Foundation pit internal curing thermal insulation material tiling supporting device

By designing the curing and insulation material laying support device in the foundation pit, the problem of poor insulation effect in the prior art is solved, the combination of a closed curing space and a hot air device is realized, the insulation effect of concrete is improved, and the device can be reused for easy construction.

CN223226634UActive Publication Date: 2025-08-15BEIJING URBAN & RURAL CONSTR GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422584540.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-10-25
Publication Date
2025-08-15
Estimated Expiration
2034-10-25

AI Technical Summary

Technical Problem

During winter construction, it is difficult for the prior art to effectively improve the insulation effect of concrete in foundation pits, especially when pouring the base plate, middle plate and side wall, the insulation effect of the insulation material is poor and cannot be combined with the hot air device to increase the curing temperature.

Method used

A flat support device for laying insulation material in the foundation pit is designed, including a fixed slide, a sliding fixing device, a support line and a connecting sleeve. The insulation material is fixed on the support device through these components to form a closed maintenance space, and a hot air device can be provided therein to improve the insulation effect.

Benefits of technology

The insulation material forms a closed space with the foundation pit enclosure structure, which is convenient for insulation, and the maintenance temperature can be increased by setting up a hot air device. The support device can be reused, simple to operate, and easy to install and disassemble.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223226634U_ABST
    Figure CN223226634U_ABST
Patent Text Reader

Abstract

The utility model discloses a supporting device for paving a curing thermal insulation material in a foundation pit. The supporting device comprises a fixed slide way, a sliding fixing device, a supporting line and a connecting sleeve. The supporting lines are connected through the connecting sleeves and the threaded connecting rods. The side supporting lines pass through the through holes and are connected with the sliding fixing devices through the clamping heads. The sliding fixing device is connected with the fixed sliding way through the sliding groove. A heat preservation material can be flatly laid and fixed to the supporting device, the flatly laid heat preservation material and the foundation pit support structure form a closed maintenance space, heat preservation is facilitated, and meanwhile the heat preservation maintenance effect can be improved by arranging a hot air device and other measures in the closed maintenance space according to needs; the supporting device can be recycled and reused, is easy to operate and is convenient for workers to mount and dismount.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a supporting device, in particular to a supporting device for paving concrete curing and heat-insulating materials in a foundation pit. Background Art

[0002] During winter, when constructing the main structure of a new underground rail transit station using an open excavation pit, the poured concrete floor, mid-slab, and side walls require thermal insulation and curing. During construction, the common practice is to lay insulation materials (such as quilts or blankets) flat on the concrete surface of the poured floor, mid-slab, and side walls. This provides poor insulation, and measures such as adding hot air devices between the insulation material and the concrete to be cured are not suitable to increase the curing temperature. Summary of the Invention

[0003] The purpose of the utility model is to provide a support device for laying out thermal insulation materials for curing in a foundation pit in order to solve the above-mentioned problems. The thermal insulation materials can be laid out and fixed on the support device. The laid out thermal insulation materials and the foundation pit retaining structure form a closed curing space, which is convenient for heat preservation. At the same time, according to needs, a hot air device and other measures can be set in the closed curing space to improve the thermal insulation and curing effect. The support device can be recycled and reused, and is simple to operate, so that workers can install and disassemble it easily.

[0004] The utility model invention mainly achieves the above-mentioned purpose through the following technical solutions:

[0005] 4. The repairing kit for automotive dents, according to claim 1, wherein a bottom of the foot stand comprises a through-hole, and the two foot pieces comprise two bosses, wherein the bosses comprise a through-hole, a screw bolt, and a nut. The through-hole comprises a first end, and a second end, and a second end of the foot is mounted on the side of the foot stand. The bosses comprise a through-hole, a second end of the foot stand, and a second end of the foot stand.

[0006] Preferably, the length of a single fixed slide is 2 meters to 5 meters.

[0007] Preferably, among the sliding fixing devices installed on the fixed slide, the spacing between adjacent sliding fixing devices is 20 cm to 60 cm, and the sliding fixing device adjacent to the end of the fixed slide is not less than 20 cm away from the adjacent fixed slide end.

[0008] Preferably, the length of the threaded connecting rod should be greater than two-thirds of the length of the connecting sleeve and less than the length of the connecting sleeve.

[0009] Preferably, the length of the side support line is 5 meters to 20 meters, the length of the middle support line is 10 meters to 20 meters, and the difference between the length of the side support line and the length of the middle support line cannot be greater than 5 meters.

[0010] Preferably, the distance between the front clamping plate and the rear clamping plate provided on the sliding fixing device should be slightly larger than the thickness of the two side plates of the slide groove.

[0011] The present invention has at least the following advantages or beneficial effects:

[0012] The utility model provides a support device for laying out thermal insulation materials for curing in a foundation pit. The support device comprises a fixed slide, a sliding fixing device, a support line, and a connecting sleeve. Thermal insulation materials can be laid out and fixed to the support device. The laid-out thermal insulation materials and the foundation pit retaining structure form a sealed curing space, facilitating heat preservation. Furthermore, as needed, a hot air device or other measures can be installed within the sealed curing space to enhance the thermal insulation and curing effect. The support device is recyclable and reusable, and is simple to operate, making it easy for workers to install and disassemble. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] In order to more clearly illustrate the technical solution of the present invention, the following is a brief introduction to the drawings required for the present invention. It should be understood that the following drawings should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying any creative work.

[0014] Figure 1 A three-dimensional diagram of a support device for paving the thermal insulation material in the foundation pit;

[0015] Figure 2 A three-dimensional diagram of the fixed slideway and the sliding fixing device;

[0016] Figure 3 A three-dimensional diagram of the support line and the connecting sleeve;

[0017] Figure 4 This is a diagram of the usage status of the flat laying support device for curing the thermal insulation material in the foundation pit.

[0018] Icons: 1-fixed slide; 2-sliding fixing device; 3-support line; 4-connecting sleeve; 11-bolt fixing hole; 12-slide groove; 21-panel; 22-perforation; 23-front clamp; 24-rear clamp; 31-side support line; 32-middle support line; 301-connecting line; 302-clamp; 303-threaded connecting rod; 41-wire hole handle; A-insulation material; B-foundation pit retaining structure; C-completed concrete pouring; D-inclined wire. DETAILED DESCRIPTION

[0019] In order to make the purpose, technical solutions and advantages of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings of the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments.

[0020] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely represents selected embodiments of the present invention. All other embodiments derived by persons of ordinary skill in the art based on the embodiments of the present invention without creative effort are also within the scope of the present invention.

[0021] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, it does not need to be further defined or explained in subsequent drawings.

[0022] In the description of the embodiments of the present invention, it should be noted that if the terms "center", "up", "down", "left", "right", "inside", "outside", etc. appear, the orientation or position relationship indicated is based on the orientation or position relationship shown in the accompanying drawings, or is the orientation or position relationship commonly placed in the present invention. It is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present invention.

[0023] In the description of the embodiments of the present invention, it should be noted that, unless otherwise specified or limited, the terms "disposed," "installed," "connected," and "connected" should be understood in a broad sense. For example, they can refer to fixed connections, detachable connections, or integral connections; they can refer to mechanical connections, welded connections, etc.; they can refer to direct connections or indirect connections through an intermediate medium. Those skilled in the art will understand the specific meanings of the above terms in the present invention based on specific circumstances. Example

[0024] Please refer to Figure 1 The three-dimensional diagram of the support device for paving the thermal insulation material in the foundation pit is shown. Figure 2 The fixed slide and the sliding fixing device shown in the three-dimensional diagram, Figure 3 The support line and the connecting sleeve are shown in a three-dimensional diagram, Figure 4 The diagram of the use state of the support device for laying out heat-insulating materials for curing in a foundation pit is shown. The utility model provides a support device for laying out heat-insulating materials for curing in a foundation pit, which is mainly characterized in that: it comprises a fixed slideway (1), a sliding fixing device (2), a support line (3) and a connecting sleeve (4); a plurality of bolt fixing holes (11) are evenly and symmetrically arranged on one side of the fixed slideway (1) along the length direction, and a slide groove (12) is arranged in the middle position of the other side of the fixed slideway (1) along the length direction; the sliding fixing device (2) comprises a panel (21), a through hole (22) is arranged in the middle position of the panel (21), and a front clamping plate (23) and a rear clamping plate (24) are symmetrically arranged on the panel (21); the support line (3) comprises a side support line (31) and a middle support line (32 ), the side support line (31) includes a connecting line (301), a clamp (302) is provided at one end of the connecting line (301), and a threaded connecting rod (303) is provided at the other end of the connecting line (301); the middle support line (32) includes a connecting line (301), and threaded connecting rods (303) are provided at both ends of the connecting line (301); a plurality of wire hole handles (41) are symmetrically provided on the connecting sleeve (4); the support lines (3) are connected to the threaded connecting rod (303) through the connecting sleeve (4); the side support line (31) is connected to the sliding fixing device (2) through the through hole (22) using the clamp (302); the sliding fixing device (2) is connected to the fixed slideway (1) through the slide groove (12).

[0025] It should be noted that:

[0026] The length of a single fixed slideway (1) is 2 meters to 5 meters.

[0027] In the sliding fixing devices (2) installed on the fixed slide (1), the spacing between adjacent sliding fixing devices (2) is 20 cm to 60 cm, and the distance between the sliding fixing device (2) adjacent to the end of the fixed slide (1) is not less than 20 cm from the end of the adjacent fixed slide (1).

[0028] The length of the threaded connecting rod (303) should be greater than two-thirds of the length of the connecting sleeve (4) and less than the length of the connecting sleeve (4).

[0029] The length of the side support line (31) is 5 meters to 20 meters, and the length of the middle support line (32) is 10 meters to 20 meters. The difference between the length of the side support line (31) and the length of the middle support line (32) cannot be greater than 5 meters.

[0030] The distance between the front clamping plate (23) and the rear clamping plate (24) provided on the sliding fixing device (2) should be slightly larger than the thickness of the two side plates of the slide groove (12).

[0031] Before pouring concrete:

[0032] The number of fixed slideways (1) required is determined based on the length of the cast concrete structure and the length of a single fixed slideway (1), and then expansion bolts are installed at corresponding positions of the foundation pit retaining structure (B) for installing the fixed slideways (1). The corresponding fixed slideways (1) are prepared according to the determined number.

[0033] The number of side support lines (31) and middle support lines (32) included in each support line (3) is determined according to the width of the foundation pit. Generally speaking, when the width of the foundation pit is less than 25 meters, the middle support line (32) can be omitted. Prepare the corresponding side support lines (31) and middle support lines (32) according to the determined number.

[0034] It should be noted that after the support wire (3) is installed, an inclined wire (D) should be selected according to actual needs. One end of the inclined wire (D) is connected to the wire hole handle (41), and the other end is connected to the expansion bolt set on the foundation pit retaining structure (B). The main purpose of setting the inclined wire (D) is to reduce the downward deformation of the support wire (3) and improve the bearing capacity of the support wire (3).

[0035] According to the determined spacing between adjacent sliding fixtures (2), a corresponding number of sliding fixtures (2) are prepared.

[0036] The fixed slideways (1) are sequentially installed at corresponding positions of the foundation pit retaining structure (B) using expansion bolts provided on the foundation pit retaining structure (B).

[0037] After the concrete pouring is completed:

[0038] The side support wires (31) are sequentially passed through the perforations (22) from the back of the sliding fixture (2), and the side support wires (31) are fixed to the sliding fixture (2) using the clamping head (302).

[0039] Insert the sliding fixture (2) of the mounting side support line (31) into the slide groove (12) in sequence, and move the sliding fixture (2) to a suitable position in sequence according to the spacing requirements.

[0040] Use the connecting sleeve (4) and the threaded connecting rod (303) to connect the support wires (3) between the corresponding sliding fixtures (2) on both sides of the foundation pit in sequence, and use the wire hole handle (41) to tighten the connecting sleeve (4) to tighten the connected support wires (3) so that the support wires (3) are in a tensioned state. If it is necessary to install the inclined wire (D), it should be done after the support wires (3) are installed.

[0041] After the installation of the support device for laying the thermal insulation material in the foundation pit is completed, the sliding fixing device (2), the support line (3), the connecting sleeve (4) and the inclined wire (D) are checked, and then the thermal insulation material (A) is laid on the support line (3) as needed.

[0042] After the concrete curing is completed, the laid insulation material (A) is recycled.

[0043] Remove the inclined wires (D) (if any) in sequence, then loosen the connecting sleeve (4), disconnect the adjacent support wires (3), and recycle the middle support wire (32) (if any) and the connecting sleeve (4).

[0044] The sliding fixture (2) is removed from the chute (12) in sequence, and then the side support line (31) is removed from the sliding fixture (2) and stored in a classified manner.

[0045] Finally, the fixed slideway (1) is removed and recycled for storage.

[0046] The above description omits the basic techniques, operating procedures, safety measures and quality requirements necessary for the construction process that are well known to those skilled in the art.

[0047] The above are merely preferred embodiments of the present invention and are not intended to limit the present invention. Those skilled in the art will readily appreciate that various modifications and variations are possible. Any modifications, equivalent substitutions, or improvements made within the spirit and principles of the present invention shall be included within the scope of protection of the present invention.

Claims

1. The main features of the support device for paving thermal insulation materials in foundation pits are: The invention comprises a fixed slideway (1), a sliding fixing device (2), a support line (3) and a connecting sleeve (4); a plurality of bolt fixing holes (11) are evenly and symmetrically arranged on one side of the fixed slideway (1) along the length direction, and a slide groove (12) is arranged at the middle position of the other side of the fixed slideway (1) along the length direction; the sliding fixing device (2) comprises a panel (21), a through hole (22) is arranged at the middle position of the panel (21), and a front card (23) and a rear card (24) are symmetrically arranged on the panel (21); the support line (3) comprises a side support line (31) and a middle support line (32), and the side support line (31) comprises a connecting line (301), a clamp (302) is provided at one end of the connecting line (301), and a threaded connecting rod (303) is provided at the other end of the connecting line (301), the middle support line (32) includes the connecting line (301), and threaded connecting rods (303) are provided at both ends of the connecting line (301); a plurality of wire hole handles (41) are symmetrically provided on the connecting sleeve (4); the support lines (3) are connected to the threaded connecting rod (303) through the connecting sleeve (4); the side support line (31) is connected to the sliding fixing device (2) through the through hole (22) using the clamp (302); the sliding fixing device (2) is connected to the fixed slideway (1) through the slide groove (12).

2. The device for paving and supporting heat-insulating materials for curing in a foundation pit according to claim 1, characterized in that: The length of a single fixed slideway (1) is 2 meters to 5 meters.

3. The device for paving and supporting heat-insulating materials for curing in a foundation pit according to claim 1, characterized in that: In the sliding fixing devices (2) installed on the fixed slide (1), the spacing between adjacent sliding fixing devices (2) is 20 cm to 60 cm, and the distance between the sliding fixing device (2) adjacent to the end of the fixed slide (1) is not less than 20 cm from the end of the adjacent fixed slide (1).

4. The device for paving and supporting heat-insulating materials for curing in a foundation pit according to claim 1, characterized in that: The length of the threaded connecting rod (303) should be greater than two-thirds of the length of the connecting sleeve (4) and less than the length of the connecting sleeve (4).

5. The device for paving and supporting heat-insulating materials for curing in a foundation pit according to claim 1, characterized in that: The length of the side support line (31) is 5 meters to 20 meters, and the length of the middle support line (32) is 10 meters to 20 meters. The difference between the length of the side support line (31) and the length of the middle support line (32) cannot be greater than 5 meters.