A simulation test device for verifying the effect of tunnel grouting

By designing a simulation test device to simulate the tunnel grouting process and monitor grouting parameters and geological conditions in real time, the problem of accuracy and efficiency in the evaluation of tunnel grouting effect in existing technologies has been solved, and efficient and reliable evaluation of tunnel grouting effect has been achieved.

CN224957938UActive Publication Date: 2026-11-10YUNNAN CONSTR INVESTMENT HLDG GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522530833.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-28
Publication Date
2026-11-10
Estimated Expiration
2035-11-28

AI Technical Summary

Technical Problem

Existing technologies for inspecting the effectiveness of tunnel grouting suffer from problems such as damaging structural integrity, low detection efficiency, and insufficient accuracy, making it difficult to achieve efficient and accurate evaluation of tunnel grouting effectiveness.

Method used

A simulation test device was designed, including a simulation box, a support frame, a grouting pipe, a grouting pressure detection device, and a transparent observation window. By simulating the grouting process, the influence of grouting parameters and geological conditions can be monitored in real time. The modular design facilitates assembly and maintenance.

Benefits of technology

It enables the reproduction and simulation of the tunnel grouting process under experimental conditions, improves the accuracy and reliability of grouting effect evaluation, reduces construction risks and costs, and provides comprehensive monitoring support.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224957938U_ABST
    Figure CN224957938U_ABST
Patent Text Reader

Abstract

This utility model discloses a simulation test device for verifying the effect of tunnel grouting, comprising: a simulation box with a supporting frame; the supporting frame being connected to the simulation box as a whole by binding straps; several grouting pipes, each positioned at the top of the supporting frame, with its inlet end extending out of the simulation box and connected to a grouting pump; and two sets of grouting pressure detection devices arranged opposite each other, placed in pairs on either the lower part of one side or the upper part of the other side of the simulation box. The simulation box is also filled with a filler material. This utility model features a novel design and simple construction, enabling the reproduction and simulation of the tunnel grouting process under experimental conditions. It allows for in-depth research into the influence of grouting parameters, geological conditions, and other factors on the grouting effect, providing a basis for optimizing grouting schemes, improving grouting effectiveness, and reducing construction risks in tunnel engineering.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to a simulation test device, specifically a simulation test device for testing the effect of tunnel grouting. It is mainly used to simulate the effect of tunnel grouting and belongs to the field of auxiliary testing technology for tunnel construction. Background Technology

[0002] Generally, in tunnel construction, grouting technology is a key construction process widely used for reinforcing surrounding rock and preventing water seepage. Its effectiveness directly affects the stability, durability, and subsequent operational safety of the tunnel. With the continuous expansion of tunnel construction scale and the increasing complexity of engineering environments, the accurate verification of tunnel grouting effects is becoming increasingly important.

[0003] Currently, there are numerous methods for verifying the effectiveness of tunnel grouting, such as core drilling, ground-penetrating radar detection, and acoustic wave testing; however, these methods all have certain limitations. Developing a more effective method for verifying the effectiveness of tunnel grouting is urgently needed.

[0004] The drawbacks of using the core drilling method are that it damages the structural integrity, has low detection efficiency, a limited sampling rate (usually ≥5%), and poor prediction effect on structural surfaces parallel to the tunnel axis.

[0005] The drawbacks of using ground-penetrating radar are that the error in judging the thickness of the invert arch is large, the steel reinforcement / steel frame can only be qualitatively detected, the dielectric constant needs to be calibrated on site, and the accuracy of cavity location depends on post-processing technology.

[0006] The limitations of using acoustic testing methods include the requirement that the grout reaches 70% of its design strength before testing, and insufficient assessment of physical indicators such as density and adhesion, necessitating verification using other methods. In short, it is often inconvenient. Therefore, developing a highly practical and reliable simulation testing device for verifying the effectiveness of tunnel grouting is key to solving these technical problems. Summary of the Invention

[0007] To address the numerous defects and shortcomings in the aforementioned background technology, this utility model has made improvements and innovations. The aim is to provide a novel design and simple construction that can reproduce and simulate the tunnel grouting process under experimental conditions, and to conduct in-depth research on the influence of grouting parameters, geological conditions, and other factors on the grouting effect. This can optimize grouting schemes for tunnel engineering, improve grouting effect, reduce construction risks, meet the simulation test needs of tunnel engineering with different support types, and facilitate equipment installation and maintenance, thereby reducing test costs and time costs.

[0008] To solve the above problems and achieve the above-mentioned invention objectives, this utility model provides a simulation test device for testing the effect of tunnel grouting, which is achieved by adopting the following design structure and the following technical solution:

[0009] As an improvement to the simulation test device for verifying the effect of tunnel grouting according to this utility model, it includes:

[0010] The simulation chamber is equipped with a supporting frame.

[0011] The supporting frame is connected to the simulation box as a whole by cable ties;

[0012] Several grouting pipes are installed at the top of the support frame, and the grout inlet end of each grouting pipe extends out of the simulation box and is connected to the grouting pump.

[0013] Two sets of grouting pressure detection devices are arranged opposite each other. The two sets of grouting pressure detection devices are placed in pairs on the lower part of one side or the upper part of the other side of the simulation box. The simulation box is also filled with filler material.

[0014] As an improvement of the present invention, the simulation box has openings on both sides, and a transparent observation window is installed at each opening.

[0015] As a further improvement of the present invention, the transparent observation window is made of transparent high-strength organic glass.

[0016] As a further improvement of the present invention, the simulation box is a hollow box with an open top and closed bottom and sides, and an openable top cover is provided on the box.

[0017] As a further improvement of the present invention, the supporting frame is a hollow bracket made of several steel bars arranged in a longitudinal and transverse and vertical manner and connected by welding. The hollow bracket has a box-shaped structure.

[0018] As a further improvement of the present invention, the binding strap is made of lead wire or iron wire;

[0019] The grouting conduits are configured as two to four, and each grouting conduit is connected to the supporting frame at equal or unequal intervals by U-bolts or wires.

[0020] As a further improvement of the present invention, the working section of the grouting conduit is provided with a plurality of grouting holes that penetrate both the front and back sides in a ring shape.

[0021] The non-free end of the grouting conduit is a closed cylindrical or conical shape, and several grouting holes penetrating both sides are circumferentially opened on the conical structure.

[0022] A grout inlet pipe extends from the free end of the grouting conduit and is connected to the grouting pump via a connecting pipe on the grouting pump.

[0023] A grout stop valve is also installed on the grouting pipe.

[0024] As a further improvement of the present invention, the grouting pressure detection device includes:

[0025] Pressure sensor, the pressure sensor is placed inside the simulation chamber;

[0026] The data acquisition unit is electrically connected to the pressure sensor via a connecting cable, and it is located outside the simulation chamber.

[0027] As a further improvement of the present invention, the filler is a slag body intended for grouting and consolidation;

[0028] The grouting pump is a BW-250 / 50 reciprocating plug pump.

[0029] As a further improvement to the present invention, the outer surface of the simulation box is sequentially coated with an injection molding layer, an anti-rust layer, a waterproof layer, and a warning layer from the inside to the outside, and the warning layer is coated with fluorescent powder.

[0030] The working principle is as follows: Before using the simulation test device for verifying the effect of tunnel grouting with the above-mentioned design structure, the completed device needs to be installed as a backup. The specific installation and use steps are as follows:

[0031] Step 1: In the test preparation stage, the construction personnel prepare the same surrounding rock as the tunnel to be grouted in advance. At the same time, the various components of this utility model are transported to the designated construction location by the corresponding handling equipment or directly by manual labor for placement. For the grouting material, the same liquid grout as the actual project is used and is strictly mixed according to the design ratio to ensure the stability of the grout performance.

[0032] Step 2: Place the pre-made simulation box (1) on a flat and solid ground, and arrange the three pre-prepared grouting pipes (4) at equal intervals and connect them to the support frame (2) with U-bolts or wires to form an integral structure. The grout stop valve (42) set on the exposed end of the grout inlet pipe (41) is threaded and can be reused. The exposed end of the grout inlet pipe (41) is connected to the grouting pump (8).

[0033] Subsequently, the construction personnel first filled a certain amount of filler (6) into the simulation box (1). The filler (6) is the slag to be grouted and solidified. After the filler (6) is filled to a certain height, the construction personnel placed the pressure sensors (51) of one of the pre-prepared grouting pressure detection devices (5) in pairs on the lower side of one side of the simulation box (1), and connected the acquisition instrument (52) of the grouting pressure detection device (5) to the outside of the simulation box (1) through the connecting line (53). Then, the construction personnel continued to fill the filler (6) into the simulation box (1). After the filler (6) is filled to a certain height, it is compacted appropriately. Then, the construction personnel placed the pressure sensors (51) of another pre-prepared grouting pressure detection device (5) in pairs on the upper side of the other side of the simulation box (1), and connected the acquisition instrument (52) of the grouting pressure detection device (5) to the outside of the simulation box (1) through the connecting line (53). The construction personnel continued to fill the filler (6), and after filling to the appropriate position, it was compacted appropriately. When installing the grouting pressure detection device (5), ensure that the stress distribution and variation law at the corresponding position can be accurately measured according to the requirements of the monitoring plan;

[0034] Step 3: After installation, cover the simulation box (1) with the top cover (11). At the same time, pass the connecting lines (3) of the two sets of grouting pressure detection devices (5) through the through holes pre-drilled on the top cover (11), and connect the acquisition instrument (52) to each connecting line (3) so that it is located above the top cover (11). Finally, thread the connecting pipe (81) of the grouting pump (8) to the grout inlet pipe (41) to conduct a simulation test of the tunnel grouting effect.

[0035] During the experiment, the grouting test plan was strictly followed. Grouting pressure is one of the most critical parameters, as it determines whether the grout can be successfully injected into the surrounding rock and the diffusion range within the surrounding rock. When determining the grouting pressure, factors such as the permeability of the stratum, burial depth, and rock strength need to be considered comprehensively. According to relevant research and engineering experience, for strata with good permeability, such as sand, the grouting pressure can be set at 0.5-1.0 MPa; while for rock strata with poor permeability, the grouting pressure needs to be increased to 1.0-2.0 MPa. During the experiment, if the grout diffusion rate is found to be too slow or unable to reach the expected range, the grouting pressure can be appropriately increased, but the increase should not exceed 0.2 MPa; if a large amount of grout leakage occurs, the grouting pressure should be reduced, and the cause should be investigated and adjusted. During the grouting process, the changes in grouting pressure should be closely monitored, and the diffusion path and range of the grout should be observed in real time using the transparent observation window of the simulation box (1). Grouting should be stopped after the predetermined grouting volume is reached. During the grouting process, monitoring work should be carried out simultaneously. The pressure sensor (51) continuously monitors the stress changes inside the surrounding rock and displays the readings through the data acquisition instrument (52).

[0036] Finally, during the entire implementation process described above, before grouting begins, initial data is collected from each grouting pressure detection device (5) as a benchmark for subsequent comparative analysis. During grouting, the data collection frequency is dynamically adjusted according to changes in parameters such as grouting pressure. When the grouting pressure changes significantly, the data collection frequency is increased to once every 2 seconds to promptly capture fluctuations in monitoring data caused by changes in grouting parameters; when the grouting parameters are relatively stable, data is collected at a frequency of once every 10 seconds to ensure the integrity and accuracy of the data. After grouting is completed, data is continuously collected for 1 hour to observe subsequent changes in the model and ensure a comprehensive understanding of the long-term stability of the grouting effect. The collected data is first preliminarily sorted and screened. Obvious abnormal data points are removed, such as sudden data caused by sensor failure or external interference. For stress monitoring data, stress-time curves are plotted to analyze the trend of surrounding rock stress and thus evaluate the grouting effect.

[0037] After grouting, the grout was allowed to solidify according to the test plan. Core samples were then taken from different locations in the grouting model. The integrity of the core samples was assessed using acoustic wave detection, and compressive strength tests were conducted on a pressure testing machine to verify the grouting effect. Finally, the test results were compared with actual engineering test results to verify the accuracy of the simulation test. If the results are similar, it indicates that this simulation test method and device can accurately simulate actual tunnel grouting conditions, providing a reliable reference for practical engineering.

[0038] The beneficial effects of this utility model compared with the prior art are:

[0039] 1. This utility model has a novel design and simple structure. It can reproduce and simulate the tunnel grouting process under experimental conditions, and conduct in-depth research on the influence of grouting parameters, geological conditions and other factors on the grouting effect. It can optimize the grouting scheme for tunnel engineering, improve the grouting effect and reduce construction risks.

[0040] 2. The reasonable layout of this utility model realizes all-round and three-dimensional monitoring of the grouting process. It can monitor the stress distribution and changes inside the grout body in real time and synchronously, providing rich data support for in-depth analysis of the mechanical properties of the grout body. A transparent observation window is set on each side of the simulation box, which can observe the diffusion path and range of the grout in real time.

[0041] 3. In terms of the structural design of the device, a modular and assemblable design concept is adopted. Each part of this utility model is designed as an independent modular component, which can be flexibly combined and adjusted according to different test requirements. This design not only improves the versatility and scalability of the device, enabling it to meet the simulation test requirements of tunnel engineering with different support types, but also facilitates the installation and maintenance of the equipment, reducing test costs and time costs.

[0042] 4. The test device designed in this utility model to match therewith can provide reliable hardware support for simulation tests, and ensure the accuracy and repeatability of the tests. Relevant studies show that the grouting scheme can be effectively optimized, the grouting effect can be improved, and the engineering risk can be reduced through simulation tests. This study is devoted to exploring an innovative simulation test method and device for inspecting the tunnel grouting effect, aiming to provide a more scientific, accurate and comprehensive means for inspecting the grouting effect in tunnel engineering construction, promote the improvement of tunnel engineering quality, and provide useful reference for similar projects;

[0043] 5. This utility model can observe the flowing position of grouting slurry in the model box through the transparent observation window, provide intuitive guidance for grouting control, and can greatly reduce the economic cost and shorten the time cost of the test;

[0044] 6. The exterior of the simulation box of this utility model is coated with antirust paint and waterproof layer, so it can prevent rust while prolonging the service life of the whole device, realize environmental protection while saving resources. At the same time, the exterior of the device is coated with a self-luminous fluorescent material, which can clearly mark the position of the device at night, in dark rooms and in underground construction environments, can effectively play a role in safety prompting, improve the visibility, be easy for people to identify, and increase the safety in construction and daily life. Brief Description of the Drawings

[0045] The specific embodiments of the utility model will be further described in detail below with reference to the accompanying drawings, in which:

[0046] Figure 1 is a schematic diagram of the use state of the utility model;

[0047] Figure 2 is a schematic diagram of the partial overall structure of the utility model;

[0048] Figure 3 is one of the schematic diagrams of the overall structure of the utility model;

[0049] Figure 4 is the second schematic diagram of the overall structure of the utility model;

[0050] Figure 5 is the third schematic diagram of the overall structure of the utility model;

[0051] Figure 6 is the second schematic diagram of the installation and use state of the utility model;

[0052] Figure 7 is the fourth schematic diagram of the overall structure of the utility model;

[0053] Wherein, the reference numerals in the drawings: 1—simulation box, 11—upper cover;

[0054] 2—Supporting framework;

[0055] 3—Cable straps;

[0056] 4—Grouting guide pipe, 41—Grouting inlet pipe, 42—Grouting stop valve;

[0057] 5—Grouting pressure detection device, 51—Pressure sensor, 52—Data acquisition instrument, 53—Connecting cable;

[0058] 6—Filling material;

[0059] 7—Transparent viewing window;

[0060] 8—Grouting pump, 81—Connecting pipe. Detailed Implementation

[0061] To make the technical means, inventive features, objectives, and effects of this utility model readily understandable, the technical solution of this utility model will be further described in detail below with reference to the accompanying drawings and specific embodiments. It should be noted that, unless otherwise specified, the embodiments and features in the embodiments of this application can be combined with each other. The present utility model will now be described in detail with reference to the accompanying drawings and embodiments.

[0062] like Figures 1 to 7 The simulation test device shown here for verifying the effect of tunnel grouting includes:

[0063] Simulation box 1, simulation box 1 is equipped with a support frame 2;

[0064] Support frame 2 is connected to simulation box 1 as a whole by binding straps 3 passing through it.

[0065] Several grouting pipes 4 are installed on the top of the support frame 2, and the grout inlet end of each grouting pipe 4 extends out of the simulation box 1 and is located outside and connected to the grouting pump 8.

[0066] Two sets of grouting pressure detection devices 5 are arranged opposite each other. The two sets of grouting pressure detection devices 5 are placed in pairs on the lower part of one side or the upper part of the other side of the simulation box 1. The simulation box 1 is also filled with filler material 6.

[0067] Furthermore, such as Figure 3 As shown, the simulation box 1 has openings on both sides, and a transparent observation window 7 is installed at each opening.

[0068] Specifically, the transparent observation window 7 is made of transparent high-strength organic glass.

[0069] More specifically, such as Figure 1As shown, the simulation box 1 is a box-shaped body with a hollow interior, an open top, and closed bottom and sides. An openable top cover 11 is provided on the box-shaped body.

[0070] In this utility model, the simulation box 1 is composed of multiple stainless steel plates, wooden templates, or adhesive boards of different sizes, which are spliced ​​together and fixedly connected to form an integral structure.

[0071] Furthermore, the supporting frame 2 is a hollow support structure made of several steel bars arranged in a longitudinal and transverse and vertical manner and connected by welding. The hollow support structure is a box-shaped structure.

[0072] Furthermore, the binding strap 3 is made of lead wire or iron wire;

[0073] The grouting conduit 4 is configured as two to four, and each grouting conduit 4 is connected to the support frame 2 at equal or unequal intervals by U-bolts or wires.

[0074] Furthermore, such as Figure 2 and Figure 7 As shown, the working section of the grouting conduit 4 is provided with a plurality of grouting holes that penetrate both the front and back sides in a ring shape;

[0075] The non-free end of the grouting conduit 4 is a closed cylindrical or conical shape, and several grouting holes that penetrate both the front and back sides are circumferentially opened on the conical structure.

[0076] The free end of the grouting conduit 4 is connected to a grout inlet pipe 41, which is connected to the grouting pump 8 via a connecting pipe 81 on the grouting pump 8.

[0077] A grout stop valve 42 is also provided on the grouting conduit 4.

[0078] Specifically, the grouting pressure detection device 5 includes:

[0079] Pressure sensor 51 is placed inside simulation chamber 1;

[0080] The data acquisition device 52 is electrically connected to the pressure sensor 51 via a connecting cable 53. The data acquisition device 52 is located outside the simulation chamber 1.

[0081] More specifically, the filler 6 is a slag body intended for grouting and consolidation;

[0082] The grouting pump 8 is a BW-250 / 50 reciprocating plug pump.

[0083] Furthermore, the outer surface of the simulation box 1 is sequentially coated with an injection molding layer, a rust-proof layer, a waterproof layer, and a warning layer from the inside out, with fluorescent powder applied to the warning layer.

[0084] Specifically, in this utility model, a polymer wear-resistant material is injection molded onto the injection molding layer; the anti-rust layer includes an epoxy zinc-rich primer and a chlorinated rubber topcoat, as well as an epoxy micaceous iron oxide intermediate paint located between the epoxy zinc-rich primer and the chlorinated rubber topcoat; the waterproof layer is a polyurethane waterproof coating; and the warning layer is a yellow or black reflective warning tape, reflective film, or reflective paint.

[0085] Meanwhile, in this utility model, all connections referred to are fixed connections, movable connections, or detachable connections. Fixed connections are welded connections or directly processed into an integral structure; movable connections or detachable connections are hinged connections, threaded connections, bayonet connections, plug-in connections, bolt assembly connections, or screw connections.

[0086] In summary, a more specific embodiment of this utility model is as follows:

[0087] Before using the simulation test device for verifying the effect of tunnel grouting with the above-mentioned design structure, the already manufactured device needs to be installed as a backup. The specific installation and use steps are as follows:

[0088] Step 1: In the test preparation stage, the construction personnel prepare the same surrounding rock as the tunnel to be grouted in advance. At the same time, the various components of this utility model are transported to the designated construction location by the corresponding handling equipment or directly by manual labor for placement. For the grouting material, the same liquid grout as the actual project is used and is strictly mixed according to the design ratio to ensure the stability of the grout performance.

[0089] Step 2: Place the pre-made simulation box 1 on a flat and solid ground, and arrange the three pre-prepared grouting pipes 4 at equal intervals and connect and fix them to the support frame 2 as an integral structure by U-bolts or wires. The grout stop valve 42 set on the exposed end of the grout inlet pipe 41 is threaded and can be reused. The exposed end of the grout inlet pipe 41 is connected to the grouting pump 8.

[0090] Subsequently, the construction workers first filled a certain amount of filler material 6 into the simulation box 1. Filler material 6 is the slag to be grouted and solidified. After the filler material 6 is filled to a certain height, the construction workers placed a pair of pressure sensors 51 from one of the pre-prepared grouting pressure detection devices 5 on the lower side of one side of the simulation box 1, and connected the acquisition instrument 52 of this set of grouting pressure detection devices 5 to the outside of the simulation box 1 via a connecting line 53. Next, the construction workers continued to fill the simulation box 1 with filler material 6. After the filler material 6 is filled to a certain height, it is appropriately compacted. Then, the construction workers placed a pair of pressure sensors 51 from the other side of the simulation box 1, and connected the acquisition instrument 52 of this set of grouting pressure detection devices 5 to the outside of the simulation box 1 via a connecting line 53. They continued to fill the simulation box 1 with filler material 6, and after filling it to the appropriate position, it was appropriately compacted. When installing the grouting pressure detection device 5, according to the requirements of the monitoring plan, it is ensured that the stress distribution and change pattern at the corresponding position can be accurately measured.

[0091] Step 3: After installation, cover the simulation box 1 with the top cover 11. At the same time, pass the connecting wires 3 of the two sets of grouting pressure detection devices 5 through the pre-drilled holes on the top cover 11, and connect the data acquisition instrument 52 to each connecting wire 3 so that it is located above the top cover 11. Finally, thread the connecting pipe 81 of the grouting pump 8 to the grout inlet pipe 41 to conduct a simulation test of the tunnel grouting effect.

[0092] During the experiment, the established grouting test plan was strictly followed. Grouting pressure is one of the most critical parameters, determining whether the grout can be successfully injected into the surrounding rock and its diffusion range within the rock. When determining the grouting pressure, factors such as the permeability of the strata, burial depth, and rock strength need to be comprehensively considered. According to relevant research and engineering experience, for strata with good permeability, such as sand, the grouting pressure can be set at 0.5-1.0 MPa; while for rock strata with poor permeability, the grouting pressure needs to be increased to 1.0-2.0 MPa. During the experiment, if the grout diffusion rate is found to be too slow or unable to reach the expected range, the grouting pressure can be appropriately increased, but the increase should not exceed 0.2 MPa; if a large amount of grout leakage occurs, the grouting pressure should be reduced, and the cause should be investigated and adjusted. During the grouting process, the changes in grouting pressure were closely monitored, and the diffusion path and range of the grout were observed in real time using the transparent observation window of simulation chamber 1. Grouting was stopped after the predetermined grouting volume was reached. Monitoring was conducted simultaneously during the grouting process. Pressure sensor 51 continuously monitors stress changes inside the surrounding rock and displays the data through data acquisition instrument 52.

[0093] Finally, during the entire implementation process described above, initial data was collected from each grouting pressure detection device 5 before grouting began, serving as a benchmark for subsequent comparative analysis. During grouting, the data acquisition frequency was dynamically adjusted based on changes in parameters such as grouting pressure. When significant changes in grouting pressure occurred, the data acquisition frequency was increased to once every 2 seconds to promptly capture fluctuations in monitoring data caused by changes in grouting parameters. When grouting parameters were relatively stable, data was collected once every 10 seconds to ensure data integrity and accuracy. After grouting, data was continuously collected for one hour to observe subsequent changes in the model and ensure a comprehensive understanding of the long-term stability of the grouting effect. The collected data underwent preliminary processing and screening. Obvious abnormal data points, such as sudden changes caused by sensor malfunctions or external interference, were removed. For stress monitoring data, stress-time curves were plotted to analyze the trend of surrounding rock stress and thus evaluate the grouting effect.

[0094] After grouting, the grout was allowed to solidify according to the test plan. Core samples were then taken from different locations in the grouting model. The integrity of the core samples was assessed using acoustic wave detection, and compressive strength tests were conducted on a pressure testing machine to verify the grouting effect. Finally, the test results were compared with actual engineering test results to verify the accuracy of the simulation test. If the results are similar, it indicates that this simulation test method and device can accurately simulate actual tunnel grouting conditions, providing a reliable reference for practical engineering.

[0095] In the above-described implementation process, the grouting pressure detection device 5 is a readily available commercial product. The grouting pressure detection device 5 can also be connected to a computer during use to transmit data to the computer in real time for analysis. Data acquisition must be performed strictly according to the predetermined acquisition frequency and time intervals.

[0096] This invention utilizes a device that can reproduce and simulate the tunnel grouting process under experimental conditions. By controlling variables, it can conduct in-depth research on the influence of factors such as grouting parameters and geological conditions on the grouting effect.

[0097] Finally, it should be noted that the specific embodiments of this utility model have been described in detail above with reference to the accompanying drawings. However, this utility model is not limited to the above-described embodiments. Within the scope of knowledge possessed by those skilled in the art, various changes can be made to it.

Claims

1. A simulation test device for verifying the effect of tunnel grouting, characterized in that, include: The simulation box (1) is equipped with a support frame (2); The support frame (2) is connected to the simulation box (1) as a whole by means of a binding strap (3); Several grouting pipes (4) are installed on the top of the support frame (2), and the grout inlet end of each grouting pipe (4) extends out of the simulation box (1) and is located outside and connected to the grouting pump (8). Two sets of grouting pressure detection devices (5) are arranged opposite to each other. The two sets of grouting pressure detection devices (5) are placed in pairs on the lower part of one side or the upper part of the other side of the simulation box (1). The simulation box (1) is also filled with filler (6).

2. The simulation test device for verifying the effect of tunnel grouting according to claim 1, characterized in that, The simulation box (1) has openings on both sides, and a transparent observation window (7) is installed at each opening.

3. The simulation test device for verifying the effect of tunnel grouting according to claim 2, characterized in that, The transparent observation window (7) is made of transparent high-strength organic glass.

4. A simulation test device for verifying the effect of tunnel grouting according to claim 1 or 2, characterized in that, The simulation box (1) is a hollow box with an open top and closed bottom and sides. An openable top cover (11) is provided on the box.

5. The simulation test device for verifying the effect of tunnel grouting according to claim 1, characterized in that, The supporting frame (2) is a hollow support made of several steel bars arranged in a longitudinal and transverse and vertical manner and connected by welding. The hollow support is a box-shaped structure.

6. The simulation test device for verifying the effect of tunnel grouting according to claim 1, characterized in that, The binding strap (3) is made of lead wire or iron wire; The grouting conduits (4) are configured as two to four, and each grouting conduit (4) is connected to the support frame (2) at equal or unequal intervals by U-bolts or wires.

7. The simulation test device for verifying the effect of tunnel grouting according to claim 1, characterized in that, The working section of the grouting conduit (4) is provided with a number of grouting holes that penetrate both the front and back sides in a ring shape; The non-free end of the grouting conduit (4) is a closed cylindrical or conical shape, and several grouting holes that penetrate both the front and back sides are circumferentially opened on the conical structure. The free end of the grouting conduit (4) is connected to a grout inlet pipe (41), which is connected to the grouting pump (8) via a connecting pipe (81) on the grouting pump (8). A grout stop valve (42) is also provided on the grouting conduit (4).

8. The simulation test device for testing the effect of tunnel grouting according to claim 1, characterized in that, The grouting pressure detection device (5) includes: Pressure sensor (51) is placed inside simulation box (1); The data acquisition device (52) is electrically connected to the pressure sensor (51) via a connecting cable (53), wherein the data acquisition device (52) is located outside the simulation box (1).

9. The simulation test device for verifying the effect of tunnel grouting according to claim 1, characterized in that, The filler (6) is a slag body to be grouted and solidified; The grouting pump (8) is a BW-250 / 50 reciprocating plug pump.

10. The simulation test device for verifying the effect of tunnel grouting according to claim 1, characterized in that, On the outer surface of the simulation box (1), an injection molding layer, an anti-rust layer, a waterproof layer, and a warning layer are sequentially sprayed from the inside to the outside. The warning layer is coated with fluorescent powder.