Suspension type building construction garbage conveying channel

By introducing positioning rods, buffer plates and spring structures into the construction waste conveying channels of suspended buildings, combined with water pumps, spray pipes and atomized spray heads, buffering and dust reduction treatment of construction waste is achieved, solving the impact damage and dust pollution problems of traditional channels, and reducing maintenance costs and health hazards.

CN223048379UActive Publication Date: 2025-07-01ZHONGKE CONSTR (HUBEI) CONSTR GRP CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421874457.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-08-05
Publication Date
2025-07-01
Estimated Expiration
2034-08-05

AI Technical Summary

Technical Problem

The lack of buffering devices in traditional garbage conveying channels leads to an increase in the impact of construction waste on the channels, increasing maintenance costs, and failing to effectively reduce dust, endangering the construction environment and workers' health.

Method used

The combined structure of positioning rod, buffer plate and spring is adopted to buffer the impact force of construction waste, and at the same time, dust reduction treatment is carried out through the cooperation of water pump, spray pipe and atomizing nozzle.

Benefits of technology

It effectively reduces the impact damage of construction waste to the passage, reduces maintenance costs, and solves the harm of dust to the construction environment and workers' health.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223048379U_ABST
    Figure CN223048379U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of building construction, in particular to a suspension type building construction garbage conveying channel which comprises a shell assembly and a box body, the top end of the shell assembly is sequentially provided with a protection plate, a water pump and a water tank from left to right, and the improved garbage conveying channel is provided with a positioning rod, a buffer plate and a spring in a matched mode. When the suspension type building construction waste conveying channel is used, construction waste can directly impact a buffer plate when falling down, the impact force generated when the construction waste falls down is reduced, damage caused by collision of the waste to the channel body is reduced, and therefore the maintenance cost of the waste conveying channel is reduced; when the suspension type building construction waste conveying channel is used, dust falling treatment is carried out on building waste sliding out of the channel body, the problem that dust drifts away at will, and consequently the construction environment and the health of workers are harmed is solved, and therefore the suspension type building construction waste conveying requirement is met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, and particularly relates to a suspended construction waste conveying channel for buildings. Background Art

[0002] Construction waste refers to the muck, waste soil, waste materials, silt and other waste generated during the construction, laying or demolition and repair of various buildings, structures, pipe networks, etc. by construction, construction units or individuals. With the acceleration of the industrialization and urbanization processes, the construction industry has also developed rapidly, and the accompanying construction waste has increased day by day. The amount of construction waste in China has accounted for more than 1 / 3 of the total urban waste. To ensure complete civilized construction, the cleaning and transportation of multi-layer construction waste are essential. Otherwise, it will occupy the construction site, making the originally limited construction site become narrow and hindering the normal progress of construction. Therefore, a suspended construction waste conveying channel for buildings is indispensable.

[0003] The existing patent (publication number: CN206512974U) discloses a high-rise building waste channel, including a waste channel body and a dustbin communicated with the bottom end of the waste channel body. A plurality of waste inlets are arranged in the length direction of the waste channel body. The high-rise building waste channel further includes a waste conveying mechanism arranged in the waste channel body. The waste conveying mechanism includes a buffer plate, a groove arranged on the buffer plate, and an inclined guide plate for guiding the waste sent in from the waste inlet to the groove. The buffer plate is connected with the inner wall of the channel at the bottom of the waste inlet through a first elastic reset mechanism. By setting the buffer plate, the utility model can avoid the waste directly falling from a high place to the ground and slow down the impact force. The inventor found the following problems in the process of implementing the utility model: 1. The traditional waste conveying channel lacks a buffer device. When workers put construction waste into the conveying channel, as the construction waste descends, the impact force of the construction waste on the channel will also increase with the descent, resulting in the construction waste hitting the waste channel and causing damage to it, thereby increasing the maintenance cost of the waste transportation channel; 2. When the construction waste slides out of the channel interior, a large amount of dust will be generated. The traditional waste transportation channel cannot perform dust reduction treatment on the sliding construction waste, resulting in these dusts being harmful to the construction environment and the health of workers, thereby greatly reducing the practicability of the device. Content of the Utility Model

[0004] The purpose of the present utility model is to provide a suspended construction waste conveying channel for buildings, so as to solve the problems raised in the above-mentioned background technology. The traditional waste conveying channel lacks a buffer device, resulting in an increase in the impact force of construction waste on the channel as it descends, which causes damage to the waste channel when the construction waste impacts it, thereby increasing the maintenance cost of the waste transportation channel. In addition, the traditional waste transportation channel cannot perform dust reduction treatment on the sliding construction waste, resulting in these dusts being harmful to the construction environment and the health of workers.

[0005] To achieve the above purpose, the present utility model provides the following technical solutions: A suspended construction waste conveying channel for buildings, including a housing assembly and a box body. At the top of the housing assembly, a protective plate, a water pump, and a water tank are sequentially arranged from left to right. At the top end inside the box body, two snap rings are provided, and a spray pipe is arranged inside the two snap rings. A plurality of atomizing nozzles are arranged at the bottom end of the spray pipe. A channel main body is arranged on one side of the box body. A plurality of fixing seats are respectively arranged on the inner walls of both sides of the channel main body. A positioning rod is arranged between every two of the plurality of fixing seats. A buffer plate is arranged outside the plurality of positioning rods through bearings. A spring is arranged on one side of the plurality of buffer plates.

[0006] Further preferably, the housing assembly includes a mounting plate. Support legs are arranged at the four corners of the bottom end of the mounting plate. An installation block is arranged between the four support legs.

[0007] Further preferably, the water pump, the water tank, and the spray pipe are connected through a connecting pipe.

[0008] Further preferably, a total of five atomizing nozzles are provided, and they are equidistantly distributed at the bottom end of the spray pipe.

[0009] Further preferably, the buffer plate rotates around the central axis of the positioning rod.

[0010] Further preferably, one positioning rod, one buffer plate, and one spring form a group, and a total of three groups are provided.

[0011] Further preferably, a limiting groove is opened at the top end of the protective plate, and the internal dimensions of the limiting groove are consistent with the external dimensions of the channel main body.

[0012] Compared with the prior art, the beneficial effects of the present utility model are as follows:

[0013] In the present utility model, through the cooperation of the positioning rod, the buffer plate, and the spring, when the suspended construction waste conveying channel for buildings is in use, it is realized that when the construction waste falls, it will directly impact the buffer plate, greatly reducing the impact force when the construction waste descends, reducing the damage caused by the impact of the construction waste on the channel main body, thereby reducing the maintenance cost of the waste transportation channel.

[0014] In the present utility model, through the cooperation of a water pump, a spray pipe and atomizing nozzles, during the use of the suspended building construction waste conveying channel, dust reduction treatment is carried out on the construction waste sliding out of the channel main body, solving the problem that these dusts are randomly dispersed and cause harm to the construction environment and the health of workers, thus meeting the requirements of the suspended building construction waste conveying. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a front view structural schematic diagram of the present utility model;

[0016] Figure 2 It is a front view internal structural schematic diagram of the present utility model;

[0017] Figure 3 For the present utility model Figure 2 The enlarged structural schematic diagram at position A in it;

[0018] Figure 4 It is a side view structural schematic diagram of the present utility model.

[0019] In the figure: 1. Outer shell assembly; 101. Mounting plate; 102. Support leg; 103. Mounting block; 2. Box body; 3. Protection plate; 4. Water pump; 5. Water tank; 6. Snap ring; 7. Spray pipe; 8. Atomizing nozzle; 9. Channel main body; 10. Fixed seat; 11. Positioning rod; 12. Buffer plate; 13. Spring. DETAILED DESCRIPTION OF THE EMBODIMENTS

[0020] Next, the technical solutions in the embodiments of the present utility model will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all the embodiments. Based on the embodiments in the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative efforts belong to the scope of protection of the present utility model.

[0021] Please refer to Figures 1 to 4 , the present utility model provides a technical solution: a suspended building construction waste conveying channel, including an outer shell assembly 1 and a box body 2. At the top of the outer shell assembly 1, a protection plate 3, a water pump 4 and a water tank 5 are sequentially arranged from left to right. At the inner top of the box body 2, two snap rings 6 are arranged. Inside the two snap rings 6, a spray pipe 7 is arranged. At the bottom of the spray pipe 7, a plurality of atomizing nozzles 8 are arranged. On one side of the box body 2, a channel main body 9 is arranged. On the inner walls of both sides of the channel main body 9, a plurality of fixed seats 10 are respectively arranged. Between every two of the plurality of fixed seats 10, a positioning rod 11 is arranged. The outer parts of the plurality of positioning rods 11 are provided with buffer plates 12 through bearings. On one side of the plurality of buffer plates 12, a spring 13 is arranged.

[0022] In this embodiment, asFigure 1 As shown in the figure, the housing assembly 1 includes a mounting plate 101. Support legs 102 are provided at the four corners of the bottom end of the mounting plate 101, and a mounting block 103 is arranged between the four support legs 102.

[0023] In this embodiment, as Figure 1 shown, the water pump 4, the water tank 5 and the spray pipe 7 are connected by connecting pipes; realizing the dust suppression treatment for the construction waste slipping out of the channel main body 9, solving the problem that these dusts are randomly dispersed and causing harm to the construction environment and the health of workers, thus meeting the requirements of the suspended building construction waste transportation.

[0024] In this embodiment, as Figure 2 shown, there are a total of five atomizing nozzles 8, and they are evenly distributed at the bottom end of the spray pipe 7; greatly improving the dust suppression effect on the dust generated by the construction waste, thus avoiding the pollution of the surrounding environment by the dust.

[0025] In this embodiment, as Figure 3 shown, the buffer plate 12 rotates around the central axis of the positioning rod 11; enabling the buffer plate 12 to automatically return to the original state under the elastic structure of the spring 13, thus avoiding the situation that the construction waste accumulates on the buffer plate 12 when falling and causing the blockage of the channel main body 9.

[0026] In this embodiment, as Figure 2 shown, one positioning rod 11, one buffer plate 12 and one spring 13 form a group, and there are a total of three groups; realizing that the construction waste will directly impact the buffer plate 12 when falling, greatly reducing the impact force when the construction waste descends, reducing the damage caused by the impact of the construction waste on the channel main body 9, thus reducing the maintenance cost of the waste transportation channel.

[0027] In this embodiment, as Figure 2 shown, a limiting groove is opened at the top end of the protection plate 3, and the internal dimensions of the limiting groove are consistent with the external dimensions of the channel main body 9; increasing the stability of the channel main body 9 during use, thus avoiding the situation that the channel main body 9 topples during use.

[0028] The usage method and advantages of the present utility model: When this kind of suspended building construction waste transportation channel is in use, the working process is as follows:

[0029] As Figure 1 , Figure 2 , Figure 3 and Figure 4As shown in the figure, first place the mounting plate 101 at the designated position through the support legs 102, then connect the external water pipe to the connection valve on one side of the water tank 5, and inject clean water into the interior of the water tank 5. When the construction waste falls from the top of the channel body 9, the construction waste will directly impact the buffer plate 12. At this time, after being impacted, the buffer plate 12 will rotate around the central axis of the positioning rod 11. At the same time, the buffer plate 12 compresses the spring 13, greatly reducing the impact force when the construction waste descends, reducing the damage caused by the construction waste impacting the channel body 9, thereby reducing the maintenance cost of the garbage transportation channel. When the construction waste falls into the collection trough at the inner bottom end of the box body 2, a large amount of dust will be generated. At this time, start the water pump 4 to work. The water pump 4 transports the clean water in the water tank 5 to the interior of the spray pipe 7 through the connecting pipe, and then sprays it out from the five atomizing nozzles 8 to realize the dust reduction treatment of the construction waste sliding out of the channel body 9, solving the problem that these dusts are randomly dispersed and cause harm to the construction environment and the health of workers, thus meeting the requirements for the transportation of construction waste of suspended buildings.

[0030] The above shows and describes the basic principles, main features and advantages of the present invention. Technical staff in this industry should understand that the present invention is not limited by the above embodiments. The above embodiments and descriptions in the specification are only preferred examples of the present invention and are not used to limit the present invention. Without departing from the spirit and scope of the present invention, the present invention will have various changes and improvements, and these changes and improvements all fall within the scope of the present invention claimed. The scope of protection claimed by the present invention is defined by the appended claims and their equivalents.

Claims

1. A suspended building construction waste conveying channel, comprising a housing assembly (1) and a box body (2), characterized in that: The top of the housing assembly (1) is provided with a protective plate (3), a water pump (4) and a water tank (5) in sequence from left to right; the top of the interior of the housing (2) is provided with two clamping rings (6); a spray pipe (7) is provided inside the two clamping rings (6); a plurality of atomizing nozzles (8) are provided at the bottom of the spray pipe (7); a channel body (9) is provided on one side of the housing (2); a plurality of fixing seats (10) are provided on two inner walls of the channel body (9); positioning rods (11) are provided between each of the fixing seats (10); a buffer plate (12) is provided outside the plurality of positioning rods (11) via a bearing; a spring (13) is provided on one side of the plurality of buffer plates (12).

2. A suspended building construction waste conveying channel according to claim 1, characterized in that: The housing component (1) comprises a mounting plate (101), the four corners of the bottom end of the mounting plate (101) are each provided with a supporting leg (102), and a mounting block (103) is provided between the four supporting legs (102).

3. The suspended building construction waste conveying channel according to claim 1 is characterized by: The water pump (4), the water tank (5) and the spray pipe (7) are connected via a connecting pipe.

4. The suspended building construction waste conveying channel according to claim 1 is characterized by: There are five atomizing nozzles (8) in total, which are evenly distributed at the bottom end of the spray pipe (7).

5. The suspended building construction waste conveying channel according to claim 1 is characterized by: The buffer plate (12) rotates with the central axis of the positioning rod (11) as the center of the circle.

6. The suspended building construction waste conveying channel according to claim 1 is characterized by: A positioning rod (11), a buffer plate (12) and a spring (13) form a group, and there are three groups in total.

7. The suspended building construction waste conveying channel according to claim 1 is characterized by: A limiting groove is provided at the top of the protective plate (3), and the internal dimensions of the limiting groove are consistent with the external dimensions of the channel body (9).

Citation Information

Patent Citations

  • High -rise building garbage shaft