Positioning device in corridor ultrahigh formwork construction
By designing a positioning device for construction of high-altitude supporting formwork of building concave corridors, the position deviation problem caused by the lack of positioning structure of the steel structure corridor frame during the assembly of the ground is solved, and the precise assembly and lifting of the steel structure frame is achieved, and construction efficiency and accuracy are improved.
Patent Information
- Application Number
- CN202421802687.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-29
- Publication Date
- 2025-05-09
- Estimated Expiration
- 2034-07-29
AI Technical Summary
The existing building concave gallery high-altitude formwork frame lacks the positioning structure for assembling the steel structure corridor frame at the ground podium, resulting in easy position deviation during lifting, affecting subsequent aerial welding work.
Design a positioning device in the construction of ultra-high supporting formwork of the corridor, including the building body, hydraulic hoist, upper weld frame, lower weld frame, positioning frame and limit rod. Through the synergy of these components, the precise positioning and lifting of the steel structure frame during the assembly of the ground is achieved.
Through the use of positioning frames, we ensure the accurate positioning of the steel structure frame when assembling on the ground, avoid position deviation during lifting, improve the efficiency and accuracy of construction, and ensure the smooth progress of subsequent aerial welding work.
Smart Images

Figure CN222847846U_ABST
Abstract
Description
Technical Field
[0001] The present application belongs to the technical field of corridor building construction, and specifically relates to a positioning device in the construction of super-high formwork for corridors. Background Art
[0002] With the rapid development of the construction industry and the improvement of construction technology, more and more super-high, large-span and large-volume construction projects are emerging. For the construction of high-altitude corridor concrete structures, a ground-type full-floor steel pipe fastener formwork frame is used. It is assembled in the podium, and then the steel structure corridor frame is hoisted to the installation position by a hoisting device for welding.
[0003] For example, the patent with announcement number CN206784942U discloses a high-altitude formwork frame for a building recessed corridor, including a steel structure support, an I-beam formwork platform erected on the steel structure support and the main structure of the building, the steel structure support includes a right-angled triangle support frame welded by vertical support I-beams, horizontal I-beams, and diagonal I-beams, the vertical support I-beams are fixed to the shear wall by tension bolts, the shear wall is fixed with a steel bracket supported at the bottom of the steel structure support, and the horizontal I-beams of the steel structure supports on both sides are connected by connecting steel plates; the I-beam formwork platform includes a plurality of cantilever main beam I-beams and connecting beam I-beams, the inner end of the cantilever main beam I-beam is anchored to the main structure of the building, the outer end of the cantilever main beam I-beam is fixed to the horizontal I-beam of the steel structure support, and the connecting beam I-beam is vertically cross-laid on the cantilever main beam I-beam. The utility model can facilitate construction, speed up construction progress, and reduce construction costs.
[0004] However, the high-altitude formwork for the building's recessed corridor in the application lacks a positioning structure for assembling the steel structure corridor frame at the ground podium, which leads to position deviation during hoisting, affecting subsequent aerial welding work. Utility Model Content
[0005] The purpose of the present application is to provide a positioning device for the super-high formwork construction of the corridor to solve the problem that the above-mentioned high-altitude formwork frame for the building recessed corridor lacks a positioning structure for assembling the steel structure corridor frame at the ground podium, which leads to position deviation during hoisting and affects the subsequent aerial welding work.
[0006] The technical solution adopted in the present application is as follows: a positioning device for the super-high formwork construction of a corridor, comprising a building main body, a hydraulic lift is installed on the top of the building main body, an upper welding frame is fixedly connected to the side end of the building main body and located below the hydraulic lift, a slot is opened inside the upper welding frame, and a limiting rod is slidably connected inside the slot, a lower welding frame is fixedly connected to the side end of the building main body and located below the upper welding frame, a positioning frame is slidably connected to the side end of the upper welding frame, a slot is opened on the side end of the positioning frame, and a limiting rod is slidably connected inside the slot of the positioning frame, a podium is fixedly installed on the bottom side end of the building main body, and a steel frame is provided on the surface of the podium.
[0007] By adopting the above technical solution, the steel structure frame for placing the corridor at the podium is assembled on the ground to facilitate subsequent lifting. The lower welding frame and the upper welding frame at the side end of the building body can be welded with the upper and lower steel structures at both ends of the steel frame, and the two ends and the upper and lower ends of the corridor as a whole are welded to the side end of the building body. The hydraulic hoist is used to hoist the steel frame and transport the steel frame from the podium to the lower welding frame and the upper welding frame. The positioning frame is used for positioning before construction. During construction, first install and fix the positions of the lower welding frame and the upper welding frame, then install a hydraulic hoist on the top of the main building above the upper welding frame, and then use an external crane to hoist the materials of the positioning frame to the construction personnel's position at the lower welding frame and the upper welding frame, so that the construction personnel can put the positioning frame on the surface of the lower welding frame and the upper welding frame, and insert the limit rod into the positioning frame and the upper welding frame through the slot opened at the side end of the upper welding frame, fix the upper welding frame and the positioning frame, and after the fixation is completed, release the external crane device and replace it with the lifting device at the hydraulic hoist, connect the steel cable at the hydraulic hoist to the positioning frame and remove the limit rod, and finally use the hydraulic hoist to lower the positioning frame to the surface of the podium, and position the steel frame through the position of the positioning frame, so that the construction personnel can accurately assemble the steel frame. After the assembly is completed, remove the positioning frame and lift the steel frame to the upper welding frame by the hydraulic hoist for welding.
[0008] In a preferred embodiment, a connecting plate is fixedly connected to the top side end of the positioning frame, and a hanging groove is provided inside the connecting plate.
[0009] By adopting the above technical solution, the connecting plate installed at the positioning frame can provide the position of the hydraulic hoist crane, allowing the steel cable at the hydraulic hoist to pass through the lifting groove for fixation, thereby facilitating stable transportation of the positioning frame.
[0010] In a preferred embodiment, a lower lifting device is fixedly installed on the top of the steel frame and directly below the hydraulic lift.
[0011] By adopting the above technical solution, after the steel frame is assembled, it can be installed through the steel cable of the hydraulic hoist and the lower hoist. After the steel frame is lifted, the device is left to stand for one day to ensure that the lifting is stable before lifting.
[0012] In a preferred embodiment, a ground assembly section is installed at the side end of the steel frame.
[0013] By adopting the above technical solution, the ground assembly section is used to assemble the steel frames at the left and right ends.
[0014] In a preferred embodiment, a hanging frame is fixedly installed on the top of the building body, and a hydraulic hoist is fixedly installed on the side end of the hanging frame.
[0015] By adopting the above technical solution, the crane frame is installed and fixed on the top of the building body, and four sets of hydraulic hoists are installed at the front end of the crane frame, which can improve the stability of the device during operation.
[0016] In a preferred embodiment, a steel cable is installed inside the hydraulic lift.
[0017] By adopting the above technical solution, the steel cable is used to hang the descending positioning device and lift the steel frame.
[0018] In a preferred embodiment, a bottom side end of the positioning frame is fixedly connected to a bottom plate.
[0019] By adopting the above technical solution, when the positioning frame is sleeved inside the lower welding frame and the upper welding frame, the base plate installed at the bottom of the positioning frame can facilitate the rapid positioning and sleeve connection of the positioning frame in the air, thereby improving the construction efficiency.
[0020] In summary, due to the adoption of the above technical solution, the beneficial effects of this application are:
[0021] In this application, the materials of the positioning frame are hoisted and sent to the lower welding frame and the upper welding frame, and the positioning frame is sleeved on the surface of the lower welding frame and the upper welding frame. The base plate installed at the bottom of the positioning frame can facilitate the positioning frame to be quickly positioned and sleeved in the air, thereby improving the efficiency of construction. After the fixing is completed, the external crane device is removed and replaced with the lifting device at the hydraulic hoist. The steel cable at the hydraulic hoist is connected to the positioning frame and the limit rod is removed. Finally, the positioning frame is lowered to the surface of the podium by the hydraulic hoist. The steel frame is positioned by the position of the positioning frame, so that the construction personnel can accurately assemble the steel frame. After the assembly is completed, the positioning frame is removed, and the steel frame is lifted to the upper welding frame by the hydraulic hoist for welding to complete the construction. This device can locate the position of the lower welding frame and the upper welding frame on the podium, so that the staff can refer to the positioning frame when assembling the steel frame to avoid misalignment during subsequent hoisting and lifting. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 This is a structural schematic diagram of a positioning device in the construction of a super-high formwork for a corridor in this application;
[0023] Figure 2 It is a diagram of the hydraulic hoist and some of its adjacent structures in this application;
[0024] Figure 3 This is a schematic diagram of the positioning device structure in this application.
[0025] Markings in the figure: 1. Building body; 2. Podium; 3. Lower welding frame; 4. Upper welding frame; 5. Hydraulic hoist; 6. Positioning frame; 7. Lower hoist; 8. Steel frame; 9. Ground assembly section; 10. Slot; 11. Hoist frame; 12. Steel cable; 13. Limit rod; 14. Bottom plate; 15. Connecting plate; 16. Hoisting groove. DETAILED DESCRIPTION
[0026] In order to make the purpose, technical scheme and advantages of the embodiments of the present application clearer, the technical scheme in the embodiments of the present application will be clearly and completely described below in combination with the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0027] Example:
[0028] Reference Figure 1-3A positioning device for the super-high formwork construction of a corridor comprises a building body 1, a hydraulic hoist 5 is installed on the top of the building body 1, an upper welding frame 4 is fixedly connected to the side end of the building body 1 and located below the hydraulic hoist 5, a slot 10 is provided inside the upper welding frame 4, and a limit rod 13 is slidably connected inside the slot 10, a lower welding frame 3 is fixedly connected to the side end of the building body 1 and located below the upper welding frame 4, a positioning frame 6 is slidably connected to the side end of the upper welding frame 4, a slot is provided on the side end of the positioning frame 6, and a limit rod 13 is slidably connected inside the slot of the positioning frame 6, a skirt house 2 is fixedly installed on the bottom side end of the building body 1, and a steel frame 8 is provided on the surface of the skirt house 2. A skirt house 2 is installed at the bottom of the building body 1, and the steel structure frame of the corridor is placed at the skirt house 2, which is assembled on the ground for convenience of subsequent lifting. The lower welding frame 3 and the upper welding frame 4 at the side end of the building body 1 can be welded with the upper and lower steel structures at both ends of the steel frame 8, and the two ends and the upper and lower ends of the corridor as a whole are welded to the side end of the building body 1. The hydraulic hoist 5 is used to hoist the steel frame 8, and transport the steel frame 8 from the podium 2 to the lower welding frame 3 and the upper welding frame 4. The positioning frame 6 is used for positioning before construction. During construction, first install and fix the positions of the lower welding frame 3 and the upper welding frame 4, then install the hydraulic hoist 5 on the top of the building body 1 above the upper welding frame 4, and then use the external crane to hoist the materials of the positioning frame 6 to the construction personnel position at the lower welding frame 3 and the upper welding frame 4, so that the construction personnel will sleeve the positioning frame 6 on the surface of the lower welding frame 3 and the upper welding frame 4, and insert the limit rod 13 into the positioning frame 6 and the upper welding frame 4 through the slot 10 opened at the side end of the upper welding frame 4, fix the upper welding frame 4 and the positioning frame 6, and after the fixing is completed, release the external crane device, replace it with the lifting device at the hydraulic hoist 5, connect the steel cable 12 at the hydraulic hoist 5 to the positioning frame 6 and remove the limit rod 13, finally, the positioning frame 6 is lowered to the surface of the skirt house 2 by the hydraulic hoist 5, and the steel frame 8 is positioned by the position of the positioning frame 6, so that the construction personnel can accurately assemble the steel frame 8, and after the assembly is completed, remove the positioning frame 6, and lift the steel frame 8 to the upper welding frame 4 by the hydraulic hoist 5 for welding to complete the construction.
[0029] Reference Figure 3 The top side of the positioning frame 6 is fixedly connected with a connecting plate 15, and a lifting groove 16 is provided inside the connecting plate 15. The connecting plate 15 installed at the positioning frame 6 can provide a position for the hydraulic hoist 5 to be hoisted, so that the steel cable 12 at the hydraulic hoist 5 can be fixed through the lifting groove 16, which is convenient for stable transportation of the positioning frame 6.
[0030] Reference Figure 1The top of the steel frame 8 and the lower sling 7 are fixedly installed just below the hydraulic hoist 5. After the steel frame 8 is assembled on the surface of the podium 2, it can be installed with the lower sling 7 through the steel cable 12 of the hydraulic hoist 5. After the steel frame 8 is hoisted, the device is left to stand for one day to ensure that the hoisting is stable before lifting.
[0031] Reference Figure 1 , the side ends of the steel frame 8 are installed with ground assembly sections 9. The ground assembly sections 9 are used to assemble the steel frames 8 at the left and right ends.
[0032] Reference Figure 2 A crane frame 11 is fixedly installed on the top of the building main body 1, and a hydraulic hoist 5 is fixedly installed on the side end of the crane frame 11. The crane frame 11 is fixedly installed on the top of the building main body 1, and four sets of hydraulic hoists 5 are installed on the front end of the crane frame 11, which can improve the stability of the device when working.
[0033] Reference Figure 2 , a steel cable 12 is installed inside the hydraulic hoist 5. The steel cable 12 is used to hang the descending positioning device and lift the steel frame 8.
[0034] Reference Figure 3 The bottom side end of the positioning frame 6 is fixedly connected with a bottom plate 14. When the positioning frame 6 is sleeved inside the lower welding frame 3 and the upper welding frame 4, the bottom plate 14 installed at the bottom of the positioning frame 6 can facilitate the positioning frame 6 to be quickly positioned and sleeved in the air, thereby improving the efficiency of the construction.
[0035] The implementation principle of an embodiment of a positioning device in the super-high formwork construction of a corridor in the present application is as follows: during construction, first install and fix the positions of the lower welding frame 3 and the upper welding frame 4, then install a hydraulic lift 5 on the top of the building body 1 above the upper welding frame 4, and then use an external crane to lift the materials of the positioning frame 6 to the construction personnel's position at the lower welding frame 3 and the upper welding frame 4, let the construction personnel sleeve the positioning frame 6 on the surface of the lower welding frame 3 and the upper welding frame 4, and insert the limit rod 13 into the positioning frame 6 and the upper welding frame 4 through the slot 10 opened at the side end of the upper welding frame 4, fix the upper welding frame 4 and the positioning frame 6, when the positioning frame 6 is sleeved inside the lower welding frame 3 and the upper welding frame 4, the base plate 14 installed at the bottom of the positioning frame 6 can facilitate the rapid positioning and sleeve connection of the positioning frame 6 in the air, thereby improving the construction efficiency. After the fixation is completed, remove the external crane device and replace it with the lifting device at the hydraulic hoist 5. Connect the steel cable 12 at the hydraulic hoist 5 to the positioning frame 6 and remove the limit rod 13. Finally, lower the positioning frame 6 to the surface of the podium 2 through the hydraulic hoist 5. Position the steel frame 8 through the position of the positioning frame 6, so that the construction personnel can accurately assemble the steel frame 8. After the assembly is completed, remove the positioning frame 6, and lift the steel frame 8 to the upper welding frame 4 through the hydraulic hoist 5 for welding to complete the construction. After the steel frame 8 is assembled on the surface of the podium 2, it can be installed through the steel cable 12 of the hydraulic hoist 5 and the lower hoist 7. After the steel frame 8 is lifted, let the device stand for one day to ensure that the lifting is stable before lifting. This device can locate the position of the lower welding frame 3 and the upper welding frame 4 on the podium 2, so that the staff can refer to the positioning frame 6 when assembling the steel frame 8 to avoid misalignment during subsequent lifting.
[0036] The above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application.
Claims
1. A positioning device for corridor super-high formwork construction, comprising a building body (1), characterized in that: A hydraulic lift (5) is installed on the top of the building body (1); an upper welding frame (4) is fixedly connected to the side end of the building body (1) and located below the hydraulic lift (5); a slot (10) is provided inside the upper welding frame (4); a limit rod (13) is slidably connected inside the slot (10); a lower welding frame (3) is fixedly connected to the side end of the building body (1) and located below the upper welding frame (4); a positioning frame (6) is slidably connected to the side end of the upper welding frame (4); a slot hole is provided on the side end of the positioning frame (6); a limit rod (13) is slidably connected inside the slot hole of the positioning frame (6); a podium (2) is fixedly installed on the bottom side end of the building body (1); a steel frame (8) is provided on the surface of the podium (2).
2. A positioning device for corridor super-high formwork construction as claimed in claim 1, characterized in that: A connecting plate (15) is fixedly connected to the top side end of the positioning frame (6), and a hanging groove (16) is provided inside the connecting plate (15).
3. A positioning device for corridor super-high formwork construction as claimed in claim 1, characterized in that: A lower lifting device (7) is fixedly installed at the top of the steel frame (8) and directly below the hydraulic lift (5).
4. A positioning device for corridor super-high formwork construction as claimed in claim 1, characterized in that: A ground assembly section (9) is installed at the side end of the steel frame (8).
5. A positioning device for corridor super-high formwork construction as claimed in claim 1, characterized in that: A hanging frame (11) is fixedly mounted on the top of the building body (1), and a hydraulic lift (5) is fixedly mounted on the side end of the hanging frame (11).
6. A positioning device for corridor super-high formwork construction as claimed in claim 1, characterized in that: A steel cable (12) is installed inside the hydraulic lift (5).
7. A positioning device for corridor super-high formwork construction as claimed in claim 1, characterized in that: The bottom side end of the positioning frame (6) is fixedly connected to a bottom plate (14).
Citation Information
Patent Citations
Construct concave corridor high altitude formwork support
CN206784942U
Cited By
Positioning device for ultrahigh formwork construction of corridor
CN224432041U