Formwork erecting construction device for concrete pouring in narrow space

By pre-embedding the design of connecting bolts and triangular brackets on the base, combined with the fixing method of L-shaped bolts and nuts, the problem of supporting formwork and dismantling in narrow spaces is solved, convenient concrete pouring construction is achieved, and the stability and service life of the device are improved.

CN223135679UActive Publication Date: 2025-07-22CHINA CONSTR EIGHTH ENG BUREAU TECH CONSTR CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202422431582.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-10-09
Publication Date
2025-07-22
Estimated Expiration
2034-10-09

AI Technical Summary

Technical Problem

The prior art is difficult to effectively support formwork and remove formwork for concrete structures in narrow spaces, resulting in construction difficulties and increased costs.

Method used

The design of embedded connecting bolts and triangular brackets on the base is adopted, and the fixing method of L-shaped bolts and nuts is combined to form a stable support structure for easy installation and removal.

Benefits of technology

It realizes convenient support and dismantling in a narrow space, improves the stability and service life of the device, and reduces construction difficulty and cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223135679U_ABST
    Figure CN223135679U_ABST
Patent Text Reader

Abstract

The utility model relates to a narrow space concrete pouring formwork erecting construction device, belongs to the technical field of building construction, and particularly relates to a narrow space concrete pouring formwork erecting construction device which comprises a base, a second connecting bolt is pre-buried on the base, and the base is in threaded connection with a plurality of triangular supports through the second connecting bolt. A plurality of supporting formworks are arranged on the surface of the base, and each supporting formwork is arranged on one side of the corresponding triangular support; the utility model achieves the effects of being convenient to reinforce and dismantle and capable of recycling materials, and solves the problems that the existing structure vertical component template needs to be reinforced and dismantled according to the site construction requirement, and the template is difficult to erect and dismantle under the general condition due to narrow space.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a narrow space concrete pouring formwork construction device. Background Art

[0002] Building formwork is a temporary support structure, which is made according to the design requirements to shape the concrete structure and components according to the specified position and geometric size, maintain its correct position, and bear the deadweight of the building formwork and the external loads acting on it. The purpose of formwork engineering is to ensure the quality and construction safety of concrete engineering, speed up the construction progress and reduce engineering costs.

[0003] After searching, a Chinese patent with publication number CN113404290A discloses a concrete square column casting formwork and a construction method thereof, which relates to the technical field of concrete construction molds. The concrete square column casting formwork and the construction method thereof, by designing a detachable square column mold, can effectively improve the efficiency of mold disassembly after concrete curing, and the disassembled mold can be used multiple times to reduce construction costs; in addition, the present invention can make the mold cope with the casting of concrete square columns of different heights during actual use by slotting one end of the mold and providing a plug at the other end. Different numbers of molds can be selected to enhance the adaptability of the mold to different construction requirements.

[0004] Based on the above search combined with the existing technology, we found that;

[0005] Although the above-mentioned search patent technology can utilize formwork to cope with concrete pouring construction, according to on-site construction requirements, it is necessary to reinforce and dismantle the formwork of the vertical components of the structure. Usually, due to the narrow space, it is difficult to support and dismantle the formwork, so there are certain limitations. Utility Model Content

[0006] In order to solve the above technical problems, the utility model proposes a narrow space concrete pouring formwork construction device, which is easy to reinforce and dismantle and can recycle materials.

[0007] The technical solution to achieve the purpose of the utility model is: a narrow space concrete pouring formwork construction device, including a base, on which two connecting bolts are pre-embedded, and the base is threadedly connected to a plurality of triangular brackets through the two connecting bolts, and a plurality of formworks are arranged on the surface of the base, and each of the formworks is arranged on one side of the corresponding triangular bracket.

[0008] Preferably, a small bracket is fixedly installed at the bottom of the triangular bracket, and a plurality of connecting bolts are threadedly connected between each triangular bracket and the supporting formwork.

[0009] Preferably, L-shaped bolts are pre-embedded in the surface of the base.

[0010] Preferably, holes adapted to the L-shaped bolts are provided on the surface of the small bracket, and the L-shaped bolts and the small bracket are fixedly installed through nuts.

[0011] Compared with the prior art, the remarkable advantages of the present utility model are as follows:

[0012] First: The present utility model solves the installation problem of removing and installing formwork in a narrow space, enables good disassembly and installation of formwork, and facilitates workers to complete the pouring of concrete.

[0013] Second: By pre-burying connecting bolts and L-shaped bolts, the present utility model improves the stability and firmness of the device and extends the service life of the device.

[0014] It solves the problem that according to the requirements of on-site construction, formwork reinforcement and removal of vertical structural members are required. Usually, due to the narrow space, it is difficult to support and remove the formwork. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] The present utility model will be further explained below in conjunction with the drawings and embodiments:

[0016] Figure 1 is the overall three-dimensional structure schematic diagram of the present utility model;

[0017] Figure 2 is the overall front view structure schematic diagram of the present utility model;

[0018] Figure 3 is the side sectional view structure schematic diagram of the present utility model.

[0019] Explanation of the reference numerals in the drawings:

[0020] 1, base; 2, triangular bracket; 3, first connecting bolt; 4, formwork; 5, small bracket; 6, L-shaped bolt; 7, second connecting bolt; 8, nut. DETAILED DESCRIPTION OF THE EMBODIMENTS

[0021] The present utility model will be described in detail below. The technical solutions in the embodiments of the present utility model are clearly and completely described. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all the embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present utility model.

[0022] The present utility model provides a formwork construction device for concrete pouring in a narrow space by improvement. The technical solution of the present utility model is as follows:

[0023] As Figures 1-3As shown in the figure, a formwork construction device for concrete pouring in a narrow space includes a base 1. Connecting bolts II 7 are embedded in the base 1. The base 1 is threadedly connected with a plurality of triangular brackets 2 through the connecting bolts II 7. A plurality of formworks 4 are arranged on the surface of the base 1. Each formwork 4 is arranged on one side of the corresponding triangular bracket 2, which is convenient for later concrete pouring and maximizes the role of the formwork 4.

[0024] Furthermore, a small bracket 5 is fixedly installed at the bottom of the triangular bracket 2. A plurality of connecting bolts I 3 are threadedly connected between each triangular bracket 2 and the formwork 4, improving the practicality of the device.

[0025] Furthermore, L-shaped bolts 6 are embedded in the surface of the base 1. The L-shaped bolts 6 are used as bolts for the single-sided formwork 4, and a 50-mm-wide chamfer is poured.

[0026] Furthermore, holes adapted to the L-shaped bolts 6 are formed on the surface of the small bracket 5. The L-shaped bolts 6 and the small bracket 5 are fixedly installed through nuts 8, enhancing the stability and firmness of the device.

[0027] The specific working method is as follows: For the formwork 4 of the outer shear wall, the formwork 4 of the parapet wall is up to below the flashing height, and concrete is poured. A standardized smoke exhaust pipe is placed, and the remaining parapet wall is closed by single-sided formwork 4. Concrete is poured for the formwork 4 of the outer shear wall. The formwork 4 of the inner parapet wall is up to above the flashing, and concrete is poured. When the formwork 4 of the inner parapet wall is installed, L-shaped bolts 6 are embedded as bolts for the single-sided formwork 4, and a 50-mm-wide chamfer is poured. A finished standardized smoke exhaust pipe is installed. A standardized single-sided formwork 4 system is installed, and the concrete is poured in layers. After the formwork is removed, the exposed screw rods of the chamfer are cut off, waterproof ointment is applied, and the conventional roofing flashing construction is carried out.

[0028] The technical means disclosed in the solution of the present utility model are not limited to the technical means disclosed in the above technical means, but also include technical solutions composed of equivalent replacements of the above technical features. The matters not covered by the present utility model belong to the common general knowledge of those skilled in the art.

Claims

1. A formwork construction device for concrete pouring in a narrow space, comprising a base (1), characterized in that: The base (1) is pre-embedded with a second connecting bolt (7), and the base (1) is threadedly connected with a plurality of triangular brackets (2) through the second connecting bolt (7). A plurality of formworks (4) are arranged on the surface of the base (1), and each formwork (4) is arranged on one side of the corresponding triangular bracket (2).

2. The formwork construction device for concrete pouring in a narrow space according to claim 1, characterized in that: A small bracket (5) is fixedly installed at the bottom of the triangular bracket (2), and a plurality of first connecting bolts (3) are threadedly connected between each triangular bracket (2) and the formwork (4).

3. A formwork construction device for concrete pouring in a narrow space according to claim 1, characterized in that: An L-shaped bolt (6) is pre-embedded on the surface of the base (1).

4. A formwork construction device for concrete pouring in a narrow space according to claim 2, characterized in that: A hole adapted to the L-shaped bolt (6) is formed on the surface of the small bracket (5), and the L-shaped bolt (6) and the small bracket (5) are fixedly installed through a nut (8).