Building curtain wall with supporting ribs

By designing the support rib structure and cleaning mechanism in the architectural curtain wall, the problem of the building curtain wall without supporting ribs being easily disengaged under the action of external forces is solved, the stability and cleaning effect of the curtain wall are improved, and the maintenance cost and time are reduced.

CN222949273UActive Publication Date: 2025-06-06ZHEJIANG BAWEI CONSTRUCTION CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420858085.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-23
Publication Date
2025-06-06
Estimated Expiration
2034-04-23

AI Technical Summary

Technical Problem

Building curtain walls without supporting rib structures are prone to disengage as a whole when subjected to external forces, resulting in large losses, long maintenance time and high cost, and safety hazards in geological disasters.

Method used

A architectural curtain wall structure with support ribs is designed, including the curtain wall body, cleaning mechanism and support rib structure. The support rib structure improves the stability and strength of the curtain wall through external positioning support ribs, ring support ribs, transverse support ribs and support filling concrete, and cleans it with water spray holes and cleaning pipes through cleaning mechanisms.

Benefits of technology

By increasing the support rib structure, the stability and strength of the curtain wall are improved, the losses under external forces are reduced, the maintenance costs and time are reduced, and the cleaning effect of the curtain wall is improved through the cleaning mechanism.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222949273U_ABST
    Figure CN222949273U_ABST
Patent Text Reader

Abstract

The utility model provides a building curtain wall with a supporting rib, which comprises a curtain wall structure, a cleaning mechanism and a supporting rib structure, and the curtain wall structure is composed of a curtain wall body and the cleaning mechanism. A left ring supporting rib at the left end of the supporting rib structure is embedded into the inner side of the curtain wall body to support the curtain wall body, an outer positioning supporting rib at the right end of the supporting rib structure is embedded into the inner side of a building outer wall to be relatively supported and fixed, and the middle position of the supporting rib structure passes through a transverse supporting rib and a ring supporting rib and is internally poured with supporting filling concrete, so that the connecting strength is improved; and by adding the curtain wall structure, external water is guided in through the water guide pipe, enters the inner sides of the multiple sets of cleaning pipes and then is sprayed out through the water spraying holes, so that the left side face of the curtain wall body can be cleaned, and the cleaning effect is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of building curtain walls, in particular to a building curtain wall provided with supporting ribs. Background Art

[0002] Building curtain wall refers to the non-load-bearing exterior wall enclosure of a building, which is usually composed of panels (glass, metal plates, stone slabs, ceramic plates, etc.) and the supporting structure behind (aluminum beams and columns, steel structures, glass ribs, etc.). The common connection method between the building curtain wall and the building is to set up a corresponding supporting rib structure. As an important material with load-bearing support in buildings, the supporting rib has a wide range of applications. The supporting rib structure can improve the supporting stability and strength of the building, and can reduce the damage rate and degree of the building when accidents such as geological disasters occur. Therefore, the connection between the building curtain wall without a corresponding supporting rib structure and the building is relatively weak, and it is very easy to dismember the whole building curtain wall when it is subjected to external force, resulting in a large degree of loss and increasing the subsequent maintenance time and maintenance cost.

[0003] Secondly, when accidents such as geological disasters occur, the loose connection of the building curtain wall can easily cause the building curtain wall to fall off, which will pose a certain safety hazard of injuring people.

[0004] In summary, there are some problems in the use of building curtain walls without supporting rib structures, so it is hoped to propose a new structure to solve the above technical problems. Utility Model Content

[0005] In view of the deficiencies in the prior art, the utility model aims to provide a building curtain wall with supporting ribs to solve the problems raised in the above-mentioned background technology.

[0006] The utility model is realized by the following technical scheme: a building curtain wall provided with supporting ribs comprises: a curtain wall structure, a cleaning mechanism and a supporting rib structure, wherein the curtain wall structure is composed of a curtain wall body and the cleaning mechanism, the curtain wall body is provided on the outside of the curtain wall structure, a cleaning mechanism groove for installing the cleaning mechanism is provided on the upper end of the inner side of the curtain wall body, a cleaning mechanism for cleaning the left side of the curtain wall body is provided on the inner side of the cleaning mechanism groove, and a supporting rib structure for improving the strength of the curtain wall is provided on the right side of the curtain wall structure.

[0007] As a preferred embodiment, the right outer end of the support rib structure is provided with an external positioning support rib for supporting and fixing with the building body, and the left outer periphery of the external positioning support rib is provided with a plurality of groups of linearly equally distributed ring support ribs, which can be connected and fixed with the outer wall of the building through the external positioning support rib.

[0008] As a preferred embodiment, support filling concrete is provided inside the annular support ribs, transverse support ribs are provided at the four corners inside the support filling concrete, and the outer side surfaces of the transverse support ribs fit the outer side surfaces of the annular support ribs.

[0009] As a preferred embodiment, several groups of left ring support ribs are provided on the outside of the transverse support ribs, connecting support ribs are provided between the transverse support ribs and the external positioning support ribs, and several groups of left ring support ribs are located inside the curtain wall body and can be connected and fixed to the curtain wall body through the left ring support ribs.

[0010] As a preferred embodiment, the left side of the curtain wall body is provided with a plurality of groups of circular holes which are equally distributed linearly, and the upper left end of the cleaning mechanism is provided with a plurality of groups of cleaning tubes which are equally distributed linearly, and each group of the cleaning tubes is provided corresponding to a group of circular holes.

[0011] As a preferred embodiment, a plurality of water spray holes are provided at the lower end of the outer side surface of the cleaning pipe, a cleaning main frame is provided on the right side of the cleaning pipe, and a telescopic hose is provided at the center of the lower surface of the cleaning main frame;

[0012] A water guide pipe is provided below the telescopic hose, and several groups of cleaning pipes are interconnected with the telescopic hose so that external water is introduced through the water guide pipe, enters the inner side of several groups of cleaning pipes, and is sprayed out through the water spray holes, thereby cleaning the left side of the curtain wall body and improving the cleaning effect.

[0013] As a preferred embodiment, guide rails are provided at both front and rear ends of the lower surface of the cleaning main frame, a guide groove is opened on the inner lower surface of the cleaning mechanism groove, the guide rails and the guide groove are movably engaged with each other, and a pen-type electric telescopic rod is provided on the right side of the cleaning main frame.

[0014] After adopting the above technical scheme, the beneficial effects of the utility model are as follows: by adding a curtain wall structure and a supporting rib structure, the left ring supporting rib at the left end of the supporting rib structure is embedded in the inner side of the curtain wall body to support the curtain wall body, and the outer positioning supporting rib at the right end of the supporting rib structure is embedded in the inner side of the outer wall of the building to support it relatively and fix it, and the middle position of the supporting rib structure is supported by transverse supporting ribs and ring supporting ribs and the internal pouring and supporting concrete is filled to improve the connection strength, thereby improving the stability and strength of the curtain wall, and by adding the curtain wall structure, external water is introduced through the water guide pipe, and enters the inner side of several groups of cleaning pipes and is sprayed out through the water spray holes, thereby cleaning the left side of the curtain wall body and improving the cleaning effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0016] Figure 1 The utility model is a schematic diagram of the overall structure of a building curtain wall provided with supporting ribs.

[0017] Figure 2 The utility model is a structural schematic diagram of a curtain wall structure in a building curtain wall provided with supporting ribs.

[0018] Figure 3 The utility model is a schematic structural diagram of a cleaning mechanism in a building curtain wall provided with supporting ribs.

[0019] Figure 4 The utility model is a structural schematic diagram of the supporting rib structure in the building curtain wall provided with supporting ribs.

[0020] In the figure, 100-curtain wall structure, 101-curtain wall body, 102-cleaning mechanism;

[0021] 200-supporting reinforcement structure, 201-external positioning supporting reinforcement, 202-connecting supporting reinforcement, 203-transverse supporting reinforcement, 204-ring supporting reinforcement, 205-supporting poured concrete, 206-left ring supporting reinforcement;

[0022] 102a-cleaning main frame, 102b-pen-type electric telescopic rod, 102c-guide rail, 102d-cleaning pipe, 102e-water spray hole, 102f-telescopic hose, 102g-water guide pipe. DETAILED DESCRIPTION

[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0024] See also Figures 1 to 4 The utility model provides a technical solution: a building curtain wall with supporting ribs, comprising: a curtain wall structure 100, a cleaning mechanism 102 and a supporting rib structure 200, wherein the curtain wall structure 100 is composed of a curtain wall body 101 and a cleaning mechanism 102;

[0025] A curtain wall body 101 is disposed outside the curtain wall structure 100, a cleaning mechanism groove for installing a cleaning mechanism 102 is provided at the upper end of the inner side of the curtain wall body 101, and a cleaning mechanism 102 for cleaning the left side of the curtain wall body 101 is disposed inside the cleaning mechanism groove;

[0026] A supporting rib structure 200 is provided on the right side of the curtain wall structure 100 for improving the strength of the curtain wall.

[0027] The right outer end of the support rib structure 200 is provided with an external positioning support rib 201 for supporting and fixing with the building body, and the left outer periphery of the external positioning support rib 201 is provided with a plurality of groups of linearly equally distributed ring support ribs 204, which can be connected and fixed with the outer wall of the building through the external positioning support rib 201.

[0028] Support filling concrete 205 is provided inside the ring support rib 204 , and transverse support ribs 203 are provided at the four corners inside the support filling concrete 205 , and the outer side surfaces of the transverse support ribs 203 fit the outer side surfaces of the ring support ribs 204 .

[0029] Several groups of left ring support ribs 206 are provided on the outside of the transverse support ribs 203, and connecting support ribs 202 are provided between the transverse support ribs 203 and the outer positioning support ribs 201. Several groups of left ring support ribs 206 are located on the inner side of the curtain wall body 101, and can be connected and fixed to the curtain wall body 101 through the left ring support ribs 206.

[0030] See also Figure 1-Figure 2 and Figure 4 As the first embodiment of the utility model: first, the left ring support rib 206 at the left end of the support rib structure 200 is embedded in the inner side of the curtain wall body 101, and can be connected and fixed with the curtain wall body 101 and support the curtain wall body 101. Secondly, the outer positioning support rib 201 at the right end of the support rib structure 200 is embedded in the inner side of the outer wall of the building, so that it is relatively supported and fixed. The middle position of the support rib structure 200 is supported and connected by the transverse support rib 203 and the ring support rib 204, and the internal pouring support filling concrete 205 can improve the connection strength, thereby improving the stability and strength of the curtain wall.

[0031] The left side of the curtain wall body 101 is provided with a plurality of groups of circular holes which are equally distributed linearly. The upper left end of the cleaning mechanism 102 is provided with a plurality of groups of cleaning tubes 102d which are equally distributed linearly. Each group of cleaning tubes 102d is provided corresponding to a group of circular holes.

[0032] A plurality of water spray holes 102e are provided at the lower end of the outer side of the cleaning pipe 102d. A cleaning main frame 102a is provided on the right side of the cleaning pipe 102d. A telescopic hose 102f is provided at the center of the lower surface of the cleaning main frame 102a.

[0033] A water pipe 102g is provided below the telescopic hose 102f, and several groups of cleaning pipes 102d are interconnected with the telescopic hose 102f, so that external water is introduced through the water pipe 102g, enters the inner side of several groups of cleaning pipes 102d, and is sprayed out through the water spray hole 102e, thereby cleaning the left side of the curtain wall body 101 and improving the cleaning effect.

[0034] See also Figure 1-Figure 4 , as the second embodiment of the utility model: based on the above-mentioned first embodiment, firstly, after long-term use, some dust that has not been washed away by rainwater will be laid on the left side of the curtain wall body 101. The user can introduce external water through the water pipe 102g, and enter the inner side of several groups of cleaning pipes 102d interconnected with the water pipe 102g, and then spray it out through the water spray hole 102e, so that the left side of the curtain wall body 101 can be cleaned, thereby improving the cleaning effect.

[0035] Guide rails 102c are provided at both ends of the lower surface of the cleaning main frame 102a, and a guide groove is provided on the lower surface inside the cleaning mechanism groove. The guide rails 102c and the guide groove are movably engaged with each other, and a pen-type electric telescopic rod 102b is provided on the right side of the cleaning main frame 102a.

[0036] See also Figure 1-Figure 3 , as the third embodiment of the present utility model: based on the above-mentioned second embodiment, a plurality of groups of circular holes in linear equal distribution are provided on the left side of the curtain wall body 101, a telescopic hose 102f is provided at the center of the lower surface of the cleaning main frame 102a, guide rails 102c are provided at the front and rear ends of the lower surface of the cleaning main frame 102a, a guide groove is provided on the inner lower surface of the cleaning mechanism groove, and a pen-type electric telescopic rod 102b is provided on the right side of the cleaning main frame 102a. First, when the cleaning mechanism 102 is in use, its cleaning tube 102d does not extend out of the circular hole, which can improve the aesthetics of the curtain wall structure 100. Secondly, when cleaning operations are required, the user starts the pen-type electric telescopic rod 102b to drive the cleaning main frame 102a to slide the guide rail 102c along the guide groove, so that the telescopic hose 102f is extended and moved, and the cleaning tube 102d can be extended out of the circular hole for cleaning operations.

[0037] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. Building curtain wall with supporting ribs, including: A curtain wall structure (100), a cleaning mechanism (102) and a supporting rib structure (200), characterized in that: the curtain wall structure (100) is composed of a curtain wall body (101) and a cleaning mechanism (102); A curtain wall body (101) is provided on the outside of the curtain wall structure (100); a cleaning mechanism groove for installing a cleaning mechanism (102) is provided on the inner upper end of the curtain wall body (101); a cleaning mechanism (102) for cleaning the left side of the curtain wall body (101) is provided on the inner side of the cleaning mechanism groove; A supporting rib structure (200) for improving the strength of the curtain wall is provided on the right side of the curtain wall structure (100).

2. The building curtain wall with supporting ribs as claimed in claim 1, characterized in that: The right outer end of the support rib structure (200) is provided with an external positioning support rib (201) for supporting and fixing with the building body, and the left outer periphery of the external positioning support rib (201) is provided with a plurality of groups of linearly equally distributed ring support ribs (204).

3. The building curtain wall with supporting ribs as claimed in claim 2, characterized in that: Support filling concrete (205) is provided inside the annular support rib (204), and transverse support ribs (203) are provided at the four corners inside the support filling concrete (205), and the outer side surfaces of the transverse support ribs (203) are in contact with the outer side surfaces of the annular support ribs (204).

4. The building curtain wall with supporting ribs as claimed in claim 3, characterized in that: A plurality of groups of left ring support ribs (206) are arranged outside the transverse support ribs (203), connecting support ribs (202) are arranged between the transverse support ribs (203) and the outer positioning support ribs (201), and a plurality of groups of left ring support ribs (206) are located inside the curtain wall body (101).

5. The building curtain wall with supporting ribs as claimed in claim 1, characterized in that: The left side of the curtain wall body (101) is provided with a plurality of groups of circular holes which are evenly distributed linearly, and the upper left end of the cleaning mechanism (102) is provided with a plurality of groups of cleaning tubes (102d) which are evenly distributed linearly, and each group of the cleaning tubes (102d) is arranged corresponding to a group of circular holes.

6. The building curtain wall with supporting ribs as claimed in claim 5, characterized in that: A plurality of water spray holes (102e) are provided at the lower end of the outer side surface of the cleaning pipe (102d); a cleaning main frame (102a) is provided on the right side of the cleaning pipe (102d); and a telescopic hose (102f) is provided at the center of the lower surface of the cleaning main frame (102a); A water guide pipe (102g) is provided below the telescopic hose (102f), and a plurality of groups of cleaning pipes (102d) are interconnected with the telescopic hose (102f).

7. The building curtain wall with supporting ribs as claimed in claim 6, characterized in that: The front and rear ends of the lower surface of the cleaning main frame (102a) are both provided with guide rails (102c); the inner lower surface of the cleaning mechanism groove is provided with a guide groove; the guide rails (102c) and the guide groove are movably engaged with each other; and a pen-type electric telescopic rod (102b) is provided on the right side of the cleaning main frame (102a).