Reinforcement cage of long spiral cast-in-situ bored pile with integrated structure
By using steel casing and steel pipe to reinforce the tapered mouth protection device in long spiral bored piles, combined with position sensors, the problems of tapered mouth falling off and verticality control of the steel cage were solved, achieving a safe, economical and efficient construction effect.
Patent Information
- Application Number
- CN202422644503.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-31
- Publication Date
- 2025-09-05
- Estimated Expiration
- 2034-10-31
AI Technical Summary
In the existing long spiral bored pile construction, the welding joints of the tapered mouth of the steel cage are prone to fall off, resulting in the steel cage not reaching the designed depth, making the verticality and pile positioning difficult to control, and the construction cost is high and the risk is great.
Steel casing protection devices and steel pipe reinforced tapered mouth protection devices are used, combined with position sensors to ensure the verticality and design depth of the steel cage, and are fixed to the steel casing body through ship-shaped pile diameter clamps to prevent the tapered mouth from falling off.
The verticality control of the steel cage and the achievement of the designed depth are achieved, which reduces construction costs, improves construction efficiency and safety, and simplifies the operation process.
Smart Images

Figure CN223305004U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction engineering, in particular to a long spiral bored pile reinforcement cage with an integrated structure. Background Art
[0002] At present, when constructing long spiral bored piles (also known as the post-insertion steel cage process) at most construction sites, the tapered mouth of the steel cage is usually formed by welding the main reinforcement on one side. When the steel cage is embedded in the concrete and the vibrating hammer is activated, the weld at the tapered mouth of the steel cage is easily detached, causing the steel cage inlet pipe to pass through the tapered mouth, and then the steel cage does not reach the designed depth. In addition, in the existing technology, there is no steel casing protection device at the top of the pile, and the verticality of the steel cage and the quality of pile positioning are difficult to control. Moreover, this traditional method requires a lot of manpower under tight construction schedules, which leads to increased costs and correspondingly increased risks, making it difficult to guarantee construction quality.
[0003] Therefore, how to provide an integrated structure long spiral bored pile reinforcement cage and its manufacturing method, and how to ensure construction quality by changing the reinforcement cage manufacturing method and applying it, has become a technical problem that technical personnel in this field urgently need to solve. Utility Model Content
[0004] The purpose of the utility model is to provide an integrated structure long spiral bored pile reinforcement cage, which is used to solve the technical problem of the existing long spiral bored pile (that is, the post-insertion reinforcement cage process) in which the reinforcement cage verticality and pile positioning are difficult to control; at the same time, it also solves the technical defect that the welding place of the tapered mouth of the reinforcement cage falls off, causing the reinforcement cage introduction pipe to pass through the tapered mouth, resulting in the reinforcement cage not reaching the design requirement depth.
[0005] In order to achieve the above purpose, the utility model adopts the following technical solutions:
[0006] An integrated structure long spiral bored pile reinforcement cage, comprising: a steel casing protection device, and a steel pipe reinforced tapered mouth protection device connected to the steel casing protection device;
[0007] The steel casing protection device comprises: a steel casing body, and a ship-shaped pile diameter clamp connected to the steel casing body;
[0008] The steel pipe reinforced tapered mouth protection device is made of steel pipe and is welded to the steel bar tapered body;
[0009] A position sensor is installed on the top of the steel casing protection device, and the position sensor is used to obtain the pile position and the steel cage position and verticality information.
[0010] In actual application, the steel casing body is welded from 3mm steel plates and is cylindrical in shape, and the steel casing body is set at the designed pile top elevation.
[0011] The ship-shaped pile diameter clamps are made of Ф8 threaded steel bars and are arranged at intervals along the vertical direction of the pile.
[0012] Specifically, the steel pipe reinforced conical mouth protection device is made of a DN100 steel pipe and has a length of 150 mm; the welding point between the steel pipe and the steel bar cone is connected by spot welding.
[0013] Compared with the prior art, the integrated structure long spiral bored pile reinforcement cage described in the utility model has the following advantages:
[0014] The utility model provides an integrated structure long spiral bored pile reinforcement cage. When in use, the ship-shaped pile diameter clamp is welded and fixed to the reinforcement cage main reinforcement of the steel casing body, and the steel casing body is arranged at the designed pile position to ensure the pile foundation point position. The verticality of the reinforcement cage insertion is received and processed by the position sensor and the information is transmitted to the pile driver or crane operator at the same time. The tapered mouth of the reinforcement cage is welded and reinforced with a steel pipe. When the reinforcement cage is implanted in the concrete and the vibrating hammer is started, the welding part of the tapered mouth of the reinforcement cage can be effectively prevented from falling off, thereby avoiding the reinforcement cage inlet pipe from passing through the tapered mouth and allowing the reinforcement cage to reach the designed depth. In addition, the integrated structure long spiral bored pile reinforcement cage provided by the utility model is simple and practical to operate as a whole, and has high installation and disassembly efficiency during construction. It can be reused and effectively reduces construction costs, achieving the goals of safety, economy and efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 A schematic structural diagram of a steel casing protection device in a steel cage of an integrated long spiral bored pile provided by an embodiment of the present invention;
[0016] Figure 2 This is a schematic structural diagram of a tapered mouth protection device for reinforcing steel pipes in a reinforcement cage of an integrated long spiral bored pile provided by an embodiment of the present utility model.
[0017] Reference numerals:
[0018] 1-Steel casing protection device; 11-Steel casing body; 12-Ship-shaped pile diameter clamp; 2-Steel pipe reinforced cone mouth protection device; 3-Position sensor. DETAILED DESCRIPTION
[0019] For ease of understanding, the integrated structure long spiral bored pile reinforcement cage provided by the embodiment of the present invention is described in detail below in conjunction with the accompanying drawings.
[0020] The present invention provides an integrated structure long spiral bored pile reinforcement cage, such as Figure 1 and Figure 2 As shown, it includes: a steel casing protection device 1, and a steel pipe reinforced tapered mouth protection device 2 connected to the steel casing protection device 1;
[0021] The steel casing protection device comprises 1: a steel casing body 11, and a ship-shaped pile diameter clamp 12 connected to the steel casing body 11;
[0022] The steel pipe reinforced tapered mouth protection device 2 is made of steel pipe and is welded to the steel bar tapered body;
[0023] A position sensor 3 is installed on the top of the steel casing protection device 1, and the position sensor 3 is used to obtain the pile position and the position and verticality information of the steel cage.
[0024] Compared with the prior art, the integrated structure long spiral bored pile reinforcement cage described in the embodiment of the utility model has the following advantages:
[0025] The integrated structure long spiral bored pile reinforcement cage provided by the embodiment of the present invention is welded and fixed to the main reinforcement of the reinforcement cage of the steel casing body 11 when in use, and the steel casing body 11 is arranged at the designed pile position and ensures the pile foundation point position. The verticality of the reinforcement cage insertion is received and processed by the position sensor 3 and the information is transmitted to the pile driver or crane operator at the same time; the tapered mouth of the reinforcement cage is welded and reinforced with a steel pipe, and when the reinforcement cage is implanted in the concrete and the vibrating hammer is started, it can effectively prevent the welding part of the tapered mouth of the reinforcement cage from falling off, thereby avoiding the reinforcement cage inlet pipe from passing through the tapered mouth and allowing the reinforcement cage to reach the designed depth; in addition, the integrated structure long spiral bored pile reinforcement cage provided by the embodiment of the present invention is simple and practical to operate as a whole, and has high installation and disassembly efficiency during construction, can be reused, and effectively reduces construction costs, achieving the goals of safety, economy and efficiency.
[0026] In actual application, such as Figure 1 and Figure 2 As shown, the steel casing body 11 can be welded from 3mm steel plates and be cylindrical, and the steel casing body 11 can be set at the designed pile top elevation.
[0027] Among them, such as Figure 1 and Figure 2 As shown, the ship-shaped pile diameter clamps 12 can be made of Ø8 threaded steel bars and are arranged at intervals along the vertical direction of the pile.
[0028] Specifically, if Figure 1 and Figure 2 As shown, the steel pipe reinforced tapered mouth protection device 2 can be made of a DN100 steel pipe with a length of 150 mm; the welding point between the steel pipe and the steel bar cone is connected by spot welding.
[0029] During construction, you can first measure and lay out the lines and verify the pile position, then use the drilling rig to drill the hole, then pump the concrete into the pile, then make the (integrated structure long spiral bored pile) steel cage, then hoist the steel cage for construction, and finally clean the pile head.
[0030] The present invention further provides a method for manufacturing an integrated structure long spiral bored pile reinforcement cage, comprising the following steps:
[0031] Step S1: Before construction, use BIM technology to extract the size and layout of the steel casing protection device 1 and the steel pipe reinforcement tapered mouth protection device 2 according to the design drawings;
[0032] Step S2: The steel casing body 11 of the steel casing protection device 1 is made of 3mm steel plate by welding and is 1000m high, and is arranged at the designed pile top position;
[0033] Step S3: The position sensor 3 extracts the pile position and the position and verticality information of the reinforcement cage, and the output interface outputs the processed information to the pile driver or crane operator;
[0034] Step S4: The ship-shaped pile diameter card 12 is made of Ø8 threaded steel bars with a height of 50 mm and a length of 410 mm, and is welded to the main reinforcement of the steel cage of the steel casing body 11;
[0035] Step S5: Steel pipe reinforced tapered mouth protection device 2 is processed with DN100 steel pipe, length 150mm, the steel pipe is sleeved on the welded steel bar cone, and the bottom is spot welded again.
[0036] The above description is merely a specific embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any modifications or substitutions that can be easily conceived by a person skilled in the art within the technical scope disclosed in the present invention should be included within the scope of protection of the present invention. Therefore, the scope of protection of the present invention should be based on the scope of protection of the claims.
Claims
1. An integrated structure long spiral bored pile reinforcement cage, characterized in that: include: A steel casing protection device, and a steel pipe reinforced tapered mouth protection device connected to the steel casing protection device; The steel casing protection device comprises: a steel casing body, and a ship-shaped pile diameter clamp connected to the steel casing body; The steel pipe reinforced tapered mouth protection device is made of steel pipe and is welded to the steel bar tapered body; A position sensor is installed on the top of the steel casing protection device, and the position sensor is used to obtain the pile position and the steel cage position and verticality information.
2. The integrated structure long spiral bored pile reinforcement cage according to claim 1, characterized in that: The steel casing body is welded from 3mm steel plates and is cylindrical in shape, and the steel casing body is arranged at the designed pile top elevation.
3. The integrated structure long spiral bored pile reinforcement cage according to claim 1 or 2, characterized in that: The ship-shaped pile diameter clamps are made of Ф8 threaded steel bars and are arranged at intervals along the vertical direction of the pile.
4. The integrated structure long spiral bored pile reinforcement cage according to claim 3, characterized in that: The steel pipe reinforced conical mouth protection device is made of a DN100 steel pipe and has a length of 150 mm; the welding point between the steel pipe and the steel bar cone is connected by spot welding.