Concrete modular public toilet

By combining concrete and PC materials in a modular design, the problems of easy deformation and corrosion of light steel structures and complex construction of precast concrete structures are solved, enabling the rapid and low-cost construction of outdoor public toilets with good stability and significant pipe protection.

CN224064002UActive Publication Date: 2026-03-31CHINA SCI & TECH (BEIJING) ENG TECH RES INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-04-27
Publication Date
2026-03-31

AI Technical Summary

Technical Problem

The existing light steel structure of outdoor public toilets is prone to deformation and corrosion after long-term use, resulting in high maintenance costs. On the other hand, the construction process of precast concrete structures is complex, time-consuming, and costly, requiring a large number of workers and equipment.

Method used

The modular design, which combines concrete and PC materials, includes a base box, walls, and roof. The base box consists of a concrete floor panel and side panels, while the walls and roof are made of PC material. They are connected by connecting steel bars and socket sleeves. The components are pre-assembled in the factory and quickly assembled on site, with pipes pre-embedded in the base box.

Benefits of technology

It enables rapid and low-cost on-site setup, has good structural stability, provides excellent pipeline protection, reduces hollowness, and lowers maintenance costs and construction complexity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224064002U_ABST
    Figure CN224064002U_ABST
Patent Text Reader

Abstract

The utility model discloses a concrete modularized public toilet which comprises a bottom box, a wall body and a roof. The bottom box comprises a ground panel of a concrete structure and side panels located on the periphery of the ground panel, a plurality of drainage holes are formed in the ground panel, and drainage branch pipes are installed in the drainage holes; water supply holes are further formed in the positions, corresponding to the drainage holes, of the ground plate, and water supply branch pipes are arranged in the water supply holes in advance. A drainage main pipe and a water supply main pipe are laid below the ground plate, the drainage branch pipe is connected with the drainage main pipe through a connector, and the water supply main pipe is connected with the water supply branch pipe through a connector. The wall bodies and the roof are made of PC materials, the roof is detachably connected with the wall bodies, and the adjacent wall bodies are also detachably connected. The public toilet disclosed by the utility model can be quickly built on site, the building cost is lower, and the structural stability is better.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of modular building structure technology, and in particular to a concrete modular public toilet. Background Technology

[0002] Currently, outdoor public toilets, especially those built later or temporarily, mainly take the form of light steel structure prefabricated modular structures and precast concrete structures. While light steel structure toilets are lightweight and easy to assemble, they are prone to ground deformation and wall / roof corrosion after prolonged use, resulting in high maintenance costs. Furthermore, due to the limited thickness of the steel flooring, walking on light steel structure toilets often results in a strong hollow feeling accompanied by ground shaking, leading to a very poor user experience. Precast concrete structures effectively solve the shortcomings of light steel structures, but current concrete toilets generally require on-site foundation excavation, pipe laying, backfilling, and then tiling and finishing. This results in a large workload during assembly, requiring more workers and equipment, leading to higher construction costs and longer construction time. Utility Model Content

[0003] In view of the above-mentioned shortcomings of the existing technology, the purpose of this utility model is to solve the above-mentioned technical problems in the existing technology and provide a modular concrete public toilet that can be constructed on site more quickly, with lower construction costs and better structural stability.

[0004] To solve the above-mentioned technical problems, the technical solution adopted by this utility model is as follows: a modular concrete public toilet, characterized in that it includes a base box, walls and a roof;

[0005] The base box includes a concrete floor slab and side panels surrounding the floor slab. The floor slab is located above the side panels and is connected by several vertically arranged reinforcing bars. The lower ends of the reinforcing bars pass through the floor slab and extend into the side panels, while their upper ends extend upward to form inserts. Several drainage holes are provided on the floor slab, and drainage branch pipes are installed in the drainage holes. Water supply holes are also provided on the floor slab corresponding to each drainage hole, and water supply branch pipes are pre-installed in the water supply holes, extending from the upper side of the floor slab. A main drainage pipe and a main water supply pipe are laid below the floor slab. The drainage branch pipes are connected to the main drainage pipe through connecting joints, and the main water supply pipe is connected to the water supply branch pipes through connecting joints.

[0006] Both the walls and the roof are made of PC material. The roof and the walls are detachably connected, and adjacent walls are also detachably connected. The roof and the roof extend to the outside of the surrounding walls. On the lower side of the wall, there are pre-set holes corresponding to the positions of the insert bars. The wall is connected to the bottom box by inserting the insert bars through the holes.

[0007] Furthermore, both the main drainage pipe and the main water supply pipe are fixedly connected to the underside of the floor panel via pipe clamps.

[0008] Furthermore, a drain pipe hole and a water supply pipe hole are provided on the side panel, and the free ends of the main drain pipe and the main water supply pipe extend out from the drain pipe hole and the water supply pipe hole respectively.

[0009] Furthermore, on the floor panel, a toilet mounting groove is formed around the drain hole corresponding to the installation position of the toilet.

[0010] Furthermore, on the ground panel and side panel, anchor holes are provided at the positions corresponding to the connecting bars. The connecting bars are inserted into the anchor holes, and the anchor holes are filled with concrete grout.

[0011] Furthermore, a sleeve is pre-installed inside the insertion hole of the wall. The diameter of the sleeve is larger than the diameter of the connecting rib, and it can form a clearance fit with the connecting rib.

[0012] Furthermore, adhesive is filled between the connecting rib and the sleeve.

[0013] Furthermore, a sealing gasket is provided between the lower side of the wall and the floor panel.

[0014] Furthermore, hoisting holes are provided at corresponding positions on the side panels on opposite sides of the floor panel.

[0015] Compared with the prior art, the present invention has the following advantages:

[0016] 1. The combination of concrete and PC materials results in good overall stability, a better user experience, and easier and faster assembly.

[0017] 2. The base box is made of concrete, which has good stability, can effectively shield and protect the pipes, and has no hollow feeling, and is also more durable; at the same time, no foundation excavation is required during the construction process, making construction more convenient and faster.

[0018] 3. The walls and roof are made of PC material, which is lighter, easier to assemble, easier to maintain, and lower in cost. Attached Figure Description

[0019] Figure 1 This is a schematic diagram of the structure of this utility model.

[0020] Figure 2This is an exploded structural diagram of the present invention.

[0021] Figure 3 This is a schematic diagram of the bottom box.

[0022] In the diagram: 1—wall, 2—roof, 3—floor panel, 4—side panel, 5—connecting steel bars, 6—toilet mounting groove, 7—lifting hole. Detailed Implementation

[0023] The present invention will be further described below with reference to the accompanying drawings and embodiments.

[0024] To make the objectives, technical solutions, and advantages of the embodiments of this utility model clearer, the technical solutions of the embodiments of this utility model will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of this utility model, not all of them. Therefore, the following detailed description of the embodiments of this utility model provided in the accompanying drawings is not intended to limit the scope of the claimed utility model, but merely to represent selected embodiments of this utility model. All other embodiments obtained by those skilled in the art based on the embodiments of this utility model without inventive effort are within the scope of protection of this utility model.

[0025] It should be noted that similar reference numerals and letters in the following figures indicate similar items. Therefore, once an item is defined in one figure, it does not need to be further defined and explained in subsequent figures. In the description of this invention, it should be noted that the terms "center," "upper," "lower," "left," "right," "vertical," "horizontal," "inner," and "outer," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the figures, or the orientation or positional relationship commonly used when the product is in use. They are only for the convenience of describing the invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on the invention. Furthermore, the terms "first," "second," and "third," etc., are only used to distinguish descriptions and should not be construed as indicating or implying relative importance. In addition, the terms "horizontal," "vertical," etc., do not indicate that the component is required to be absolutely horizontal or suspended, but can be slightly tilted. For example, "horizontal" simply means that its direction is more horizontal than "vertical," and does not mean that the structure must be completely horizontal, but can be slightly tilted. In the description of this invention, it should also be noted that, unless otherwise explicitly specified and limited, the terms "set," "install," "connect," and "link" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this invention based on the specific circumstances.

[0026] Example: See Figure 1 , Figure 2 as well as Figure 3 A modular concrete public toilet, comprising a base box, walls 1 and a roof 2.

[0027] The base box includes a concrete floor panel 3 and side panels 4 surrounding the floor panel 3. The floor panel 3 is located above the side panels 4 and is connected by several vertically arranged connecting steel bars 5. The lower end of each connecting steel bar 5 passes through the floor panel 3 and extends into the side panel 4, while its upper end extends upward to form a reinforcing bar. During factory prefabrication, anchoring holes are opened on the floor panel 3 and side panels 4 at the positions corresponding to the connecting steel bars. The connecting steel bars are inserted into the anchoring holes, which are then filled with concrete grout.

[0028] Several drainage holes are provided on the floor panel 3, and drainage branch pipes are installed in the drainage holes. In practice, a toilet mounting groove 6 is formed around the drainage hole corresponding to the toilet's installation position on the floor panel 3. During assembly, the toilet is installed in the toilet mounting groove 6, and the toilet's drain outlet is connected to the drainage branch pipe. A water supply hole is also provided on the floor panel 3 corresponding to each drainage hole, and a water supply branch pipe is pre-installed in each water supply hole, extending from the upper side of the floor panel 3. In practice, each water supply branch pipe is connected to an angle valve to facilitate connection to the toilet's water tank. To further improve the convenience of on-site installation, a connecting pipe is pre-embedded between the toilet installation groove 6 and the wall 1. One end of the connecting pipe is connected to the toilet installation groove 6, and the other end passes through the upper side of the floor panel 3. In this way, when installing the toilet, you only need to connect the toilet tank to the connecting pipe through the pipe, and then connect the toilet inlet to the connecting pipe to quickly complete the installation, without the need for subsequent decoration and construction, thus greatly improving the installation efficiency.

[0029] A main drainage pipe and a main water supply pipe are laid beneath the floor panel 3. The drainage branch pipes are connected to the main drainage pipe via connectors, and the main water supply pipe is connected to the branch water supply pipes via connectors. In practice, both the main drainage pipe and the main water supply pipe are fixedly connected to the underside of the floor panel 3 using pipe clamps. To improve the overall adaptability of the toilet, drainage pipe holes and water supply pipe holes are provided on the side panel 4. The free ends of the main drainage pipe and the main water supply pipe extend from the drainage pipe holes and the water supply pipe holes respectively, so as to facilitate connection with external water supply pipes and sewage pipes.

[0030] Both wall 1 and roof 2 are made of PC material. Roof 2 is detachably connected to wall 1, and adjacent walls 1 are also detachably connected. All four edges of roof 2 extend to the outer sides of the surrounding walls 1. During implementation, connecting ribs are pre-embedded in the upper part of wall 1, protruding from the upper side of wall 1. Connecting holes are provided on the lower side of roof 2 corresponding to the connecting ribs, through which the connecting ribs are inserted to connect with wall 1. To improve the stability of the entire toilet, the inner sides of adjacent walls 1 are connected by multiple L-shaped connectors distributed from top to bottom, with two plates of each L-shaped connector fixedly connected to the two walls 1 respectively. On the lower side of wall 1, corresponding to the position of the connecting ribs, insertion holes are pre-set. Wall 1 inserts the connecting ribs through these holes to connect with the base box. A sleeve is pre-set inside the insertion hole of wall 1. The diameter of the sleeve is larger than the diameter of the connecting rib, allowing for a clearance fit with the connecting rib. Adhesive is filled between the connecting rib and the sleeve. This effectively improves the connection stability between the wall 1 and the base box. A sealing gasket is provided between the lower side of the wall 1 and the floor panel 3.

[0031] Lifting holes 7 are provided at corresponding positions on the side panels 4 on both sides of the ground panel 3 to facilitate lifting during installation.

[0032] In the actual production process, the design is first carried out according to the needs, and then the various parts are processed in the factory and pre-assembled. After the assembly is completed, the interior of the toilet is decorated in the factory and then disassembled. After being transported to the site, only the ground needs to be leveled, and then the assembly and connection to the external water supply and sewage pipes can be carried out. There is no need for foundation excavation and other work, which can greatly improve the construction efficiency and reduce the construction cost.

[0033] The base box in this design uses a concrete structure, which offers excellent stability, effectively shielding and protecting pipes without any hollow areas, and also provides better durability. Furthermore, no foundation excavation is required during construction, making it more convenient and faster. The walls and roof are made of PC material, which is lighter, easier to assemble, easier to maintain, and lower in cost.

[0034] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of this utility model and not to limit the technical solutions. Those skilled in the art should understand that any modifications or equivalent substitutions to the technical solutions of this utility model that do not depart from the spirit and scope of this technical solution should be covered within the scope of the claims of this utility model.

Claims

1. A modular public concrete toilet, characterized by: The bottom box, the wall body and the roof are included; The bottom box includes a ground plate of a concrete structure and side plates located around the ground plate, the ground plate is located above the side plates and connected by a plurality of vertically arranged connecting steel bars, the lower ends of the connecting steel bars penetrate into the side plates after passing through the ground plate, and the upper ends of the connecting steel bars extend upward to form inserting steel bars; a plurality of drainage holes are formed in the ground plate, and drainage branch pipes are installed in the drainage holes; water supply holes are formed in the ground plate corresponding to the drainage holes, water supply branch pipes are pre-installed in the water supply holes, and the water supply branch pipes extend out from the upper side of the ground plate; a drainage main pipe and a water supply main pipe are laid below the ground plate, the drainage branch pipes are connected to the drainage main pipe through connecting joints, and the water supply main pipe is connected to the water supply branch pipes through connecting joints; The wall body and the roof are made of PC material, the roof and the wall body are detachably connected, adjacent wall bodies are also detachably connected, and the periphery edges of the wall bodies extend to the outside of the wall bodies; the wall bodies are sleeved on the inserting steel bars through the insertion holes to realize the connection between the wall bodies and the bottom box.

2. A concrete modular public toilet as claimed in claim 1, wherein: The drainage main pipe and the water supply main pipe are fixedly connected to the lower side of the ground plate through pipe clamps.

3. A modular public toilet according to claim 1 or 2, characterized in that: Drainage pipe holes and water supply pipe holes are formed in the side plates, and the free ends of the drainage main pipe and the water supply main pipe extend out from the drainage pipe holes and the water supply pipe holes.

4. A concrete modular public toilet as claimed in claim 1, wherein: A toilet mounting groove is formed around the drainage hole corresponding to the mounting position of the toilet on the ground plate.

5. A concrete modular public toilet as claimed in claim 1, wherein: Planting hole corresponding to the connecting steel bar is formed on the ground plate and the side plate, the connecting steel bar is inserted into the planting hole, and the planting hole is filled with concrete slurry.

6. A concrete modular public toilet as claimed in claim 1, wherein: A sleeve pipe is pre-installed in the insertion hole of the wall body, the diameter of the sleeve pipe is larger than the diameter of the connecting steel bar, and the sleeve pipe can be gap-fitted with the connecting steel bar.

7. A concrete modular public toilet according to claim 6, characterized in that: An adhesive is filled between the connecting steel bar and the sleeve pipe.

8. A concrete modular public toilet as claimed in claim 1, wherein: A sealing gasket is arranged between the lower side of the wall body and the ground plate.

9. A concrete modular public toilet as claimed in claim 1, wherein: Hoisting holes are formed in the side plates on the opposite sides of the ground plate.