Process and installation for crushing or fragmenting bituminous products

The described process and installation efficiently fragment bituminous waste using rotary shear shredders with controlled residence time and transfer, addressing inefficiencies and energy consumption in existing technologies by transforming solid materials into viscous masses for improved recycling.

FR3147116A1Active Publication Date: 2024-10-04SOPREMA SA
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
FR2023003262
Authority / Receiving Office
FR · FR
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-03
Publication Date
2024-10-04
Estimated Expiration
2043-04-03

AI Technical Summary

Technical Problem

Existing recycling technologies for bituminous waste from construction and demolition sites are inefficient and energy-intensive due to the need for uniform-sized inputs, lack of energy optimization, and frequent maintenance requirements.

Method used

A process and installation utilizing multiple rotary shear shredders with controlled residence time and intermediate transfer to reduce bituminous materials progressively, minimizing heat loss and energy consumption, transforming solid materials into viscous masses for easier recycling.

Benefits of technology

The process achieves reliable and energy-efficient fragmentation of bituminous materials, reducing energy input and maintaining positive caloric load, facilitating subsequent recycling by transforming solid materials into viscous masses for improved heat exchange and separation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 00000000_0000_ABST
    Figure 00000000_0000_ABST
Patent Text Reader

Abstract

Method and installation for grinding or fragmenting bituminous products The invention relates to a method for grinding raw materials (RM) mainly formed of elements of the membrane type or similar, this method consisting of treating these products (RM) through at least two successive grinding stations (1, 2, 3), so as to reduce each time the average size of the elements forming the bituminous products successively treated (PT1, PT2, PT3).The process is characterized in that it consists of implementing a rotary shear shredder (1', 2', 3') at each of the grinding stations (1, 2, 3), preferably at least three in number, controlling the heating of the products (MP, PT1, PT2) by shearing during their processing by regulating their residence time, and therefore their processing time, in each shredder (1', 2', 3'), and transferring the processed products (PT1, PT2) from one grinding station (1, 2) to the next consecutive grinding station (2, 3), while limiting heat loss. Figure to be published with the abbreviation: Fig. 1.
Need to check novelty before this filing date? Find Prior Art

Description

Title of the invention: Method and installation for grinding or fragmenting bituminous products

[0001] The present invention relates to the field of recycling and recovery of waste from factories, and demolition, restoration and construction sites in connection with roofing and waterproofing materials and systems, in particular in connection with waste composed mainly of bituminous products formed from elements of the type membranes, portions of membranes, shingles or the like.

[0002] In this context, the invention relates to a process and an installation for grinding or fragmenting raw materials mainly in the form of bituminous products, as well as a process and an installation for thermomechanical treatment for the purpose of recycling raw materials, comprising respectively a process or an installation of the aforementioned type.

[0003] In the context of the current general trend towards seeking possible valorization of waste, a growing demand, which is currently not being satisfactorily resolved, either technically or economically, concerns factory waste and especially construction site waste (demolition, restoration, construction) containing mainly, or possibly substantially exclusively, bituminous products in the form of membranes, panels, shingles or the like.

[0004] From documents WO 2021 / 213792 and WO 2021 / 213793, processes and installations for treating waste of the type mentioned above with a view to recovering and revaluing the bituminous substances they contain are already known.

[0005] However, although they can process products of any size and format, these installations operate optimally when the inputs are of a small size and a substantially homogeneous format.

[0006] The present invention aims to provide a simple, robust, reliable, and energy-efficient solution for pretreating factory and construction site waste containing bituminous materials, preferably in the majority, by reducing its size to make it suitable for optimized subsequent recycling. This solution should be implementable without the addition of any facilitating substances and should not require excessively frequent maintenance.

[0007] To this end, the invention relates to a process for grinding or fragmenting raw materials mainly in the form of bituminous products, for example formed from elements such as membranes, portions of membranes, shingles or the like, particularly as production, construction site or demolition waste, This process essentially consists of treating these products through at least two successive crushing or fragmentation stations, so as to reduce each time the average size of the elements forming the successively treated bituminous products, a process characterized in that it consists of implementing a rotary shear shredder at each of the crushing stations, preferably at least three in number, controlling heating by shearing the products during their treatment by regulating their residence time, and therefore treatment time, in each shredder and transferring the treated products from one crushing station to the respective consecutive crushing station, limiting heat losses.

[0008] The invention also relates to an installation for crushing or fragmenting raw materials, predominantly in the form of bituminous products formed from elements such as membranes, portions of membranes, shingles, or the like, as production, construction, or demolition waste. This installation essentially comprises at least two successive crushing or fragmenting stations, configured to reduce the average size of the elements forming the successively processed bituminous products along at least one dimension. The installation also comprises, upstream of the first crushing station, a raw material feed station and, downstream of the last crushing station, a treated product discharge station, as well as intermediate transfer means for treated products between two consecutive crushing stations. The installation is characterized in that each of the crushing stations,preferably comprising at least three, includes a rotary shear shredder, in that it includes means for regulating the residence time, and therefore the processing time, of the products during their treatment in each shredder, in order to control the heating of said products by shearing, and in that the intermediate transfer means for processed products, from one grinding station to the next grinding station respectively, are configured to limit heat loss.

[0009] The invention will be better understood from the following description, which relates to a preferred embodiment, given by way of non-limiting example, and explained with reference to the accompanying schematic drawings, in which:

[0010] [Fig-1] is a schematic perspective view of a grinding or fragmentation according to a preferred embodiment of the invention, with three stations;

[0011] [Fig.2] is a partial view in detail and at another scale showing the first grinding station of the installation of the [Fig.1];

[0012] [Fig.3] is a partial view in detail and at another scale showing the arrangement formed by the second and third grinding stations of the installation of the [Fig.1];

[0013] [Fig.4] is a perspective view of an alternative embodiment of the first station of grinding shown [Fig.2], and,

[0014] [Fig.5] is a perspective and top view of a part of the shredder forming part of the first shredding station for example, and where applicable also of the other station(s) (feed hopper removed and drive motors of the shafts not shown).

[0015] The invention relates firstly, as can be seen from the figures, to a process for grinding or fragmenting raw materials (RM), which are mainly in the form of bituminous products and are for example formed of elements such as membranes, portions of membranes, shingles or the like, in particular as production, construction site or demolition waste.

[0016] This process essentially consists of treating these products (MP) through at least two, preferably at least three, successive grinding or fragmentation stations (1, 2, 3), so as to reduce each time (i.e. at each treatment at the level of a station) the average size of the elements forming the successively treated bituminous products (PT1, PT2, PT3), between the inputs and outputs of the station concerned.

[0017] This process is characterized in that it consists of implementing a rotary shear shredder (1', 2', 3') at each of the grinding stations (1, 2, 3), controlling the heating by shearing of the products (MP, PT1, PT2) during their treatment by regulating their residence time, and therefore their treatment time, in each shredder (1', 2', 3') and transferring the treated products (PT1, PT2), from one grinding station (1, 2) to the next grinding station (2, 3) respectively consecutive or following, while limiting heat losses.

[0018] Thanks to the invention, the bituminous products forming the raw materials are reliably and progressively fragmented in successive stages, thus limiting overall energy expenditure. Furthermore, the resulting treated products (preferably pellets with an average particle size of 10 to 15 mm) carry a positive specific heat capacity, also due to the limited dissipation during transfer between stations, thereby reducing the energy input in subsequent processing stages, before separation and recycling of the bituminous materials. This results in significant energy savings across the entire recycling process (a more favorable energy balance).

[0019] Indeed, in relation to the process according to the invention and taking into account the nature of the products processed, it has been observed that the mechanical energy of shredding by shearing is transformed into thermal energy, advantageously heating the material of the products processed: the friction of the material processed (primarily bituminous-based) between the shredding elements gradually heats the latter as it passes through the various successive stations, preferentially to actually result in an output at the exit of the last station which has a viscous constitution.

[0020] The physical characteristics of the bituminous materials present in the processed products (non-Newtonian rheology, low thermal conductivity and high specific heat capacity - 2100 J / kg.K) significantly slow down the heating of the material. Preheating the fragments of bituminous products (particularly membranes) or "chips" in the shredders (1', 2', 3') transforms the initially solid bituminous material into a viscous, non-solid mass, which gives it new physical properties that subsequently facilitate heat exchange in the process of transforming this material into a liquid mass for the separation and recycling of the recovered bitumen or bitumen mixture.

[0021] In accordance with a preferred embodiment, and as illustrated in the attached figures, the invention provides for three consecutive grinding stations (1, 2 and 3), which constitutes an optimized compromise between installation complexity, treatment reliability and energy expenditure.

[0022] In the context of this embodiment, it is advantageously provided, in view of a good distribution of stresses and wear in the different shredders and of obtaining a homogeneous overall treatment, to calibrate the respective shredders (1', 2', 3') in such a way that the first shredder (1') delivers treated products (PT1) whose constituent elements have a width of at most 100 mm, preferably at most 80 mm, that the second shredder (2') delivers treated products (PT2) whose constituent elements have a width of at most 30 mm, preferably at most 20 mm and that the third shredder (3') delivers treated products (PT3) whose constituent elements have a width of at most 15 mm, preferably at most 12 mm.

[0023] In order to guarantee a certain uniformity of treatment over time in each grinding station (1, 2, 3) and of the treated products having substantially constant dimensional and physical state characteristics for successive operating cycles, the process may consist of regulating the residence time of the products (MP, PT1, PT2) being treated in each shredder (1', 2', 3') according to the quantity of product to be treated (MP, PT1, PT2), for example determined by continuous weighing of the first shredder (1') at least, preferably of each shredder (1', 2', 3').

[0024] Preferably, the processing is done in batches and the quantity of product present in a shredder is regulated by simultaneous control of its feeding and its evacuation.

[0025] In order to limit the power required for its operation, it may be provided that the rotating shredding elements (12) of the shredder are heated at least (1') of the first shredding station (1), at least during the start-up phases of the shredder concerned. For this purpose, the shredding elements of the first shredder (1') or preferably of each shredder (1', 2', 3') are equipped with suitable heating means (heating elements) or mounted on a heating shaft (for example a hollow shaft through which hot oil flows).

[0026] The invention also relates to a thermomechanical treatment process for the purpose of recycling raw materials (RM) mainly in the form of bituminous products formed from elements such as membranes, portions of membranes, shingles or the like, as production, construction site or demolition waste.

[0027] This process comprises a plurality of successive processing steps including grinding, size reduction, heating and separation operations, some of which are carried out in combination, and said processing process being carried out in a continuous or intermittent (batch) overall flow, possibly regulated.

[0028] This process is characterized in that it comprises a first treatment phase corresponding to the process of grinding or fragmenting raw materials (RM) described above.

[0029] Preferably, said raw materials (RM) will have previously been subjected to a controlled selective reconstitution from batches of waste having varied origins and compositions in terms of the rate of presence and nature of bituminous and non-bituminous materials present (in order to have batches each having a known composition).

[0030] For further processing of the treated products from the raw material (RM) grinding or fragmentation process described above, it may be envisaged to implement the processes and facilities described in documents WO 2021 / 213792 and WO 2021 / 213793 on behalf of the applicant.

[0031] The invention also relates, as shown by way of example in [Fig.1] and partially in Figures 2 to 4, to an installation (4) for crushing or fragmenting raw materials (RM) mainly in the form of bituminous products formed from elements of the type membranes, portions of membranes, shingles or the like, as production, construction site or demolition waste.

[0032] This installation essentially comprises at least two, preferably at least three, successive crushing or fragmentation stations (1, 2, 3), configured to reduce the average size of the elements forming the bituminous products (MP, PT1, PT2) to be processed by each station along at least one dimension. These different stations thus form a progressive crushing or fragmentation line, by successive stages.

[0033] This installation (4) also includes, upstream of the first grinding station (1), a raw material (RM) feeding station (5) and, downstream of the last station grinding (3), a treated product evacuation station (6) (PT3), as well as intermediate transfer means (7, 7') of treated products (PT1, PT2) between two consecutive grinding stations (1, 2; 2, 3).

[0034] This installation (4) is characterized in that each of the grinding stations (1,2, 3) comprises a rotary shear shredder (1', 2', 3'), in that it comprises means (8) for regulating the residence times, and therefore the treatment times, of the products (MP, PT1, PT2) during their treatment in each shredder (1', 2', 3'), in order to control heating by shearing of said products (MP, PT1, PT2) and in that the intermediate transfer means (7, 7') of treated products (PT1, PT2), from one grinding station (1, 2) to the next grinding station (2, 3) respectively, are configured to limit heat losses.

[0035] As a beneficial compromise, the installation (4) comprises three consecutive grinding stations (1, 2 and 3), and their respective shredders (1', 2', 3') are preferably calibrated such that the first shredder (1') delivers treated products (PT1) whose constituent elements have a width of at most 100 mm, preferably at most 80 mm, that the second shredder (2') delivers treated products (PT2) whose constituent elements have a width of at most 30 mm, preferably at most 20 mm and that the third shredder (3') delivers treated products (PT3) whose constituent elements have a width of at most 15 mm, preferably at most 12 mm.

[0036] Advantageously, the means (8) for regulating residence times include means for measuring the quantity of product to be processed (MP, PT1, PT2) present in the different shredders (1', 2', 3'), for example in the form of means (8) for continuous weighing of each shredder (1', 2', 3'). These weighing means may, for example, consist of load cells integrated into the support structure or chassis of each shredding station.

[0037] The different shredders (1', 2', 3') are preferably of the same type, the first (1') at least being of a larger size than the others.

[0038] In accordance with an advantageous embodiment of the invention, and as shown in [Fig.5], the shredders (1', 2', 3') each comprise two parallel rotating shafts (13, 13') rotating mutually in opposite directions and equipped with shredding elements (12) of the knife type, the elements of one shaft (13, 13') being interpenetrating with those of the other shaft (13', 13) and scrapers (12') being arranged between two adjacent elements (12) along the shaft (13, 13') considered, the shredder (1') of the first grinding station (1) at least favorably comprising rotating shredding elements (12) equipped with heating means.

[0039] As a concrete, but not limiting, solution for implementing the invention, the shredders (1', 2', 3') may be based on commercially available shredders from the type B850 and B600 of the company BLIK, the first (1') being of type B850 and the second and third (2', 3') being of type B650.

[0040] These known shredders are preferably specifically adapted for the needs of implementing the invention and in particular equipped with various sensor means (temperature of the knives, internal temperature, torque at the axis level,...) allowing their operating condition to be monitored and allowing a central control unit connected to them to control the installation (4).

[0041] To prevent the treated products (PT1, PT2) from sticking, the installation may also include means (9) for spraying mineral oil and / or mineral powder, such as talc, onto the intermediate transfer means (7, 7') for the treated products (PT1, PT2), for example, in the form of belt conveyors with thermal insulation properties. Where applicable, the shredder feed hoppers also have suitable means for preventing the products poured into them from sticking.

[0042] In order to limit bulk and avoid heat loss, the lower outlet of the shredder (2') of the second grinding station (2) can be arranged in the immediate vicinity of the upper inlet (hopper) of the shredder (3') of the third grinding station (3), these two grinding stations (2' and 3') being preferably arranged in a mutually superimposed manner.

[0043] The installation (4) may also include a device (10) for detecting, and where appropriate ejecting, metallic elements or parts present in the processed products (PT2, PT3), located after the second shredder (2') or after the third shredder (3'), for example in the form of a detection and on-the-fly extraction device acting on a passing flow of processed products (PT2, PT3).

[0044] Finally, the shredder (1') of the first grinding station (1) at least is advantageously provided with a crusher (11), which makes it possible to break the arch of raw material (MP) which may form in its feed hopper due to an irregular inlet flow and / or the presence of large elements.

[0045] In relation to a practical construction of the various shredders mentioned above (1', 2', 3'), the latter may result from the following modifications applied to commercially available B850 and B600 shredders:

[0046] - A weighing device (8) is arranged at least under the first crusher (1') of This allows for the continuous weighing of the product contained in the crusher. Furthermore, a tare weight is adjusted to account for any potential clogging.

[0047] - The counter knives of the crushers are equipped with electric heating elements, heating cartridge type.

[0048] - Temperature sensors are placed respectively in each cartridge and at the level of the counter knives. The first serves as a safety feature to limit the temp- Maximum temperature to prevent ignition on parts in contact with the product being treated. The second sensor regulates the heating temperature of the counter knives.

[0049] - Each cartridge is independently controlled by a temperature regulator. The The temperature setpoint can be configured from a process monitoring screen which is part of a central control unit connected to the crushers and controlling the installation (4).

[0050] - Two levels of emergency stop are managed for access to the crushers: the first This is used to cut off the power supply to the motors driving the shafts (13, 13') of the crushers to prevent any risk to the operator. The second level, emergency stop, cuts off all other power sources: thus, operating conditions are maintained after intervention by the operator.

[0051] - A preheating function for the grinders is programmable in the supervisory control system to make them operational as soon as the machine operators arrive.

[0052] - A surveillance camera is placed above each crusher and on the Conveyors at the output of each crusher: they allow the operator to check the behavior of each crusher and, if necessary, correct the feed speeds.

[0053] - The images from all the cameras are recorded on a server and allow to review whether any inappropriate behavior has occurred.

[0054] - Infrared fire safety sensors are placed around the area of crushers and constantly monitors any abnormal temperature rise.

[0055] The size and shape of the chips are highly dependent on the raw material to be ground. However, by adjusting the temperature of the grinders, the residence time in the grinders, and the quantity of material contained in the hopper of the relevant grinder, it is possible to guarantee a virtually consistent chip size at the output of each of said grinders.

[0056] The smaller the chips, the smaller the reinforcement portions within them. This is because thermal conductivity is very low in bitumen. Reducing the chip size also has the advantage of increasing their contact surface area with the heating elements in the mills: thus, the chips heat up faster in the mills.

[0057] The desired temperature for the treated products, at the outlet of the mills, is between 40°C and 70°C. The successive millings through the three mills recommended by the invention considerably modify the shape of the chips: the longer they have been subjected to a high residence time in the mills, the more complex their shape and the more efficient their heat exchange characteristics.

[0058] In relation to the invention, several measures can be envisaged to To maximize heat retention in the chips during transfer between stations: the conveying speed can be adjusted to minimize transfer time; the conveyor belts (7, 7') can be made of thick rubber / polymer materials to reduce heat loss; the conveyor belts (7, 7') can include successive cavities (buckets) that will limit heat loss around the chips; the conveyor belts (7, 7') can be fitted with longitudinal curved partitions to form tunnels. The same applies, of course, to the conveyor belt forming part of the discharge means (6) in [Fig. 1].

[0059] The invention also relates to a thermomechanical processing installation for the purpose of recycling raw materials (RM) mainly in the form of bituminous products formed from elements such as membranes, portions of membranes, shingles or the like, as production, construction site or demolition waste.

[0060] This installation (not shown) includes at least means for grinding, dimensional reduction, heating and separation, these means being arranged to form at least one line for processing and extracting material(s) to be recovered, operating in continuous or intermittent flow, possibly regulated.

[0061] This installation is characterized in that the processing and extraction line or lines comprise a first set of means corresponding to a raw material (RM) crushing or fragmentation installation (4) as described above, said installation (4) comprising where appropriate, or possibly associated with, a site or station for the controlled selective composition of said raw materials (RM), from batches of waste having varied origins and compositions in terms of the rate of presence and nature of bituminous and non-bituminous materials present.

[0062] Preferably, to limit heat losses, the discharge station (6) of the grinding or fragmentation installation (4) directly supplies at least one heated mixer which is also part of said treatment installation.

[0063] The thermomechanical processing installation according to the present invention may in particular include, following a raw material (RM) grinding or fragmentation installation (4) as described above, an installation as described in documents WO 2021 / 213792 and WO 2021 / 213793 on behalf of the applicant.

[0064] Of course, the invention is not limited to the embodiment described and shown in the accompanying drawings. Modifications remain possible, particularly with regard to the composition of the various elements or by substitution of technical equivalents, without departing from the scope of protection of the invention.

Claims

Claims

1. Method for grinding or fragmenting raw materials (MP) mainly in the form of bituminous products, for example formed from elements of the membrane type, portions of membranes, shingles or the like, in particular as production, construction or demolition waste, this method essentially consisting of treating these products (MP) by means of at least two successive grinding or fragmentation stations (1, 2, 3), so as to reduce each time the average size of the elements forming the successively treated bituminous products (PT1, PT2, PT3), method characterized in that it consists of implementing a shredder with rotary shears (1', 2', 3') at each of the grinding stations (1, 2, 3), preferably at least three in number, to control heating by shearing of the products (MP, PT1, PT2) during their treatment by regulating their duration of stay, and therefore processing, in each shredder (1',2', 3') and to transfer the treated products (PT1, PT2), from a grinding station (1, 2) to the grinding station (2, 3) respectively consecutive, while limiting heat losses.,

2. Grinding method according to claim 1, characterized in that it consists of providing three grinding stations (1, 2 and 3) and calibrating the respective shredders (1', 2', 3') in such a way that the first shredder (1') delivers treated products (PT1) whose constituent elements have a width of at most 100 mm, preferably at most 80 mm, that the second shredder (2') delivers treated products (PT2) whose constituent elements have a width of at most 30 mm, preferably at most 20 mm and that the third shredder (3') delivers treated products (PT3) whose constituent elements have a width of at most 15 mm, preferably at most 12 mm.

3. Grinding method according to claim 1 or 2, characterized in that it consists of regulating the residence time of the products (MP, PT1, PT2) being treated in each shredder (1', 2', 3') as a function of the quantity of product to be treated (MP, PT1, PT2), for example determined by continuous weighing of the first shredder (1') at least, preferably of each shredder (1', 2', 3').

4. A grinding method according to any one of claims 1 to 3, ca-

5.

6. characterized in that it consists of heating the rotary shredding members (12) at least of the shredder (1') of the first grinding station (1), at least during the start-up phases of the shredder concerned. Thermomechanical treatment method for the purpose of recycling raw materials (RP) mainly in the form of bituminous products formed from elements of the membrane type, portions of membranes, shingles or the like, as production, construction or demolition waste, said method comprising a plurality of successive treatment steps including grinding, dimensional reduction, heating and separation operations, some of which are carried out in a combined manner, and said treatment method being carried out in a continuous or intermittent overall flow, where appropriate regulated,process characterized in that it comprises a first treatment phase corresponding to the process of grinding or fragmenting raw materials (MP) according to any one of claims 1 to 4, said raw materials (MP) having preferably been previously subjected to controlled selective recomposition from batches of waste having varied origins and compositions, in terms of the rate of presence and nature of bituminous and non-bituminous materials present., Installation (4) for crushing or fragmenting raw materials (MP) mainly in the form of bituminous products formed of elements of the membrane type, portions of membranes, shingles or the like, as production, construction or demolition waste, this installation essentially comprising at least two successive crushing or fragmentation stations (1, 2, 3), configured to reduce the average size according to at least one dimension of the elements forming the bituminous products (MP, PT1, PT2) to be treated by each of them, said installation (4) also comprising, upstream of the first crushing station (1), a station (5) for supplying raw materials (MP) and, downstream of the last crushing station (3), a station (6) for discharging the treated products (PT3), as well as intermediate transfer means (7, 7') of treated products (PT1, PT2) between two consecutive crushing stations (1, 2;2, 3), installation (4) characterized in that each of the crushing stations (1, 2, 3), preferably at least three in number, comprises a shredder with rotary shears (1', 2', 3'), in that it comprises means (8) for regulating the residence times, and therefore treatment times, of the; products (MP, PT1, PT2) during their processing in each shredder (1', 2', 3'), with a view to controlling heating by shearing of said products (MP, PT1, PT2) and in that the intermediate transfer means (7, 7') of processed products (PT1, PT2), from a grinding station (1, 2) to the respective following grinding station (2, 3), are configured to limit heat losses.

7. Crushing or fragmentation installation (4) according to claim 6, characterized in that it comprises three consecutive crushing stations (1, 2 and 3), the respective shredders (1', 2', 3') of which are calibrated in such a way that the first shredder (1') delivers treated products (PT1) whose constituent elements have a width of at most 100 mm, preferably at most 80 mm, that the second shredder (2') delivers treated products (PT2) whose constituent elements have a width of at most 30 mm, preferably at most 20 mm and that the third shredder (3') delivers treated products (PT3) whose constituent elements have a width of at most 15 mm, preferably at most 12 mm.

8. Crushing or fragmentation installation (4) according to any one of claims 6 and 7, characterized in that the means (8) for regulating the residence times comprise means for measuring the quantity of product to be treated (MP, PT1, PT2) present in the different shredders (1', 2', 3'), for example in the form of means for continuous weighing of each shredder (1', 2', 3').

9. Crushing or fragmentation installation (4) according to any one of claims 6 to 8, characterized in that the shredders (1', 2', 3') each comprise two parallel rotating shafts, rotating mutually in opposite directions and provided with knife-type shredding members, the members of one shaft being interpenetrating with those of the other shaft and scrapers being arranged between two neighboring members along the shaft in question, and in that the shredder (1') of the first crushing station (1) at least comprises rotating shredding members (12) equipped with heating means.

10. Crushing or fragmentation installation (4) according to any one of claims 6 to 9, characterized in that it also comprises means (9) for spraying mineral oil and / or mineral powder, such as for example talc, onto the means (7, 7') for intermediate transfer of the treated products (PT1, PT2), for example in the form of belt conveyors with thermal insulation properties.

11. Crushing or fragmentation installation (4) according to any one of claims 6 to 10, characterized in that the lower outlet of the shredder (2') of the second crushing station (2) is arranged in the immediate vicinity of the upper inlet of the shredder (3') of the third crushing station (3), these two crushing stations (2' and 3') being preferably arranged in a mutually superimposed manner.

12. Crushing or fragmentation installation (4) according to any one of claims 6 to 11, characterized in that it also comprises a device (10) for detecting, and where appropriate ejecting, the metal elements or parts present in the treated products (PT2, PT3), located after the second shredder (2') or after the third shredder (3'), for example in the form of a device for detecting and extracting on the fly acting on a moving flow of treated products (PT2, PT3).

13. Crushing or fragmentation installation (4) according to any one of claims 6 to 12, characterized in that the shredder (1') of the first crushing station (1) at least is provided with a rammer (11).

14. Thermomechanical treatment installation for the purpose of recycling raw materials (MP) mainly in the form of bituminous products formed from elements of the membrane type, portions of membranes, shingles or the like, as production, construction or demolition waste, said installation comprising at least means for grinding, dimensional reduction, heating and separation, these means being arranged to form at least one line for processing and extracting material(s) to be recovered, operating in continuous or intermittent flow, where appropriate regulated, installation characterized in that the or each processing and extraction line comprises a first set of means corresponding to an installation (4) for grinding or fragmenting raw materials (MP) according to any one of claims 6 to 13, said installation (4) comprising where appropriate, or being possibly associated with,a site or station for controlled selective composition of said raw materials (RM), from batches of waste with varied origins and compositions, in terms of the rate of presence and nature of bituminous and non-bituminous materials present.

15. Treatment installation according to claim 14, characterized in that the evacuation station (6) of the crushing or fragmentation installation (4) directly supplies at least one heating mixer also forming part of said treatment facility.

Citation Information

Patent Citations

  • Installation and method for treating composite materials based on thermoplastic materials

    WO2021213792A1

  • Heatable mixer for composite products

    WO2021213793A1

  • Recycling plant for the cold reduction of rubber products, comprises a shredder, an advancing unit, cooling zones, a reducing unit, and a control unit

    DE10357968A1

  • Rubber reducing and recycling system

    US5904305A

  • Process for recycling a bituminous waste product such as a bituminous waste membrane product

    WO2021104652A1