Assembly type air conditioning equipment platform
By designing a prefabricated air-conditioning equipment platform for prefabricated buildings, using brackets composed of galvanized square pipes and angle steel bars, support plates and fence components of patterned steel plates, the complex and time-consuming installation of the double-layer equipment platform in prefabricated buildings is solved, and the effect of rapid assembly and material saving is achieved.
Patent Information
- Application Number
- CN202422202085.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-09
- Publication Date
- 2025-06-17
- Estimated Expiration
- 2034-09-09
AI Technical Summary
The double-layer equipment platform in prefabricated buildings is not conducive to the installation of lightweight partition panels, the process is complex and time-consuming, and the cast-in-place concrete structure increases the amount of secondary structure and construction and maintenance time.
A prefabricated air conditioning equipment platform is designed, including a bracket, a support plate and a fence assembly. The bracket is composed of galvanized square pipe and angle steel bars. The support plate and fence assembly are made of patterned steel plates. The bracket is arranged between the concrete prefabricated walls on both sides of the walls between the equipment. The support plate covers the space between the walls on both sides. The fence assembly is used to fix the support plate.
It realizes rapid assembly without space limitations, solves the disadvantage of the double-layer equipment platform to the installation of lightweight partition panels, simplifies the process, and reduces construction time and material waste.
Smart Images

Figure CN222990890U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction, in particular to a prefabricated air-conditioning equipment platform. Background Art
[0002] With the large-scale popularization and application of prefabricated buildings, the requirements for prefabrication assembly rate are also continuously increasing. The prefabricated components mainly include precast beams, precast stairs, precast slabs, precast walls, and lightweight panel walls. In residential buildings, sometimes an air-conditioning equipment platform needs to be shared between two households. During design, this place is generally designed as a double-layer air-conditioning board. The double-layer air-conditioning board is made of reinforced concrete structure. The exterior wall with the double-layer air-conditioning board design needs to be constructed in two steps. That is, first masonry to the construction position of the air-conditioning board, then formwork and pour the air-conditioning board part. After the concrete strength reaches the masonry requirement, the remaining wall is masonry to the top. When the lightweight panel wall is used for the exterior wall installation in prefabricated residential buildings, since the ALC board construction is the installation of the whole board, it cannot be masonry to the lower part of the double-layer air-conditioning board like aerated concrete blocks and continue to construct upward after the double-layer air-conditioning board and the up-turned beam are poured.
[0003] For the equipment platform slab made of cast-in-place concrete structure, four concrete columns are arranged under the ring beam around the upper air-conditioning board and poured together with the upper air-conditioning board. After demoulding, the ALC board is filled from the middle. This method increases the amount of secondary structure, and the maintenance time of the concrete structure in winter construction is long, which is not conducive to the construction period. Moreover, the cutting amount of the ALC board is large, the waste of the board is serious, and it is time-consuming and laborious. Summary of the Invention
[0004] In order to overcome the deficiencies of the prior art, the utility model provides a prefabricated air-conditioning equipment platform, which is not restricted by space and has a fast assembly speed, and solves the problems that the double-layer equipment platform in prefabricated buildings is not conducive to the installation of lightweight partition walls, with complex processes and long time consumption.
[0005] To achieve the above object, the prefabricated air-conditioning equipment platform of the utility model includes a bracket, the bracket is arranged between the concrete precast wall surfaces protruding on both sides of the equipment room wall surface, a support plate for supporting the air conditioner is arranged on the bracket, the support plate covers the space between the two concrete precast wall surfaces, and a surrounding component for enclosing is arranged on the support plate.
[0006] Furthermore, the bracket includes two first square tubes and two second square tubes. The first square tubes are perpendicular to the concrete precast wall surface, the second square tubes are parallel to the concrete precast wall surface, the first square tubes and the second square tubes form a rectangle. A third square tube is connected between the two first square tubes, and both ends of the third square tube are respectively connected to the midpoints of the two first square tubes on both sides. Fourth square tubes are respectively connected between the first square tubes and the two second square tubes, and both ends of the fourth square tubes are respectively connected to the midpoints of the third square tube and the second square tubes.
[0007] Further, angle steel bars are respectively provided at the bottom of the second square pipe. The angle steel bars extend along the length direction of the second square pipe. One side of the angle steel bar is connected to the bottom of the second square pipe, and the other side of the angle steel bar is attached to the concrete precast wall surface. The angle steel bar is fixed to the concrete precast wall surface by expansion bolts.
[0008] Further, the projection of the support plate on the horizontal plane coincides with the rectangle formed by the first square pipe and the second square pipe.
[0009] Further, the enclosure assembly includes a first baffle and two second baffles. The first baffle is arranged on the first square pipe on the side far from the wall surface of the equipment room. The second baffle is arranged on the second square pipe. The two ends of the first baffle are respectively connected to the ends of the second baffles on both sides. The first baffle and the first square pipe have the same length, and the second baffle and the second square pipe have the same length.
[0010] Further, the support plate, the first baffle and the second baffle are made of patterned steel plates. The first square pipe, the second square pipe, the third square pipe and the fourth square pipe are made of galvanized square pipes with a size of 40mm * 40mm. The angle steel bar is made of 5# angle steel.
[0011] Further, the length of the first square pipe is 1300mm, the length of the second square pipe is 850mm, and the height of the first baffle and the second baffle is 100mm.
[0012] The assembled air-conditioning equipment platform of the present utility model is not restricted by space and has a fast assembly speed, solving the problems that the double-layer equipment platform in the assembled building is not conducive to the installation of lightweight partition boards, with complex processes and time-consuming. Description of the Drawings
[0013] The following further describes and elaborates the present utility model with reference to the drawings.
[0014] Figure 1 It is a schematic structural diagram of the assembled air-conditioning equipment platform of the preferred embodiment of the present utility model.
[0015] Figure 2 It is a cross-sectional view of the assembled air-conditioning equipment platform.
[0016] Figure 3 It is a schematic structural diagram for showing the bracket.
[0017] Reference numerals: 11, the first square pipe; 12, the second square pipe; 13, the third square pipe; 14, the fourth square pipe; 2, the support plate; 31, the first baffle; 32, the second baffle; 4, the angle steel bar; 5, the expansion bolt; 6, the concrete precast wall surface. Detailed Embodiment
[0018] The following will more clearly and completely elaborate on the technical solution of the present utility model by describing the preferred embodiment of the present utility model with reference to the drawings.
[0019] As Figure 1 and Figure 2 shown, the prefabricated air-conditioning equipment platform in the preferred embodiment of the present utility model includes a bracket, the bracket is arranged between the concrete precast wall surfaces 6 protruding on both sides of the equipment room wall surface, a support plate 2 for supporting the air conditioner is arranged on the bracket, the support plate 2 covers the space between the two concrete precast wall surfaces 6, and a surrounding component is arranged on the support plate 2.
[0020] As Figure 1 and Figure 3 shown, the bracket includes two first square tubes 11 and two second square tubes 12. The first square tubes 11 are perpendicular to the concrete precast wall surface 6, the second square tubes 12 are parallel to the concrete precast wall surface 6, the first square tubes 11 and the second square tubes 12 enclose a rectangle. A third square tube 13 is connected between the two first square tubes 11, and both ends of the third square tube 13 are respectively connected to the midpoints of the two first square tubes 11 on both sides. Fourth square tubes 14 are respectively connected between the first square tubes 11 and the two second square tubes 12, and both ends of the fourth square tubes 14 are respectively connected to the midpoints of the third square tube 13 and the second square tubes 12. The first square tubes 11, the second square tubes 12, the third square tubes 13 and the fourth square tubes 14 are made of galvanized square tubes with a size of 40mm * 40mm. The length of the first square tubes 11 is 1300mm, and the length of the second square tubes 12 is 850mm.
[0021] As Figure 1 and Figure 2 shown, angle steel strips 4 are respectively arranged at the bottoms of the second square tubes 12. The angle steel strips 4 extend along the length direction of the second square tubes 12. One side of the angle steel strips 4 is connected to the bottom of the second square tubes 12, and the other side of the angle steel strips 4 is attached to the concrete precast wall surface 6. The angle steel strips 4 are fixed to the concrete precast wall surface 6 through expansion screws 5. The angle steel strips 4 are made of 5# angle steel.
[0022] As Figure 1 shown, the projection of the support plate 2 on the horizontal plane coincides with the rectangle enclosed by the first square tubes 11 and the second square tubes 12. The surrounding component includes a first baffle 31 and two second baffles 32. The first baffle 31 is arranged on the first square tube 11 on the side away from the equipment room wall surface, the second baffles 32 are arranged on the second square tubes 12. Both ends of the first baffle 31 are respectively connected to the ends of the two second baffles 32 on both sides. The first baffle 31 and the first square tube 11 have the same length, and the second baffles 32 and the second square tubes 12 have the same length. The support plate 2, the first baffle 31 and the second baffles 32 are made of patterned steel plates. The height of the first baffle 31 and the second baffles 32 is 100mm.
[0023] The prefabricated air-conditioning equipment platform of the present utility model is not restricted by space and has a fast assembly speed, solving the problems that the double-layer equipment platform in prefabricated buildings is not conducive to the installation of lightweight partition boards, with complex processes and time-consuming.
[0024] The above specific embodiments only describe the preferred embodiments of the present utility model, rather than limiting the protection scope of the present utility model. Without departing from the design concept and spiritual scope of the present utility model, various deformations, substitutions and improvements made by those of ordinary skill in the art to the technical solutions of the present utility model according to the written description and drawings provided by the present utility model shall fall within the protection scope of the present utility model. The protection scope of the present utility model is determined by the claims.
Claims
1. An assembled air conditioning equipment platform, characterized in that: The invention comprises a bracket, wherein the bracket is arranged between the raised concrete prefabricated walls (6) on both sides of the wall of the equipment room, the bracket is provided with a support plate (2) for supporting the air conditioner, the support plate (2) covers the space between the concrete prefabricated walls (6) on both sides, and the support plate (2) is provided with a enclosure component for enclosure.
2. The assembled air conditioning equipment platform according to claim 1, characterized in that: The bracket comprises two first square tubes (11) and two second square tubes (12); the first square tubes (11) are perpendicular to the precast concrete wall surface (6); the second square tubes (12) are parallel to the precast concrete wall surface (6); the first square tubes (11) and the second square tubes (12) form a rectangle; a third square tube (13) is connected between the two first square tubes (11); two ends of the third square tube (13) are respectively connected to the midpoints of the first square tubes (11) on both sides; a fourth square tube (14) is respectively connected between the first square tube (11) and the two second square tubes (12); two ends of the fourth square tube (14) are respectively connected to the midpoints of the third square tube (13) and the second square tubes (12).
3. The assembled air conditioning equipment platform according to claim 2, characterized in that: An angle steel bar (4) is provided at the bottom of each of the second square tubes (12). The angle steel bar (4) extends along the length direction of the second square tube (12). One side of the angle steel bar (4) is connected to the bottom of the second square tube (12). The other side of the angle steel bar (4) is attached to the precast concrete wall surface (6). The angle steel bar (4) is fixed to the precast concrete wall surface (6) by means of expansion screws (5).
4. The assembled air conditioning equipment platform according to claim 3, characterized in that: The projection of the support plate (2) on a horizontal plane coincides with a rectangle formed by the first square tube (11) and the second square tube (12).
5. The assembled air conditioning equipment platform according to claim 4, characterized in that: The enclosure assembly comprises a first baffle (31) and two second baffles (32); the first baffle (31) is arranged on a first square tube (11) at a side away from a wall of an equipment room; the second baffle (32) is arranged on a second square tube (12); two ends of the first baffle (31) are respectively connected to ends of the second baffles (32) at two sides; the first baffle (31) and the first square tube (11) are of the same length; and the second baffle (32) and the second square tube (12) are of the same length.
6. The assembled air conditioning equipment platform according to claim 5, characterized in that: The support plate (2), the first baffle plate (31) and the second baffle plate (32) are made of patterned steel plates, the first square tube (11), the second square tube (12), the third square tube (13) and the fourth square tube (14) are made of 40mm*40mm galvanized square tubes, and the angle steel bar (4) is made of 5# angle steel.
7. The assembled air conditioning equipment platform according to claim 6, characterized in that: The length of the first square tube (11) is 1300 mm, the length of the second square tube (12) is 850 mm, and the heights of the first baffle (31) and the second baffle (32) are 100 mm.