First-layer reinforced concrete stand plate structure
By using inclined backfill soil and brick formwork in the first-floor reinforced concrete grandstand slab structure, and binding the reinforcing steel bars in the formwork with the reinforcing steel bars of the beams and slabs, the construction was simplified and the safety was improved. This solved the problems of complex construction and safety hazards, and achieved an efficient construction process.
Patent Information
- Application Number
- CN202423030958.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-09
- Publication Date
- 2025-10-28
- Estimated Expiration
- 2034-12-09
AI Technical Summary
The construction of the existing first-floor reinforced concrete grandstand slab involves complex procedures and safety hazards, and the dismantling of the support system and backfilling of earthwork are cumbersome.
The method employs inclined earth filling and brick formwork structure, with the reinforcing steel bars in the formwork tied to the reinforcing steel bars of the beams and slabs, ensuring a stable and tight connection between the concrete beams and slabs and the concrete of the beam body. This simplifies the construction process and shortens the time required to remove the supports.
Through improved construction methods, concrete beams and slabs can be cast in one go, reducing construction time, lowering costs, improving quality, and reducing safety risks.
Smart Images

Figure CN223482362U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the technical field of building construction, specifically to a first-floor reinforced concrete grandstand structure. Background Technology
[0002] Reinforced concrete grandstand slabs are a common building structure, possessing advantages such as good durability, high load-bearing capacity, and relatively low cost, and are widely used in various buildings and structures. During the construction of the first-floor reinforced concrete grandstand slabs, scaffolding systems are often used to support the formwork, a complex process with certain safety hazards. After construction is completed, the support system must be dismantled, and finally, backfilling is carried out. Utility Model Content
[0003] In order to solve one or more technical problems existing in the prior art, this utility model provides a first-floor reinforced concrete grandstand structure.
[0004] The technical solution of this utility model to solve the above-mentioned technical problems is as follows: A first-floor reinforced concrete grandstand structure includes backfill soil, the top of which is an inclined structure. Multiple brick formworks are provided on the inner side of the upper part of the backfill soil, arranged alternately along the front-back direction of the backfill soil. The brick formworks extend along the left-right direction of the grandstand, and an inclined pad layer is provided between adjacent brick formworks. Reinforcing bars are installed inside the brick formworks, and beam concrete is poured inside the brick formworks. The upper surface of the beam concrete is flush with the upper surface of the pad layer. The upper end of the reinforcing bars protrudes from the upper end of the brick formworks at a predetermined height. Beam and slab reinforcing bars are tied between the reinforcing bars in adjacent brick formworks. A concrete beam and slab are poured on the pad layer, and the upper ends of the reinforcing bars and the beam and slab reinforcing bars are embedded in the concrete beam and slab. Concrete steps are provided on the concrete beam and slab.
[0005] The beneficial effects of this utility model are: the first-floor reinforced concrete grandstand slab structure of this utility model can stably and tightly connect the concrete beams and slabs with the beam concrete by extending a portion of the reinforcing steel bars into the brick formwork and tying them to the beam and slab reinforcing steel bars, which facilitates construction and shortens the construction time for supporting and dismantling the step formwork, etc.
[0006] Based on the above technical solution, the present invention can be further improved as follows.
[0007] Furthermore, a protective pad is provided at the bottom of the brick mold, and the lower end of the reinforcing bar is placed on the protective pad.
[0008] The beneficial effect of adopting the above-mentioned further solution is that by setting protective pads, the reinforcing bars and brick formwork can be effectively protected.
[0009] Furthermore, the upper inner side of the backfill soil is provided with multiple grooves, and the front and rear sides of the grooves are provided with brick layers to form a brick mold.
[0010] Furthermore, the brick mold is arranged laterally through the left and right sides of the grandstand panel.
[0011] Furthermore, a gap is reserved between the front and rear sides of the reinforcing steel bar and the front and rear side walls of the brick mold.
[0012] The advantage of adopting the above-mentioned further solution is that it avoids damage to the brick mold.
[0013] Furthermore, the thickness of the concrete beam slab is greater than the thickness of the cushion layer.
[0014] Furthermore, the distance between any two adjacent brick molds is equal.
[0015] Furthermore, four brick formworks are provided on the inner side of the upper part of the backfill soil.
[0016] Furthermore, the upper surface of the pad layer is aligned with the upper end face of the brick mold in an inclined direction.
[0017] Furthermore, the beam and slab reinforcement bars extend along the inclined direction of the cushion layer. Attached Figure Description
[0018] Figure 1 This is a schematic diagram of the construction process of the first-floor reinforced concrete grandstand slab structure of this utility model. Figure 1 ;
[0019] Figure 2 This is a schematic diagram of the construction process of the first-floor reinforced concrete grandstand slab structure of this utility model. Figure 2 ;
[0020] Figure 3 This is a schematic diagram of the construction process of the first-floor reinforced concrete grandstand slab structure of this utility model. Figure 3 ;
[0021] Figure 4 This is a schematic diagram showing the completed construction of the first-floor reinforced concrete grandstand structure of this utility model.
[0022] In the accompanying drawings, the components represented by the reference numerals are as follows:
[0023] 1. Earthwork filling; 2. Groove; 3. Brick layer; 4. Protective pad block; 5. Subbase; 6. Reinforcing steel in the formwork; 7. Beam and slab reinforcement; 8. Concrete steps; 9. Concrete beams and slabs; 10. Beam concrete; 11. Brick formwork. Detailed Implementation
[0024] The principles and features of this utility model are described below with reference to the accompanying drawings. The examples given are only for explaining this utility model and are not intended to limit the scope of this utility model.
[0025] like Figures 1-4 As shown, this embodiment of a first-floor reinforced concrete grandstand structure includes a backfill 1. The top of the backfill 1 is an inclined structure. Multiple brick formworks 11 are provided on the inner side of the upper part of the backfill 1. The multiple brick formworks 11 are arranged sequentially at intervals along the front-back direction of the backfill 1. The brick formworks 11 extend along the left-right direction of the grandstand. An inclined pad layer 5 is provided between two adjacent brick formworks 11. Reinforcing bars 6 are provided inside the brick formworks 11. Beam concrete 10 is poured inside the brick formworks 11. The upper surface of the beam concrete 10 is flush with the upper surface of the pad layer 5. The upper end of the reinforcing bars 6 protrudes from the upper end of the brick formworks 11 at a predetermined height. Beam and slab reinforcing bars 7 are tied between the reinforcing bars 6 in two adjacent brick formworks 11. A concrete beam and slab 9 is poured on the pad layer 5. The upper ends of the reinforcing bars 6 and the beam and slab reinforcing bars 7 are embedded in the concrete beam and slab 9. A concrete step 8 is provided on the concrete beam and slab 9.
[0026] like Figure 1 and Figure 2 As shown, in this embodiment, the bottom of the brick mold 11 is provided with a protective pad 4, and the lower end of the reinforcing bar 6 is placed on the protective pad 4. By setting the protective pad, the reinforcing bar and the brick mold can be effectively protected.
[0027] like Figure 1 and Figure 2 As shown, the upper inner side of the earthwork 1 in this embodiment is provided with multiple grooves 2, and the front and rear sides of the grooves 2 are provided with brick layers 3 to form a brick mold 11.
[0028] like Figure 1 and Figure 2 As shown, in this embodiment, the brick mold 11 is arranged horizontally through the left and right sides of the grandstand panel.
[0029] like Figure 3 As shown, in this embodiment, a gap is reserved between the front and rear sides of the reinforcing bar 6 and the front and rear side walls of the brick mold 11 to avoid damage to the brick mold.
[0030] like Figure 3 and Figure 4 As shown, the thickness of the concrete beam slab 9 in this embodiment is greater than the thickness of the cushion layer 5.
[0031] Optionally, the distance between any two adjacent brick molds 11 is equal.
[0032] like Figures 1-4As shown, the upper inner side of the earthwork 1 in this embodiment is provided with four brick molds 11.
[0033] like Figures 1-4 As shown, in this embodiment, the upper surface of the pad layer 5 is aligned with the upper end face of the brick mold 11 in the inclined direction.
[0034] like Figures 1-4 As shown, in this embodiment, the beam and slab reinforcement 7 extends along the inclined direction of the cushion layer 5.
[0035] The construction method of the first-floor reinforced concrete grandstand slab structure in this embodiment is as follows: (1) Earthwork filling: according to the required earthwork volume on site, pre-fill the earthwork to the construction position. (2) Positioning and layout: according to the construction drawings, use instruments such as RTK to locate the plane and elevation positions, and mark the white lime lines for the beam and slab positions. (3) Excavation of beam and slab positions: excavate the earthwork at the beam and slab positions using excavators, manual labor, etc. (4) Layout of brick formwork positions: perform secondary layout of the excavated basic construction site, accurately confirm the plane position and elevation of the brick formwork, and compact and level the earthwork under the brick formwork. (5) Brick formwork masonry: mason the brick formwork according to the on-site positioning lines, requiring full mortar and smooth masonry. After masonry, support the inside of the brick formwork, and provide wooden formwork support on the north side of the brick formwork at the highest and lowest points. (6) Backfilling of the core soil: backfill, level, and compact the core soil between the brick formworks, paying attention not to over-compact to prevent the brick formwork from tilting inward. (7) Foundation layer pouring. A foundation layer is poured under the concrete of the beams and slabs. During pouring, attention should be paid to ensuring the thickness and flatness of the foundation layer. (8) Reinforcement binding. According to the drawings, the reinforcement bars are bound at the positions of the brick formwork. (9) Reinforcement bar placement. The bound reinforcement cage is placed into the brick formwork, and its protective layer is properly supported. The lower part of the grandstand beam is poured, exposing the upper reinforcement bars of the beam. (10) Concrete pouring. The grandstand beam is poured in one go according to the drawings. It is ensured that the concrete of the beam is vibrated in place and the surface is flat. After completion, curing work is carried out in a timely manner.
[0036] In this embodiment, the first-floor reinforced concrete grandstand slab structure achieves a stable and tight connection between the concrete beams and slabs and the main concrete structure by extending a portion of the reinforcing steel bars from the top of the brick formwork and tying them to the beam and slab reinforcement. This facilitates construction and shortens the construction time for supporting and dismantling the step formwork. This first-floor reinforced concrete grandstand slab structure in this embodiment changes the original support method and construction steps, allowing the upper layer of concrete to be poured in one go, saving costs, improving quality, and reducing safety risks.
[0037] In the description of this utility model, it should be understood that the terms "center", "longitudinal", "transverse", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", "axial", "radial", "circumferential", etc., indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing this utility model and simplifying the description, and are not intended to indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this utility model.
[0038] Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include at least one of that feature. In the description of this utility model, "a plurality of" means at least two, such as two, three, etc., unless otherwise explicitly specified.
[0039] In this utility model, unless otherwise explicitly specified and limited, the terms "installation," "connection," "joining," and "fixing," etc., should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral part; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; they can refer to the internal communication of two components or the interaction between two components, unless otherwise explicitly limited. Those skilled in the art can understand the specific meaning of the above terms in this utility model according to the specific circumstances.
[0040] In this utility model, unless otherwise explicitly specified and limited, "above" or "below" the second feature can mean that the first feature is in direct contact with the second feature, or that the first feature is in indirect contact with the second feature through an intermediate medium. Furthermore, "above," "on top of," and "over" the second feature can mean that the first feature is directly above or diagonally above the second feature, or simply that the first feature is at a higher horizontal level than the second feature. "Below," "below," and "under" the second feature can mean that the first feature is directly below or diagonally below the second feature, or simply that the first feature is at a lower horizontal level than the second feature.
[0041] In the description of this specification, the references to terms such as "one embodiment," "some embodiments," "example," "specific example," or "some examples," etc., indicate that a specific feature, structure, material, or characteristic described in connection with that embodiment or example is included in at least one embodiment or example of the present invention. In this specification, the illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples. Moreover, without contradiction, those skilled in the art can combine and integrate the different embodiments or examples described in this specification, as well as the features of different embodiments or examples.
[0042] Although embodiments of the present invention have been shown and described above, it is understood that the above embodiments are exemplary and should not be construed as limiting the present invention. Those skilled in the art can make changes, modifications, substitutions and variations to the above embodiments within the scope of the present invention.
Claims
1. A first-floor reinforced concrete grandstand slab structure, characterized in that, The structure includes earthwork, the top of which is an inclined structure. Multiple brick formworks are provided on the inner side of the upper part of the earthwork, spaced apart in a sequential manner along the front-to-back direction of the earthwork. The brick formworks extend along the left-to-right direction of the grandstand platform, and an inclined pad layer is provided between adjacent brick formworks. Reinforcing bars are installed within the brick formworks, and concrete beams are poured within the brick formworks. The upper surface of the concrete beams is flush with the upper surface of the pad layer. The upper ends of the reinforcing bars protrude from the top of the brick formworks at a predetermined height. Beam and slab reinforcing bars are tied between the reinforcing bars in adjacent brick formworks. A concrete beam and slab are poured on the pad layer, with the upper ends of the reinforcing bars and the beam and slab reinforcing bars embedded within the concrete beam and slab. Concrete steps are provided on the concrete beam and slab.
2. The first-floor reinforced concrete grandstand slab structure according to claim 1, characterized in that, The bottom of the brick mold is provided with a protective pad, and the lower end of the reinforcing bar is placed on the protective pad.
3. The first-floor reinforced concrete grandstand slab structure according to claim 1, characterized in that, The upper inner side of the earthwork is provided with multiple grooves, and the front and rear sides of the grooves are provided with brick layers to form a brick mold.
4. The first-floor reinforced concrete grandstand slab structure according to claim 1, characterized in that, The brick mold is arranged horizontally through the left and right sides of the grandstand panel.
5. The first-floor reinforced concrete grandstand slab structure according to claim 1, characterized in that, A gap is reserved between the front and rear sides of the reinforcing steel bars and the front and rear side walls of the brick mold.
6. The first-floor reinforced concrete grandstand slab structure according to claim 1, characterized in that, The thickness of the concrete beam slab is greater than the thickness of the cushion layer.
7. The first-floor reinforced concrete grandstand slab structure according to claim 1, characterized in that, The distance between any two adjacent brick molds is equal.
8. The first-floor reinforced concrete grandstand slab structure according to claim 1, characterized in that, The inner side of the upper part of the earthwork is provided with four brick formwork.
9. The first-floor reinforced concrete grandstand slab structure according to claim 1, characterized in that, The upper surface of the pad layer is aligned with the upper end face of the brick mold in an inclined direction.
10. The first-floor reinforced concrete grandstand slab structure according to claim 1, characterized in that, The reinforcing bars of the beam and slab extend along the inclined direction of the cushion layer.