Formwork for the construction of a building structure and building structural element incorporating such formwork

Plaster formwork with 50% dry plaster powder and 50% water composition accelerates concrete drying to 24 hours, providing structural integrity and insulation, addressing the challenge of lengthy construction times and cumbersome prefabricated elements.

FR3148050A1Pending Publication Date: 2024-10-25ZORMATI MOLKA
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
FR2023004001
Authority / Receiving Office
FR · FR
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-20
Publication Date
2024-10-25

AI Technical Summary

Technical Problem

The construction phase of concrete buildings is lengthy due to the immutable drying time of concrete, which cannot be accelerated without compromising structural solidity and compliance, and prefabricated structural elements are cumbersome and costly.

Method used

The use of plaster formwork with a 50% dry plaster powder and 50% water composition that absorbs moisture from fresh concrete, reducing drying time to around 24 hours and serving as a permanent structural element.

Benefits of technology

The plaster formwork accelerates concrete drying, eliminates the need for dismantling, and provides structural integrity, thermal and sound insulation, while allowing immediate continuation of construction operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 00000000_0000_ABST
    Figure 00000000_0000_ABST
Patent Text Reader

Abstract

Formwork for constructing a building structure and building structural element comprising such formwork. One aspect of the invention relates to formwork (100) for constructing a building structure (200, 300), wherein: the formwork comprises two longitudinal walls (110) substantially parallel to each other and two transverse walls (120) extending between the two longitudinal walls to form a base suitable for receiving fresh concrete and pierced reinforcing bars; and the formwork (100) is a hollow, disposable piece made of plaster with a proportion of substantially 50% dry plaster powder and 50% water. Another aspect of the invention relates to a building structural element (200, 300), comprising several formworks (100) according to the first aspect, assembled with each other vertically and / or horizontally. Figure to be published with the abbreviation: Figure 5
Need to check novelty before this filing date? Find Prior Art

Description

Title of the invention: Formwork for the construction of a building structure and building structure element comprising such formwork TECHNICAL FIELD OF THE INVENTION

[0001] The present invention relates to formwork for the construction of a building structure such as a wall, a floor or a column, designed to form a base onto or into which fresh concrete can be poured.

[0002] The invention finds applications in the field of construction, for the construction of a concrete building structure, accelerated compared to conventional techniques. TECHNOLOGICAL BACKGROUND OF THE INVENTION

[0003] It is known in the construction field that the construction phase of the building structure, such as load-bearing walls and floors, is a relatively long phase that property developers and builders strive to reduce as much as possible. Indeed, the faster a home is built, the faster it can be inhabited and therefore the faster it is financially profitable. In a period of housing shortage, builders and developers are therefore looking for all possible solutions to speed up the construction of housing. However, while it is possible to speed up certain administrative phases and increase the number of workers to speed up the construction of a building, certain technical facts are immutable and cannot be accelerated without jeopardizing the solidity and / or conformity of the building.

[0004] For example, for buildings with a concrete structure, one of the immutable technical facts is the drying time of the concrete. Indeed, concrete is a material made up of cement, sand, gravel and water, mixed together using a cement mixer or a mixer. As soon as the cement grains come into contact with the water, chemical reactions begin. Initially, the chemical reactions are slow: the concrete is then fresh and workable, which allows it to be filled into formwork or spread on a floor-type structure. The chemical reactions, called hydration reactions, subsequently cause the concrete to gradually dry out and harden. These chemical reactions continue for several days and even several weeks. It is generally considered that, if the concrete has a setting time of a few hours, its strength, called "strength class", is only reached after a minimum period of 28 days.It is therefore considered, in the construction industry, that 28 days from pouring are necessary for the concrete. to be sufficiently dried and hardened to allow construction to continue, such as the completion of the second work.

[0005] To speed up the construction of a building, builders and property developers have chosen to use so-called "kit" structures, with prefabricated structural elements, i.e. manufactured off-site, then brought back, mounted and assembled on-site. However, some of the prefabricated structural elements can be large; they are then difficult to transport and generate high transport costs. In addition, for multi-story buildings, the dimensions of the structural elements can be such that it is even impossible to prefabricate them.

[0006] There is therefore a real need for a technique enabling the rapid manufacture of structural elements of a building. Summary of the invention

[0007] To address the above-mentioned problems of concrete drying, the applicant proposes a plaster formwork which not only allows the concrete to dry quickly but also eliminates the need for certain finishing operations. The applicant also proposes building structure elements made using such formwork.

[0008] The term "formwork" refers to a structure in or onto which concrete is poured so that it takes the desired shape and is protected during the drying time. Generally, formwork is a temporary structure which, once the concrete has dried and consolidated, is removed. In the following description, those skilled in the art will understand that, unlike the state of the art, the formwork according to the invention is not temporary and that it remains permanently in the structure. Indeed, the formwork according to the invention is a "lost" formwork, that is to say, non-removable, which is an integral part of the structure of the building.

[0009] In the description, the term "internal" or "interior" refers to surfaces or areas located within the recess or cavity of the formwork, as opposed to the term "external" or "exterior" which refers to surfaces or areas located on the contour of the formwork.

[0010] According to a first aspect, the invention relates to a formwork for producing a building structure, the formwork comprising two longitudinal walls substantially parallel to each other and two transverse walls extending between the two longitudinal walls to form a base capable of receiving fresh concrete, characterized in that the formwork is a hollow, disposable part, made of plaster with a proportion of approximately 50% dry plaster powder and 50% water.

[0011] This formwork has the advantage of reducing the drying time of the concrete by ab sorption of the moisture contained in the said concrete. Indeed, plaster being a porous material, it absorbs the moisture contained in the concrete, which allows the concrete to dry out. This formwork also has the advantage of constituting a structural element with a smooth and flat surface, on which the decorative elements can be placed directly, without plaster.

[0012] In addition to the characteristics which have just been mentioned in the preceding paragraph, the formwork according to one aspect of the invention may have one or more additional characteristics among the following, considered individually or according to all technically possible combinations: • it has two open faces, each designed to communicate with the open face of another formwork, stacked. • at least the longitudinal walls comprise, at their ends, a male or female stacking overhang for fitting the longitudinal walls of at least one other formwork, one end of the longitudinal walls comprising a male stacking overhang, the other end of the longitudinal walls comprising a female stacking overhang. • the transverse walls comprise, on their outer faces, a male or female assembly system for fitting at least one transverse wall of another identical formwork, one outer face comprising a male assembly element, the other outer face comprising a female assembly element. • the longitudinal walls and the transverse walls are of identical dimensions, the formwork having a substantially hollow, right square prism shape. • the longitudinal walls have a length greater than the length of the transverse walls, the formwork having a substantially straight, hollow paving stone shape. • the transverse walls are angular with a V-shaped section, the formwork having a substantially irregular hexagonal prism shape, at least partially hollow.

[0013] A second aspect of the invention relates to a building structure element, characterized in that it comprises several formworks according to the first aspect, assembled with each other vertically and / or horizontally.

[0014] This structural element, consisting essentially of formwork according to the first aspect, has the same advantages as those stated previously for the formwork according to the first aspect.

[0015] A "vertical structure" is a structure extending mainly in a plane extending between the earth and the sky; a vertical structure is built in stacking formwork on top of each other from the ground. A horizontal structure is a structure that extends primarily in a plane parallel to the ground; a horizontal structure is constructed by positioning formwork next to each other on the ground or in a plane parallel to the ground. A horizontal structure therefore extends in a plane perpendicular to a vertical structure.

[0016] In addition to the characteristics which have just been mentioned in the preceding paragraph, the structural element according to the second aspect of the invention may have one or more complementary characteristics among the following, considered individually or according to all technically possible combinations: • the formwork, in the form of roughly straight paving stones, is stacked on top of each other and assembled against each other so as to form a wall, fresh concrete being poured inside said formwork. • the formwork, in the form of irregular hexagonal prisms, is placed next to each other between beams to form a floor, with fresh concrete being poured over the longitudinal walls of the formwork. • the formwork, roughly in the shape of straight square prisms, is stacked on top of each other to form a column, with fresh concrete being poured inside the formwork. • structural elements, such as twisted rebars, are housed inside the stacked formwork. BRIEF DESCRIPTION OF THE FIGURES

[0017] Other advantages and characteristics of the invention will appear on reading the following description, illustrated by the figures in which:

[0018] [Fig.l] represents, in a perspective view, a first example of formwork according to the invention;

[0019] [Fig.2] represents, in a perspective view, a second example of formwork according to the invention;

[0020] [Fig. 3] represents, in a perspective view, a third example of formwork according to the invention;

[0021] [Fig.4] represents, in a perspective view, an example of a vertical structural element, produced with formwork according to the invention;

[0022] [Fig. 5] represents, in a perspective view, another example of a vertical structural element, produced with formwork according to the invention; and

[0023] [Fig.6] represents, in a perspective view, an example of a horizontal structural element, produced with formwork according to the invention.

[0024] In the figures, identical elements are identified by identical references. For reasons of readability of the figures, the size scales between the elements represented are not respected. DETAILED DESCRIPTION

[0025] An example of the embodiment of a formwork for a building structure making it possible to accelerate the drying of concrete is described in detail below, with reference to the attached drawings. This example illustrates the characteristics and advantages of the invention. It is however recalled that the invention is not limited to this example.

[0026] Three examples of formwork 100 (100a, 100b, 100c) for building structures are shown in Figures 1, 2 and 3. The first example, shown in [Fig.l], is a formwork 100a for manufacturing a vertical structural element such as a wall. The formwork 100a is also called a wall formwork. The second example, shown in [Fig.2], is a formwork 100b for manufacturing a vertical structural element such as a column. The formwork 100b is also called a column formwork. The third example, shown in [Fig.3], is a formwork 100c for manufacturing a horizontal structural element such as a floor. The formwork 100c is also called a floor formwork.

[0027] Whatever the example, the formwork 100 is made from a plaster comprising a proportion of 50% dry plaster powder and 50% water. The dosage of dry plaster powder in the water varies depending on the shape and dimensions of the formwork but the proportion is always 50% plaster powder and 50% water, to within a few hundredths. Indeed, plaster is a material in powder form, obtained by cooking and grinding gypsum. The plaster powder, once mixed with water, forms a moldable paste which can be shaped using a mold. When drying, the plaster paste becomes compact and hard. In the invention, the plaster is mixed and molded to form one of the formworks 100 as shown in Figures 1, 2 and 3.

[0028] Whatever the example considered, the formwork 100 comprises two longitudinal walls 110 and two transverse walls 120 extending between the two longitudinal walls 110. The two longitudinal walls 110 are substantially parallel to each other. The two transverse walls 120 are opposite each other and each housed between two ends of the longitudinal walls. The longitudinal walls 110 and the transverse walls 120 together form a polyhedron-shaped base, at least partially hollow.

[0029] In the embodiment of [Fig.l], the longitudinal walls 110 of the formwork 100a have a length L, greater than the width 1 of the transverse walls 120; the height h of the longitudinal walls is identical to the height of the transverse walls. The polyhedron shape of the formwork 100a is then a straight block. In other words, in this embodiment, the formwork 100a has a rectangular section with sides L and 1. The formworks 100a of [Fig.l], preferably designed for the construction of walls, may all have identical dimensions or, on the contrary, dimensions that vary from one formwork to another in order to adapt to needs; in particular, the length L of the longitudinal walls of the wall formworks 100a may vary from one formwork to another so as to allow staggered installation of said formworks.

[0030] In the embodiment of [Fig.2], the longitudinal walls 110 and the transverse walls 120 of the formwork 100b are of the same length, for example length 1, and of the same height, for example h. The polyhedron shape of the formwork 100b is then a right square prism, or even a cube when the height h of the formwork is equal to the length 1 of the sides. The formwork 100b then has a square section.

[0031] In the embodiments of Figures 1 and 2, the formworks 100 are hollow. They are each adapted to receive fresh concrete within it, the fresh concrete then taking the internal shape of the formwork. In other words, each formwork 100a or 100b of the examples of Figures 1 and 2 comprises a cavity 160 adapted to be filled with concrete. Indeed, the formwork constitutes, for the concrete, a sort of mold making it possible to give said concrete the desired shape. Each formwork 100 comprises two open faces 150 facing each other; the open faces 150 are the horizontal faces of the formworks, each open face 150 allowing communication between the interior of the formwork and the interior of another vertically adjacent formwork.Thus, when several formworks 100 are stacked on top of each other, the fresh concrete poured into the last stacked formwork (i.e. the topmost formwork in the stack) can flow successively into each of the other stacked formworks, until the entire column of stacked formworks is filled with fresh concrete. The concrete can then be poured vertically.

[0032] Some formworks, such as that of the example in [Fig. 1], may also comprise at least one lateral orifice 170 formed in each of the two longitudinal 110 or transverse 120 walls. The orifice 170 of each of the vertical faces (longitudinal walls or transverse walls) of a formwork is arranged opposite the orifice 170 of a vertical face 110 or 120 of the adjacent formwork. In the example in [Fig. 1], the formwork 100a comprises a lateral orifice 170 in each of the transverse walls 120, the two orifices 170 of the formwork 100a being opposite each other. Thus, when several formworks are arranged side by side, for example to form a wall, the cavities 160 of these formworks are in communication with each other. This communication of the cavities 160, via the lateral orifices 170, can allow the passage of the twisted rebar and / or the pouring of fresh concrete from one formwork to another.The concrete can then be poured horizontally.

[0033] In certain embodiments of the formwork 100, the longitudinal walls 110 and / or the transverse walls 120 are provided, at their ends, with an overhang. stacking overhang 130 male or female. The stacking overhang 130 is designed to form, at the upper 100s and lower 100i ends of the formwork, a nesting system allowing a formwork to be partially nested in another adjacent formwork. The stacking overhang 130 comprises, for example, a female overhang 132 and a male overhang 134, the female overhang and the male overhang being of complementary shapes to each other to nest in each other. For example, the female overhang 132 may be a notch or a groove made on all or part of the periphery of one end of the formwork, for example the upper 100s end or the lower 100i end of the formwork. In the example of [Fig.l], the female overhang 132 is a notch extending over the entire periphery of the upper end 100s of the formwork 100a.Alternatively, the female overhang 132 may extend only to the end of the longitudinal walls 110 or only to the end of the transverse walls 120 of the formwork. The male overhang 134 may be a vertical projection or a projection made on all or part of the periphery of one end of the formwork, for example the upper end 100s or the lower end 100i of the formwork. In the example of [Fig.2], the male overhang 134 is a projection extending over the entire periphery of the upper end 100s of the formwork 100b. Alternatively, the male overhang 134 may extend only to the end of the longitudinal walls 110 or only to the end of the transverse walls 120 of the formwork.The person skilled in the art will understand that the formworks to be stacked are structurally identical to each other and that, if the female overhang 132 extends to the upper end 100s of the formwork, then the male overhang 134 extends to the lower end 100i of the same formwork, or vice versa (the female overhang at the lower end 100i and the male overhang at the upper end 100s), so that the male overhang 134 of one formwork can fit into the female overhang 132 of the adjacent, identical, stacked formwork.

[0034] In certain embodiments of the formwork 100, the longitudinal walls 110 and / or the transverse walls 120 may be equipped, on their outer faces, with an assembly system 140. The assembly system 140 comprises two separate assembly elements, designed to be inserted into one another and thus ensure the coupling of two neighboring formworks. The assembly system 140 comprises, for example, a male assembly element and a female assembly element, the male assembly element and the female assembly element being of complementary shapes to one another. For example, the male assembly element, an example of which is represented by the reference 144 in [Fig. 1], may for example be a rib extending vertically along one of the longitudinal walls 110 or transverse walls 120 of the formwork 100a.The female assembly element (not visible in the figures) may be, for example, a groove of complementary shape and dimensions to the male assembly element. If the male assembly element is po . located on a transverse wall 120 of the formwork, as in the example of [Fig.l], then the female assembly element is positioned on the other transverse wall 120 of the formwork. Thus, all the formworks can be identical and assembled with each other, the male assembly element of one formwork being assembled with the female assembly element of the neighboring formwork.

[0035] Those skilled in the art will understand that the stacking overhangs 130 make it possible to vertically assemble two or more identical formworks 100, and that the assembly elements 140 make it possible to horizontally assemble two or more identical formworks 100. Thus, the examples of formworks 100a and 100b of FIGS. 1 and 2 can be assembled either vertically, or horizontally, or both vertically and horizontally to form vertical structural elements, such as walls or columns. Formworks 100b designed to construct only one column preferably comprise only stacking overhangs 130, the outer surfaces of the longitudinal 110 and transverse 120 walls being smooth and devoid of any assembly system.On the contrary, formworks 100b designed to construct a wall comprise stacking overhangs 130 ensuring the stacking of the formworks and at least one assembly element on one of the exterior surfaces of a longitudinal or transverse wall to allow the assembly of said formworks 100b with other formworks such as formworks 100a.

[0036] In the embodiment of [Fig. 3], the transverse walls 120 of the formwork 100c are angular walls 122 / 124, unlike the embodiments of FIGS. 1 and 2 where the transverse walls - just like the longitudinal walls - are rectilinear. In the embodiment of [Fig. 3], the transverse walls 120 comprise two surfaces 122 and 124 forming a non-flat angle with each other. The measurement of the angle a, formed between the surfaces 122 and 124 of a transverse wall 120, is a function in particular of the width 1 of the transverse wall 120 (i.e. the distance between the two longitudinal walls 110) and of the length L of these longitudinal walls 110. In the example of [Fig. 3], the angle a is approximately 90°. The 122 / 124 angular walls, also called pignets, are designed to be inserted into beams, as explained below.With its two longitudinal walls 110 and its two angular walls 122 / 124, the formwork 100c according to the embodiment of [Fig.3] has a substantially non-regular hexagonal prism shape. It therefore has a non-regular hexagonal section; the transverse walls 122 / 124 have a V-shaped section. The formwork 100c according to this embodiment has at least one cavity 165 adapted to receive electrical, mechanical and / or hydraulic devices or any other operating device of the building. Those skilled in the art will understand that the cavity(ies) 165 have . dimensions adapted to the devices to be passed through but that these dimensions are sufficiently small so as not to hinder the solidity of the floor made from these formworks, as explained below. In the example of [Fig.3], the formwork 100c comprises two cavities 165, of tubular shapes, adapted to receive in particular electrical wiring.

[0037] Examples of wall formwork 100a, column formwork 100b and floor formwork 100c have been described previously. Those skilled in the art will understand, however, that features described for one example of formwork may be adapted to another type of formwork, depending on the needs and in particular the structural element to be constructed. For example, the assembly member 140 described for the wall formwork may be adapted to the column formwork (for example to assemble two column formworks together or a column formwork with a wall formwork) or to the floor formwork (for example to assemble two floor formworks together). Similarly, the stacking overhang 130 described for the wall and column formworks may be adapted to the floor formworks to ensure that the floor formworks fit together.

[0038] Whatever the embodiment considered, the formwork 100 has the advantage of drying the fresh concrete in contact with said formwork, by absorbing water. Indeed, plaster, once dry, is a hydrophilic material capable of absorbing water. The plaster formwork 100 is therefore capable of absorbing a large part of the water contained in the fresh concrete and gradually releasing this water into the air. Tests have shown that a plaster formwork as described above can dry the concrete with which it is in contact in about ten minutes and reaches its maximum strength in about 24 hours (instead of 28 days for conventional constructions).

[0039] Examples of building structural elements, constructed with formwork according to the invention, are shown in Figures 4, 5 and 6. [Fig. 4] shows an example of a vertical structural element 200 consisting of two posts 210 and a wall 220. [Fig. 5] shows the same vertical structural element as [Fig. 4] but during the construction of said structural element. The two posts 210 of the structural element 200 are constructed from several formworks 100b (of the example of [Fig. 2]) stacked on top of each other. The wall 220 is constructed from several formworks 100a (of [Fig. 1]) stacked on top of each other and assembled next to each other. In this example, the formworks 100b of the posts are each provided with an assembly element 140 ensuring the assembly of each formwork 100b of the post with one or more formworks 100a of the wall 220.The formwork 100a of the wall 220 may comprise identical longitudinal wall lengths L or, as seen in [Fig.4], different lengths L so that they can be placed in a staggered pattern on top of each other, a staggered arrangement having the advantage of being . structurally stronger than a single stack.

[0040] Once constructed, i.e. when the formworks 100a and 100b are stacked, the columns 210 and the wall 220 are ready to receive the fresh concrete. The fresh concrete is then poured into the last formworks 100a or 100b of the stack (i.e. the formworks furthest from the ground), in the direction of gravity. The fresh concrete then flows from one formwork to the other via the openings 150 of each of the formworks, until the stacked formwork structure is filled with fresh concrete. In some embodiments, structural elements are positioned inside the formworks, such as for example twisted rebars, of all kinds of diameters. The fresh concrete is then poured into the formworks, around these structural elements.

[0041] [Fig. 6] shows an example of a horizontal structural element 300, consisting of a plurality of floor formworks 100c. Several floor formworks 100c are stacked on top of each other horizontally between beams 320. In other words, the floor formworks 100c are juxtaposed against each other so as to form a line of formworks 310 installed between two beams arranged parallel to each other. Indeed, for the construction of a floor, for example a ceiling or any other platform, beams 320 are positioned and fixed in a horizontal plane and floor formwork 100c are inserted one after the other by sliding between the two beams 320. The floor formwork 100c is, in particular, installed between two beams 320 by sliding each set of surfaces 122 / 124 forming a transverse wall 120, inside one of the two beams 320.The floor formworks 100c are positioned juxtaposed one after the other; the cavities 165 of the formworks 100c then communicate with each other so as to form one or more conduits passing through the horizontal structural element 300 from one side to the other. The horizontal structural element 300, for example a floor or a ceiling, then comprises, between two beams 320, as many conduits as a floor formwork 100c comprises cavities 165, each of these conduits extending parallel to the beams 320.

[0042] Once constructed, that is to say when the formworks 100c are housed in the beams, the floor or ceiling 300 is ready to receive a welded mesh as well as the fresh concrete. Before pouring the concrete, shims (not visible in the figures) are placed on the surface formed by the juxtaposed formworks and then a welded mesh is positioned resting on the shims. The fresh concrete can then be poured onto the welded mesh, the concrete enveloping said welded mesh and covering the upper surface of the juxtaposed formworks 100c. Electrical or hydraulic construction elements can then be inserted inside the conduits formed by the cavities 165.

[0043] Several embodiments of formwork have been described previously to allow the rapid construction of walls, floors and / or columns. Those skilled in the art may produce other forms of formwork, for similar or different applications, based on the characteristics of the formwork described above. Angular formwork may, for example, be manufactured to create the corners of building walls. Such angular formwork may, for example, have a cross-section in the shape of a right angle and comprise two external walls forming a right angle together, two internal walls forming a right angle together and two transverse walls each connecting an external wall and an internal wall.As in the examples of figures 1, 2 and 3, the angular formwork may include a cavity (depending on the shape of the external and internal walls, i.e. in the shape of a square) capable of receiving twisted reinforcing bars and / or fresh concrete; it may also include openings on the horizontal faces and / or orifices on the transverse faces to allow the passage of twisted reinforcing bars, or other structural parts, and the pouring of concrete vertically and / or horizontally.

[0044] Other forms of formwork can also be produced, such as arched formwork (whose section forms an arc of a circle) to produce rounded walls, circular formwork (whose section is round or with a crown shape) to produce columns, etc.

[0045] A structural element as described above has the advantage of drying out quickly, on average in 24 hours, because the water contained in the fresh concrete is absorbed by capillarity by the plaster formwork 100 which themselves gradually release the water into the air. The desired level of solidity for the structural element is achieved as soon as the concrete is dried. Construction operations can therefore continue quickly after the structural element has been constructed, i.e. approximately 24 hours later (instead of several weeks for a conventional concrete construction).

[0046] Not only does the structural element described above allow the concrete to dry quickly, but it also has the advantage of not requiring any formwork dismantling operation. Indeed, for a conventional concrete construction, when the concrete is dried, it is necessary to dismantle the formwork to release the concrete structure; however, this formwork dismantling operation requires labor and time. The structural element constructed with formwork according to the invention therefore offers additional time savings and financial savings in terms of labor since the formwork is so-called lost formwork which is an integral part of the structural element.

[0047] As explained previously, the formworks 100 of all embodiments are lost formworks which remain in place within the structural element 200 or 300. Since these formworks 100 are made of plaster and plaster is a smooth material frequently used as a coating or covering for interior masonry, the elements structural elements made with the plaster formwork according to the invention do not need to be coated with plaster or any other coating layer intended to smooth the concrete structure. Although being made of concrete, the structural elements described above are, by the manufacturing technique, directly coated with a plaster material which can be used as a coating. The formwork 100 therefore allows an additional saving in terms of construction time, by avoiding the installation of a coating layer on the surface of the structural element.

[0048] The plaster formwork 100 also has additional advantages in terms of insulation. Indeed, plaster is a material known for its sound insulation and thermal insulation properties. Leaving the plaster formwork in place in the concrete structural element therefore improves both the thermal insulation and the sound insulation of the structure.

[0049] A concrete structure, made with lost plaster formwork as described above, thus offers numerous advantages, in addition to the main advantage of rapid drying of the concrete. The invention therefore makes it possible to meet the need to speed up the construction of buildings.

Claims

Claims

1. Formwork (100) for producing a building structure (200, 300), the formwork comprising two longitudinal walls (110) substantially parallel to each other and two transverse walls (120) extending between the two longitudinal walls to form a base capable of receiving fresh concrete, characterized in that the formwork (100) is a hollow, disposable part, made of plaster with a proportion of substantially 50% dry plaster powder and 50% water.

2. Formwork according to claim 1, characterized in that it comprises two open faces (150), each designed to communicate with the open face of another formwork, stacked.

3. Formwork according to claim 1 or 2, characterized in that at least the longitudinal walls (110) comprise, at their ends, a male or female stacking overhang (130) for fitting the longitudinal walls of at least one other formwork, one end of the longitudinal walls comprising a male stacking overhang (134), the other end of the longitudinal walls comprising a female stacking overhang (132).

4. Formwork according to any one of claims 1 to 3, characterized in that the transverse walls (120) comprise, on their outer faces, a male or female assembly system (140) for fitting at least one transverse wall of another formwork, one outer face comprising a male assembly element (144), the other outer face comprising a female assembly element.

5. Formwork according to any one of claims 1 to 4, characterized in that the longitudinal walls (110) and the transverse walls (120) are of identical dimensions, the formwork (100b) having substantially the shape of a right, hollow square prism.

6. Formwork according to any one of claims 1 to 4, characterized in that the longitudinal walls (110) have a length greater than the length of the transverse walls (120), the formwork (100a) having substantially the shape of a straight, hollow block.

7. Formwork according to any one of claims 1 to 4, characterized in that the transverse walls (120) are angular with a V-shaped section, the formwork (100c) having substantially the shape of a non-regular hexagonal prism, at least partially hollow.

8. Building structure element (200, 300), characterized in that it comprises several formworks (100) according to any one of claims 1 to 7, assembled with each other vertically and / or horizontally.

9. Structural element according to claim 8, characterized in that structural elements, such as twisted rebars, are housed inside the assembled formwork (100a, 100b).

10. Structural element according to claim 8 or 9, characterized in that the formwork (100a), in the form of substantially straight paving stones, are stacked on top of each other and assembled against each other so as to form a wall (220), fresh concrete being poured inside said formwork.

11. Structural element according to claim 8 or 9, characterized in that the formwork (100c), in the form of substantially irregular hexagonal prisms, are juxtaposed next to each other, between beams (320) so as to form a floor (300), fresh concrete being poured above the longitudinal walls (110) of the formwork.

12. Structural element according to claim 8 or 9, characterized in that the formwork (100b), in the form of substantially straight square prisms, are stacked on top of each other so as to form a post (210), fresh concrete being poured inside the formwork.

Citation Information

Patent Citations

  • Gypsum block-based assembled wall building method and gypsum block

    CN113047470A

  • Assembled is hollow block of gypsum for non -bearing wall

    CN207228464U

  • Wall formed by staggered stacking of plaster blocks, and plaster block for use in such a wall

    EP0115886A1