Novel carrying frame for house construction

By designing a new type of mounting frame with adjustable height and flipped protective baffle, the existing mounting frame height fixation and simple safety door structure are solved, and construction convenience and safety are improved.

CN222976346UActive Publication Date: 2025-06-13NINGXIA XINGHONG SHENGDA CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421975564.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-08-15
Publication Date
2025-06-13
Estimated Expiration
2034-08-15

AI Technical Summary

Technical Problem

The existing mounting frame is height-fixed and cannot be adjusted when used, and the safety door of the workbench is simple and inconvenient for use.

Method used

A new type of mounting frame is designed including a transport base, a lifting platform and an additional guardrail. The transport base has four separate brackets and universal wheels, the lifting platform can be lifted and equipped with a flip-open protective baffle and an additional guardrail.

Benefits of technology

The height adjustment of the mounting frame is realized to facilitate the adaptation of the construction position. At the same time, the convenience and safety of the user are improved through the design of the flip protective baffle.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222976346U_ABST
    Figure CN222976346U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of house construction, and discloses a novel carrying frame for house construction, which comprises a conveying base, four independent support structures are arranged at the top of the conveying base, reinforcing rods are fixedly arranged between supports on the same side above the conveying base on the same side, four universal wheels which are far away from each other are arranged at the bottom of the conveying base, and the four universal wheels are arranged on the conveying base. According to the novel climbing ladder, by arranging the protective baffle which is opened in an overturning mode, when a user enters the lifting table through the climbing ladder, the protective baffle is overturned to be unfolded, so that the notch is formed in the right side of the additionally-installed guardrail, and the protective baffle falls down and is closed after the user climbs into the additionally-installed guardrail; bolts are inserted into the second locking holes to rotate to be in butt joint with the second alignment inserting holes in the wall face in the opening direction of the additionally-installed guardrail, the additionally-installed guardrail is completely closed after swinging of the protection baffle is locked, the bolts are inserted into the second locking holes when the additionally-installed guardrail is not used, and compared with an existing protection guardrail structure, when a user climbs up and down, door opening and closing become more convenient.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of house construction, in particular to a new type of carrier for house construction. Background Art

[0002] During the process of house construction, the construction operations at higher positions usually rely on carriers. The existing carriers have certain drawbacks when in use. The height of the existing carriers is fixed during erection and cannot be adjusted secondly. At the same time, the safety door structure of the workbench is simple and it is rather inconvenient during the process of climbing onto the safety platform. For this reason, we propose a new type of carrier for house construction. Content of the Utility Model

[0003] The utility model mainly solves the technical problems existing in the above-mentioned prior art, and provides a new type of carrier for house construction.

[0004] In order to achieve the above purpose, the utility model adopts the following technical scheme. A new type of carrier for house construction includes a transportation base. The top of the transportation base is a structure of four independent supports. Reinforcement rods are fixedly installed between the supports on the same side above the transportation base on the same side. Four mutually separated universal wheels are arranged at the bottom of the transportation base. An elevating platform is arranged above the transportation base. Alignment jacks are respectively opened inside the four feet of the elevating platform. The four supports of the transportation base are all designed with hollow interiors, and the sizes correspond to the sizes of the four feet of the elevating platform. The four feet of the elevating platform are inserted and installed inside the four supports of the transportation base. Positioning jacks I are respectively opened on the surfaces of the four supports of the transportation base. Locking bolts for locking are inserted into the positioning jacks I. The locking bolts pass through the positioning jacks I and are inserted into the corresponding alignment jacks. A protective guardrail for protection is installed at the top of the elevating platform. The right side of the protective guardrail is designed with an opening for personnel to enter, and a protective baffle is arranged on the right side of the protective guardrail.

[0005] Further, two mutually separated limit clamping plates are fixedly installed on the side of the protective baffle corresponding to the inside of the protective guardrail. After the protective baffle is closed, the two limit clamping plates are clamped into the inner side of the opening part of the protective guardrail.

[0006] Further, installation jacks are respectively opened inside the protruding parts on the right side of the protective guardrail. The whole of the protective baffle is of a convex structure, and the top is movably installed between the two protective baffles through bolts.

[0007] Further, alignment jacks II are arranged at equal intervals on the inner wall surface of the opening part of the protective guardrail. Locking holes II corresponding to the sizes of the alignment jacks II are opened inside the limit clamping plates. After the locking holes II and the alignment jacks II are in corresponding positions, they are fixed and aligned through bolts.

[0008] Furthermore, a mounting groove is provided on the right side of the lifting platform, the mounting groove is connected to the top wall of the lifting platform, and a through hole for drainage is provided on the upper surface of the lifting platform.

[0009] Furthermore, the inner wall surfaces of both sides of the installation groove are provided with locking holes, and a climbing ladder is fixedly installed between the two locking holes. After the lifting platform is lowered, the lower end of the climbing ladder is inserted into the right opening of the transport base.

[0010] Beneficial Effects

[0011] The utility model provides a new type of mounting frame for house construction, which has the following beneficial effects:

[0012] 1. A new type of mounting frame for house construction is provided with a flip-open protective baffle. The protective baffle is mounted between two installation sockets and then locked by a bolt. After that, the protective baffle can be flipped over at the opening position of the additional guardrail. Since the overall structure of the protective baffle is a convex shape, the lower size of the protective baffle is larger than the opening size of the additional guardrail. After the protective baffle is erected, it will completely block the opening part of the additional guardrail, and the fixing bolt is inserted into the protective baffle. When the user enters the lifting platform through the climbing ladder, the protective baffle is flipped over to open a gap on the right side of the additional guardrail. After climbing into the additional guardrail, the protective baffle falls down and closes, and the bolt is inserted into the second locking hole and rotated to connect with the second positioning socket on the wall in the opening direction of the additional guardrail. After locking the swing of the protective baffle, the additional guardrail is completely closed. When it is idle, the bolt is inserted in the second locking hole. Compared with the existing protective railing structure, it is more convenient for users to open and close the door when climbing up and down.

[0013] 2. The new type of carrying frame for house construction is provided with a transport base and a lifting platform that can be lifted up and down. After the four legs of the lifting platform are inserted into the four brackets of the transport base, the locking bolt is inserted into one of the corresponding positioning holes and rotated so that the front end of the locking bolt is docked with the alignment holes opened in the four legs of the lifting platform. At this time, the lifting height of the entire lifting platform will be locked. When the entire device is idle, the four legs of the lifting platform will be completely retracted into the interior of the four support frames of the transport base. At this time, the lower end of the climbing frame installed in the mounting groove is stuck in the right opening of the transport base. When the device is in use, the lifting height of the lifting platform is adjusted according to the construction position. After that, the user climbs up through the climbing frame installed in the mounting groove, pushes the protective baffle to rotate upward to open the right opening of the guardrail. After the user enters the interior of the guardrail through the opening, the protective baffle is closed and locked to carry out subsequent work. The entire device is very convenient to use, and the closed protective baffle makes the user safer during the construction process. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The structures, ratios, sizes, etc. illustrated in this specification are only used to match the content disclosed in the specification for those familiar with this technology to understand and read, and are not used to limit the implementation conditions of the present utility model. Therefore, they do not have substantial technical significance.

[0015] Figure 1 It is a schematic diagram of the overall structure;

[0016] Figure 2 It is a schematic diagram of the protective baffle structure;

[0017] Figure 3 It is a schematic diagram of the installed guardrail structure.

[0018] Legend Explanation:

[0019] 1. Transport base; 2. Reinforcement rod; 3. Universal wheel; 4. Lifting platform; 5. Installed guardrail; 6. Installation groove; 7. Locking hole one; 8. Positioning jack one; 9. Alignment jack; 10. Locking bolt; 11. Installation jack; 12. Protective baffle; 13. Limit clamping plate; 14. Locking hole two; 15. Alignment jack two. Specific Embodiment

[0020] A new type of carrier for building construction, as Figures 1 - 3 shown, includes a transport base 1. The top of the transport base 1 is composed of four independent bracket structures. Reinforcement rods 2 are fixedly installed between two brackets on the same side. Four mutually separated universal wheels 3 are arranged at the bottom of the transport base 1. A lifting platform 4 is arranged above the transport base 1. Through holes for drainage are provided on the upper surface of the lifting platform 4. Alignment jacks 9 are provided inside the four feet of the lifting platform 4. The four brackets of the transport base 1 are designed with hollow interiors and their sizes correspond to the sizes of the four feet of the lifting platform 4. The four feet of the lifting platform 4 are inserted and installed inside the four brackets of the transport base 1. Positioning jacks one 8 are provided on the surfaces of the four brackets of the transport base 1. Locking bolts 10 for locking are inserted and installed in the positioning jacks one 8. The locking bolts 10 pass through the positioning jacks one 8 and are inserted into the corresponding alignment jacks 9. An installed guardrail 5 for protection is installed on the top of the lifting platform 4. The right side of the installed guardrail 5 is designed with an opening for personnel to enter. A protective baffle 12 is arranged on the right side of the installed guardrail 5.

[0021] Installation jacks 11 are provided inside the protruding parts on the right side of the installed guardrail 5. The overall structure of the protective baffle 12 is convex, and the top is movably installed between two protective baffles 12 through bolts. Two mutually separated limit clamping plates 13 are fixedly installed on the side of the protective baffle 12 corresponding to the inside of the installed guardrail 5. After the protective baffle 12 is closed, the two limit clamping plates 13 are clamped into the inner side of the opening part of the installed guardrail 5.

[0022] The inner wall surface of the opening part where the guardrail 5 is installed is provided with equidistantly arranged alignment holes 15, and the interior of the limiting card plate 13 is provided with locking holes 14 corresponding to the size of the alignment holes 15. The locking holes 14 and the alignment holes 15 are aligned with each other by bolts after their positions correspond, and the opening part where the guardrail 5 is installed is closed by the protective baffle 12.

[0023] A mounting groove 6 is provided on the right side of the lifting platform 4, and the mounting groove 6 is connected to the top wall of the lifting platform 4. Locking holes 7 are provided on the inner side walls of the mounting groove 6. A climbing ladder is fixedly installed between the two locking holes 7. After the lifting platform 4 is lowered, the lower end of the climbing ladder is inserted into the right opening of the transport base 1.

[0024] The working principle of this utility model:

[0025] By providing a flip-open protective baffle 12, the protective baffle 12 is mounted between the two mounting holes 11 and locked by bolts, and then the protective baffle 12 can be flipped over at the opening position of the additional guardrail 5. Since the overall structure of the protective baffle 12 is a convex shape, the size of the bottom of the protective baffle 12 is larger than the opening size of the additional guardrail 5. After the protective baffle 12 is vertically erected, it will completely block the opening part of the additional guardrail 5. When the fixing bolts are inserted into the protective baffle 12, when the user climbs the ladder When entering onto the lifting platform 4, flip the protective baffle 12 to expand it so that a gap is opened on the right side of the additional guardrail 5. After climbing into the additional guardrail 5, the protective baffle 12 falls down and closes, and the bolt is inserted into the second locking hole 14 and rotated to dock with the matching socket 2 15 on the wall in the opening direction of the additional guardrail 5. After locking the swing of the protective baffle 12, the additional guardrail 5 is completely closed. When idle, the bolt is inserted in the second locking hole 14. Compared with the existing protective railing structure, it becomes more convenient for users to open and close the door when climbing up and down.

[0026] The lifting platform 4 is lifted up and down and is in a state of being lifted and lowered. After the four legs of the lifting platform 4 are inserted into the four brackets of the lifting platform 1, the locking bolt 10 is inserted into the corresponding positioning socket 8 and rotated so that the front end of the locking bolt 10 is docked with the alignment socket 9 opened in the four legs of the lifting platform 4. At this time, the lifting height of the entire lifting platform 4 will be locked. When the entire device is idle, the four legs of the lifting platform 4 will be completely retracted into the four support frames of the conveying base 1. At this time, the lower end of the climbing frame installed in the mounting groove 6 is inserted into the right opening of the conveying base 1. When the device is in use, the lifting height of the lifting platform 4 is adjusted according to the construction position. Then, the user climbs up through the climbing frame installed in the mounting groove 6, pushes the protective baffle 12 to rotate upward to open the right opening of the additional guardrail 5. After the user enters the interior of the additional guardrail 5 through the opening, the protective baffle 12 is closed and locked to carry out subsequent work. The entire device is very convenient to use, and the closed protective baffle 12 makes the user safer during the construction process.

[0027] The above shows and describes the basic principles, main features and advantages of the present utility model. Those skilled in the art should understand that the present utility model is not limited by the above embodiments. What is described in the above embodiments and the specification only illustrates the principles of the present utility model. Without departing from the spirit and scope of the present utility model, the present utility model will have various changes and improvements, and these changes and improvements all fall within the scope of the present utility model claimed.

Claims

1. A new type of loading frame for house construction, comprising a transport base (1), the top of the transport base (1) is a four-independent bracket structure, a reinforcement rod (2) is fixedly installed between the brackets on the same side above the transport base (1), four universal wheels (3) away from each other are arranged at the bottom of the transport base (1), and a lifting platform (4) is arranged above the transport base (1), characterized in that: The four legs of the lifting platform (4) are each provided with a positioning socket (9), the four brackets of the transport base (1) are each hollow and designed to have a size corresponding to the size of the four legs of the lifting platform (4), the four legs of the lifting platform (4) are inserted and installed in the four brackets of the transport base (1), the surfaces of the four brackets of the transport base (1) are each provided with a positioning socket (8), a locking bolt (10) for locking is inserted and installed in the positioning socket (8), the locking bolt (10) passes through the positioning socket (8) and is inserted into the corresponding positioning socket (9), the top of the lifting platform (4) is provided with an additional guardrail (5) for protection, the right side of the additional guardrail (5) is an opening designed for users to enter, and a protective baffle (12) is provided on the right side of the additional guardrail (5).

2. A new type of mounting frame for house construction according to claim 1, characterized in that: Two limit clamping plates (13) are fixedly mounted on one side of the protective baffle (12) corresponding to the inside of the additional guardrail (5) and are located away from each other. When the protective baffle (12) is closed, the two limit clamping plates (13) are inserted into the inside of the opening of the additional guardrail (5).

3. A new type of mounting frame for house construction according to claim 1, characterized in that: The right protruding part of the additional guardrail (5) is provided with a mounting hole (11), and the top of the overall convex structure of the protective baffle (12) is movably mounted between the two protective baffles (12) by means of bolts.

4. A new type of mounting frame for house construction according to claim 2, characterized in that: The inner wall surface of the opening part of the additional guardrail (5) is provided with equidistantly arranged alignment holes (15), and the interior of the limit clamping plate (13) is provided with locking holes (14) corresponding in size to the alignment holes (15). The locking holes (14) and the alignment holes (15) are aligned and fixed by bolts after their positions correspond.

5. The new type of mounting frame for house construction according to claim 1 is characterized in that: A mounting groove (6) is provided on the right side of the lifting platform (4), the mounting groove (6) is connected to the top wall of the lifting platform (4), and a through hole for drainage is provided on the upper surface of the lifting platform (4).

6. A new type of mounting frame for building construction according to claim 5, characterized in that: The inner wall surfaces of both sides of the installation groove (6) are provided with locking holes (7), and a climbing ladder is fixedly installed between the two locking holes (7). After the lifting platform (4) is lowered, the lower end of the climbing ladder is inserted into the right opening of the transport base (1).