Steel trestle steel pipe pile inserting and driving guide device

By using the combination device of the Bere beam frame system, positioning frame and guide frame limiting system during the steel pipe pile insertion and driving process of the temporary steel trench, the problems of slow construction speed and unsatisfactory stability in the traditional method are solved, and the rapid, accurate and efficient insertion and driving of steel pipe piles is achieved.

CN222935993UActive Publication Date: 2025-06-03CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422155224.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-09-03
Publication Date
2025-06-03
Estimated Expiration
2034-09-03

AI Technical Summary

Technical Problem

The traditional temporary steel trench steel pipe pile insertion and driving method is slow to construct, and the position and verticality of the pipe pile are difficult to ensure, resulting in the unsatisfactory stability of the steel trench.

Method used

The combination device of the Bere beam frame system, positioning frame and guide frame limiting system is used to ensure the rapid insertion and accurate positioning of steel pipe piles through standard Bere beams, standard support frames, walkway plates, guardrails and ladders.

Benefits of technology

The speed and efficiency of steel pipe pile insertion construction are improved, the position accuracy and stability of steel pipe piles are ensured, and the overall construction quality is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222935993U_ABST
    Figure CN222935993U_ABST
Patent Text Reader

Abstract

The utility model discloses a steel trestle steel pipe pile inserting and driving guide device, and relates to the field of bridges. Comprising a bailey beam frame system, a positioning frame and a guide frame limiting system, the bailey beam frame system comprises multiple sets of standard bailey beams, standard supporting frames and walkway plates, the multiple sets of standard bailey beams are vertically placed in parallel through the standard supporting frames fixedly connected with the standard bailey beams, and the walkway plates are fixedly installed on the multiple sets of standard bailey beams; the positioning frame is fixedly arranged on the walkway plate, the guide frame limiting system comprises transverse limiting channel steel and a plurality of vertical limiting channel steel, the transverse limiting channel steel penetrates through the multiple sets of standard Bailey beams and is fixedly connected with the vertical limiting channel steel, and the vertical limiting channel steel is vertically and fixedly connected to the branch trestle. The trestle bridge steel pipe pile inserting and driving device is used for solving the problems of low steel pipe pile inserting and driving construction speed and low precision, and improves the safety quality and the working efficiency of trestle bridge steel pipe pile inserting and driving construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the field of bridges, and particularly relates to a guiding device for inserting and driving steel pipe piles of a steel trestle bridge. Background Technique

[0002] A temporary steel trestle bridge refers to a temporary steel structure bridge used during bridge construction or maintenance. It is usually made of steel, has high load-bearing capacity and stability, and is used to temporarily replace the original bridge for transportation. Compared with conventional bridges, a temporary steel trestle bridge can be erected more quickly, and can also be disassembled and moved according to needs, flexibly meeting different construction periods and site requirements.

[0003] During the erection process of a temporary steel trestle bridge, the insertion and driving of steel pipe piles is a crucial link. Traditional construction methods mainly use a single-hole guiding frame for the positioning and insertion of steel pipe piles, but this method has exposed many defects in practice: the construction speed is slow, the position and verticality of the pipe piles are difficult to guarantee, and the stability of the steel trestle bridge is not ideal.

[0004] Therefore, it is necessary to provide a convenient guiding device for inserting and driving steel pipe piles to improve the quality and working efficiency of the insertion and driving of steel pipe piles of a steel trestle bridge. Content of the Utility Model

[0005] To overcome the above technical problems, the utility model provides a guiding device for inserting and driving steel pipe piles of a steel trestle bridge to improve the quality and working efficiency of the construction tooling for inserting and driving steel pipe piles of the trestle bridge.

[0006] The technical solution adopted by the utility model is as follows:

[0007] A guiding device for inserting and driving steel pipe piles of a steel trestle bridge, both ends of the device are fixedly installed on an existing branch trestle bridge, and the device includes:

[0008] A Bailey beam frame system, the Bailey beam frame system includes multiple groups of standard Bailey beams, multiple standard support frames and a walkway board. Multiple groups of the standard Bailey beams are arranged vertically in parallel. The standard support frames are fixedly connected with multiple groups of the standard Bailey beams. The walkway board is fixedly installed on multiple groups of the standard Bailey beams. Multiple positioning holes are opened on the walkway board.

[0009] A positioning frame, the positioning frame is fixedly arranged at the positions of the positioning holes on the walkway board.

[0010] A guiding frame limiting system, including a transverse limiting channel steel and multiple vertical limiting channel steels. The transverse limiting channel steel passes through multiple groups of the standard Bailey beams. The transverse limiting channel steel is fixedly connected with multiple vertical limiting channel steels. Multiple vertical limiting channel steels are vertically and fixedly connected to the branch trestle bridge.

[0011] Further, the positioning frame is in a square shape.

[0012] Furthermore, the positioning frame is made of No. 10 channel steel.

[0013] Furthermore, there are 3 sets of the standard Bailey beams in the Bailey beam frame system.

[0014] Furthermore, the standard support frame is fixedly connected to the multiple sets of standard Bailey beams through pin shafts.

[0015] Furthermore, the Bailey beam frame system further includes a ladder, and the ladder is fixedly connected to one side of the Bailey beam frame system.

[0016] Furthermore, the Bailey beam frame system further includes guardrails, and the guardrails are fixedly connected to both sides of the walkway slab.

[0017] Furthermore, the vertical limit channel steel is fixedly connected to both ends of the horizontal limit channel steel, and the vertical limit channel steel is fixedly connected to the deck of the support trestle bridge.

[0018] The beneficial effects of the present utility model are as follows:

[0019] 1. The present utility model is assembled with existing construction materials such as standard Bailey beams, and is convenient for hoisting, thus accelerating the construction speed and saving the processing cost.

[0020] 2. By arranging guiding holes on the walkway slab, the present utility model can achieve the rapid driving of steel pipe piles and fix the positions of the steel pipe piles, which can not only improve the processing efficiency, but also ensure the construction quality of the driving of steel pipe piles. Description of the Drawings

[0021] Figure 1 is a side view of the steel trestle bridge steel pipe pile driving guiding device provided by the present utility model;

[0022] Figure 2 is a schematic structural view of a set of standard Bailey beams;

[0023] Figure 3 is a front view of the steel trestle bridge steel pipe pile driving guiding device provided by the present utility model;

[0024] Figure 4 is a top view of the steel trestle bridge steel pipe pile driving guiding device provided by the present utility model;

[0025] Figure 5 is a schematic structural position view of the positioning frame.

[0026] In the drawings, the list of components represented by each reference numeral is as follows:

[0027] 1. Standard Bailey beam; 2. Standard support frame; 3. Walkway board; 4. Guardrail; 5. Ladder; 6. Positioning frame; 7. Horizontal limiting channel steel; 8. Vertical limiting channel steel; 9. Support trestle bridge; 10. Steel pipe pile. Detailed implementation mode

[0028] Next, the technical solutions in the embodiments of the present invention will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work shall fall within the protection scope of the present invention.

[0029] Next, the technical solutions in the embodiments of the present application will be clearly and completely described in conjunction with the accompanying drawings.

[0030] During the driving process of the steel pipe piles of the steel trestle bridge, in order to ensure the stability and safety of the steel trestle bridge, generally, a support trestle bridge 9 is used for support. A steel pipe pile driving guide frame device provided in the present invention is also fixedly arranged on the support trestle bridge 9.

[0031] As Figures 1 - 5 shown, the present invention provides a steel pipe pile driving guide frame device for a steel trestle bridge, which includes a Bailey beam frame system, a positioning frame 6 and a guide frame limiting system. Among them, the positioning frame 6 is placed on the Bailey beam frame system, and the guide frame limiting system is fixedly connected to both ends of the bottom of the Bailey beam frame system. The Bailey beam frame system is used for the basic support of the steel trestle bridge and provides a construction platform. The positioning frame 6 is used to ensure the accuracy of the driving position and can determine the quantity according to the engineering requirements, so as to realize the rapid driving of the steel pipe piles 10 and improve the processing efficiency. The guide frame limiting system is used to fix the steel pipe pile driving guide device of the steel trestle bridge to the existing support trestle bridge 9 and determine the position and direction of the steel trestle bridge.

[0032] Specifically, as Figure 1 and Figure 3 shown, the Bailey beam frame system includes multiple groups of standard Bailey beams 1, multiple standard support frames 2, walkway boards 3, guardrails 4 and ladders 5. In this embodiment, 3 groups of standard Bailey beams 1 are provided. As Figure 2As shown in the figure, there is a set of standard Bailey beams 1. It should be noted that the length of the above-mentioned standard Bailey beams 1 needs to be determined according to the engineering requirements. The standard support frame 2 is perpendicular to the standard Bailey beam 1, and the standard support frame 2 is placed between every two groups of standard Bailey beams 1 and fixed by a pin shaft, so that the 3 groups of standard Bailey beams 1 are placed parallel and vertically. The walkway plate 3 is fixed on the top of the 3 groups of standard Bailey beams 1 by welding, and a plurality of positioning holes are opened on the walkway plate 3. The number and positions of the above-mentioned positioning holes correspond to those of the steel pipe piles 10 to be inserted. The guardrail 4 is fixed on both sides of the walkway plate 3 by bolts and connected to the standard Bailey beam 1. The ladder 5 is fixed at one end of the standard Bailey beam 1 by welding. In the Bailey beam frame system, the standard Bailey beam 1 and the standard support frame 2 are both existing construction materials, which are convenient to use and can save tooling costs. Among them, the standard Bailey beam 1 constitutes the main frame of the device, the standard support frame 2 is used to enhance the stability of the overall frame, the walkway plate 3 is used to provide a construction platform, the guardrail 4 is used to improve the construction safety, and the ladder 5 facilitates the construction personnel to go up and down between the support trestle 9 and the walkway plate 3.

[0033] As Figure 1 , Figure 4 and Figure 5 shown, the positioning frame 6 is fixed by welding on the edge of the positioning hole of the walkway plate 3. In this embodiment, the positioning frame 6 is in a square shape and is made of No. 10 channel steel. The square shape helps to reduce the deviation during the insertion process, ensure the accurate insertion of the steel pipe pile 10, and improve the accuracy and stability of the overall structure. The No. 10 channel steel has excellent mechanical properties and is convenient for processing. As a common building material, it can reduce the material cost on the premise of ensuring the quality. Through the guidance of the positioning frame 6, the insertion speed of the steel pipe pile 10 is accelerated and the construction efficiency is improved.

[0034] Specifically, as Figures 1 - 3 shown, the guide frame limit system is located at the head and tail ends of each group of standard Bailey beams 1, including a horizontal limit channel steel 7 and a plurality of vertical limit channel steels 8. The horizontal limit channel steel 7 passes through the 3 groups of standard Bailey beams 1, and the plurality of vertical limit channel steels 8 are perpendicular to the horizontal limit channel steel 7 and welded at both ends of the horizontal limit channel steel 7. The vertical limit channel steel 8 is fixedly connected to the support trestle 9. In this embodiment, there are 2 vertical limit channel steels 8, which are respectively fixed at both ends of the horizontal limit channel steel 7. Among them, the horizontal limit channel steel 7 is used to ensure that the guide frame limit system can be firmly fixed to the Bailey beam frame system and serves as the support foundation for the vertical limit channel steel 8, while the vertical limit channel steel 8 can fix the steel trestle steel pipe pile driving guide device to the support trestle 9 by welding to the deck of the support trestle 9.

[0035] The working principle of the present utility model:

[0036] Before construction, according to the construction requirements, prepare 3 sets of standard Bailey beams 1 with appropriate lengths. Connect multiple standard support frames 2 to the 3 sets of standard Bailey beams 1 with pin shafts to form a stable parallel vertical structure for the three sets of standard Bailey beams 1. Weld the walkway plates 3 on the standard Bailey beams 1, and install the guardrails 4 and ladders 5. According to the project requirements, use No. 10 channel steel to make multiple square-shaped positioning frames 6 and weld them on the positioning holes of the walkway plates 3 to complete the assembly of the steel trestle steel pipe pile driving guide device.

[0037] During construction, hoist the steel trestle steel pipe pile driving guide device as a whole. Pass two transverse limiting channel steels 7 through the first and last ends of the 3 sets of standard Bailey beams 1 respectively. Three vertical limiting channel steels 8 are perpendicular to the transverse limiting channel steels 7 and welded to both ends of the transverse limiting channel steels 7. Weld the vertical limiting channel steels 8 to the bridge deck of the branch trestle 9. After the device is fixed, hoist multiple steel pipe piles 10 and insert them into the positioning frames 6, and use a vibratory hammer to drive them in turn to achieve the rapid driving of multiple steel pipe piles 10.

[0038] After completion, remove the vertical limiting channel steels 8 from the branch trestle 9, hoist the device to the position of the next row of steel pipe piles 10, and carry out a new round of driving.

[0039] The above has described in detail an embodiment of the present invention, but the content described is only a preferred embodiment of the present invention and cannot be considered as limiting the scope of implementation of the present invention. All equivalent changes and improvements made according to the scope of the application of the present invention shall still fall within the scope covered by the patent of the present invention.

Claims

1. A steel trestle steel pipe pile driving guide device, wherein both ends of the device are fixedly mounted on an existing supporting trestle (9), It is characterized in that include: A Bailey beam frame system, the Bailey beam frame system comprising a plurality of groups of standard Bailey beams (1), a plurality of standard support frames (2) and a walkway plate (3), the plurality of groups of standard Bailey beams (1) being arranged vertically in parallel, the standard support frames (2) being fixedly connected to the plurality of groups of standard Bailey beams (1), the walkway plate (3) being fixedly mounted on the plurality of groups of standard Bailey beams (1), and the walkway plate (3) being provided with a plurality of positioning holes, A positioning frame (6), wherein the positioning frame (6) is fixedly arranged at the position of the positioning hole of the walkway plate (3), The guide frame limiting system comprises a transverse limiting channel steel (7) and a plurality of vertical limiting channel steels (8), wherein the transverse limiting channel steel (7) passes through a plurality of groups of standard Bailey beams (1), the transverse limiting channel steel (7) is fixedly connected to the plurality of vertical limiting channel steels (8), and the plurality of vertical limiting channel steels (8) are vertically fixedly connected to the supporting trestle (9).

2. The steel trestle steel pipe pile driving guide device according to claim 1 is characterized in that: The positioning frame (6) is in the shape of a square.

3. A steel trestle steel pipe pile driving guide device according to claim 1 or 2, characterized in that: The positioning frame (6) is made of No. 10 channel steel.

4. The steel trestle steel pipe pile driving guide device according to claim 1, characterized in that: The Bailey beam frame system is provided with three groups of standard Bailey beams (1).

5. The steel trestle steel pipe pile driving guide device according to claim 1, characterized in that: The standard support frame (2) is fixedly connected to the plurality of groups of standard Bailey beams (1) via pins.

6. The steel trestle steel pipe pile driving guide device according to claim 1, characterized in that: The Bailey beam frame system further comprises a ladder (5), wherein the ladder (5) is fixedly connected to one side of the Bailey beam frame system.

7. A steel trestle steel pipe pile driving guide device according to claim 1 or 6, characterized in that: The Bailey beam frame system further comprises a guardrail (4), wherein the guardrail (4) is fixedly connected to both sides of the walkway plate (3).

8. The steel trestle steel pipe pile driving guide device according to claim 1, characterized in that: The vertical limit channel steel (8) is fixedly connected to the two ends of the transverse limit channel steel (7), and the vertical limit channel steel (8) is fixedly connected to the bridge deck of the supporting trestle (9).