Complete assembly type construction device for pre-closed post-cast strip

By designing a pre-sealed post-pouring strip complete set of construction equipment, mechanized construction of post-pouring strips has been realized, solving the problems of high cost and low efficiency caused by manual operation in the existing technology, and improving construction quality and safety.

CN224063939UActive Publication Date: 2026-03-31ZHEJIANG JIACHENG BUILDING
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-03-11
Publication Date
2026-03-31

AI Technical Summary

Technical Problem

In existing prefabricated building construction, the post-pouring strip process relies on manual operation, resulting in high labor costs, slow construction progress, difficulty in ensuring quality, and messy sites that are inconvenient to clean up.

Method used

Design a pre-sealed post-cast strip complete set of construction equipment, including vehicle body, lifting device, material storage device, material injection device and vibration device, to achieve efficient construction of post-cast strip through mechanized transportation and automated material injection and vibration.

Benefits of technology

It reduced labor intensity, improved construction quality and efficiency, reduced site clutter, and enhanced construction safety and progress.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224063939U_ABST
    Figure CN224063939U_ABST
Patent Text Reader

Abstract

The utility model discloses a pre-closed post-cast strip complete assembly type construction device which comprises a device body, a vehicle body, wheels and a cab are arranged on the device body, lifting devices are arranged at the upper end of the vehicle body, and a material storage device is arranged between the lifting devices. A feeding device and a discharging device are arranged at the two side ends of the material storage device respectively, the upper end of the material storage device and the lifting device are connected and provided with a platform device, a machine box and a control device are arranged at the upper end of the platform device, a first driving arm and a second driving arm are arranged at the upper end of the machine box, and the control device is arranged at the lower end of the machine box. The first driving arm and the second driving arm are connected with a material injection device and a vibrating device respectively. The device is simple and reasonable in structure, convenient to use, flexible to operate, diversified in function, capable of reducing labor intensity, high in practicability and wide in application range, greatly improves construction quality, accelerates project progress and improves working efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to a pre-sealed post-pouring strip complete set of construction equipment, belonging to the technical field of building construction equipment. Background Technology

[0002] With the development of modern industrial technology, houses can be built in batches like machine production. Prefabricated house components are transported to the construction site and assembled. Prefabricated buildings are assembled on-site using prefabricated components. This type of building is fast to build, less affected by weather conditions, saves labor and can improve building quality.

[0003] Currently, in the construction of prefabricated buildings, after the prefabricated components are assembled, a post-pouring process is usually required to connect the gaps between the prefabricated components. According to the design or construction specifications, temporary construction joints are left at corresponding positions in the foundation slab, walls, and beams, temporarily dividing the structure into several parts. After the internal shrinkage of the components, the concrete of the construction joint is poured after a certain period of time to connect the structure into a whole. Generally, construction and pouring are carried out manually, including the transportation, pouring, and vibration of raw materials. This has problems such as high labor costs, tedious work, impact on construction progress, inability to guarantee construction quality, messy site, unfavorable construction safety, and troublesome subsequent cleanup.

[0004] Therefore, we propose a pre-sealed post-pouring strip complete set of construction equipment. Summary of the Invention

[0005] (a) Technical problems to be solved

[0006] To address the aforementioned problems, this utility model provides a pre-sealed post-cast strip complete set construction device that features a simple and reasonable structure, convenient use, flexible operation, diverse functions, reduced labor intensity, strong practicality, wide applicability, and greatly improves the construction quality of the post-cast strip location, accelerates project progress, and increases work efficiency.

[0007] (II) Technical Solution

[0008] This utility model discloses a pre-sealed post-pouring strip complete set of construction equipment, comprising: a device body, a vehicle body, wheels and a cab on the device body, a lifting device at the upper end of the vehicle body, a material storage device between the lifting devices, a feeding device and a discharging device at both ends of the material storage device, a platform device connected and installed at the upper end of the material storage device and the lifting device, a housing and a control device at the upper end of the platform device, a drive arm one and a drive arm two at the upper end of the housing, and a material injection device and a vibration device respectively connected to the drive arm one and the drive arm two.

[0009] Furthermore, the lifting device is equipped with a scissor bar slide, multiple sets of scissor bars, and multiple hydraulic rods.

[0010] Furthermore, the storage device is equipped with a storage box and a cover. The storage box has an internal stirring shaft and stirring blades, and the side of the storage box is also equipped with a viewing window, a foot pedal and a cleaning outlet.

[0011] Furthermore, the feeding device and the discharging device are respectively equipped with a feeding pump and a discharging pump.

[0012] Furthermore, the platform device is equipped with a support platform, three fixed guardrails, and movable guardrails.

[0013] Furthermore, the control device is equipped with a control panel, a control lever one, and a control lever two.

[0014] Furthermore, both the first and second drive arms are provided with multiple arm sections, which are connected by movable joints, and both the first and second drive arms are fixedly installed to the chassis via connecting seats.

[0015] Furthermore, the injection device is equipped with an injection connection pipe and a nozzle. One end of the injection connection pipe is connected to the upper outlet of the discharge device, and the other end is connected to the nozzle, which is fixedly connected to the end of the drive arm.

[0016] Furthermore, the vibrating device is equipped with a vibrating rod, a vibrating rod connecting pipe, a guide roller, and a take-up device, with the vibrating rod fixedly connected to the end of the second drive arm.

[0017] (III) Beneficial Effects

[0018] Compared with the prior art, this utility model has the following beneficial effects: the utility model has a simple and reasonable structure, is easy to use, flexible in operation, and has multiple functions. It reduces labor intensity, is highly practical, has a wide range of applications, greatly improves the construction quality of the post-pouring strip, speeds up the project progress, and improves work efficiency. Attached Figure Description

[0019] To more clearly illustrate the technical solutions in the embodiments of this utility model or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0020] Figure 1 This is a schematic diagram of the structure of this utility model.

[0021] Figure 2 This is a partial structural schematic diagram of the present invention.

[0022] Figure 3 This is a partial side view of the structure of this utility model.

[0023] 1-Equipment body; 2-Vehicle body; 3-Wheels; 4-Cockpit; 5-Lifting device; 6-Storage device; 7-Feeding device; 8-Discharge device; 9-Platform device; 10-Chassis; 11-Control device; 12-Drive arm one; 13-Drive arm two; 14-Injection device; 15-Vibration device; 5-1-Scissor bar slide; 5-2-Scissor bar; 5-3-Hydraulic rod; 6-1-Storage box; 6-2-Cover; 6-3-Viewing window; 6-4-Step pedal; 6 -5-Cleaning outlet; 7-1-Feed pump; 8-1-Discharge pump; 9-1-Bearing platform; 9-2-Fixed guardrail; 9-3-Movable guardrail; 11-1-Control panel; 11-2-Control lever one; 11-3-Control lever two; 12-1-Arm; 12-2-Movable joint; 12-3-Connecting seat; 14-1-Injection connecting pipe; 14-2-Nozzle; 15-1-Vibrator; 15-2-Vibrator connecting pipe; 15-3-Guide roller; 15-4-Retractor. Detailed Implementation

[0024] This section will describe in detail the specific embodiments of the present utility model. The preferred embodiments of the present utility model are shown in the accompanying drawings. The purpose of the drawings is to supplement the textual description with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the present utility model, but they should not be construed as limiting the scope of protection of the present utility model.

[0025] like Figure 1 The present invention discloses a pre-sealed post-pouring strip complete set of construction equipment, comprising: a device body 1, a vehicle body 2, wheels 3 and a cab 4 on the device body 1, a lifting device 5 on the upper end of the vehicle body 2, a material storage device 6 between the lifting devices 5, a feeding device 7 and a discharging device 8 on both sides of the material storage device 6, a platform device 9 connected to the lifting device 5 on the upper end of the material storage device 6, a housing 10 and a control device 11 on the upper end of the platform device 9, a drive arm 12 and a drive arm 2 13 on the upper end of the housing 10, and a material injection device 14 and a vibration device 15 connected to the drive arm 12 and the drive arm 2 13 respectively.

[0026] The lifting device 5 is equipped with a scissor bar slide 5-1, multiple sets of scissor bars 5-2 and multiple hydraulic rods 5-3.

[0027] The storage device 6 is provided with a storage box 6-1 and a cover 6-2. The storage box 6-1 is provided with a stirring shaft and stirring blades at the inner end. The storage box is also provided with a viewing window 6-3, a foot pedal 6-4 and a cleaning outlet 6-5 on the side.

[0028] The feeding device 7 and the discharging device 8 are respectively equipped with a feeding pump 7-1 and a discharging pump 8-1;

[0029] The platform device 9 is equipped with a support platform 9-1, three fixed guardrails 9-2, and movable guardrails 9-3;

[0030] The control device 11 is equipped with a control panel 11-1, a control lever 11-2, and a control lever 11-3;

[0031] Both the first drive arm 12 and the second drive arm 13 are provided with multiple arm sections 12-1, which are connected by movable joints 12-2. Both the first drive arm 12 and the second drive arm 13 are fixedly installed to the chassis 10 through connecting seats 12-3.

[0032] The injection device 14 is provided with an injection connection pipe 14-1 and a nozzle 14-2. One end of the injection connection pipe 14-1 is connected to the upper outlet of the discharge device 8, and the other end is connected to the nozzle 14-2. The nozzle 14-2 is fixedly connected to the end of the drive arm 12.

[0033] The vibrating device 15 is equipped with a vibrating rod 15-1, a vibrating rod connecting pipe 15-2, a guide roller 15-3, and a take-up device 15-4. The vibrating rod 15-1 is fixedly connected to the end of the drive arm 13.

[0034] This utility model has a simple and reasonable structure, is easy to use, flexible in operation, and has multiple functions. It reduces labor intensity, is highly practical, and has a wide range of applications. It greatly improves the construction quality of the post-pouring strip, speeds up the project progress, and improves work efficiency.

[0035] The working principle of this utility model is as follows: This utility model discloses a pre-sealed post-pouring strip complete assembly construction device, comprising a device body 1, a vehicle body 2, wheels 3, a cab 4, a lifting device 5, a material storage device 6, a feeding device 7, a discharging device 8, a platform device 9, a chassis 10, a control device 11, a first drive arm 12, a second drive arm 13, a material injection device 14, and a vibrating device 15. The main body 1 is a small vehicle, including the vehicle body 2, wheels 3, and cab 4, which is easy to move, convenient to transport, and saves time and effort. The lifting device 5 and the material storage device 6 are located at the upper end of the vehicle body 2. The lifting device 5 is located on both sides of the material storage device 6. The platform device 9 is fixedly connected to the lifting device 5 and is located at the upper end of the vehicle body 2. The material storage device 6 has a foot pedal 6-4 on its side. The device is connected to the vehicle body 2, the foot pedal 6-4, and the material storage box 6-1. Workers can climb onto platform device 9, which includes a support platform 9-1, three fixed guardrails 9-2, and movable guardrails 9-3. Movable guardrails 9-3 are movable doors. Workers can operate control device 11 on the support platform 9-1. Control device 11 includes control panel 11-1, control lever one 11-2, and control lever two 11-3. Control lever one 11-2 controls the movement of drive arm one 12, and control lever two 11-3 controls the movement of drive arm two 13. In addition, injection device 14 and vibration device 15 are respectively connected and fixed to drive arm one 12 and drive arm two 13. The injection and vibration construction operations of injection device 14 and vibration device 15 are controlled and operated through control panel 11-1, ensuring construction safety. It is a complete set of construction pouring strips for pre-sealed post-pouring strips, with complete pouring strips, good sealing performance, ensuring construction quality, and improving work efficiency.

[0036] The lifting device 5 includes a scissor bar slide 5-1, multiple sets of scissor bars 5-2, and multiple hydraulic rods 5-3. Through scissor-type hydraulic lifting, it adapts to the construction of complete sets of pouring strips at different heights. During the pouring process, the material to be poured is first loaded into the storage tank 6-1 by the feed pump 7-1. The storage tank 6-1 is also equipped with a viewing window 6-3 and a cleaning outlet 6-5. The viewing window 6-3 allows for easy observation of the material level inside the tank, and the cleaning outlet 6-5 allows for direct drainage when cleaning the inside of the tank. The trolley can be driven to the pouring site, and then the nozzle 14- is moved by controlling the drive arm 12. 2. The nozzle 14-2 is replaceable to adapt to different gaps in the pouring strip. The material is sprayed from the nozzle 14-2 to the joint of the pouring strip through the discharge pump 8-1 and the injection connection pipe 14-1. At the same time, the pouring material is vibrated by the vibrator 15-1 to reduce the gaps between the pouring materials and make them tightly connected, resulting in good construction effect. The vibrator 15-1 is connected to the vibrator connection pipe 15-2, the guide roller 15-3 and the retractor 15-4. It is controlled by the drive arm 13. The length of the retractor of the vibrator connection pipe 15-2 is adjustable, which makes the operation flexible, reduces labor costs and saves time and effort.

[0037] This utility model relates to a pre-sealed post-pouring strip complete set of construction equipment. The raw materials are transported by a trolley, which is convenient and fast. During the construction process, the combination of injection and vibration ensures good quality of the pouring strip, providing better safety and practicality for construction. The equipment is flexible in operation, reduces labor, better meets various requirements in the construction process, improves construction efficiency, and speeds up the project progress.

[0038] The embodiments described above are merely preferred embodiments of the present invention and are not intended to limit the concept and scope of the present invention. Various modifications and improvements made to the technical solutions of the present invention by those skilled in the art without departing from the design concept of the present invention should fall within the protection scope of the present invention. The technical content for which protection is sought in the present invention has been fully described in the claims.

Claims

1. A pre-sealing post-cast strip complete assembly construction device, characterized in that: Including the device body (1), the device body (1) is provided with a vehicle body (2), a wheel (3) and a cab (4), the upper end of the vehicle body (2) is provided with a lifting device (5), the lifting device (5) is provided with a storage device (6) between, the storage device (6) is provided with a feeding device (7) and a discharging device (8) on both sides, the upper end of the storage device (6) is connected with the lifting device (5) and provided with a platform device (9), the upper end of the platform device (9) is provided with a machine box (10) and a control device (11), the upper end of the machine box (10) is provided with a driving arm one (12) and a driving arm two (13), the driving arm one (12) and the driving arm two (13) are respectively connected with a feeding device (14) and a vibrating device (15).

2. A pre-enclosed post-cast strip complete assembly type construction device according to claim 1, characterized in that: The lifting device (5) is provided with a scissor lever chute (5-1), a plurality of scissor levers (5-2) and a plurality of hydraulic rods (5-3).

3. A pre-enclosed post-cast strip complete assembly type construction device according to claim 1, characterized in that: The storage device (6) is provided with a storage tank (6-1) and a cover (6-2), the inside of the storage tank (6-1) is provided with a stirring shaft and stirring blades, and the side of the storage tank is also provided with a viewing window (6-3), a stepping plate (6-4) and a cleaning outlet (6-5).

4. The pre-closed post-cast strip complete assembly type construction device according to claim 1, characterized in that: The feeding device (7) and the discharging device (8) are respectively provided with a feeding pump (7-1) and a discharging pump (8-1).

5. The pre-closed post-cast strip complete assembly type construction device according to claim 1, characterized in that: The platform device (9) is provided with a bearing table (9-1), a three-sided fixed guardrail (9-2) and a movable guardrail (9-3).

6. A pre-enclosed post-cast strip complete assembly type construction device according to claim 1, characterized in that: The control device (11) is provided with a control screen (11-1), a control lever one (11-2) and a control lever two (11-3).

7. A pre-enclosed post-cast strip complete assembly type construction device according to claim 1, characterized in that: The driving arm one (12) and the driving arm two (13) are both provided with a plurality of arm rods (12-1), the plurality of arm rods are connected through a movable joint (12-2), and the driving arm one (12) and the driving arm two (13) are both fixedly installed on the machine box (10) through a connecting seat (12-3).

8. The pre-closed post-cast strip complete assembly type construction device according to claim 1, characterized in that: The feeding device (14) is provided with a feeding connecting pipe (14-1) and a spray head (14-2), one end of the feeding connecting pipe (14-1) is connected and installed on the upper outlet of the discharging device (8), the other end is connected and installed with the spray head (14-2), and the spray head (14-2) is fixedly connected to the end of the driving arm one (12).

9. The pre-closed post-cast strip complete assembly type construction device according to claim 1, characterized in that: The vibrating device (15) is provided with a vibrating rod (15-1), a vibrating rod connecting pipe (15-2), a guide roller (15-3) and a retractor (15-4), and the vibrating rod (15-1) is fixedly connected to the end of the driving arm two (13).