Large-cantilever roof cornice aluminum plate curtain wall mounting device
By using a combination device of frame body, columns, reinforcement rods, working platforms, auxiliary platforms, climbing mechanisms and stabilization mechanisms in the construction of aluminum panel curtain walls with large cantilever roof eaves, the problem of poor construction environment in the existing technology in high cantilever construction is solved, and a safer and more efficient construction effect is achieved.
Patent Information
- Application Number
- CN202421421756.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-20
- Publication Date
- 2025-06-06
- Estimated Expiration
- 2034-06-20
AI Technical Summary
The existing simple cantilever gutter aluminum plate installation bracket is constructed using only a combination of suspension ladder and load bearing platform. When encountering the eaves of a large cantilever roof, due to the large cantilever length and the construction height, this combination cannot provide a better construction environment.
A large cantilever roof eaves aluminum panel curtain wall installation device is adopted, including a frame body and an aerial work vehicle. The frame body is composed of four columns, a reinforcement rod is arranged between the columns, and a working platform and an auxiliary platform are arranged on the top of the columns. A climbing mechanism is arranged between the two, and a stabilizing mechanism and an oblique support rod are arranged on the columns to form a triangular structure to increase the stability of the working platform.
This device provides sufficient working surface for the construction of roof eaves curtain walls, greatly reducing the investment in mechanical measures, and ensuring the stable, safe and orderly construction of roof eaves curtain walls.
Smart Images

Figure CN222949428U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of building engineering decoration and renovation construction, and particularly relates to a large cantilever roof eaves aluminum plate curtain wall installation device. Background Art
[0002] At present, with the development of the economy and society and the continuous improvement of people's living quality, exterior curtain wall decoration has been rapidly applied and developed in recent years, especially in some urban landmark building groups. Various curtain wall structures and shapes emerge in an endless stream, which also gives different meanings and display effects to the buildings.
[0003] The Chinese utility model patent currently announced as CN215716656U discloses a simple cantilever gutter aluminum plate installation bracket, which is provided with a hanging ladder and a bearing platform. The hanging ladder includes a hanging part and a telescopic part. The bottom of the hanging part is sleeved on the telescopic part, and the two are connected by bolts. The hanging part is used to hang the hanging ladder on the gutter, and the bearing platform is arranged on the telescopic part. It includes a triangular support frame riding on the outside of the telescopic part and a springboard arranged on the triangular support frame. A simple cantilever gutter aluminum plate installation device is provided, which has the advantages of low safety hazards, retractable, simple use, fast installation speed and low cost.
[0004] This patent only uses a combination of a hanging ladder and a load-bearing platform for construction. When encountering the eaves part of a large cantilevered roof, due to the long cantilever length and the high construction height, this combination cannot provide a better construction environment. Utility Model Content
[0005] The utility model aims to provide an installation device for an aluminum plate curtain wall at the eaves of a large cantilevered roof, which solves the problem that an existing simple cantilevered gutter aluminum plate installation bracket is constructed by only using a combination of a hanging ladder and a bearing platform. When encountering the eaves part of a large cantilevered roof, due to the large cantilever length and the high construction working height, the combination cannot provide a better construction environment.
[0006] The above-mentioned technical purpose of the utility model is achieved through the following technical scheme: a large cantilever roof eaves aluminum plate curtain wall installation device, including a frame and an aerial work vehicle, the aerial work vehicle is arranged on one side of the frame, the frame is composed of four columns, and reinforcing rods are arranged between the four columns. The number of the reinforcing rods is several and evenly arranged. A working platform is arranged on the top of the column, and an auxiliary platform is arranged below the working platform. Climbing mechanisms are arranged between the two auxiliary platforms and between the auxiliary platform and the working platform. A stabilizing mechanism is arranged on the column, and an oblique support rod is arranged between the column and the working platform. A triangle is formed between the column, the working platform and the oblique support rod.
[0007] The above technical scheme is adopted, by setting a frame, an aerial work vehicle, columns, reinforcing rods, a work platform, an auxiliary platform, a climbing mechanism, a stabilizing mechanism and diagonal braces. When in use, first the frame is composed of four columns, and then the strength of the frame is increased by the reinforcing rods. Then the climbing mechanism enables the workers to climb onto the auxiliary platform and the work platform. The auxiliary platform can be convenient for placing aluminum curtain walls or other tools, which can be handed to the workers on the work platform by other workers. Then the diagonal braces, columns and work platform form a triangle, which can increase the stability of the work platform. The installers stand on the work platform as much as possible to perform curtain wall installation operations to reduce the difficulty of installation operations. The aluminum panels of the roof eaves curtain walls outside the range of the work platform are directly constructed by aerial work vehicles. This combined construction method provides sufficient working surfaces for the construction of roof eaves curtain walls, greatly reduces the investment in mechanical measures, and provides a basis for the smooth, safe and orderly construction of roof eaves curtain walls.
[0008] Further: the stabilizing mechanism includes a fixing sleeve, a vertical plate, a cross bar, an oblique rod and a grounding rod, the fixing sleeve is set on the column by bolts, the vertical plate is set on the fixing sleeve, the cross bar is set at the lower end of the vertical rod, the oblique rod is set at the upper end of the vertical plate, the oblique rod is set at an angle, the grounding plate is set at the other end of the cross bar and the oblique rod, and the grounding rod is set vertically.
[0009] By adopting the above technical scheme, by setting a fixing sleeve, a vertical plate, a horizontal bar, an oblique bar and a grounding rod, when in use, the vertical plate is first fixed to the column through the fixing sleeve, and then the vertical plate can fix the horizontal bar and the oblique bar, and then the grounding rod is in contact with the ground, and the vertical plate, the horizontal bar and the oblique bar jointly form a triangular support frame to further improve the stability of the frame.
[0010] Further: the climbing mechanism includes a vertical pole, a climbing pole and a fixed pole, the vertical pole is arranged between the auxiliary platforms and between the auxiliary platform and the working platform, the number of the vertical poles is two and they are symmetrically arranged, the climbing pole is arranged on the vertical pole, the number of the climbing poles is several and they are evenly arranged, one end of the fixed pole is arranged on the vertical pole, and the other end of the fixed pole is detachably arranged on the column.
[0011] By adopting the above technical solution, by setting up vertical poles, climbing poles and fixed poles, when in use, the vertical poles are first set between the auxiliary platforms and between the auxiliary platform and the working platform, and are detachably set on the vertical poles through the fixed poles, and then the operators can reach the auxiliary platform or the working platform through the climbing poles.
[0012] Furthermore: safety nets are arranged on the sides of the working platform and the auxiliary platform, and the working platform and the auxiliary platform are fully covered with steel springboards.
[0013] By adopting the above technical solution, a safety net is provided. When in use, the safety net can protect the operating personnel, prevent the operating personnel from falling off the working platform or the auxiliary platform, and avoid safety accidents.
[0014] Furthermore: a through passage is provided on the working platform, and the climbing mechanism extends to the top of the through passage.
[0015] By adopting the above technical solution, a through passage is provided. When in use, the vertical pole extends to the outside of the through passage, and the operator can enter the working platform through the through passage.
[0016] Furthermore: the lower surface of the column is provided with universal wheels with a locking function, and the number of the universal wheels is four and they are symmetrically arranged.
[0017] By adopting the above technical solution, by setting the universal wheel, when in use, the universal wheel can improve the maneuverability of the column, making the column easy to move, and the universal wheel has a self-locking function, which can prevent the column from sliding when in use.
[0018] Furthermore: the climbing pole is provided with an anti-slip layer for increasing friction.
[0019] By adopting the above technical solution, an anti-skid layer is provided. When in use, the anti-skid layer can increase the friction between the operator and the climbing pole, thereby preventing the operator from slipping and thus avoiding safety accidents.
[0020] Furthermore: the lower surface of the grounding rod is provided with an anti-slip pad for increasing friction.
[0021] By adopting the above technical solution, the anti-skid pad is provided. When in use, the anti-skid pad can increase the friction between the grounding rod and the ground, and can further improve the stability of the column.
[0022] In summary, the utility model has the following beneficial effects:
[0023] By setting up a frame, an aerial work vehicle, columns, reinforcing rods, a work platform, an auxiliary platform, a climbing mechanism and diagonal braces, when in use, first the frame is composed of four columns, and then the strength of the frame is increased by the reinforcing rods, and then the climbing mechanism enables the workers to climb onto the auxiliary platform and the work platform. The auxiliary platform can be convenient for placing aluminum curtain walls or other tools, which can be handed to the workers on the work platform by other workers, and then the diagonal braces, columns and work platforms form a triangle, which can increase the stability of the work platform. The installers stand on the work platform as much as possible to perform curtain wall installation operations to reduce the difficulty of installation operations. The roof eaves curtain wall aluminum panels outside the range of the work platform are directly constructed by aerial work vehicles. This combined construction method provides sufficient working surfaces for the construction of roof eaves curtain walls, greatly reduces the investment in mechanical measures, and provides a basis for the smooth, safe and orderly construction of roof eaves curtain walls.
[0024] By setting a fixing sleeve, a vertical plate, a horizontal bar, an oblique bar and a grounding rod, when in use, the vertical plate is first fixed to the column through the fixing sleeve, and then the vertical plate can fix the horizontal bar and the oblique bar, and then the grounding rod contacts the ground, and the vertical plate, the horizontal bar and the oblique bar jointly form a triangular support frame to further improve the stability of the frame.
[0025] Based on the above-mentioned improvements, the overall technical effect achieved by the device is that it can provide sufficient working surface for the construction of roof eaves curtain walls, greatly reduce the investment in mechanical measures, and provide a basis for the smooth, safe and orderly construction of roof eaves curtain walls. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0027] Figure 2 It is a structural schematic diagram of the column, working platform and through passage of the utility model;
[0028] Figure 3 It is a structural schematic diagram of the stabilizing mechanism of the utility model;
[0029] Figure 4 The utility model Figure 2 Enlarged view of point A in the middle.
[0030] In the figure, 1, frame; 2, aerial work vehicle; 3, column; 4, reinforcing rod; 5, working platform; 6, auxiliary platform; 7, climbing mechanism; 8, stabilizing mechanism; 9, diagonal support rod; 10, safety net; 11, through passage; 12, universal wheel; 13, anti-skid layer; 14, anti-skid mat; 801, fixing sleeve; 802, vertical plate; 803, horizontal rod; 804, diagonal rod; 805, grounding rod; 701, vertical rod; 702, climbing rod; 703, fixing rod. DETAILED DESCRIPTION
[0031] The utility model is further described in detail below in conjunction with the accompanying drawings.
[0032] Example:
[0033] See also Figure 1-Figure 4 The utility model provides a technical solution: a large cantilever roof eaves aluminum plate curtain wall installation device, including a frame 1 and an aerial work vehicle 2, the aerial work vehicle 2 is arranged on one side of the frame 1, the frame 1 is composed of four columns 3, and reinforcing rods 4 are arranged between the four columns 3. The number of reinforcing rods 4 is several and evenly arranged. A working platform 5 is arranged on the top of the column 3, and an auxiliary platform 6 is arranged below the working platform 5. Climbing mechanisms 7 are arranged between the two auxiliary platforms 6 and between the auxiliary platform 6 and the working platform 5. A stabilizing mechanism 8 is arranged on the column 3, and an oblique support rod 9 is arranged between the column 3 and the working platform 5. A triangle is formed between the column 3, the working platform 5 and the oblique support rod 9.
[0034] By arranging the frame 1, the aerial work vehicle 2, the columns 3, the reinforcing rods 4, the working platform 5, the auxiliary platform 6, the climbing mechanism 7, the stabilizing mechanism 8 and the diagonal bracing rods 9, when in use, first the frame 1 is composed of four columns 3, and then the strength of the frame 1 is increased by the reinforcing rods 4, and then the climbing mechanism 7 enables the operators to climb onto the auxiliary platform 6 and the working platform 5, the auxiliary platform 6 can be convenient for placing the aluminum plate curtain wall or other tools, which can be handed over to the operators on the working platform 5 by other operators, and then the diagonal bracing rods 9, the columns 3 and the working platform 5 form a triangle, which can increase the stability of the working platform 5, and the installers stand on the working platform 5 as much as possible to perform curtain wall installation operations to reduce the difficulty of installation operations, and the roof eaves curtain wall aluminum plates outside the range of the working platform 5 are directly operated and constructed by the aerial work vehicle 2, and this combined construction method provides sufficient working surface for the roof eaves curtain wall construction, greatly reduces the input of mechanical measures, and provides a basis for the stable, safe and orderly construction of the roof eaves curtain wall.
[0035] refer to Figure 3The stabilizing mechanism 8 includes a fixing sleeve 801, a vertical plate 802, a cross bar 803, an oblique bar 804 and a grounding rod 805. The fixing sleeve 801 is arranged on the column 3 by bolts, the vertical plate 802 is arranged on the fixing sleeve 801, the cross bar 803 is arranged at the lower end of the vertical bar, the oblique bar 804 is arranged at the upper end of the vertical plate 802, the oblique bar 804 is arranged obliquely, the grounding plate is arranged at the other end of the cross bar 803 and the oblique bar 804, and the grounding rod 805 is arranged vertically. By setting a fixing sleeve 801, a vertical plate 802, a horizontal bar 803, an oblique bar 804 and a grounding rod 805, when in use, first the vertical plate 802 is fixed to the column 3 through the fixing sleeve 801, and then the vertical plate 802 can fix the horizontal bar 803 and the oblique bar 804, and then the grounding rod 805 contacts the ground, and the vertical plate 802, the horizontal bar 803 and the oblique bar 804 together form a triangular support frame, so as to further improve the stability of the frame 1.
[0036] refer to Figure 2 and Figure 3 The climbing mechanism 7 includes a vertical pole 701, a climbing pole 702 and a fixed pole 703. The vertical pole 701 is arranged between the auxiliary platforms 6 and between the auxiliary platform 6 and the working platform 5. There are two vertical poles 701 and they are symmetrically arranged. The climbing pole 702 is arranged on the vertical pole 701. There are several climbing poles 702 and they are evenly arranged. One end of the fixed pole 703 is arranged on the vertical pole 701, and the other end of the fixed pole 703 is detachably arranged on the column 3. By arranging the vertical pole 701, the climbing pole 702 and the fixed pole 703, when in use, the vertical pole 701 is firstly arranged between the auxiliary platforms 6 and between the auxiliary platform 6 and the working platform 5, and is detachably arranged on the column 3 through the fixed pole 703, and then the operator can reach the auxiliary platform 6 or the working platform 5 through the climbing pole 702.
[0037] refer to Figure 2 Safety nets 10 are provided on the sides of the working platform 5 and the auxiliary platform 6. The working platform 5 and the auxiliary platform 6 are fully covered with steel springboards. By providing the safety nets 10, when in use, the safety nets 10 can protect the workers and prevent the workers from falling off the working platform 5 or the auxiliary platform 6, thereby avoiding safety accidents.
[0038] refer to Figure 2 A through passage 11 is provided on the working platform 5, and the climbing mechanism 7 extends to the top of the through passage 11. By providing the through passage 11, when in use, the vertical pole 701 extends to the outside of the through passage 11, and the operator can enter the working platform 5 through the through passage 11.
[0039] refer to Figure 3The lower surface of the column 3 is provided with a universal wheel 12 with a locking function. There are four universal wheels 12 and they are symmetrically arranged. By setting the universal wheel 12, when in use, the universal wheel 12 can improve the maneuverability of the column 3, so that the column 3 can be easily moved. Then the universal wheel 12 has a self-locking function, which can prevent the column 3 from sliding when in use.
[0040] refer to Figure 2 The climbing pole 702 is provided with an anti-skid layer 13 for increasing friction. By providing the anti-skid layer 13, when in use, the anti-skid layer 13 can increase the friction between the operator and the climbing pole 702, thereby preventing the operator from slipping and avoiding safety accidents.
[0041] refer to Figure 3 The lower surface of the grounding rod 805 is provided with an anti-skid pad 14 for increasing friction. By providing the anti-skid pad 14, when in use, the anti-skid pad 14 can increase the friction between the grounding rod 805 and the ground, and can further improve the stability of the column 3.
[0042] Brief description of the usage process:
[0043] When in use, firstly, the frame 1 is modeled and subjected to force calculation, and the longitudinal and transverse distances, step distances and construction measures that meet the structural force requirements are selected;
[0044] Then, after the frame 1 is erected on the lower structural floor to form a stable structural force system, the diagonal braces 9, the working platform 5 and the auxiliary platform 6 are erected and fixed;
[0045] Finally, steel springboards are laid on the auxiliary platform 6 and the working platform 5, and dense safety nets 10 are hung on the sides to provide workers with a safe and effective operating platform. After the frame 1 is accepted, the curtain wall physical structure construction begins. The roof eaves aluminum curtain wall within the range of the frame 1 is installed and operated by workers standing on the working platform 5, and the roof eaves aluminum curtain wall outside the range of the working platform 5 is installed and operated by workers standing on the aerial work vehicle 2.
[0046] This specific embodiment is merely an explanation of the present invention and is not a limitation of the present invention. After reading this specification, those skilled in the art may make non-creative modifications to the present embodiment as needed, but such modifications are protected by patent law as long as they are within the scope of the claims of the present invention.
Claims
1. A large cantilever roof eaves aluminum curtain wall installation device, comprising a frame (1) and an aerial work vehicle (2), characterized in that: The aerial work vehicle (2) is arranged on one side of a frame (1). The frame (1) is composed of four columns (3). A reinforcing rod (4) is arranged between the four columns (3). The reinforcing rod (4) is arranged in a plurality and evenly arranged. A working platform (5) is arranged on the top of the column (3). An auxiliary platform (6) is arranged below the working platform (5). A climbing mechanism (7) is arranged between two auxiliary platforms (6) and between the auxiliary platform (6) and the working platform (5). A stabilizing mechanism (8) is arranged on the column (3). An oblique support rod (9) is arranged between the column (3) and the working platform (5). A triangle is formed between the column (3), the working platform (5) and the oblique support rod (9).
2. The large cantilever roof cornice aluminum curtain wall installation device according to claim 1, characterized in that: The stabilizing mechanism (8) comprises a fixing sleeve (801), a vertical plate (802), a cross bar (803), an inclined bar (804) and a grounding rod (805); the fixing sleeve (801) is arranged on the column (3) by means of bolts; the vertical plate (802) is arranged on the fixing sleeve (801); the cross bar (803) is arranged at the lower end of the vertical bar; the inclined bar (804) is arranged at the upper end of the vertical plate (802); the inclined bar (804) is arranged obliquely; the grounding rod (805) is arranged at the other end of the cross bar (803) and the inclined bar (804); and the grounding rod (805) is arranged vertically.
3. The large cantilever roof cornice aluminum curtain wall installation device according to claim 1, characterized in that: The climbing mechanism (7) comprises a vertical pole (701), a climbing pole (702) and a fixing pole (703); the vertical pole (701) is arranged between the auxiliary platforms (6) and between the auxiliary platform (6) and the working platform (5); there are two vertical poles (701) and they are symmetrically arranged; the climbing pole (702) is arranged on the vertical pole (701); there are a plurality of climbing poles (702) and they are evenly arranged; one end of the fixing pole (703) is arranged on the vertical pole (701); the other end of the fixing pole (703) is detachably arranged on the column (3).
4. The large cantilever roof cornice aluminum curtain wall installation device according to claim 1, characterized in that: Safety nets (10) are provided on the sides of the working platform (5) and the auxiliary platform (6), and the working platform (5) and the auxiliary platform (6) are fully covered with steel springboards.
5. The large cantilever roof cornice aluminum curtain wall installation device according to claim 1, characterized in that: The working platform (5) is provided with a through passage (11), and the climbing mechanism (7) extends to the top of the through passage (11).
6. The large cantilever roof cornice aluminum curtain wall installation device according to claim 1, characterized in that: The lower surface of the column (3) is provided with a universal wheel (12) with a locking function, and the universal wheels (12) are four in number and symmetrically arranged.
7. The large cantilever roof cornice aluminum curtain wall installation device according to claim 3, characterized in that: The climbing pole (702) is provided with an anti-slip layer (13) for increasing friction.
8. The large cantilever roof cornice aluminum curtain wall installation device according to claim 2, characterized in that: The lower surface of the grounding rod (805) is provided with an anti-skid pad (14) for increasing friction.
Citation Information
Patent Citations
Simple cantilever gutter aluminum plate mounting bracket
CN215716656U