An expanded thermal power generation system

By adopting a dual-set electrical equipment wiring method in the expansion of thermal power plants, the old and new generator units are ensured to serve as backups for each other, thus solving the problems of power supply reliability and continuity, and achieving efficient utilization of equipment and low-cost expansion.

CN224959380UActive Publication Date: 2026-11-10POWERCHINA HEBEI ELECTRIC POWER SURVEY & DESIGN INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202620056287.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2026-01-16
Publication Date
2026-11-10
Estimated Expiration
2036-01-16

AI Technical Summary

Technical Problem

During the expansion of thermal power plants, the existing equipment wiring methods reduce the reliability and continuity of power supply, affecting the normal operation of the units, and the construction cost and cycle are long.

Method used

The system adopts a dual-set electrical equipment wiring method, with the new and old generator sets connected by backup lines to ensure mutual backup of equipment. This reduces the need for additional equipment, simplifies wiring, and saves space and costs.

Benefits of technology

It improves the operational reliability and flexibility of the generator set, reduces equipment footprint and construction costs, simplifies construction and maintenance, and ensures independent operation of the unit during maintenance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224959380U_ABST
    Figure CN224959380U_ABST
Patent Text Reader

Abstract

This utility model discloses an expanded thermal power generation system for the construction of a thermal power plant. It includes the existing plant section, comprising existing generator sets, an existing main transformer supplying power to the outside world, and an existing auxiliary transformer supplying power to the plant. The low-voltage output of the existing auxiliary transformer is connected to the plant's busbar, which is connected to the existing low-voltage dry-type transformer. Its output is connected to the existing plant equipment lines via the original circuit breaker to supply power to the existing plant. The new plant generator sets are connected to the newly built main transformer and the newly added auxiliary transformer. The low-voltage output of the newly added auxiliary transformer is connected to two sections of the plant's busbar, both of which are connected to the newly added low-voltage dry-type transformer. The outputs of the two newly added low-voltage dry-type transformers are connected to the newly added plant equipment lines via a new circuit breaker to supply power to the newly added plant equipment and to provide mutual backup. The newly added plant equipment lines are also connected to the existing plant equipment lines via a second circuit breaker. The wiring is simple, the number of new electrical devices is small, and the two generator sets can operate independently without affecting each other during maintenance.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model applies to the field of thermal power plants and relates to a power generation system consisting of the arrangement and connection of equipment used in the power plant (in-plant equipment) during the renovation, expansion or phased construction of old power plants. Background Technology

[0002] Currently, thermal power plants and thermal power generating units remain the main mode of power generation in my country. Many of the power plants approved for construction are expansion projects on the basis of existing power plants, often located adjacent to the old ones. Generating units must be equipped with coal conveying systems, water supply systems, and water treatment systems. However, the investment in these systems during expansion and renovation is enormous, and the construction period is very long. Therefore, to improve overall efficiency, considering the process flow and overall layout, the auxiliary systems such as coal conveying, water supply, and water treatment systems of both the old and new generating units are often shared between the two phases of the project. That is, the auxiliary systems of the expanded units often partially or entirely use the auxiliary systems of the old plant; therefore, they can be called "common systems."

[0003] There are generally two ways to supply power to public auxiliary systems such as coal conveying systems, water supply systems, and water treatment systems: One is to draw power from the existing plant's power supply system for newly built units. If the capacity and layout of the existing plant's power supply system cannot meet the access requirements for expansion, i.e., it cannot meet the power demand of the expanded generator units, the existing design often involves modifying and expanding the original power distribution equipment based on the existing plant's power supply system. The other method is to connect the newly added power equipment during the expansion to the auxiliary power wiring system of the newly added generator units. However, both methods connect the newly built and expanded public systems separately to the existing plant or the expanded units, reducing the reliability and continuity of power supply and affecting the normal operation of the expanded units. When the power equipment in the existing plant or the expanded units is under maintenance or malfunctions, the auxiliary systems of other generator units will also lose power, causing the expanded or newly built generator units to malfunction and unable to generate electricity. Therefore, both methods reduce the continuity and reliability of the entire power plant's power generation. Utility Model Content

[0004] The technical problem to be solved by this utility model is to provide an expanded thermal power generation system that rationally arranges the equipment when expanding and renovating an existing thermal power plant, with less new equipment required, thereby reducing construction costs and construction period.

[0005] To solve the above-mentioned technical problems, the technical solution adopted by this utility model is as follows: An expanded thermal power generation system includes an existing plant generator set, an existing main transformer connected to the existing generator set for external power supply, and an existing plant service transformer for internal power supply. The low-voltage output terminals of the existing plant service transformer are connected to two sections of internal busbars. The internal busbars are connected to the existing plant low-voltage dry-type transformer. The output terminals of the existing plant low-voltage dry-type transformer are connected to the existing internal equipment lines supplying power to the original internal electrical equipment through the original circuit breaker. The system also includes a new plant generator set, which is connected to a newly built main transformer for external power supply. The new plant generator set is also connected to a newly added plant service transformer for internal power supply. The low-voltage output terminals of the newly added plant service transformer are connected to two sections of internal busbars. Each section of the internal busbar is connected to a newly added low-voltage dry-type transformer. The output terminals of these two newly added low-voltage dry-type transformers are connected to the newly added internal equipment lines supplying power to the newly added internal electrical equipment through a new circuit breaker and are mutually redundant. At the same time, the newly added internal equipment lines are connected to the existing internal equipment lines through a second circuit breaker.

[0006] A further improvement of this utility model is that: the old plant generator set, the original main transformer, the original plant service transformer, the old plant low-voltage dry-type transformer and the original plant equipment lines are all in two sets, and the original plant equipment lines are connected to each other as backup lines through a circuit breaker.

[0007] A further improvement of this utility model lies in the following: the connection between the newly added in-plant equipment lines and the existing in-plant equipment lines is such that the two lines of the newly added in-plant equipment lines are respectively connected to the two existing in-plant equipment lines, which serve as backup lines for each other, through circuit breaker two. Due to the adoption of the above technical solution, the technical progress achieved by this utility model is: This invention is applicable to coal-fired power plants with multiple generator sets. The electrical system wiring is simple, requiring minimal additional electrical equipment during renovation and expansion, thus saving layout space and floor area. Each generator set can operate independently, and maintenance of both generator sets will not affect each other, ensuring reliable and safe operation of the units. The wiring system is reliable and easy to apply in engineering projects. The electrical wiring system of this invention facilitates the construction, installation, maintenance, and repair of the units, while also saving on project costs, making it easy to apply and promote in engineering projects.

[0008] This utility model features a simple electrical wiring system, improving the reliability and flexibility of simultaneous operation of multiple generator sets. It utilizes mature electrical equipment, resulting in a smaller equipment layout and footprint, facilitating maintenance and repair, and offering significant economic benefits. This utility model can be widely applied in the design of power supply systems for multiple generator sets. The equipment used in this utility model has mature operating experience, ensuring safety, stability, and reliability, and meeting the operational needs of various power plant systems. Attached Figure Description

[0009] Figure 1 This is a connection structure diagram of this utility model; Among them, 1. Old plant generator set, 11. New plant generator set, 2. Existing main transformer, 21. Newly built main transformer, 3. Existing plant service transformer, 31. Newly added plant service transformer, 4. Existing plant equipment and lines, 5. Existing circuit breaker, 51. New circuit breaker, 52. Circuit breaker one, 3. Circuit breaker two, 6. Old plant low-voltage dry-type transformer, 7. Newly added low-voltage dry-type transformer, 8. Newly added plant equipment and lines. Detailed Implementation

[0010] An expanded thermal power generation system, such as Figure 1 As shown. Generator set 1 in the old plant is the original generator set before the expansion. Generator set 1 is connected to the original main transformer 2 that supplies power to the outside. The low-voltage output terminals of the original plant auxiliary transformer 3, which supplies power to the power plant, are connected to two sections of the plant's internal busbars (…). Figure 1 The winning bid includes line segments 1A and 1B or 2A and 2B. One section of the factory busbar connects to the old factory's low-voltage dry-type transformer 6. The outgoing line of the old factory's low-voltage dry-type transformer 6 passes through the original circuit breaker 5 and enters the original factory equipment line 4 to supply power to the original factory's electrical equipment. In the newly built factory area, a new factory generator set 11 is also installed. Figure 1 (#3 in the text) The new plant generator set 11 is connected to the newly built main transformer 21 that supplies power to the outside. The new plant generator set 11 is also connected to the newly added plant service transformer 31 that supplies power to the plant. The low-voltage output terminal of the newly added plant service transformer 31 is connected to two sections of the plant busbar ( Figure 1 The winning bids include 3A and 3B. Each section of the plant busbar is connected to a newly added low-voltage dry-type transformer 7. The outgoing terminals of the two newly added low-voltage dry-type transformers 7 are connected to the newly added plant equipment line 8, which supplies power to the newly added plant electrical equipment, through a new circuit breaker 51. The two newly added low-voltage dry-type transformers 7 are mutually redundant. At the same time, the newly added plant equipment line 8 is connected to the existing plant equipment line 4 through circuit breaker 2 53.

[0011] The old plant generator set 1, the original main transformer 2, the original plant service transformer 3, the old plant low-voltage dry-type transformer 6, and the original plant equipment wiring 4 mentioned in this utility model can all have two sets (e.g., Figure 1 In this context, #1 and #2 refer to two existing generator sets (1), and these two sets of original plant equipment lines (4) are connected as backup lines to each other via circuit breaker 52. The connection between the newly added plant equipment line (8) and the original plant equipment line (4) is as follows: the two lines of the newly added plant equipment line (8) are connected to the two backup lines of the original plant equipment line (4) via circuit breaker 53, respectively. Figure 1 As shown in the figure, the original in-plant equipment line 4 is two sets of backup lines for each other, and the newly added in-plant equipment line 8 is also two sets of backup lines for each other.

[0012] With the electrical connection structure of this utility model, when the power supply to the old plant fails, the newly built dry transformer can supply power to the common load of the generator units, thereby ensuring the reliability and continuity of the operation of the expanded generator units.

[0013] The equipment involved in this utility model (such as generator sets, main transformers, plant service transformers, and low-voltage dry-type transformers) can be different devices of the same model, and the circuit breakers of different grades involved can be different devices of the same model. They are just installed in different positions on the line or connected to different lines. When the original #1 and #2 generator sets' plant service 1A and 2A sections, the old plant low-voltage dry-type transformer 6, or its distribution circuit breaker 5 fails, causing the 400V PC 1A and 1B sections to lose power simultaneously, the old plant low-voltage dry-type transformer 7 of the expanded #3 generator set can supply power to the old plant's 400V PC 1A and 1B sections, thereby ensuring power supply to the common loads that affect the normal operation of the expanded units and ensuring the reliability and continuity of the expanded units' operation.

Claims

1. An expanded thermal power generation system, characterized in that: This includes the old plant generator set (1) and the original main transformer (2) connected to the old plant generator set (1) for external power supply and the original plant service transformer (3) for internal power supply. The low-voltage output terminal of the original plant service transformer (3) is connected to two sections of internal busbars. The internal busbars are connected to the old plant low-voltage dry-type transformer (6). The output terminal of the old plant low-voltage dry-type transformer (6) is connected to the original internal equipment line (4) that supplies power to the original internal equipment through the original circuit breaker (5). It also includes the new plant generator set (11), and the new plant generator set (11) is connected to the newly built main transformer for external power supply. (21) The new plant generator set (11) is also connected to a new plant service transformer (31) that supplies power to the plant. The low-voltage output terminal of the new plant service transformer (31) is connected to two sections of the plant busbar. Each section of the plant busbar is connected to a new low-voltage dry-type transformer (7). The output terminals of these two new low-voltage dry-type transformers (7) are connected to the new plant equipment line (8) that supplies power to the new plant electrical equipment through a new circuit breaker (51) and are mutually redundant. At the same time, the new plant equipment line (8) is connected to the original plant equipment line (4) through circuit breaker two (53).

2. The expanded thermal power generation system according to claim 1, characterized in that: The old plant generator set (1), the original main transformer (2), the original plant service transformer (3), the old plant low-voltage dry-type transformer (6) and the original plant equipment lines (4) are all in two sets. The original plant equipment lines (4) are connected to each other as backup lines through circuit breaker one (52).

3. The expanded thermal power generation system according to claim 2, characterized in that: The connection between the newly added in-plant equipment line (8) and the original in-plant equipment line (4) is that the two lines of the newly added in-plant equipment line (8) are connected to the two backup lines of the original in-plant equipment line (4) through circuit breaker two (53).