack 17. The output end of the electric reducer 12 drives the connecting disk 11 to rotate on the annular slide rail 10, so the connecting disk 11 drives the connecting plate 3 to rotate. Therefore, when the device stays at a different position, the position of pouring or vibrating can be adjusted by rotating the connecting plate 3.

[0024] A connecting port 4 is provided on the connecting plate 3, the lower end of the connecting port 4 is in a closed state, and an extension plate 5 is provided on the inner side of the connecting port 4, that is, the lower end surface of the extension plate 5 is in contact with the connecting plate 3, and a first electric push rod 6 is installed on the inner side of the connecting plate 3, and the telescopic end of the first electric push rod 6 is connected to the extension plate 5, so when working, the extension plate 5 can be driven to move in the horizontal direction by controlling the telescopic movement of the first electric push rod 6, and during the movement, the connecting plate 3 can bear the weight, thereby ensuring the stability of the extension plate 5 during the movement. Figure 4 As shown, a limit slide bar 19 is installed on the connecting plate 3, the limit slide bar 19 passes through the connecting plate 3, and the limit slide bar 19 is connected to the extension plate 5. In this embodiment, two groups of limit slide bars 19 are symmetrically arranged, and the two groups of limit slide bars 19 can move in the connecting plate 3. Correspondingly, the length of the limit slide bar 19 is greater than the length of the connecting plate 3. Therefore, in the process of moving the extension plate 5, the connection relationship between the extension plate 5 and the connecting plate 3 is strengthened through the cooperation between the limit slide bar 19 and the connecting plate 3 to ensure its stability.

[0025] A load-bearing frame 7 is mounted on the extension plate 5, and the width of the load-bearing frame 7 is greater than the width of the extension plate 5. At the same time, a casting pipe 8 is mounted on the load-bearing frame 7, and the casting pipe 8 is provided with several groups, such as Figure 2 As shown, in this embodiment, two groups of casting pipes 8 are symmetrically provided, and the upper ends of the two groups of casting pipes 8 extend to the top of the extension plate 5 and are connected through a tee pipe 21, and the upper end of the tee pipe 21 is connected to the external concrete delivery pipeline. Therefore, when working, the concrete delivery pipeline delivers concrete to the casting pipe 8 through the tee pipe 21, and then the casting pipe 8 is poured below it, and the pouring range is changed by moving the extension plate 5.

[0026] like Figure 1 and Figure 3As shown, a vibrating assembly is also installed on the load-bearing frame 7. Specifically, the vibrating assembly includes a lower mounting plate 13. Two groups of symmetrically arranged second electric push rods 14 are installed on the load-bearing frame 7. The second electric push rods 14 are vertically arranged. At the same time, the telescopic ends of the second electric push rods 14 are connected to the lower mounting plate 13. Concrete vibrating rods 20 are installed on the lower mounting plate 13, and the concrete vibrating rods 20 are provided with several groups. In this embodiment, two groups of concrete vibrating rods 20 are evenly provided. When working, the lower mounting plate 13 is pushed up and down by the second electric push rods 14, and then the concrete vibrating rods 20 can be inserted into the poured concrete, and then the concrete vibrating rods 20 are started. The concrete vibrating rod 20 is a commonly used tool in concrete construction. It is mainly composed of a cast iron shell, a vibration motor, a vibration head and a power cord. The working principle is to generate high-frequency vibrations through the vibration head to discharge the air inside the concrete to achieve a dense and smooth effect.

[0027] In this embodiment, the concrete vibrator 20 is powered by a battery pack 17 .

[0028] The above shows and describes the basic principles, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principles of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.

Claims

1. A silicon-graphene external wall thermal insulation integrated pouring and vibrating device, comprising a base (1), characterized in that: A load-bearing seat (2) is installed above the base (1), and a connecting plate (3) is provided above the load-bearing seat (2). The connecting plate (3) is connected to the load-bearing seat (2) through a rotating component, and a connecting port (4) is provided on the connecting plate (3). An extension plate (5) is provided on the inner side of the connecting port (4). A first electric push rod (6) is installed on the inner side of the connecting plate (3), and the telescopic end of the first electric push rod (6) is connected to the extension plate (5). A load-bearing frame (7) is installed on the extension plate (5). A casting pipe (8) is installed on the load-bearing frame (7), and the casting pipe (8) is provided in a plurality of groups. A vibrating component is also installed on the load-bearing frame (7).

2. A silicon-graphene external wall insulation integrated pouring and vibrating device according to claim 1, characterized in that: The rotating assembly comprises a lower support seat (9), an annular slide rail (10) is installed above the lower support seat (9), a connecting disk (11) is provided above the annular slide rail (10), and the connecting disk (11) is connected to the connecting plate (3), the annular slide rail (10) is connected to the connecting disk (11) via a slider, an electric reducer (12) is installed on the inner side of the lower support seat (9), and the output end of the electric reducer (12) is connected to the connecting plate (3).

3. The silicon-graphene external wall insulation integrated pouring and vibrating device according to claim 1 is characterized in that: The vibrating assembly comprises a lower mounting plate (13), two groups of symmetrically arranged second electric push rods (14) are mounted on the load-bearing frame (7), telescopic ends of the second electric push rods (14) are connected to the lower mounting plate (13), and concrete vibrating rods (20) are mounted on the lower mounting plate (13), and a plurality of groups of concrete vibrating rods (20) are provided.

4. The silicon-graphene external wall thermal insulation integrated pouring and vibrating device according to claim 1, characterized in that: A cavity (15) is provided on the inner side of the load-bearing seat (2), a partition (16) is installed on the inner side of the load-bearing seat (2), a battery pack (17) is installed above the partition (16), and the partition (16) is connected to the load-bearing seat (2) by bolts.

5. The silicon-graphene external wall thermal insulation integrated pouring and vibrating device according to claim 4, characterized in that: A protective door (18) is installed on the load-bearing seat (2), one end of the protective door (18) is hinged to the load-bearing seat (2), and the protective door (18) is in communication with the cavity (15).

6. The silicon-graphene external wall thermal insulation integrated pouring and vibrating device according to claim 1, characterized in that: A limiting slide bar (19) is installed on the connecting plate (3), the limiting slide bar (19) passes through the connecting plate (3), and the limiting slide bar (19) is connected to the extension plate (5).

7. The silicon-graphene external wall thermal insulation integrated pouring and vibrating device according to claim 1, characterized in that: The width of the load-bearing frame (7) is greater than the width of the extension plate (5).