Integrated scaffold overhanging platform for external facade of high-rise building

By designing an integrated cantilever platform for scaffolding, and utilizing pre-embedded bolts and basket brace-type cantilever scaffolding, the complex construction problem of cantilever structures in high-rise buildings was solved, enabling rapid installation and efficient construction, and adapting to different facade shapes.

CN223593771UActive Publication Date: 2025-11-25QINGJIAN GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422882963.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-11-26
Publication Date
2025-11-25
Estimated Expiration
2034-11-26

AI Technical Summary

Technical Problem

The construction of existing high-rise building cantilever structures is difficult, the formwork support system is complicated, it consumes a lot of manpower and time, and the commonly used scaffolding occupies internal space or poses a danger of working at height, which affects the construction progress.

Method used

Design an integrated cantilever scaffolding platform, including anchor plates, base, positioning piles, tie rods and fixing components, which is fixed to the main building through pre-embedded bolts. Combined with basket tie rod type cantilever scaffolding, it can achieve rapid installation and disassembly.

Benefits of technology

It simplifies the construction process, saves construction time, reduces the risks of working at heights, improves construction efficiency and progress, is applicable to different facade shapes, and enhances the practicality of the device.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223593771U_ABST
    Figure CN223593771U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of high-rise building outer wall construction, in particular to an integrated scaffold overhanging platform for a high-rise building outer vertical face, which comprises a scaffold and a supporting platform, the supporting platform comprises a base, a positioning pile, an anchoring plate, a pull rod and a fixing assembly, and the anchoring plate abuts against the outer side of the high-rise building outer vertical face. The base is fixed to the outer side of the anchoring plate and is perpendicular to the outer vertical face, the positioning pile is perpendicularly installed above the base, the anchoring plate and the upper end of the pull rod are fixedly connected with the outer vertical face through the fixing assembly, the lower end of the pull rod is connected to the far end of the base, and the bottom of the scaffold is inserted into the positioning pile. The scaffold is convenient to mount and fix by using the fixing pile mounted on the base, the anchor plate can be assisted to fix the base by using the pull rod, and the position of the fixing pile can be adjusted according to the size of the scaffold by connecting the pile body and the I-shaped outrigger by using the sliding block, so that the scaffolds with different sizes can be used.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to high -rise building outer wall construction field, specifically at high -rise building outer facade's integrated scaffold overhanging platform. BACKGROUND

[0002] In order to meet the effect of highlighting building facade modeling and the need of high -rise upper space expansion when building design, in recent years, the building of high -altitude overhanging concrete structure, component design is more and more.But high -rise overhanging structure construction is difficult, formwork support is particularly complex, the commonly used formwork support system such as because of various factors is difficult to implement, the existing formwork support system process is complicated, and a large amount of labor and construction period is consumed.

[0003] In the high -altitude overhanging structure used to meet the effect of highlighting building facade modeling and the need of upper space expansion in present building design, ordinary type steel overhanging scaffold needs to embed bolt in the main body, fixed channel steel, occupies a large amount of internal space, is not suitable for the structure type of small indoor area.

[0004] When type steel overhanging scaffold is installed, high -altitude operation is dangerous, and channel steel needs to be hoisted and installed individually, and the construction time is long, and the foot eye needs to be blocked after the wall channel steel, which affects the construction progress of outer wall.

[0005] The floor scaffold exists the problems such as the height of erection is too high and the site is limited, and type steel overhanging scaffold needs to erect the frame body in simple and suspended time every overhanging layer, if the number of high -rise overhanging layers is too much, then the construction period is greatly affected, and the subsequent removal of each layer of overhanging I -beam, the hole sealing and plastering of outer wall all need to consume labor and have certain influence on the waterproof of outer wall.

[0006] Therefore, in view of the problems of separate use of scaffold installation higher, long construction time of type steel overhanging scaffold in the prior art, the technical personnel in the field urgently need a scaffold installation structure which is simple in structure, can install lower layer of scaffold in appropriate position, and can achieve the purpose of overhanging. SUMMARY

[0007] In view of the problems in the prior art, the utility model aims at providing a high -rise building outer facade integrated scaffold overhanging platform which is convenient to use, can be directly hoisted and installed during the construction of overhanging part, saves a lot of construction time compared with the previous formwork support system, and can save construction period.

[0008] To achieve the above object, the utility model adopts the technical scheme, which is: an integrated scaffold overhanging platform for the facade of high-rise building, which comprises a scaffold and a supporting platform, the supporting platform comprises a base, a positioning pile, an anchoring plate, a pull rod and a fixing assembly, the anchoring plate is attached to the outer side of the facade of high-rise building, the base is fixed to the outer side of the anchoring plate and perpendicular to the facade, the positioning pile is vertically installed above the base, the anchoring plate and the upper end of the pull rod are fixedly connected to the facade through the fixing assembly, the lower end of the pull rod is connected to the distal end of the base, and the bottom of the scaffold is inserted into the positioning pile.

[0009] The integrated scaffold overhanging platform for the facade of high-rise building, the fixing assembly comprises a fixed nut, a pre-buried bolt and a pre-buried lifting ring, the pre-buried bolt and the pre-buried lifting ring are set in the main body of the high-rise building, the pre-buried bolt is arranged below the pre-buried lifting ring, the anchoring plate is provided with an anchoring hole, the pre-buried bolt passes through the anchoring hole, the fixed nut is screwed on the pre-buried bolt, and the upper end of the pull rod is connected to the pre-buried lifting ring.

[0010] The integrated scaffold overhanging platform for the facade of high-rise building, the pull rod comprises an upper section pull rod, a lower section pull rod and a threaded sleeve, the bottom of the lower section pull rod is connected to the base, the bottom of the upper section pull rod and the top of the lower section pull rod are provided with threads, the top of the upper section pull rod is provided with a pull hook, the threaded sleeve is screwed on the threads, and the pull hook is hung in the pre-buried lifting ring.

[0011] The integrated scaffold overhanging platform for the facade of high-rise building, the base is provided with an upper pull ear plate, the upper pull ear plate is provided with an ear plate hole, the bottom of the lower section pull rod is provided with an upper pull plate, the upper pull plate is provided with an upper pull hole, and the upper pull hole and the ear plate hole are provided with an upper pull bolt.

[0012] The integrated scaffold overhanging platform for the facade of high-rise building, the anchoring plate is in the shape of a straight plate or an arc-shaped plate, and the anchoring hole is in the shape of a circle and / or an ellipse.

[0013] The integrated scaffold overhanging platform for the facade of high-rise building, the base comprises an I-shaped cantilever beam and a connecting beam, the I-shaped cantilever beam is vertically fixed to the anchoring plate, the connecting beam connects adjacent I-shaped cantilever beams, and the positioning pile is arranged on the I-shaped cantilever beam.

[0014] The positioning pile comprises a pile body, a sliding block, a sliding groove and a locking bolt, the sliding groove is arranged at the bottom of the sliding block, the sliding block is slidably connected to the upper surface of the I-shaped cantilever beam through the sliding groove, the pile body is fixed above the sliding block, locking screw holes are arranged on the sliding block, and the locking bolt is abutted against the surface of the I-shaped steel after penetrating through the locking screw holes.

[0015] The scaffold comprises steel pipes, scaffold boards, skirting boards, connecting pieces and safety nets, the steel pipes are connected into a steel pipe frame with horizontal, vertical and inclined staggered arrangements through the connecting pieces, the scaffold boards are laid between the horizontal steel pipes, the skirting boards are vertically arranged outside the vertical steel pipes, the vertical steel pipes comprise fixed pipes which are inserted into the positioning piles, and the safety nets are arranged outside the steel pipe frame.

[0016] The number of the pull rods arranged at the same position at the distal end of the base is not less than 1.

[0017] The anchor plate and the embedded bolt are used to fix the base on the outer wall of the building body, the fixed pile installed on the base is used to facilitate the installation and fixation of the scaffold, the pull rod is used to assist the anchor plate in fixing the base, the sliding block is used to connect the pile body and the I-shaped cantilever beam, the position of the fixed pile can be adjusted according to the size of the scaffold, and different size scaffolds can be used; different shapes of the anchor plate are arranged, suitable anchor plates can be selected according to different shapes of the outer facade, and the practicability of the device is enhanced; the threaded sleeve is used to connect the upper section pull rod and the lower section pull rod, the tension of the pull rod and the length of the pull rod can be adjusted, and the pull rod is convenient to disassemble and assemble; the pull hook and the pull plate are used to fix the two ends of the pull rod, the connection strength of the pull rod is ensured, and the angle of the pull rod can be adjusted. BRIEF DESCRIPTION OF DRAWINGS

[0018] Figure 1 A side structure schematic view for installation and use of the utility model is shown in the figure;

[0019] Figure 2 A three-dimensional structure schematic view for installation and use of the utility model is shown in the figure;

[0020] Figure 3 A support platform structure schematic view of the utility model is shown in the figure;

[0021] Figure 4 An anchor plate structure schematic view of the utility model is shown in the figure;

[0022] Figure 5 An I-shaped steel installation position schematic view in the embodiment of the utility model is shown in the figure.

[0023] Explanation of reference numerals in the attached drawings: scaffolding 10, steel pipe 11, support platform 20, base 21, I-beam 211, upper pull plate 212, positioning pile 22, pile body 221, slider 222, anchor plate 23, anchor hole 231, tie rod 24, upper tie rod 241, lower tie rod 242, threaded sleeve 243, embedded bolt 25, embedded lifting ring 26, exterior facade 30. Detailed Implementation

[0024] To enable those skilled in the art to better understand the technical solution of this utility model, the technical solution of this utility model will be described below in conjunction with specific embodiments and accompanying drawings.

[0025] Modern architectural designs often feature high-altitude cantilever structures to achieve the desired effect of highlighting the building facade and expanding the upper space. However, the formwork support for high-altitude cantilever structures is challenging, and the quality and safety requirements are high. Conventional formwork support systems are often insufficient to meet the construction needs.

[0026] The scaffolding method of pre-embedding U-bolts to fix I-beams requires each I-beam to have its bolts pre-embedded individually. The hoisting and installation process is complicated, and the subsequent cutting of the channel steel and sealing of the wall openings will affect the construction progress of that floor and require a certain amount of labor.

[0027] If the height of the ground-supported scaffolding is too high, the cost will be too high, and the construction site of some high-rise buildings is too small to meet the site requirements.

[0028] like Figures 1-5 As shown, the technical solution in this embodiment allows for the fabrication of the external scaffold steel support before the main construction, and it can be directly hoisted and installed during construction at the cantilevered parts. Compared with the previous formwork support system, this saves a lot of construction time. Furthermore, the support frame is fixed by pre-embedded bolts in the external wall, which makes disassembly and assembly convenient and can greatly save the construction period.

[0029] This technical solution utilizes a basket-link cantilever scaffolding construction method, integrating the cantilever platform and scaffolding into a unified formwork support frame composed of multiple frame units. Before the main construction, BIM modeling is used to determine the steel profile parameters, and the prefabricated steel structure frame is constructed. First, the detailed parameters of individual I-beam supports are determined, and multiple individual I-beams are welded and fixed using anchoring steel plates to form the unified formwork support frame. Depending on the structural characteristics, each cantilever layer's formwork support frame can consist of several formwork support frames.

[0030] Example 1

[0031] An integrated scaffold cantilever platform for the outer facade of high-rise buildings, comprising a scaffold 10, a support platform 20, the scaffold comprising steel pipes 11, scaffold boards, skirting boards, connecting pieces, safety nets, the steel pipes being connected by connecting pieces to form a horizontally, vertically and obliquely staggered steel pipe frame, the scaffold boards being laid between the horizontal steel pipes, the skirting boards being vertically arranged outside the vertical steel pipes, the overall structure of the scaffold being basically the same as that of the existing scaffold structure, the difference being that a downward extending fixing pipe needs to be arranged at the bottom of the scaffold according to the arrangement of the support platform, the fixing pipe being composed of vertical steel pipes, and the safety nets being arranged outside the steel pipe frame.

[0032] The support platform comprises a base 21, positioning piles 22, anchor plates 23, pull rods 24 and fixing assemblies.

[0033] The anchor plate is in the shape of a straight plate or an arc-shaped plate, the anchor plate being abutted against the outer side of the outer facade 30 of the high-rise building, the anchor plate being fixedly connected with the outer facade through the fixing assembly, the anchor plate being provided with anchor holes 231, the anchor holes being in the shape of a circle and / or an ellipse.

[0034] The base is fixedly arranged on the outer side of the anchor plate and perpendicular to the outer facade, the base comprising I-shaped cantilever beams 211 and connecting beams, the I-shaped cantilever beams being fixedly arranged on the anchor plate, the connecting beams connecting adjacent I-shaped cantilever beams, the connecting beams also being able to use connecting flat plates.

[0035] The positioning piles are vertically arranged above the base, the positioning piles being arranged on the I-shaped cantilever beams, the positioning piles comprising pile bodies 221, sliding blocks 222, sliding grooves and locking bolts, the sliding grooves being arranged at the bottom of the sliding blocks, the sliding blocks being slidingly sleeved on the upper surfaces of the I-shaped cantilever beams through the sliding grooves, the pile bodies being fixedly arranged above the sliding blocks, the sliding blocks being provided with locking screw holes, the locking bolts being abutted against the surfaces of the I-shaped cantilever beams after penetrating through the locking screw holes, and the fixing pipes being inserted into the positioning piles.

[0036] The upper ends of the pull rods are fixedly connected with the outer facade through the fixing assemblies, and the lower ends of the pull rods are connected with the distal ends of the base.

[0037] The pull rods comprise upper section pull rods 241, lower section pull rods 242 and threaded sleeves 243, the lower sections of the lower section pull rods being connected with the base, the lower sections of the upper section pull rods and the upper sections of the lower section pull rods being provided with threads, the upper sections of the upper section pull rods being provided with pull hooks, and the threaded sleeves being screwed on the threads.

[0038] The fixing assemblies comprise fixing nuts, embedded bolts 25 and embedded lifting rings 26, the embedded bolts and the embedded lifting rings being arranged in the main body of the high-rise building in a set, the embedded bolts being arranged below the embedded lifting rings, the embedded bolts penetrating through the anchor holes, the fixing nuts being screwed on the embedded bolts, and the upper ends of the pull rods being hung on the embedded lifting rings through the pull hooks.

[0039] The base is provided with an upper pulling ear plate 212, and the upper pulling ear plate is provided with an ear plate hole. The bottom of the lower section pulling rod is provided with an upper pulling plate, and the upper pulling plate is provided with an upper pulling hole. The upper pulling hole and the ear plate hole are provided with an upper pulling bolt.

[0040] In order to improve the tensile force of the pulling rod, the same upper pulling ear plate at the distal end of the base is provided with not less than one pulling rod. When a plurality of pulling rods are provided, the plurality of pulling rods are connected to a plurality of pre-buried lifting rings.

[0041] Embodiment 2

[0042] The same as embodiment 1 will not be described again, and the construction of the support platform is mainly described.

[0043] The parameters are determined, and detailed construction drawings are provided by the design unit. The detailed parameters of each overhanging layer are confirmed by the scaffold team, and the data required for the design of the steel structure formwork support frame is confirmed.

[0044] After confirming the data required for the steel structure formwork support frame, i.e. the support platform, the steel structure unit performs cutting and processing.

[0045] Confirm the processing parts, including pre-buried bolts, pre-buried lifting rings, pre-buried bolt hole I-beam end plates (anchor plates), I-beams (I-beam cantilever beams), I-beam pulling rods (pulling rods), and scaffold positioning piles (positioning piles).

[0046] An anchor plate is welded to the end of the I-beam after cutting. The anchor holes on the anchor plate are one round and one oval, and are arranged in a cross shape or staggered. They are mainly used to adjust the position between the anchor plate and the main body. In addition, a triangular support steel plate is added to the position where the I-beam is connected to the anchor plate to strengthen the firmness.

[0047] The position of the I-beam pulling point is determined according to the calculation, and a lifting lug steel plate (pulling lug) is welded at this position. The pulling lug is connected to the upper pulling plate at the end of the pulling rod by a pulling bolt.

[0048] According to the vertical positioning of the fixed pipe of the scaffold, a movable scaffold positioning pile is arranged at the vertical rod position on the upper surface of the I-beam main beam or the longitudinal connecting beam of the base. The scaffold vertical rod is sleeved outside the movable scaffold positioning pile to prevent the vertical rod from slipping.

[0049] The whole composed of the I-beam, the pre-buried bolt, the anchor plate, the pre-buried lifting ring, the I-beam pulling rod, and the scaffold positioning pile is regarded as a unit. According to the structural characteristics, the anchor plate can be lengthened in the form of adhering to the outer wall of the building to weld more I-beams, and a plurality of units can be combined to form a support frame suitable for various projects.

[0050] The pull rod is made of Φ20*1.6m, Φ20*1.0m carbon steel and three Φ14 carbon steel, which are double-welded and combined and installed.

[0051] Each pull rod is made of two Φ16 round steels with a length of about 1.6m, one end of which is hammered flat and the other end is arched. The upper pull point is welded with an opening steel plate at a certain angle, and the lower pull point is welded with an opening steel plate of the same specification. The two arched ends are connected by bolts. Similarly, a pull hook is set at the upper pull point and welded, which is hung in the pre-embedded lifting lug.

[0052] A special temporary fixing screw is provided to ensure that the pre-embedded part does not deviate during concrete pouring. After the concrete is poured, the turnover accessories that need to be twisted out before the formwork is removed.

[0053] Hoist and install, support platform construction sequence: hoist and install the support platform, tighten the bolts, install the formwork support scaffold, embed the pull ring in the upper layer of concrete, and fix the pull rod.

[0054] After the support platform is processed, it is stored in the processing site. When the main body construction reaches the cantilever layer, use the tower crane or automobile crane to hoist the support platform to the construction layer and fix it, which can be used as a frame to set up the formwork support scaffold of the layer.

[0055] Based on the planar arrangement of I-beams, pre-embedding is carried out. Two Φ1.2cm round holes are opened on each cantilever beam on the outer formwork, and then the special screw is fixed on the outer formwork to ensure that the pre-embedded part does not deviate during concrete pouring.

[0056] When the concrete strength reaches more than 5MPa or the required strength, start installing the double-end screw.

[0057] When the concrete reaches more than 10MPa or the specified requirement, start setting up the outer frame. During this process, heavy materials are strictly prohibited from being stacked on the support platform. Any materials hoisted on the tower crane are strictly prohibited during this process. When the connection of the pull rod is not available, the scaffold can be set up to a maximum height of 12 meters.

[0058] When the concrete strength of the upper layer of the cantilever layer reaches the required strength, the pull rod should be assembled as soon as possible, and the pull rod should be adjusted to the stressed state in time, and then the scaffold can be set up upwards.

[0059] Before pouring the concrete of the upper layer of the cantilever layer, arrange the pre-embedded part (150mm long) of the pull rod upper end pull-in point.

[0060] After the outer formwork is removed and the concrete strength reaches the specified requirement (generally about 48 hours after pouring), start twisting the pre-embedded lifting ring into the pre-embedded part and connecting the pull rod, and adjust it to the stressed state. Finally, set up the outer frame upwards to 20 meters (within).

[0061] Dismantling, after the outer wall construction is finished, hold force is hoisted by tower crane, and the support platform is dismantled.

[0062] The above examples are only for illustrating the structural concept and characteristics of the present application, and the purpose is to enable the ordinary skilled in the art to understand the content of the present application and to implement it, and cannot limit the protection scope of the present application. Any equivalent changes or modifications made according to the essence of the present application should be covered within the protection scope of the present application.

Claims

1. An integrated scaffold overhang platform for high-rise building facade, comprising a scaffold, a support platform, characterized in that: The support platform comprises a base, a positioning pile, an anchoring plate, a pull rod, a fixing assembly, the anchoring plate is attached to the outer side of the outer facade of the high-rise building, the base is fixed to the outer side of the anchoring plate and perpendicular to the outer facade, the positioning pile is vertically installed above the base, the upper end of the anchoring plate and the pull rod is fixedly connected to the outer facade through the fixing assembly, the lower end of the pull rod is connected to the distal end of the base, and the bottom of the scaffold is inserted into the positioning pile.

2. The integrated scaffolding cantilever platform for high-rise building facade according to claim 1, characterized in that: The fixing assembly comprises a fixed nut, a pre-buried bolt and a pre-buried lifting ring, the pre-buried bolt and the pre-buried lifting ring are provided in a set in the main body of the high-rise building, the pre-buried bolt is arranged below the pre-buried lifting ring, the anchoring plate is provided with an anchoring hole, the pre-buried bolt passes through the anchoring hole, the fixed nut is screwed on the pre-buried bolt, and the upper end of the pull rod is connected to the pre-buried lifting ring.

3. The integrated scaffolding cantilever platform for high-rise building facade according to claim 2, characterized in that: The pull rod comprises an upper section pull rod, a lower section pull rod and a threaded sleeve, the bottom of the lower section pull rod is connected to the base, the bottom of the upper section pull rod and the top of the lower section pull rod are provided with threads, the top of the upper section pull rod is provided with a pull hook, and the threaded sleeve is screwed on the threads.

4. The integrated scaffolding cantilever platform for high-rise building facade according to claim 3, characterized in that: The base is provided with an upper pull ear plate, the upper pull ear plate is provided with an ear plate hole, the bottom of the lower section pull rod is provided with an upper pull plate, the upper pull plate is provided with an upper pull hole, and the upper pull hole and the ear plate hole are provided with an upper pull bolt.

5. The integrated scaffolding cantilever platform for high-rise building facade according to claim 4, characterized in that: The anchoring plate is in the shape of a straight plate or an arc-shaped plate, and the anchoring hole is in the shape of a circle and / or an ellipse.

6. The integrated scaffolding cantilever platform for high-rise building facade according to claim 1, characterized in that: The base comprises an I-shaped cantilever beam and a connecting beam, the I-shaped cantilever beam is fixedly arranged on the anchoring plate, the connecting beam connects adjacent I-shaped cantilever beams, and the positioning pile is arranged on the I-shaped cantilever beam.

7. The integrated scaffolding cantilever platform for high-rise building facade according to claim 6, characterized in that: The positioning pile comprises a pile body, a sliding block, a sliding groove, and a locking bolt, the sliding groove is arranged at the bottom of the sliding block, the sliding block is slidably sleeved on the upper surface of the I-shaped cantilever beam through the sliding groove, the pile body is fixed above the sliding block, the sliding block is provided with a locking screw hole, and the locking bolt is abutted against the surface of the I-shaped cantilever beam after passing through the locking screw hole.

8. The integrated scaffolding cantilever platform for high-rise building facade according to claim 1, characterized in that: The scaffold comprises steel pipes, foot plates, toe plates, connecting pieces, and safety nets, the steel pipes are arranged in a horizontal, vertical and oblique staggered manner through the connecting pieces, the foot plates are arranged between the horizontal steel pipes, the toe plates are arranged outside the vertical steel pipes, the vertical steel pipes comprise fixed pipes, the fixed pipes are inserted into the positioning piles, and the safety nets are arranged outside the steel pipe frame.

9. The integrated scaffolding cantilever platform for high-rise building facade according to claim 1, characterized in that: The pull rods arranged at the same position of the distal end of the base are not less than one.