Construction platform for hanging basket
By using M12 limit bolts to fix the construction platform on the hanging basket, combining protective guardrails and platform tripods, and laying steel springboards as pedestrian walkways, the problems of difficult to ensure welding quality and low material utilization of traditional platforms were solved, achieving convenient installation and improved safety.
Patent Information
- Application Number
- CN202422186219.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-06
- Publication Date
- 2025-09-12
- Estimated Expiration
- 2034-09-06
AI Technical Summary
The traditional construction platform has the problem that the welding quality is difficult to guarantee, the matching degree is not high, the material utilization rate is low and there is a risk of cutting the hanging basket accessories after welding.
Use M12 limit bolts to fix the construction platform to avoid welding operations. Use protective guardrails and platform tripods. The tripods are paved with steel springboards as pedestrian walkways. The standard spacing between the platform tripods and guardrail columns is 1.5m.
The construction platform can be easily installed and disassembled, which reduces construction risks, improves material utilization, and avoids safety hazards in welding operations.
Smart Images

Figure CN223329717U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of hanging basket construction, in particular to a construction platform used on a hanging basket. Background Art
[0002] Hanging basket is the main equipment in cantilever construction. According to the structural form, it can be divided into four types: truss type, cable-stayed type, steel type and mixed type. According to the requirements of concrete cantilever construction process and the requirements of design drawings for hanging basket, the characteristics, weight, type of steel used, construction process, etc. of various types of hanging baskets are comprehensively compared; the design principles of hanging baskets are: light weight, simple structure, strong and stable, easy to move forward and assemble and disassemble, strong reusability, and small deformation after being subjected to force.
[0003] 1. Traditional platforms have welding conditions, the welding quality cannot be estimated, and there are hidden dangers to safety.
[0004] 2. The matching degree of traditional platforms is not high, and they are generally matched with the corresponding model of hanging basket.
[0005] 3. Traditional platforms have welding, which needs to be cut off after construction. The material utilization rate is low and there is a possibility of cutting the hanging basket accessories. Utility Model Content
[0006] Therefore, in order to solve the above-mentioned shortcomings, the present invention provides a construction platform for a hanging basket.
[0007] The utility model is implemented in this way: a construction platform for a hanging basket is constructed; the construction platform is fixed on the front upper crossbeam of the hanging basket, and is easy to install and disassemble, avoiding welding operations and reducing construction risks. The construction platform consists of a protective guardrail and a platform tripod, and a steel springboard is laid on the platform tripod as a pedestrian passage.
[0008] According to the utility model, a construction platform for a hanging basket is characterized in that an M12 limit bolt is provided at the lower end of the tripod, and the M12 limit bolt is used to fix the tripod on the front upper crossbeam.
[0009] According to the utility model, a construction platform for a hanging basket is provided; the upper crossbeam is a square tube with a specification of 2*400*200mm.
[0010] According to the utility model, a construction platform for a hanging basket is provided; the protective railing is made of a Φ48*3mm steel pipe.
[0011] According to the utility model, a construction platform for a hanging basket is provided; a standard arrangement spacing between a platform tripod and a protective guardrail is 1.5 m.
[0012] This utility model offers the following advantages: The operating platform is secured to the 2 x 400 x 200 mm square tube on the front upper crossbeam of the hanging basket using M12 limit bolts, making installation and removal easy and eliminating welding work. This reduces construction risks. The platform tripod and guardrail posts are arranged with a standard spacing of 1.5 meters. A steel gangplank is laid on the tripod as a pedestrian walkway. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1-Figure 2 This is a schematic diagram of the construction platform used for the hanging basket in this application;
[0014] Figure 3 It is a schematic diagram of the implementation of the construction platform described in the utility model application.
[0015] Among them: front upper crossbeam 1, protective guardrail 2, platform tripod 3, steel springboard 4, and limit bolt 5. DETAILED DESCRIPTION
[0016] The following will be combined with the Figure 1-Figure 3 This utility model is described in detail, and the technical solutions in the embodiments of this utility model are clearly and completely described. Obviously, the embodiments described are only some of the embodiments of this utility model, not all of them. Based on the embodiments of this utility model, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of this utility model.
[0017] The utility model provides a construction platform for a hanging basket, such as Figure 1-Figure 3 As shown, it can be implemented as follows; the construction platform is fixed to the upper front crossbeam 1 of the hanging basket with M12 limit bolts, which is easy to install and disassemble, avoids welding operations, and reduces construction risks. The construction platform consists of a protective guardrail 2 and a platform tripod 3. The platform tripod 3 is paved with a steel springboard 4 as a pedestrian passage.
[0018] In the construction platform described in the present application, a limiting bolt 5 is provided at the lower end of the tripod 3 .
[0019] In the construction platform described in this application, the upper crossbeam is a square tube with a specification of 2*400*200mm.
[0020] In the construction platform described in this application, the guardrail 2 is made of Φ48*3mm steel pipe.
[0021] In the construction platform described in this application, the standard arrangement spacing between the platform tripod 3 and the protective guardrail 2 is 1.5m.
[0022] The operating platform is secured to the 2x400x200mm square tube on the front upper crossbeam of the hanging basket using M12 limit bolts. This facilitates installation and removal, eliminating welding work and reducing construction risks. The platform's tripod and guardrail posts are arranged with a standard spacing of 1.5m. A steel gangplank is laid on the tripod as a pedestrian walkway.
[0023] The above description of the disclosed embodiments will enable one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention is not limited to the embodiments shown herein but is intended to conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A construction platform for a hanging basket, characterized by: The construction platform is fixed on the front upper crossbeam (1) of the hanging basket, and is easy to install and dismantle, avoiding welding operations and reducing construction risks. The construction platform is composed of a protective guardrail (2) and a platform tripod (3). The platform tripod (3) is paved with a steel springboard (4) as a pedestrian passage. An M12 limit bolt (5) is provided at the lower end of the tripod (3), and is fixed to the front upper crossbeam (1) of the hanging basket using the M12 limit bolt; The upper crossbeam is a square tube with a specification of 2*400*200mm; The guardrail (2) is made of Φ48*3mm steel pipe; The standard arrangement spacing between the platform tripod (3) and the protective guardrail (2) is 1.5m.