Vertical cable for marine seismic exploration
By installing anchor balls and floats on vertical cables for marine seismic exploration, and using threaded connections and chute structures, the problem of traditional cables being susceptible to pushing or pulling under the action of sea currents or water flows is solved, achieving higher stability and data accuracy.
Patent Information
- Application Number
- CN202421611588.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-09
- Publication Date
- 2025-04-18
- Estimated Expiration
- 2034-07-09
AI Technical Summary
Traditional vertical cables for marine seismic exploration are easily pushed or pulled under the action of sea currents or water flow, resulting in position changes and affecting data accuracy.
A vertical cable for marine seismic exploration was designed. By installing anchor balls and floats on the cables, and using threaded connections and chute structures, the anchor balls are fixed and the slide friction are reduced, the cables are stabilized, and the movement under the action of water flow is reduced.
Effectively fixing the anchor ball reduces the swaying and swing of the cable in the water flow, improving the stability of the cable and the accuracy of data recording.
Smart Images

Figure CN222774663U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of marine seismic exploration, in particular to a vertical cable for marine seismic exploration. Background Art
[0002] As we all know, marine seismic exploration uses the characteristics of seismic waves propagating in the ocean to capture seismic signals through sensors and measuring equipment placed on the seabed or on the water surface, so as to study the geological structure of the seabed and underground, search for oil and gas resources, monitor geological disasters, etc. This technology analyzes the propagation path and reflection characteristics of seismic waves to reveal important information such as underground rock formations, faults and topography, and provide key data support for geological science research and resource exploration. Usually, marine seismic exploration requires the use of vertical cables, which are mainly used to suspend seismic sensors or seismic recorders to ensure that they can be accurately deployed on the seabed or the bottom of the ocean, thereby effectively recording seismic data.
[0003] However, traditional vertical cables used in marine seismic exploration are usually soft and long, which gives them a certain degree of freedom in the water. When ocean currents or water flows through the cables, fluid dynamic effects are generated on and around the cable surface, causing the cable to be pushed or pulled. Therefore, technical improvements are urgently needed. Utility Model Content
[0004] The purpose of the utility model is to solve the shortcomings existing in the prior art, and to propose a vertical cable for marine seismic exploration. When the vertical cable for marine seismic exploration is used, by installing an anchor ball of appropriate size as required, the threaded sleeve is conveniently connected through a threaded rod, and the anchor ball can be effectively fixed on the vertical cable to prevent the anchor ball from falling off or moving due to environmental factors. The slider is conveniently positioned through a slide groove, and the friction generated by the slider sliding in the slide groove is conveniently reduced through a roller, thereby making the sliding more convenient, and then the anchor ball slides to the bottom of the cable body. By adding a suitable number of anchor balls, the cable body can be stabilized and its movement in the water flow can be reduced, thereby reducing the position change caused by the fluid dynamics effect.
[0005] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0006] A vertical cable for marine seismic exploration, comprising a cable body, wherein the outer wall of the cable body is provided with a protective shell, the middle part of the outer walls on both sides of the protective shell is provided with a slide groove, the inside of the slide groove is slidably connected with a slider, the outer wall of the slider on one side away from the center of the cable body is fixedly connected with a connecting rope, the outer wall of the connecting rope on one side away from the center of the cable body is fixedly connected with a threaded sleeve, the inside of the threaded sleeve is threadedly connected with a threaded rod, and the outer wall of the threaded rod on one side away from the center of the cable body is fixedly connected with an anchor ball;
[0007] The front and rear ends of the outer wall of the protective shell are fixedly connected with mounting half rings, a plurality of snap-in grooves are opened in the middle of the upper surface of the mounting half ring, the inside of the snap-in grooves are snap-connected with snap-in blocks, and the ends of the snap-in blocks away from the center of the cable body are fixedly connected with floats.
[0008] Through the above technical scheme, compared with the existing vertical cable for marine seismic exploration, when the vertical cable for marine seismic exploration is used, the clamping block and the clamping groove are engaged to facilitate the placement of a suitable number of buoys according to the required installation, and the mounting plate is connected to the mounting half ring through multiple fastening bolts to limit the position of the buoys. The suitable number of buoys can be conveniently installed and placed on different mounting half rings as needed, thereby adapting to different needs and environmental conditions, reducing the swaying and swinging of the vertical cable in the water, ensuring the overall stability, and having high practical performance.
[0009] Furthermore, a seismic sensor is provided in the middle of the lower surface of the cable body;
[0010] Through the above technical solution, it is convenient to detect seabed earthquake fluctuations through seismic sensors.
[0011] Furthermore, the front end and the rear end of the slide groove are provided with limit grooves, and the outer walls of the front end and the rear end of the slide block are fixedly connected with limit blocks;
[0012] Through the above technical solution, the matching is improved by using the limiting grooves and the limiting blocks.
[0013] Furthermore, the limit blocks are slidably connected inside the limit grooves respectively;
[0014] Through the above technical solution, the limiting blocks are slidably connected inside the limiting grooves, so that the sliding block can be limited.
[0015] Furthermore, the inner wall of the adjacent side of the slide groove is provided with a plurality of storage grooves, the outer walls of the adjacent ends of the plurality of storage grooves are rotatably connected with a plurality of rollers, and the outer walls of the rollers are respectively tightly fitted with the outer wall of the adjacent side of the slider;
[0016] Through the above technical solution, the friction of the slider when sliding is reduced by the roller, making the sliding more convenient.
[0017] Furthermore, the middle part of the upper surface of the mounting half ring is connected to a mounting plate via a plurality of bolts;
[0018] Through the above technical solution, the matching is improved by installing the plate.
[0019] Furthermore, the anchor ball is made of aluminum alloy;
[0020] Through the above technical solution, the anchor ball is made of aluminum alloy, which has a lower density. This means that the anchor ball is lighter overall while maintaining sufficient weight, which helps reduce the tension on the cable and makes it easier to maintain a vertical state in the water.
[0021] Furthermore, the float is made of polyethylene;
[0022] Through the above technical solution, polyethylene has a very low density, which means that it can provide high buoyancy, which is crucial for keeping the vertical cable in a vertical state in the water.
[0023] The utility model has the following beneficial effects:
[0024] 1. The utility model proposes a vertical cable for marine seismic exploration. Compared with the existing vertical cables for marine seismic exploration, when the vertical cable for marine seismic exploration is used, by installing anchor balls of appropriate sizes as required, the threaded sleeves are conveniently connected through threaded rods, and the anchor balls can be effectively fixed on the vertical cable to prevent the anchor balls from falling off or moving due to environmental factors. The sliders can be positioned through the slide grooves, and the friction generated by the sliders sliding in the slide grooves can be reduced through rollers, thereby making the sliding more convenient, and then the anchor balls can slide to the bottom of the cable body. By adding a suitable number of anchor balls, the cable body can be stabilized and its movement in the water flow can be reduced, thereby reducing the position changes caused by the fluid dynamics effect.
[0025] 2. The utility model proposes a vertical cable for marine seismic exploration. Compared with the existing vertical cables for marine seismic exploration, when the vertical cable for marine seismic exploration is used, the clamping block and the clamping groove are engaged with each other to facilitate the installation and placement of a suitable number of buoys according to the needs. The mounting plate is connected to the mounting half ring by a plurality of fastening bolts, so as to limit the position of the buoys. A suitable number of buoys can be conveniently installed and placed on different mounting half rings as needed, thereby adapting to different needs and environmental conditions, reducing the swaying and swinging of the vertical cable in the water, ensuring the overall stability, and having high practical performance. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 This is an axonometric diagram of a vertical cable for marine seismic exploration proposed by the utility model;
[0027] Figure 2 This is an axonometric schematic diagram of a vertical cable for marine seismic exploration proposed by the utility model;
[0028] Figure 3 This is a schematic diagram of the structure of a seismic sensor in a vertical cable for marine seismic exploration proposed by the utility model;
[0029] Figure 4This is a schematic diagram of the structure of a threaded rod in a vertical cable for marine seismic exploration proposed by the utility model;
[0030] Figure 5 This is a schematic diagram of the structure of a semi-ring installed in a vertical cable for marine seismic exploration proposed by the utility model;
[0031] Figure 6 for Figure 1 The enlarged view of point A in the middle;
[0032] Figure 7 for Figure 5 Enlarged view of point B in the middle.
[0033] Legend:
[0034] 1. Cable body; 2. Protective shell; 3. Seismic sensor; 4. Slide groove; 5. Sliding block; 6. Limit groove; 7. Limit block; 8. Connecting rope; 9. Threaded sleeve; 10. Threaded rod; 11. Anchor ball; 12. Storage groove; 13. Roller; 14. Mounting half ring; 15. Snap-in groove; 16. Snap-in block; 17. Float; 18. Mounting plate. DETAILED DESCRIPTION
[0035] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0036] Reference Figure 1-7 , an embodiment provided by the utility model:
[0037] A vertical cable for marine seismic exploration, comprising a cable body 1, wherein a protective shell 2 is arranged on the outer wall of the cable body 1, a slide groove 4 is provided in the middle of the outer walls on both sides of the protective shell 2, a slider 5 is slidably connected inside the slide groove 4, a connecting rope 8 is fixedly connected to the outer wall of the slider 5 on one side away from the center of the cable body 1, a threaded sleeve 9 is fixedly connected to the outer wall of the connecting rope 8 on one side away from the center of the cable body 1, a threaded rod 10 is threadedly connected inside the threaded sleeve 9, and an anchor ball 11 is fixedly connected to the outer wall of the threaded rod 10 on one side away from the center of the cable body 1;
[0038] The front and rear ends of the outer wall of the protective shell 2 are fixedly connected with a mounting half ring 14, and a plurality of snap-in grooves 15 are opened in the middle of the upper surface of the mounting half ring 14. The inside of the snap-in grooves 15 are snap-connected with snap-in blocks 16, and the end of the snap-in block 16 away from the center of the cable body 1 is fixedly connected with a float 17.
[0039] Compared with the existing vertical cables for marine seismic exploration, when this vertical cable for marine seismic exploration is used, the clamping block 16 and the clamping groove 15 are clamped together to facilitate the placement of a suitable number of buoys 17 as required. The mounting plate 18 is connected to the mounting half ring 14 through a plurality of fastening bolts, thereby limiting the position of the buoys 17. A suitable number of buoys 17 can be conveniently installed and placed on different mounting half rings 14 as needed, thereby adapting to different needs and environmental conditions, reducing the swaying and swinging of the vertical cable in the water, ensuring the overall stability, and having high practical performance.
[0040] A seismic sensor 3 is provided in the middle of the lower surface of the cable body 1, and the seismic sensor 3 is used to facilitate the detection of seabed seismic fluctuations. Limiting grooves 6 are provided at the front and rear ends of the slide 4, and the outer walls of the front and rear ends of the slider 5 are fixedly connected to the limiting blocks 7, which are convenient for improving the coordination through the limiting grooves 6 and the limiting blocks 7. The limiting blocks 7 are respectively slidably connected inside the limiting grooves 6, and are respectively slidably connected inside the limiting grooves 6 through the limiting blocks 7, which are convenient for limiting the slider 5. A plurality of storage grooves 12 are provided on the inner wall of the adjacent side of the slide 4, and a plurality of rollers 13 are rotatably connected to the outer walls of the adjacent ends of the plurality of storage grooves 12, and the outer walls of the rollers 13 are respectively tightly connected to the outer walls of the adjacent sides of the slider 5. The roller 13 is used to reduce the friction of the slider 5 when it slides, making the sliding more convenient. The middle part of the upper surface of the mounting half ring 14 is connected with a mounting plate 18 by multiple bolts. The mounting plate 18 is used to improve the fit. The anchor ball 11 is made of aluminum alloy. The density of aluminum alloy is low, which means that the anchor ball 11 is light as a whole while maintaining sufficient weight, which helps to reduce the tension on the cable and makes it easier to maintain a vertical state in the water. The float 17 is made of polyethylene. Polyethylene has a very low density, which means that it can provide high buoyancy, which is essential for keeping the vertical cable vertical in the water.
[0041] Working principle: When in use, by installing the anchor ball 11 of appropriate size as required, the threaded sleeve 9 is conveniently connected through the threaded rod 10, which can effectively fix the anchor ball 11 on the vertical cable to prevent the anchor ball 11 from falling off or moving due to environmental factors. The slide groove 4 is convenient for positioning the slider 5, and the roller 13 is convenient for reducing the friction generated by the slider 5 sliding in the slide groove 4, so that the sliding is more convenient, and then the anchor ball 11 slides to the bottom of the cable body 1. By adding a suitable number of anchor balls 11, the cable body 1 can be stabilized and its movement in the water flow can be reduced, thereby reducing the position change caused by the fluid dynamics effect. The clamping block 16 and the clamping groove 15 are clamped together to facilitate the installation and placement of a suitable number of floating balls 17 as required. The mounting plate 18 is connected to the mounting semi-ring 14 through a plurality of fastening bolts, so as to limit the floating ball 17. According to the needs, a suitable number of floating balls 17 can be conveniently installed and placed on different mounting semi-rings 14, so as to adapt to different needs and environmental conditions, and can reduce the swaying and swinging of the vertical cable in the water, and ensure the overall stability.
[0042] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A vertical cable for marine seismic exploration, comprising a cable body (1), characterized in that: The outer wall of the cable body (1) is provided with a protective shell (2), and the middle part of the outer walls on both sides of the protective shell (2) is provided with a slide groove (4), and the inside of the slide groove (4) is slidably connected with a slider (5), and the outer wall of the slider (5) on one side away from the center of the cable body (1) is fixedly connected with a connecting rope (8), and the outer wall of the connecting rope (8) on one side away from the center of the cable body (1) is fixedly connected with a threaded sleeve (9), and the inside of the threaded sleeve (9) is threadedly connected with a threaded rod (10), and the outer wall of the threaded rod (10) on one side away from the center of the cable body (1) is fixedly connected with an anchor ball (11); The front and rear ends of the outer wall of the protective shell (2) are fixedly connected to a mounting half ring (14), a plurality of snap-in grooves (15) are provided in the middle of the upper surface of the mounting half ring (14), the inside of the snap-in grooves (15) are snap-connected to snap-in blocks (16), and one end of the snap-in block (16) away from the center of the cable body (1) is fixedly connected to a floating ball (17).
2. A vertical cable for marine seismic exploration according to claim 1, characterized in that: A seismic sensor (3) is arranged in the middle of the lower surface of the cable body (1).
3. A vertical cable for marine seismic exploration according to claim 1, characterized in that: The front end and the rear end of the slide groove (4) are both provided with limiting grooves (6), and the outer walls of the front end and the rear end of the slide block (5) are both fixedly connected to limiting blocks (7).
4. A vertical cable for marine seismic exploration according to claim 3, characterized in that: The limiting blocks (7) are respectively slidably connected inside the limiting grooves (6).
5. A vertical cable for marine seismic exploration according to claim 1, characterized in that: The inner wall of the adjacent side of the slide groove (4) is provided with a plurality of storage grooves (12), and the outer walls of the adjacent ends of the plurality of storage grooves (12) are rotatably connected to a plurality of rollers (13), and the outer walls of the rollers (13) are respectively tightly fitted with the outer wall of the adjacent side of the slide block (5).
6. A vertical cable for marine seismic exploration according to claim 1, characterized in that: The middle part of the upper surface of the mounting half ring (14) is connected to a mounting plate (18) via a plurality of bolts.
7. A vertical cable for marine seismic exploration according to claim 1, characterized in that: The anchor ball (11) is made of aluminum alloy.
8. A vertical cable for marine seismic exploration according to claim 1, characterized in that: The floating ball (17) is made of polyethylene.