Temporary glass cushion block system for glass curtain wall system
By designing a steel column body and a wedge-shaped glass pad system, the problems of traditional nylon pads being unable to adjust height and be removed were solved, achieving controllable stress on the glass curtain wall and economical reuse.
Patent Information
- Application Number
- CN202520272169.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-02-20
- Publication Date
- 2025-12-02
- Estimated Expiration
- 2035-02-20
AI Technical Summary
Traditional nylon temporary glass pads cannot be adjusted in height or removed, interfering with the load-bearing system of the glass curtain wall and causing the glass to break.
A temporary glass pad system was designed, comprising a steel column body, connecting steel plates, pad body, and fixed base. The height can be adjusted and fixed by adjusting nuts and height screws. The wedge-shaped structure facilitates disassembly, and the gaps are filled with a mixed adhesive.
It achieves adjustable glass pad height and easy removal, ensuring controllable stress on the glass curtain wall, and is economical and reusable.
Smart Images

Figure CN223621109U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the technical field, specifically to a temporary glass pad system for glass curtain wall systems. Background Technology
[0002] Large glass curtain wall systems often use multi-layered laminated glass. To eliminate the overlap of glass panes, it is necessary to use glass spacers that inject mixed adhesive to ensure that each glass pane is evenly stressed. Temporary glass spacers are required before the mixed adhesive is completely cured.
[0003] However, traditional glass pads have the following disadvantages:
[0004] Traditional glass spacers are made of nylon. These temporary nylon glass spacers cannot be adjusted in height or removed, which can interfere with the load-bearing system of the entire curtain wall and cause the glass to break. Utility Model Content
[0005] The purpose of this invention is to provide a temporary glass pad system for glass curtain wall systems, in order to solve the problem mentioned in the background art that traditional glass pads are made of nylon material, and that traditional nylon temporary glass pads cannot be adjusted in height and cannot be removed, which will interfere with the load-bearing system of the entire curtain wall and cause the glass to break.
[0006] To achieve the above objectives, this utility model provides the following technical solution: a temporary glass pad system for a glass curtain wall system, comprising a steel column body, a connecting steel plate connected to the outer side of the steel column body, a connecting port opened in the middle of one side of the connecting steel plate, a pad body slidably connected inside the connecting port, multi-layer laminated glass fixedly installed at the top of the steel column body, a fixed base fixedly installed at the bottom of the steel column body, the pad body comprising a wedge block and a connecting plate, one side of the wedge block being fixedly connected to the middle of one side of the connecting plate, and threaded holes opened at both ends of one side of the connecting plate.
[0007] Preferably, the middle of both ends of the connecting steel plate is threaded with an adjusting nut. The connecting steel plate is fixedly connected to the pad body through the adjusting nut. The user can fix the pad body in the connection port by rotating the adjusting nut so that the thread on the surface of the adjusting nut matches the thread on the inner wall of the threaded hole.
[0008] Preferably, the surface of the connecting steel plate is threaded with assembly screws, and the connecting steel plate is fixedly connected to the steel column body by the assembly screws. When the user screws on the surface of the assembly screws, the threads on the surface of the assembly screws match the threads on the inner wall of the steel column body, thereby assembling the connecting steel plate and the steel column body together.
[0009] Preferably, a sealing gasket is provided at the connection between the connecting steel plate and the steel column body, and the sealing gasket fills the gap between the connecting steel plate and the steel column body.
[0010] Preferably, both sides of the top of the fixed base are threaded with height screws, and the bottom ends of the two height screws are rotatably connected to ground stakes. The user can rotate the height screws to adjust the height of the ground stakes, and the ground stakes are inserted into the place of use to complete the fixation of the fixed base.
[0011] Preferably, each of the two height screws has a locking nut threaded to its top end, and a washer is fitted at the connection between the two height screws and the two locking nuts. When the user tightens the locking nut, the thread on the inner wall of the locking nut matches the thread on the surface of the height screw, fixing the locking nut to the height screw, and the washer seals the connection between the locking nut and the height screw.
[0012] Preferably, each of the top ends of both sides of the connecting steel plate is provided with an injection port, through which the mixed adhesive is injected into the connecting steel plate to fill the gap between the connecting steel plate and the steel column body.
[0013] Compared with the prior art, the beneficial effects of this utility model are:
[0014] 1. This pad is easy to install, and its wedge-shaped structure allows for adjustment of the glass pad height to level the entire glass curtain wall;
[0015] 2. The pad is easy to remove. After loosening the nut, it is easy to remove because of its wedge-shaped structure, which ensures that the stress of the entire large glass curtain wall system is controllable.
[0016] 3. The pad is designed with standard parts, can be reused, and is economical. Attached Figure Description
[0017] Figure 1 This is a perspective view of the utility model in use;
[0018] Figure 2 This is a cross-sectional view of the present invention in use;
[0019] Figure 3 This is a side view of the pad body of this utility model.
[0020] In the diagram: 1. Connecting steel plate; 2. Steel column body; 3. Adjusting nut; 4. Pad body; 41. Wedge block; 42. Connecting plate; 43. Threaded hole; 5. Multi-layer laminated glass; 6. Sealing pad; 7. Glue injection port; 8. Fixed base; 9. Ground stake; 10. Pad plate; 11. Locking nut; 12. Height screw; 13. Connection port; 14. Assembly screw. Detailed Implementation
[0021] The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention.
[0022] Please see Figure 1-3 This utility model provides a temporary glass pad system for a glass curtain wall system, including a steel column body 2, a connecting steel plate 1 connected to the outer side of the steel column body 2, a connecting port 13 opened in the middle of one side of the connecting steel plate 1, a pad body 4 slidably connected inside the connecting port 13, a multi-layer laminated glass 5 fixedly installed at the top of the steel column body 2, a fixed base 8 fixedly installed at the bottom of the steel column body 2, and the pad body 4 includes a wedge block 41 and a connecting plate 42. One side of the wedge block 41 is fixedly connected to the middle of one side of the connecting plate 42, and threaded holes 43 are opened at both ends of one side of the connecting plate 42.
[0023] Adjusting nuts 3 are threadedly connected to the middle of both ends of the connecting steel plate 1. The connecting steel plate 1 is fixedly connected to the pad body 4 through the adjusting nuts 3. The user rotates the adjusting nuts 3, and the threads on the surface of the adjusting nuts 3 match the threads on the inner wall of the threaded hole 43, thereby fixing the pad body 4 in the connection port 13.
[0024] The surface of the connecting steel plate 1 is threaded with assembly screws 14. The connecting steel plate 1 is fixedly connected to the steel column body 2 by the assembly screws 14. When the user screws the assembly screws 14, the threads on the surface of the assembly screws 14 match the threads on the inner wall of the steel column body 2, thereby assembling the connecting steel plate 1 and the steel column body 2 together.
[0025] A sealing gasket 6 is fitted at the connection between the connecting steel plate 1 and the steel column body 2, and the sealing gasket 6 fills the gap between the connecting steel plate 1 and the steel column body 2.
[0026] Both sides of the top of the fixed base 8 are threaded with height screws 12, and the bottom of the two height screws 12 are rotatably connected to ground stakes 9. The user can rotate the height screws 12 to adjust the height of the ground stakes 9, and the ground stakes 9 are inserted into the place of use to complete the fixation of the fixed base 8.
[0027] The top ends of the two height screws 12 are threaded with locking nuts 11. Washers 10 are fitted at the connection points between the two height screws 12 and the two locking nuts 11. When the user tightens the locking nuts 11, the threads on the inner wall of the locking nuts 11 match the threads on the surface of the height screws 12, thus fixing the locking nuts 11 onto the height screws 12. The washers 10 also seal the connection points between the locking nuts 11 and the height screws 12.
[0028] The top of both sides of the connecting steel plate 1 is provided with an injection port 7. The mixed adhesive is injected into the connecting steel plate 1 through the injection port 7 to fill the gap between the connecting steel plate 1 and the steel column body 2.
[0029] In this embodiment of the application, the glass pads of the large glass system are constructed using a mixed adhesive casting pad. Before curing, temporary glass pads need to be added. During installation, wedge-shaped nylon pads are first glued to the bottom of the glass. When the glass is installed in place, the wedge-shaped steel pads are inserted into the bottom of the glass through the notch of the bottom connecting steel plate 1. Through the wedge structure, the height of the glass is adjusted by the insertion depth. After adjustment, the nuts are tightened to prevent the pad body 4 from slipping. After the mixed adhesive casting pads have cured, the nuts are loosened. Because of the wedge structure, the temporary steel pads can be easily removed and reused.
[0030] Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A temporary glass spacer system for a glass curtain wall system, comprising a steel column body (2), characterized in that: A connecting steel plate (1) is connected to the outside of the steel column body (2). A connecting port (13) is opened in the middle of one side of the connecting steel plate (1). A pad body (4) is slidably connected inside the connecting port (13). Multi-layer laminated glass (5) is fixedly installed at the top of the steel column body (2). A fixed base (8) is fixedly installed at the bottom of the steel column body (2). The pad body (4) includes a wedge block (41) and a connecting plate (42). One side of the wedge block (41) is fixedly connected to the middle of one side of the connecting plate (42). Threaded holes (43) are opened at both ends of one side of the connecting plate (42).
2. A temporary glass spacer system for a glass curtain wall system according to claim 1, characterized in that: The connecting steel plate (1) has adjusting nuts (3) threadedly connected to the middle of both ends of its two sides. The connecting steel plate (1) is fixedly connected to the pad body (4) through the adjusting nuts (3).
3. A temporary glass spacer system for a glass curtain wall system according to claim 1, characterized in that: The surface of the connecting steel plate (1) is threaded with assembly screws (14), and the connecting steel plate (1) is fixedly connected to the steel column body (2) by the assembly screws (14).
4. A temporary glass spacer system for a glass curtain wall system according to claim 1, characterized in that: A sealing gasket (6) is fitted at the connection between the connecting steel plate (1) and the steel column body (2).
5. A temporary glass spacer system for a glass curtain wall system according to claim 1, characterized in that: Both sides of the top of the fixed base (8) are threaded with height screws (12), and the bottom ends of the two height screws (12) are rotatably connected with ground piles (9).
6. A temporary glass spacer system for a glass curtain wall system according to claim 5, characterized in that: The top ends of the two height screws (12) are threaded with locking nuts (11), and the connection between the two height screws (12) and the two locking nuts (11) is fitted with a pad (10).
7. A temporary glass spacer system for a glass curtain wall system according to claim 1, characterized in that: The top of both sides of the connecting steel plate (1) is provided with glue injection ports (7).