Pipe pile foundation pedestrian path
By setting blind holes and grooves in the connection layer on the foundation of pipe piles to fix the guardrail posts, and by adopting segmented prefabricated cap beams and connecting beams, the problems of unstable installation and high construction difficulty of guardrail posts were solved, and the stability and construction efficiency were improved.
Patent Information
- Application Number
- CN202520118531.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-19
- Publication Date
- 2025-12-23
- Estimated Expiration
- 2035-01-19
AI Technical Summary
The existing walkway foundation structure has unstable guardrail posts, making construction difficult and inefficient.
The structure adopts a pipe pile foundation, with blind holes pre-drilled at the top of the cap beam and slots set at the walkway slab. After the guardrail posts are inserted into the slots and blind holes, they are fixed by the connecting layer. The cap beam is installed in sections and adopts a prefabricated structure. Connecting beams and leveling layers are set to improve stability.
It improves the installation stability and firmness of guardrail posts, simplifies the construction process, and increases construction efficiency and structural stability.
Smart Images

Figure CN223706168U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of pedestrian walkway technology, and in particular to a pipe pile foundation pedestrian walkway. Background Technology
[0002] Waterfront walkways are typically located on riverbanks, lakeshores, or mudflats. Traditionally, these walkways often used bored piles or concrete piers as foundations, with cast-in-place concrete beams supporting the walkways, topped with wooden planks or precast concrete slabs. During project implementation, several drawbacks were discovered. For example, the guardrail posts were directly installed onto the wooden planks or precast concrete slabs on the beams. If wooden planks were used, the posts were screwed into the planks, causing the posts to wobble and resulting in poor stability. If precast concrete slabs were used, the expansion bolts were installed onto the slabs, but since the posts were located at the edges of the slabs, there was a risk of cracking at the edges, further contributing to insecure installation.
[0003] In addition, the existing construction method uses cast-in-place concrete for the support beams, which presents problems such as high construction difficulty and complex procedures, resulting in low construction efficiency. Utility Model Content
[0004] The purpose of this utility model is to provide a pedestrian walkway based on pipe pile foundation, which at least solves the problem of unstable installation of guardrail posts.
[0005] To achieve the above objectives, this utility model provides a pipe pile foundation pedestrian walkway, including pipe piles arranged in two rows at intervals. Each row of pipe piles has a capping beam installed on its top, and walkway slabs are installed on the top of the capping beams on both sides. Guardrails are installed on one or both sides of the walkway slabs in the width direction. Blind holes are reserved at intervals along the length direction on the top of the capping beams. The walkway slabs have slots corresponding to the blind holes. The guardrail posts are inserted into the slots and blind holes and then fixed by a connecting layer.
[0006] The capping beam is installed in segments on top of the pipe pile.
[0007] The two ends of the crown beam are respectively erected on the top of the adjacent pipe piles. The two crown beams on the top of the pipe piles are connected by a post-cast section. The bottom of the post-cast section is fixedly provided with a first connector, which is inserted into the central hole at the top of the pipe pile.
[0008] A stop block is installed in the central hole at the top of the pipe pile, and the first connector is located on the upper side of the stop block. Concrete is poured into the central hole on the upper side of the stop block.
[0009] The top of the two rows of pipe piles is also equipped with a connecting beam, with both ends of the connecting beam erected on top of the pipe piles and connected to the post-cast section.
[0010] The top of the crown beam is provided with a leveling layer.
[0011] The top of the crown beam and the tie beam is provided with a leveling layer.
[0012] The lower side of the walkway plate is fixedly provided with a plurality of second connecting pieces, which are located outside the crown beam and connected with the crown beam through fasteners.
[0013] Compared with the prior art, the utility model has the following technical effects:
[0014] 1. The utility model discloses a blind hole is reserved on the top of the crown beam along the length direction, and a notch is arranged on the walkway plate at the position corresponding to the blind hole, so that the column of the protective fence is inserted into the notch and the blind hole, and then is fixed through the connecting layer, the connecting layer can adopt micro-expansion concrete or dolomite glue, so that the stability and firmness of the column of the protective fence are improved.
[0015] 2. The crown beam of the utility model is installed on the top of the pipe pile in sections, adopts the assembled structure, reduces the construction difficulty, simplifies the procedure and improves the construction efficiency.
[0016] 3. The top of the two rows of pipe piles is also provided with the tie beam, so that the stability of the structure is improved.
[0017] 4. The second connecting piece is arranged, so that the walkway plate can be prevented from sliding. DRAWINGS
[0018] In order to more clearly illustrate the technical scheme in the embodiment or the prior art of the present application, the drawings needed to be used in the embodiment or the prior art description will be briefly introduced.
[0019] Figure 1 It is a front view structural schematic diagram of the utility model.
[0020] Figure 2 It is a front view structural schematic diagram of the utility model. Figure 1 It is a sectional view structural schematic diagram of A-A.
[0021] Figure 3 It is a front view structural schematic diagram of the utility model.
[0022] Figure 4 It is a front view structural schematic diagram of the utility model. Figure 2 It is an enlarged structural schematic diagram of B.
[0023] Figure 5 It is a structural schematic diagram of the crown beam installed in sections of the utility model.
[0024] Figure 6 It is a structural schematic diagram of the post-pouring section and the pipe pile of the utility model.
[0025] Figure 7 It is the main view structural schematic drawing of walkway board of the utility model.
[0026] Figure 8 It is Figure 7 It is the K direction structural schematic drawing of walkway board.
[0027] Reference signs:
[0028] Pipe pile 10, center hole 11, stop block 12, crown beam 20, blind hole 21, connecting layer 211, connecting beam 30, walkway board 40, slot 41, second connecting piece 42, fastener 43, guardrail 50, stand column 51, post-cast section 60, first connecting piece 62, leveling layer 70. DETAILED DESCRIPTION
[0029] The embodiments of the utility model are described in detail below, examples of the embodiments are shown in the drawings, the embodiments described below by referring to the drawings are exemplary, and are intended to explain the utility model, and cannot be understood as the limitation of the utility model.
[0030] Embodiment 1:
[0031] Please see Figures 1-8 A pipe pile foundation pedestrian walkway, including pipe pile 10, the pipe pile 10 is correspondingly arranged in two rows at intervals, the top of each pipe pile 10 in each row is equipped with crown beam 20, the top of the crown beam 20 on both sides is equipped with walkway board 40, the walkway board 40 is equipped with guardrail 50 on one side or both sides in width direction, the top of crown beam 20 is reserved with blind hole 21 at intervals along the length direction, the walkway board 40 is correspondingly provided with slot 41 at the position corresponding to blind hole 21, and the stand column 51 of guardrail 50 is inserted into slot 41 and blind hole 21 and then fixed by connecting layer 211.
[0032] In the embodiment, by reserving blind hole 21 at intervals along the length direction on the top of crown beam 20, and correspondingly providing slot 41 on the walkway board 40 at the position corresponding to blind hole 21, when installing, see Figure 4 The stand column 51 of guardrail 50 is inserted into slot 41 and blind hole 21 and then fixed by connecting layer 211, and connecting layer 211 can adopt micro-expansion concrete or dolomite glue, so that the stability and firmness of the installation of guardrail stand column are improved.
[0033] In order to facilitate the leveling of walkway board 40, the top of crown beam 20 is provided with leveling layer 70.
[0034] In the embodiment, slot 41 can be a circular or square through hole, or a semicircular or rectangular recess gap.
[0035] Embodiment 2:
[0036] In order to facilitate the construction of the crown beam 20, the crown beam 20 is installed in sections on the top of the pipe pile 10. The use of the assembled structure reduces the construction difficulty, simplifies the process, and improves the construction efficiency.
[0037] In the embodiment, referring to Figure 5 , the two ends of the crown beam 20 are respectively arranged on the top of the adjacent pipe piles 10, and the two crown beams 20 on the top of the pipe piles 10 are connected through the post-cast section 60. The bottom of the post-cast section 60 is fixedly provided with a first connecting piece 62, and the first connecting piece 62 is inserted into the center hole 11 on the top of the pipe pile 10. By arranging the first connecting piece 62, the stability of the connection between the post-cast section 60 and the pipe pile 10 is improved.
[0038] In the embodiment, the segmented crown beam 20 is a prefabricated reinforced concrete structure, the reinforcement at the end of the two crown beams 20 is extended, and then the concrete is poured through the mold to form the post-cast section 60.
[0039] Further, referring to Figure 6 , the center hole on the top of the pipe pile 10 is provided with a stopper 12, the first connecting piece 62 is located on the upper side of the stopper 12, and the center hole is filled with concrete on the upper side of the stopper 12, further improving the stability of the connection between the post-cast section 60 and the pipe pile 10.
[0040] The stopper 12 can be an elastic rubber block or a wooden block, which is clamped in the center hole 11.
[0041] During installation, the first connecting piece 62 is first inserted into the center hole of the pipe pile 10, and then the post-cast section 60 is formed by pouring concrete.
[0042] In the embodiment, the first connecting piece 62 is a steel reinforcement cage.
[0043] Embodiment 3:
[0044] Based on the embodiment 2, referring to Figure 2 , 4 , the top of the two rows of pipe piles 10 is further provided with a tie beam 30, the two ends of the tie beam 30 are respectively arranged on the top of the pipe piles 10, and the tie beam 30 is connected with the post-cast section 60. The tie beam 30 is arranged to improve the stability of the structure.
[0045] Specifically, the tie beam 30 is a prefabricated reinforced concrete structure, the reinforcement at the end of the tie beam 30 is extended, and then the post-cast section 60 is formed by pouring concrete through the mold, so as to connect and fix the crown beam 20 and the tie beam 30 together.
[0046] Further, the top of the crown beam 20 and the tie beam 30 is provided with a leveling layer 70, which facilitates the leveling of the walkway plate 40. In the embodiment, the leveling layer 70 is a concrete mortar.
[0047] Embodiment 4:
[0048] On the basis of Embodiment 1 or 2 or 3, referring to Figure 4 , 7 , 8, the lower side of the walkway plate 40 is fixedly provided with a plurality of second connecting pieces 42, the second connecting pieces 42 are located at the outer side of the crown beam 20, and the second connecting pieces 42 are connected with the crown beam 20 through fasteners 43. By arranging the second connecting pieces 42, the walkway plate 40 can be prevented from sliding.
[0049] In this embodiment, the second connecting pieces 42 are metal plates with longitudinal long holes, and the end of the second connecting pieces 42 connected with the walkway plate 40 is connected with the steel bars inside the walkway plate 40, that is, the second connecting pieces 42 are pre-buried on the walkway plate 40. During installation, referring to Figure 3 , the fasteners 43 are expansion screws, the fasteners 43 are fixedly installed at the outer side of the crown beam 20 and are connected and fixed with the long holes of the second connecting pieces 42.
[0050] The installation steps of the utility model are as follows:
[0051] Firstly, two rows of pipe piles 10 are punched according to the design path of the drawings.
[0052] Then, the stoppers 12 are installed on the pipe piles 10, and then the segmented crown beam 20 and the connecting beam 30 are hoisted to the top of the pipe piles 10, as shown in Figure 2 , 3 .
[0053] Then, the mold is installed at the post-pouring section 60, the post-pouring belt 60 is poured, and the crown beam 20 and the connecting beam 30 are connected and fixed together.
[0054] Then, the walkway plate 40 is installed on the crown beam 20 and the connecting beam 30. After one end of the walkway plate 40 is installed, the guardrail 50 is installed. When the guardrail 50 is installed, the upright column 51 of the guardrail 50 is inserted into the slot 41 and the blind hole 21, and then the micro-expansion concrete or the marble glue is poured into the slot 41 and the blind hole 21 to fix the upright column 51 and the blind hole 21, and then the remaining parts of the guardrail 50 are installed.
Claims
1. A pipe pile foundation footpath, characterized in that: The utility model provides a kind of pipe pile (10), the pipe pile (10) is arranged in two rows of interval corresponding, the top of each row of pipe pile (10) is equipped with crown beam (20), the top of both sides crown beam (20) is equipped with walkway board (40), walkway board (40) width direction side or both sides are equipped with guardrail (50), crown beam (20) top is reserved with blind hole (21) along length direction interval, walkway board (40) is equipped with slot (41) in the position corresponding blind hole (21), after the column (51) of guardrail (50) is inserted into slot (41) and blind hole (21), it is installed and fixed by connecting layer (211).
2. A pipe pile foundation footpath according to claim 1, characterized in that: The crown beam (20) is segmented and installed on the top of the pipe pile (10).
3. A pipe pile foundation footpath according to claim 2, characterised in that: The two ends of the crown beam (20) are respectively arranged on the top of the adjacent pipe pile (10), the two crown beams (20) on the top of the pipe pile (10) are connected by the post-cast segment (60), the bottom of the post-cast segment (60) is fixedly provided with the first connecting piece (62), and the first connecting piece (62) is inserted into the center hole (11) on the top of the pipe pile (10).
4. A pipe pile foundation footpath according to claim 3, characterized in that: The center hole on the top of the pipe pile (10) is provided with a stop block (12), the first connecting piece (62) is located on the upper side of the stop block (12), and the center hole is filled with concrete on the upper side of the stop block (12).
5. A pipe pile foundation footpath according to claim 3 or 4, characterised in that: The top of the two rows of pipe piles (10) is also provided with a tie beam (30), the two ends of the tie beam (30) are respectively arranged on the top of the pipe pile (10), and the tie beam (30) is connected with the post-cast segment (60).
6. A pipe pile foundation footpath according to any one of claims 1 to 4, characterized in that: The top of the crown beam (20) is provided with a leveling layer (70).
7. A pipe pile foundation footpath according to claim 5, characterized in that: The top of the crown beam (20) and the tie beam (30) is provided with a leveling layer (70).
8. A pipe pile foundation pedestrian walkway according to claim 1, characterized in that: The lower side of the walkway board (40) is fixedly provided with a plurality of second connecting pieces (42), the second connecting pieces (42) are located on the outer side of the crown beam (20), and the second connecting pieces (42) are connected with the crown beam (20) by fasteners (43).