Construction frame for building decoration
By designing a flexible and adjustable conveying mechanism and a universal wheel locking system on the construction scaffold, the problem of workers frequently bending over to pick up materials was solved, improving construction efficiency and safety, and ensuring timely supply of paint.
Patent Information
- Application Number
- CN202520124160.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-20
- Publication Date
- 2025-12-23
- Estimated Expiration
- 2035-01-20
AI Technical Summary
The existing scaffolding requires workers to frequently bend over to pick up materials, causing back discomfort, affecting construction efficiency and safety, and posing a risk of falls.
A construction frame with a flexible adjustable conveying mechanism was designed. The automatic conveying of paint is achieved by a motor-driven transmission system and an eccentric rod driving the connecting rod to slide. It is also equipped with casters and a locking mechanism for easy operation by workers.
Reduce workers' material handling time, decrease physical fatigue, improve construction efficiency and safety, reduce the risk of falls, optimize workflow, and ensure timely supply of coatings.
Smart Images

Figure CN223707059U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to building construction technical field, concretely is a construction frame for building decoration. BACKGROUND
[0002] Construction frame usually refers to the frame for construction, also called scaffold, is generally built by steel pipe, in the field of building construction, some outer wall surfaces are painted, and the construction frame for supporting is used to promote the scaffold, the scaffold is generally built by steel pipe, so it is stable during use, the user stands on the surface of the scaffold, and then the cement barrel and putty barrel are delivered to the scaffold through the delivery of the person below, so that the user can paint the wall surface.
[0003] The existing construction frame places the putty barrel on the surface of the standing plate, the user needs to bend down repeatedly when digging the putty, and long time of such labor can cause waist discomfort and serious lumbar strain, the action of bending down to take the material is complicated, can cause the working speed to slow down, affects the overall construction efficiency, the inconvenient material taking mode can reduce the working comfort of the user, can cause the attention to be distracted, and thus affects the construction quality, the user can be distracted when bending down to take the material, increases the risk of falling or collision, and affects the safety of the construction site.
[0004] Therefore, the construction frame for building decoration is provided. UTILITY MODEL CONTENTS
[0005] The utility model aims at providing a construction frame for building decoration to solve the problems in the background art.
[0006] To achieve the above object, the utility model provides the following technical scheme: a construction frame for building decoration, including frame body, the top of frame body is connected with slide sleeve seat, the bottom of slide sleeve seat is fixedly connected with motor, the drive end of motor is fixedly connected with transmission wheel, the top of transmission wheel is fixedly connected with eccentric rod, the outer wall of eccentric rod is equipped with arc sleeve, the bottom of slide sleeve seat is rotatably connected with belt pulley, the transmission wheel and belt pulley are connected through elastic belt, the both sides of arc sleeve are fixedly connected with connecting rod, the middle part of slide sleeve seat is fixedly connected with guide seat, the outer wall of both sides connecting rod is rotatably connected in the inner wall of guide seat, and the end of both sides connecting rod away from arc sleeve is fixedly connected with slide sleeve seat.
[0007] Preferably, the top of the belt pulley is fixedly connected with a placing disc, and a plurality of placing cavities are uniformly formed in the top of the placing disc.
[0008] Preferably, a plurality of connecting springs are fixedly connected to the inner wall of the placing cavity, and the proximal end of the connecting spring is fixedly connected with a clamping pad.
[0009] Preferably, the lower middle part of the frame body is fixedly connected with an adapter plate.
[0010] Preferably, the middle part of the fixing nut is threadedly connected with a threaded bolt, and the bottom end of the threaded bolt is fixedly connected with a positioning stud seat.
[0011] Preferably, the bottom corners of the frame body are fixedly connected with universal wheels.
[0012] Compared with the prior art, the present application has the following advantages:
[0013] 1. The conveying mechanism can be flexibly adjusted, and can convey the powder to the working position of the worker, so that the worker can take and place the paint for painting. The conveying mechanism can be automatically adjusted according to the working position of the worker, so as to reduce the time for the worker to take and place the paint, improve the overall construction efficiency, reduce the frequency of bending or walking of the worker, reduce the burden on the waist and back, improve the working comfort, reduce the risk of the worker taking the material at a high place or unstable position, reduce the possibility of falling or injury, improve the construction safety, and the flexible conveying system can be adjusted according to the construction progress and the demand of the worker, optimize the work process, and ensure the timely supply of paint.
[0014] 2. The construction frame is provided with universal wheels, which can be easily adjusted according to the construction position, and can be fixed and locked during use to avoid tilting of the frame body. The frame can be easily moved, and the worker can quickly adjust the position of the frame according to the construction needs, improve the working flexibility, and the construction frame can be adjusted according to different construction environments and needs, optimize the working space, improve the construction comfort, simplify the moving and adjusting process, reduce the dependence on manpower, reduce the labor cost, and improve the construction efficiency. BRIEF DESCRIPTION OF DRAWINGS
[0015] Fig. 1 It is a whole structure schematic diagram of the present application;
[0016] Fig. 2 It is a side view schematic diagram of the present application;
[0017] Fig. 3 It is a whole structure schematic diagram of the present application;
[0018] Fig. 4 It is a whole structure schematic diagram of the present application;
[0019] In the figure:
[0020] 1, frame; 2, sliding sleeve seat; 3, motor; 4, transmission wheel; 5, eccentric rod; 6, arc sleeve; 7, belt pulley; 8, elastic belt; 9, connecting rod; 10, guide seat; 11, placing disc; 12, placing cavity; 13, connecting spring; 14, clamping pad; 15, adapter plate; 16, fixing nut; 17, threaded bolt; 18, positioning pin seat; 19, universal wheel. DETAILED DESCRIPTION
[0021] The technical solutions in the embodiments of the utility model will be clearly and completely described below with reference to the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by those skilled in the art without creative labor fall within the protection scope of the utility model.
[0022] Please refer to Figs. 1 to 4 An embodiment provided by the utility model: a construction frame for building decoration, comprising a frame body 1, the top of the frame body 1 is slidably connected with a sliding sleeve seat 2, the bottom of the sliding sleeve seat 2 is fixedly connected with a motor 3, the driving end of the motor 3 is fixedly connected with a transmission wheel 4, the top of the transmission wheel 4 is fixedly connected with an eccentric rod 5, the outer wall of the eccentric rod 5 is sleeved with an arc sleeve 6, the bottom of the sliding sleeve seat 2 is rotatably connected with a belt pulley 7, the transmission wheel 4 and the belt pulley 7 are connected through an elastic belt 8, the middle of the two sides of the arc sleeve 6 is fixedly connected with a connecting rod 9, the middle of the sliding sleeve seat 2 is fixedly connected with a guide seat 10, the outer wall of the two side connecting rods 9 is slidably connected with the inner wall of the guide seat 10, the end of the two side connecting rods 9 away from the arc sleeve 6 is fixedly connected with the sliding sleeve seat 2;
[0023] Among them: the sliding sleeve seat 2 is matched between the top outer rod of the frame body 1, the inner diameter of the arc sleeve 6 is same with the size of the eccentric rod 5;
[0024] Better: the motor 3 drives the transmission wheel 4 to rotate, in turn drives the eccentric rod 5 to rotate, and under the cooperation of the arc sleeve 6, the two side connecting rods 9 can slide in the inner wall of the guide seat 10, in turn can push the sliding sleeve seat 2 to slide on the top of the frame body 1, and at the same time, under the cooperation of the elastic belt 8, the belt pulley 7 can rotate synchronously.
[0025] The top of the belt pulley 7 is fixedly connected with a placing disc 11, a plurality of placing cavities 12 are uniformly arranged on the top of the placing disc 11, a plurality of connecting springs 13 are fixedly connected to the inner wall of the placing cavity 12, a clamping pad 14 is fixedly connected to the end of the connecting spring 13, an adapter plate 15 is fixedly connected to the middle of the lower side of the frame body 1, a fixed nut 16 is fixedly connected to the top of the adapter plate 15, a threaded bolt 17 is threadedly connected to the middle of the fixed nut 16, a positioning stud base 18 is fixedly connected to the bottom end of the threaded bolt 17, and a universal wheel 19 is fixedly connected to the bottom of the frame body 1;
[0026] The material of the clamping pad 14 is rubber, and the material of the positioning stud base 18 is heavy metal for counterweight.
[0027] More preferably, as the belt pulley 7 rotates, the placing disc 11 rotates, the tools used by the worker during the painting operation are placed inside the placing cavity 12, and the clamping pad 14 is pressed to deform the connecting spring 13, thereby firmly holding and fixing the material barrel, and as the placing disc 11 rotates, the material can be rotated and transmitted, which is more convenient. During the use of the frame body 1, the threaded bolt 17 is rotated, and under the cooperation of the fixed nut 16, the threaded bolt 17 rotates along the inner wall of the adapter plate 15 and drives the positioning stud base 18 to move downward until it is locked to the ground, thereby ensuring the stability of the frame body 1 during use.
[0028] The working principle of the above implementation is as follows:
[0029] The working steps are as follows:
[0030] First, during the use of the frame body 1, the threaded bolt 17 is rotated, and under the cooperation of the fixed nut 16, the threaded bolt 17 rotates along the inner wall of the adapter plate 15 and drives the positioning stud base 18 to move downward until it is locked to the ground, thereby ensuring the stability of the frame body 1 during use. The motor 3 drives the transmission wheel 4 to rotate, thereby driving the eccentric rod 5 to rotate, and under the cooperation of the arc-shaped sleeve 6, the two connecting rods 9 can slide in the inner wall of the guide seat 10, thereby driving the sliding sleeve seat 2 to slide on the top of the frame body 1.
[0031] And at the same time in the cooperation of elastic belt 8 make the pulley 7 can synchronous rotation, make the placement disc 11 follow the rotation, the tool used in the worker painting operation process is placed in the inside of the placement cavity 12, and through the clamping pad 14 extrusion connecting spring 13 generates deformation, in turn can firmly hold the material bucket, and along with the rotation of the placement disc 11, namely, the material can be rotated and delivered, more convenient, flexible adjustment of the conveying mechanism can be automatically adjusted according to the working position of the worker, reduce the time of worker to take and put paint, improve the overall construction efficiency, by reducing the number of workers bending or walking, reduce physical fatigue, especially the burden of waist and back, improve the work comfort, the conveying mechanism can reduce the risk of workers taking materials in high place or unstable position, reduce the possibility of falling or injury, improve construction safety, flexible conveying system can be adjusted according to the construction progress and worker demand, optimize the work process, ensure the timely supply of paint.
[0032] It should be noted that in this text, such as the first and second relationship terms are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between the entities or operations. Moreover, the term "includes", "contains" or any other variant thereof is intended to cover non-exclusive inclusion, so that the process, method, article or equipment including a series of elements not only includes those elements, but also includes other elements not explicitly listed or inherent to such process, method, article or equipment. Without more limitations, the element defined by the statement "includes a" does not exclude the presence of another identical element in the process, method, article or equipment including the element.
[0033] Although the embodiments of the present application have been shown and described, it is understood that those skilled in the art can make various changes, modifications, replacements and variations to the embodiments without departing from the principles and spirits of the present application, and the scope of the present application is defined by the appended claims and their equivalents.
Claims
1. A construction frame for use in architectural finishing, characterized by: The utility model relates to a kind of frame bodies (1), the top of the frame body (1) is slidably connected with slide sleeve seat (2), the bottom of the slide sleeve seat (2) is fixedly connected with motor (3), the drive end of the motor (3) is fixedly connected with transmission wheel (4), the top of the transmission wheel (4) is fixedly connected with eccentric rod (5), eccentric rod (5) is sleeved with arc cover (6) on outer wall, the bottom of the slide sleeve seat (2) is rotatably connected with belt pulley (7), the transmission wheel (4) is connected with belt pulley (7) by elastic belt (8), the two sides of arc cover (6) middle part are fixedly connected with connecting rod (9), the middle part of the slide sleeve seat (2) is fixedly connected with guide seat (10), the outer wall of two side connecting rod (9) is slidably connected in the inner wall of guide seat (10), the end of two side connecting rod (9) away from arc cover (6) is fixedly connected with slide sleeve seat (2).
2. The construction frame for architectural finishing according to claim 1, characterized in that: The top of the belt pulley (7) is fixedly connected with the placing disc (11), and a plurality of placing cavities (12) are uniformly formed in the top of the placing disc (11).
3. The construction frame for architectural finishing according to claim 2, wherein: The inner wall of the placing cavity (12) is uniformly fixedly connected with a plurality of connecting springs (13), and the end of the connecting spring (13) is fixedly connected with the clamping pad (14).
4. The construction frame for architectural finishing according to claim 3, wherein: The lower middle part of the frame body (1) is fixedly connected with the link plate (15), and the top of the link plate (15) is fixedly connected with the fixed nut (16).
5. The construction frame for architectural finishing according to claim 4, wherein: The middle part of the fixed nut (16) is screw-connected with the threaded bolt (17), and the bottom end of the threaded bolt (17) is fixedly connected with the positioning nail seat (18).
6. A construction frame for architectural finishing according to claim 5, characterized in that: The bottom of the frame body (1) is fixedly connected with the universal wheel (19).