Underpass construction method
The method addresses the challenge of forming a larger hollow cross-sectional underground space in urban areas by using a narrow starting shaft to install and integrate precast concrete unit boxes, enabling efficient construction of a box structure beneath existing structures without needing a working shaft on the arrival side.
Patent Information
- Application Number
- JP2023056466
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-30
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2043-03-30
AI Technical Summary
Existing underpass construction methods face challenges in forming a larger hollow cross-sectional underground space in urban areas where a narrow working shaft limits the installation of necessary equipment and structures, preventing efficient formation of a box structure below existing structures.
The method utilizes a narrow starting shaft with a working space width of less than the planned installation area to install and integrate precast concrete unit boxes, forming a box structure by connecting and pushing them across the ground below the existing structure, using a mirror part ground improvement and sequential removal of pipe members to create a box-shaped roof and underground space.
This approach allows efficient formation of an underground space with a larger cross-section by working only from a narrow starting shaft, without requiring a working shaft on the arrival side, thereby facilitating the construction of a box structure that crosses beneath existing structures.
Smart Images

Figure 2024143678000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to an underpass construction method, and more particularly to an underpass construction method for forming an underground space using a box structure in the ground below an existing structure by working only from a narrow starting shaft with a short working space width. [Background technology]
[0002] The underpass method is adopted as a method for forming an underground space that crosses existing structures such as existing railways and roads in the ground below these structures, and known methods include the R&C method (registered trademark) (see, for example, Patent Document 1) and the SFT method (registered trademark) (see, for example, Patent Document 2). The underpass method forms a top box roof and a side box roof that support the existing structure from below by installing box-shaped pipe members in series in the ground below the existing structure where the underground space is to be formed, and then replaces the formed top box roof and side box roof with a box structure having a rectangular cross-sectional shape by propelling them into the ground below the existing structure, thereby forming an underground space by the replaced box structure.
[0003] Furthermore, for example, at construction sites in urban areas, there are cases where a work shaft cannot be provided on the arrival side of the existing structure to which the box structure is advanced because, for example, another existing structure is formed on the arrival side of the existing structure. Even in such cases, a technology has been developed that allows each work process of the underpass construction method to be carried out by using only the starting side shaft as a work shaft without providing a shaft on the arrival side (for example, see Patent Document 3).
[0004] Furthermore, in the underpass construction method, if a box structure to replace the top and side box roofs that have already been formed on the ground below an existing structure is to be formed inside a work shaft using cast-in-place concrete, a considerable amount of time would be required from assembling the formwork to curing the poured concrete. Therefore, a technology has been developed in which the box structure is first divided into multiple pieces and formed as precast concrete products in a factory or the like, and then these are transported into the work shaft and then joined together circumferentially and axially using PC steel wires or the like to form the box structure (see, for example, Patent Document 4). [Prior art documents] [Patent documents]
[0005] [Patent Document 1] JP 2007-177553 A [Patent Document 2] JP 2012-144942 A [Patent Document 3] JP 2001-73670 A [Patent Document 4] JP 2005-264552 A Summary of the Invention [Problem to be solved by the invention]
[0006] On the other hand, in recent years, there has been a demand for forming underground spaces, preferably with a larger hollow cross-sectional shape, by, for example, an underpass construction method. Also, for example in urban areas, it may not be possible to secure a site large enough for forming a work shaft even on the starting side, so there is a demand for the development of technology related to a new underpass construction method that makes it possible to form an underground space with a larger hollow cross-sectional shape in a narrow work shaft.
[0007] In other words, if, for example, there is another existing structure on the arrival side of the existing structure, making it impossible to establish a work shaft on the arrival side, and in addition, a site large enough to form a work shaft cannot be secured on the starting side, so that only a narrow work shaft with a work space width of, for example, about 10m or less can be established, in order to efficiently carry out the process of forming a box-shaped roof by crossing the ground below the existing structure in such a narrow work shaft on the starting side, through to removing the formed box-shaped roof and replacing it with it, and propelling the box structure into the ground below the existing structure to form an underground space, then correspondingly specific equipment, materials used, procedures, etc. will be required.
[0008] The object of the present invention is to provide an underpass construction method that can efficiently form an underground space that crosses the ground below an existing structure using a box structure, by working only in a narrow work shaft on the starting side, where the work space width is sufficient to accommodate, for example, a unit box and equipment to push it out, without providing a work shaft on the arrival side. [Means for solving the problem]
[0009] The present invention is an underpass construction method for forming an underground space by a box structure having a rectangular cross-sectional shape in the ground below an existing structure by working only from a narrow starting shaft formed in the ground on one side of a planned installation area of a box structure and having a work space width shorter than the extension of the planned installation area, the box structure being obtained by connecting and integrating a plurality of unit boxes made of precast concrete in the extrusion direction, and the box structure being formed by connecting and integrating a plurality of unit boxes made of precast concrete in the extrusion direction, ... a mirror portion ground improvement process for forming an improved ground for the mirror portion by ground improvement in the ground at both ends of the planned installation area in a direction crossing the bottom of the existing structure; a box-shaped roof formation process for forming a box-shaped roof of at least the top surface portion crossing the portion directly below the existing structure by pushing each of a plurality of box-shaped pipe members from the narrow starting shaft into the ground below the existing structure so as to be connected in the width direction along at least the top surface portion in the planned installation area of the box structure; The method includes a box piece extrusion process in which each of the unit boxes is installed one by one in the narrow starting shaft and the installed unit boxes are pushed forward as a unit together with the unit boxes pushed out previously, and a pipe member removal process in which the ground below the box-shaped roof of the top surface formed in the box-shaped roof forming process is excavated at the face on the narrow starting shaft side to sequentially remove at least the portion of the rear end portion of the box-shaped pipe member that faces the top surface of the unit boxes and is exposed so as to protrude rearward. In the pipe member removal process, at least the portion of the rear end portion of the box-shaped pipe member that faces the top surface of the unit boxes is removed, and in the box piece extrusion process, the unit boxes are pushed forward as a unit by the length of the removal. By repeating these two processes, at least the top surface is replaced with the box-shaped roof of the top surface of the unit boxes, thereby achieving the above-mentioned object.
[0010] In the underpass construction method of the present invention, it is preferable that the work space width, which is shorter than the extension of the planned installation area of the narrow starting shaft, is a space width capable of installing the unit box and the equipment for pushing it out.
[0011] In the underpass construction method of the present invention, it is preferable that the unit box has a thickness of 1 m or more.
[0012] Furthermore, in the underpass construction method of the present invention, the box-shaped pipe member is formed by axially connecting and integrating a plurality of the unit box-shaped pipes, each having an approximately quadrilateral hollow cross-sectional shape, and these unit box-shaped pipes are formed by separably connecting above and below a unit U-shaped upper flat piece of a predetermined length with a plurality of unit U-shaped lower pieces having an axial length shorter than that of the unit U-shaped upper flat piece, while being axially connected and integrated together, and it is preferable that in the pipe member removal process, the box-shaped pipe member is sequentially removed, one unit U-shaped lower piece at a time, at the rear end portion.
[0013] Furthermore, in the underpass construction method of the present invention, a roof supporting steel shell is installed at the tip of the unit box in the extrusion direction, interposed between the box-shaped roof of the top surface and the roof supporting steel shell, and comprising a pair of rectangular frames having an outer peripheral shape that follows the front shape of the unit box, and it is preferable that in the pipe member removal process, at least the part of the rear end portion of the box-shaped pipe member that faces the top surface of the unit box and is exposed by protruding rearward can be sequentially removed to the inside of the box structure through the gap between the pair of rectangular frames of the roof supporting steel shell.
[0014] In addition, in the underpass construction method of the present invention, it is preferable that the pair of rectangular frame bodies are installed so that the upper surface of the upper edge steel material is positioned at the same height position as the underside of the box-shaped roof of the top surface portion that was installed previously. Effect of the Invention
[0015] According to the underpass construction method of the present invention, an underground space that crosses the ground below an existing structure can be efficiently formed using a box structure by working only in a narrow work shaft on the starting side, where the work space width is sufficient to install, for example, a unit box and the equipment to push it out, without the need to install a work shaft on the arrival side. [Brief description of the drawings]
[0016] [Figure 1] FIG. 1 illustrates the process of installing a working shaft and the process of improving the ground in the underpass construction method according to a preferred embodiment of the present invention, where (a) is a schematic vertical cross-sectional view, and (b) is a schematic horizontal cross-sectional view along AA in (a). [Diagram 2] 10 is a schematic vertical cross-sectional view illustrating a state in which a box-shaped pipe member is advanced to form a box-shaped roof on a top surface portion in a box-shaped roof forming step. FIG. [Diagram 3] 5A and 5B are schematic longitudinal sectional views illustrating a box-shaped roof formed in a box-shaped roof forming step, and FIG. 5B is a schematic transverse sectional view taken along line A'-A' in FIG. 5A. [Figure 4] FIG. 2 is a simplified perspective view illustrating a roof supporting steel shell installed at the tip of the box structure. [Diagram 5] FIG. 11 is a schematic vertical cross-sectional view illustrating the formation of a box structure inside a work shaft. [Figure 6] FIG. 13 is a simplified perspective view illustrating a situation in which a box structure is formed inside a work shaft. [Figure 7] 10A to 10C are schematic vertical cross-sectional views illustrating a case piece pushing-out step and a pipe member removing step. [Figure 8] 13 is a schematic perspective view illustrating a case piece pushing-out step and a pipe member removing step. FIG. [Figure 9] 1 is a schematic vertical cross-sectional view illustrating an underground space created by a box structure formed across an existing structure. FIG. [Figure 10] 1 is a simplified perspective view illustrating an underground space created by a box structure formed across an existing structure. FIG. [Figure 11]FIG. 1A is a cross-sectional view of a box-shaped pipe member, and FIG. 1B is a cross-sectional view of a state in which a U-shaped upper flat piece and a U-shaped lower piece are separated. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0017] The underpass construction method according to a preferred embodiment of the present invention shown in Figs. 1 to 10 is adopted as a construction method for forming another new underground space 26 (see Figs. 9 and 10) in the ground below the existing structure 30, for example. In this embodiment, the R&C construction method (registered trademark) is adopted as the underpass construction method, in which the box structure 15 is advanced while excavating the ground remaining in the area inside the box roof 20 surrounded by the face 28 (see Fig. 7). In this embodiment, a site large enough to form the working shaft 31 cannot be secured, and therefore each work process of the R&C construction method is carried out in the working shaft 31 of a narrow space. In addition, since the existing structure 40 (see Figs. 3 and 5) is also formed as an underground structure on the arrival side of the box structure 15 sandwiching the existing structure 30, only the starting side shaft is used as the working shaft 31, and each work process of the R&C construction method is carried out without providing a shaft on the arrival side. 3 to 8, the box-shaped roof 20 is shown in a state in which the ground (soil and sand) remaining inside the box-shaped roof 20 is omitted.
[0018] The underpass construction method of this embodiment uses a narrow starting shaft on the departure side with a short work space width B (see Figures 1(a) and 2) as a work shaft 31, and by carrying out work only in this narrow starting shaft 31 on the departure side, without providing a work shaft on the arrival side, it adopts unique equipment, materials used, and procedures, which makes it possible to efficiently form an underground space 26 that crosses the ground on the side of the existing structure 30 using the box structure 15.
[0019] The underpass construction method 10 of this embodiment is an R&C construction method in which a narrow starting shaft with a work space width B shorter than the extension of the planned installation area of the box structure 15, which is formed in the ground on one side of the planned installation area of the box structure 15, is used as a work shaft 31, and an underground space 26 is formed in the ground below the existing structure 30, crossing below the existing structure 30, by work only from the narrow starting shaft 31, using the box structure 15 having a rectangular cross-sectional shape, the box structure 15 being obtained by connecting and integrating multiple unit box bodies 16 in the extrusion direction. a head portion ground improvement process for forming improved ground 33, 34 of the head portion by ground improvement in the ground at both ends of the planned installation area in the direction crossing the bottom of the existing structure 30; a box-shaped roof formation process for forming a box-shaped roof 21 of at least the top surface portion crossing the portion directly below the existing structure 30 by pushing each of the multiple box-shaped pipe members 17 from the narrow starting shaft 31 into the ground below the existing structure 30 in a unit box-shaped pipe 18 manner so as to be connected in the width direction along at least the top surface portion of the planned installation area of the box-shaped structure 15; The process includes a box piece extrusion process in which the unit boxes (underpass box pieces) 16 are installed one by one in the narrow starting shaft 31 and the installed unit boxes 16 are pushed forward together with the unit boxes 16 that have been previously pushed out; and a pipe member removal process in which the ground below the box-shaped roof 21 of the top surface portion formed in the box-shaped roof forming process is excavated at the face 28 on the narrow starting shaft 31 side, thereby successively removing at least the portion of the rear end portion of the box-shaped pipe member 17 that faces the top surface portion 15a of the unit box body 16 and is exposed so as to protrude rearward. In the pipe member removal process, at least the portion of the rear end portion of the box-shaped pipe member 17 that faces the top surface 15a of the unit box 16 is removed, and in the box piece extrusion process, the unit box 16 is pushed forward as a single unit.By repeating these two processes, at least the top surface 15a is replaced with the box-shaped roof 21 of the top surface, and an underground space is formed by the box structure 15 obtained by connecting and integrating multiple unit boxes 16.
[0020] In this embodiment, the work space width B, which is shorter than the extension of the planned installation area of the narrow starting shaft 31, is preferably a space width capable of installing the unit box 16 and the equipment (propulsion equipment) 27 for pushing it out, and is, for example, about 10 m, and the unit box 16 preferably has a thickness of 1 m or more, for example, about 1 m.
[0021] In this embodiment, the box-shaped pipe member 17 is preferably formed by integrally connecting a plurality of unit box-shaped pipes 18 having a substantially quadrilateral hollow cross-sectional shape in the axial direction, and these unit box-shaped pipes 18 are formed by connecting a plurality of unit U-shaped lower pieces 18b having a shorter axial length below a unit U-shaped upper flat piece 18a in an axially separable manner, as shown in Fig. 11. In the pipe member removing step, the box-shaped pipe member 17 (unit box-shaped pipe 18) is sequentially removed for each unit U-shaped lower piece 18b at the rear end portion.
[0022] Furthermore, in this embodiment, preferably, at the leading end in the extrusion direction of the connected unit boxes 16 constituting the box structure 15, a roof supporting steel shell 11 is installed between the top box roof 21 and the pair of rectangular frames 12, 13 having an outer peripheral shape that conforms to the front shape of the unit box 16 (see Figs. 4 to 6). In the pipe member removing process, the unit U-shaped lower piece 18b, which is the part facing the top surface 15a of the unit box 16 at the rear end part of the box-shaped pipe member 17 (unit box pipe 18) exposed so as to protrude backward, can be sequentially removed to the inside of the unit box 16 constituting the box structure 15 through the gap between the pair of rectangular frames 12, 13 of the roof supporting steel shell 11. The pair of rectangular frames 12, 13 are installed so that the upper surfaces of the upper edge steel members 12a, 13a are located at the same height position as the lower surface of the top box roof 21 installed previously.
[0023] In this embodiment, a work shaft 31 serving as a work base is formed on one side of the existing underground structure 30, preferably by the R&C method, prior to the work of forming an underground space 26 by the box structure 15 in the ground below the existing underground structure 30 (see FIG. 1). In this embodiment, as described above, since an existing structure 40 is formed on the other side of the existing underground structure 30, the work shaft 31 is formed only on one side, and each work process is carried out. The work shaft 31 can be easily formed by forming a retaining wall 32 using ground improvement and sheet piles, preferably by the SMW method, which is excellent in water-stopping properties, and excavating the inside of the retaining wall to a predetermined depth while retaining the earth. The surface on the work shaft 31 side is protected by sheet piles and supported by supports such as struts. In the formed work shaft 31, propulsion equipment for propelling the box-shaped pipe member 17 and the box structure 15, and removal equipment for removing the box-shaped pipe member 17 in units of U-shaped lower pieces 18b will be installed as appropriate (see Figures 7 and 8).
[0024] In this embodiment, preferably, after the SMW construction method for forming the earth retaining wall 32 of the working shaft 31 is performed, a mirror part ground improvement process is performed to form the improved ground 33, 34 of the mirror part by ground improvement in the ground at both ends of the planned installation area of the box structure 15 in the direction crossing the bottom of the existing structure 30, prior to excavating the inside of the wall. The mirror part improved ground 33, 34 can be formed in an area including a height portion similar to the planned installation area of the box structure 15 in the ground on both sides of the existing underground structure 30. The mirror part improved ground 33, 34 is formed in the starting part of the end of the earth retaining wall 32 side of the working shaft 31 as both ends of the planned installation area of the box structure 15, and the arrival side mirror part improved ground 34 is formed in the arrival part of the end of the existing facility structure 40 side (see FIG. 1). The head section improved ground 33, 34 can be easily formed by vertical ground improvement work by injecting chemicals from above ground with high pressure jets, similar to the head section ground improvement work in the shield tunneling method. The head section ground improvement process can also be carried out before the SMW method for forming the earth retaining wall 32 is carried out. Also, if the groundwater level is lower than the top of the planned installation area 35, it may be carried out instead of the ground improvement of the earth retaining wall 32.
[0025] After the working shaft 31 and the improved ground 33, 34 for the mirror section have been formed, in this embodiment, as shown in Figures 2 and 3(a) and (b), a known propulsion equipment (not shown) is installed in the working shaft 31, and, similar to the conventional R&C construction method, each of the multiple box-shaped pipe members 17 (unit box-shaped pipes 18) are connected in the width direction and pushed from the narrow starting shaft 31 into the ground below the existing structure 30, thereby forming a box-shaped roof 21 for at least the top surface portion that crosses the portion directly below the existing structure 30. In the box roof forming process, preferably, each of the multiple box-shaped pipe members 17 constituting the top box roof 21 and the box-shaped pipe members 17', 17" constituting the side box roof 22 and bottom box roof 23 is arranged in a row and connected in a circumferential direction of the cross section of the planned installation area along the top portion, both side portions, and both end portions of the bottom portion of the planned installation area of the box-shaped structure 15, and is then pushed and pushed from the work shaft 31 into the ground below the existing structure 30. This makes it possible to form a box roof 20 that includes, in addition to the top box roof 21 and side box roof 22 that cross the portion directly below the existing structure 30, preferably the bottom box roof 23 at the corner portions of both ends.
[0026] Here, each of the box-shaped pipe members 17 forming the top box-shaped roof 21 has a generally rectangular hollow cross-sectional shape (a generally square hollow cross-sectional shape in this embodiment) preferably having a width of 800 to 1400 mm and a length of 800 to 1400 mm, and has a space inside that is large enough for workers to stand and work. The box-shaped pipe members 17', 17" forming the side box-shaped roof 22 and the bottom box-shaped roof 23 also have a generally hollow square cross-sectional shape, for example, having a length of 800 to 1400 mm, and in this embodiment, they are left in the ground and buried (see FIG. 10) without being retrieved to the work shaft 31. These box-shaped pipe members 17, 17', 17" are installed in the ground with an extension sufficient to cross the ground directly below the existing underground structure 30, while sequentially adding unit box-shaped pipes divided into appropriate lengths, for example, 3 m in length.
[0027] In this embodiment, the unit box-shaped pipe 18 constituting the box-shaped pipe member 17 forming the top box-shaped roof 21 has a hollow cross-sectional shape that is approximately quadrilateral (approximately square) as shown in Figures 11(a) and (b), and consists of a U-shaped upper flat piece 18a and a U-shaped lower piece 18b that are separably connected vertically at the upper end portions of the side plate portions on both sides, and a band-shaped height adjustment hardware 18c is supported on the underside of the top plate of the U-shaped upper flat piece 18a, extends in the axial direction of the box-shaped pipe member 17, and is arranged parallel to the top plate and fixed thereto.
[0028] In this embodiment, the U-shaped upper flat piece 18a is separated from the U-shaped lower piece 18b and left in the ground when the box structure 15 is advanced so as to replace the top surface 15a with the top surface box roof 21, so that it can function as a friction-cutting member as it is. A load-bearing roller member is preferably attached to the height adjustment hardware 18c provided on the U-shaped upper flat piece 18a, so that the top surface 15a of the box structure 15 can be smoothly slid along the underside of the U-shaped upper flat piece 18a, which functions as a friction-cutting member.
[0029] In this embodiment, the box-shaped pipe member 17 is formed to a predetermined length by integrally connecting a plurality of unit box-shaped pipes 18, preferably having a hollow cross-sectional shape of a substantially quadrilateral (substantially square) and a length of, for example, about 3 m, in the axial direction using known connecting means such as bolt joints, pin joints, etc. The unit box-shaped pipe 18 is formed by connecting a plurality of unit U-shaped lower pieces 18b, which are shorter than the unit U-shaped upper flat piece 18a, for example, 3 m, separably to each other in the axial direction below the unit U-shaped upper flat piece 18a, and which are shorter than the unit U-shaped lower piece 18a, for example, 1 m. As a result, as will be described later, the unit box pipes 18 of the box-pipe members 17 forming the top box-shaped roof 21 can be removed and recovered one by one, from the unit U-shaped lower piece 18b at the rear end, through the gap between the roof-side rectangular frame 12 and the box-side rectangular frame 13 of the roof supporting steel shell 11 attached to the front end of the box structure 15, to the inside of the box structure 15, while the unit U-shaped upper flat piece 18a serving as a friction-cut member is left in the ground. These unit U-shaped lower pieces 18b can be connected and integrated in the axial direction using known joining means such as bolt joining or pin joining.
[0030] After the box roof 20, including the top box roof 21, side box roof 22, and bottom box roof 23, is formed in the planned installation area of the box structure 15 that crosses the portion directly below the existing structure 30, in this embodiment, as shown in Figures 4 to 8, the underpass box pieces 16 made of precast concrete, which are each unit box that makes up the box structure 15, are installed one by one in the narrow starting shaft 31 (see Figures 5 and 6), and a box piece extrusion process (see Figure 7) is carried out in which the installed underpass box pieces 16 are pushed forward together with the underpass box pieces (unit box) 16 that were previously extruded. In addition, a pipe member removal process (see Figures 7 and 8) is carried out in which the ground below the box-shaped roof 21 of the top surface formed in the above-mentioned box-shaped roof forming process is excavated at the face 28 on the narrow starting shaft 31 side, thereby exposing the rearwardly protruding ground below the box-shaped roof 21. The pipe member removal process successively removes the unit U-shaped lower piece 18b located at the part opposite the top surface 15a of the underpass box body piece 16 at the rear end part of the box-shaped pipe member 17.
[0031] That is, in this embodiment, preferably, the side box roof 22 and the bottom box roof 23 are left in the ground, and the unit U-shaped lower pieces 18b of the unit box pipes 18 of the box pipe members 17 constituting the top box roof 21 are replaced with the top surface 15a of the box structure 15, and the box structure 15 consisting of the multiple connected underpass box pieces 16 can be advanced from the work shaft 31 toward the ground directly below the existing structure 30 by the advancing equipment 27 installed in the work shaft 31 with the roof support steel shell 11 (see FIG. 4) for recovering the unit U-shaped lower pieces 18b attached to the tip of the box structure 15. As a result, an underground space 26 that crosses the part directly below the existing structure 30 is formed by the box structure 15 that has been advanced and installed (see FIG. 9 and FIG. 10).
[0032] In this embodiment, as described above, since the work is performed in the narrow space of the work shaft 31, in the box piece extrusion process, the box structure 15 is formed by the underpass box pieces 16, which are multiple unit boxes made of precast concrete that are continuously connected and integrated in the axial direction (see Figs. 5 to 7). Each underpass box piece 16 is formed by assembling precast pieces 16a, which are multiple divided pieces divided in the circumferential direction, as a single unit in the work shaft 31 (see Fig. 6), so as to have a thickness, for example, equivalent to the jack stroke of the propulsion equipment 27, preferably about 1 m. That is, each underpass box piece 16 can be formed by assembling the precast pieces 16a, which are multiple divided pieces divided in the circumferential direction, in the work shaft 31 from the ground, to the rear of the roof side rectangular frame 12 constituting the roof support steel shell 11 described later, which has been previously assembled in the work shaft 31, so as to form a rectangular shape in the work shaft 31, as shown in Figs. 5 and 6. The formed underpass box pieces (unit box bodies) 16 are connected in series in the axial direction, and are pushed out as the box structure 15, together with the roof supporting steel shell 11 at its tip, toward the ground directly below the existing structure 30 by a propulsion device 27 installed in the work shaft 31 (see Figure 7).
[0033] That is, for example, the underpass box pieces 16 formed for each jack stroke of the propulsion equipment 27 are connected and assembled in sequence from the rear side in the propulsion direction of the box structure 15 as constituent members of the box structure 15, in the same manner as in the conventional R&C method. The box structure 15 thus formed, together with the roof support steel shell 11 installed at the tip, is propelled from the work shaft 31 toward the ground directly below the existing structure 30, while replacing the unit U-shaped lower pieces 18b of the unit box pipes 18 of the box-shaped pipe members 17 constituting the top box roof 21 with the top surface 15a, and leaving the unit U-shaped upper flat pieces 18a of the unit box pipes 18 in the ground as friction cut members. This makes it possible to form an underground space 26 created by the box structure 15 in the ground directly below the existing structure 30 by crossing the ground directly below it (see Figures 9 and 10).
[0034] Furthermore, in this embodiment, as described above, preferably as an underpass construction method using the R&C method, as shown in Figure 7, the box structure 15 is advanced while excavating the ground inside the box roof 20 at the face 28, and only the starting shaft is used as the work shaft 31. Therefore, in the pipe member removal process, the unit U-shaped lower pieces 18b of the unit box pipes 18 of each box-shaped pipe member 17 constituting the top box roof 21 are recovered into the work shaft 31, while the box structure 15 is advanced into the ground below the existing underground structure 30.
[0035] That is, in this embodiment, a roof supporting steel shell 11 is provided at the leading end of the box structure 15 made of a plurality of underpass box pieces 16 in the propulsion direction, and includes a pair of rectangular frames 12, 13 having an outer peripheral shape that conforms to the cross-sectional shape of the box structure 15, and is interposed between the box roof 20 and the box roof 20 (see Figs. 6 and 7). As shown in Fig. 4, the roof supporting steel shell 11 includes the roof side rectangular frame 12 and the box side rectangular frame 13, and a plurality of connecting steel members 14 that join and integrate the rectangular frames 12, 13 in a state where they are arranged in parallel. The roof supporting steel shell 11 includes the roof side rectangular frame 12 and the box side rectangular frame 13, and a plurality of connecting steel members 14 that join and integrate the rectangular frames 12, 13 in a state where they are arranged in parallel. The presence of the roof supporting steel shell 11 maintains a gap between the rectangular frames 12, 13 that allows the unit U-shaped lower piece 18b of the box-shaped roof pipe 17 to pass through and allows workers to enter.
[0036] In this embodiment, the upper edge steel members 12a, 13a of the roof-side rectangular frame 12 and the box-side rectangular frame 13 in the roof supporting steel shell 11 are preferably installed so that their upper surfaces are located at the same height as the lower surface of the previously installed top box roof 21, so that the rear end portion of the top box roof is preferably placed on the upper edge steel member 12a of the roof-side rectangular frame 12, thereby enabling the roof supporting steel shell 11 to firmly and stably support the rear end portion of the top box roof 21 from below. In addition, the box-side rectangular frame 13 comes into contact with the front surface of the box structure 15, so that the roof supporting steel shell 11 can be smoothly advanced together with the box structure 15 as the box structure 15 advances. At the tip portion of the box structure 15, the roof supporting steel shell 11 can be positioned inside the tip cutting edge members attached to both sides of the box structure 15, and it is also possible to attach tip cutting edge members to both sides of the roof supporting steel shell 11 so that the ground at the face 28 can be excavated.
[0037] Furthermore, in this embodiment, as described above, when the box structure 15 is advanced while the ground inside the box roof 20 is excavated at the face 28, the unit U-shaped lower pieces 18b of the unit box pipes 18 located at the rear ends of the box pipe members 17 constituting the top box roof 21, which protrude directly above the gaps between the roof side rectangular frame body 12 and the box side rectangular frame body 13 of the roof supporting steel shell 11, can be sequentially retrieved through these gaps to the inside of the box structure 15 and removed (see Figures 7 and 8).
[0038] Furthermore, in this embodiment, when removing the unit U-shaped lower piece 18b, the load from above in the portion between the tip of the box structure 15 and the face 28 can be supported from below by the unit U-shaped upper flat piece 18a, which functions as a friction-cut member and whose tip portion is placed on the top surface 15a of the box structure 15 preferably via a load-bearing roller member and which remains connected to each other. In this embodiment, as shown in Figures 11(a) and (b), the unit U-shaped upper flat piece 18a has a flat U-shaped cross-sectional shape with both side portions bent downward, and therefore has considerable rigidity compared to a flat friction-cut plate, and can support the load from above in a stable state. In addition, in this embodiment, the unit U-shaped upper flat pieces 18a, which remain connected to each other, have band-shaped height adjustment hardware 18c fixed to the underside of the top plate, and these height adjustment hardware 18c further increase the rigidity, making it possible to support loads from above in a more stable state.
[0039] In this embodiment, as described above, in the pipe member removal process, the unit U-shaped lower piece 18b of the unit box pipe 18, which is the part facing the top surface 15a of the underpass box piece 16 at the rear end portion of each box-shaped pipe member 17 that constitutes the top surface box roof 21, is pushed forward as a unit with the underpass box piece 16 by the length that was removed.By repeating these two processes, at least the top surface 15a is replaced with the top surface box roof 21, and an underground space 26 (see Figures 9 and 10) is formed by the box structure 15 obtained by connecting and integrating multiple underpass box pieces 16.
[0040] As a result, according to the underpass construction method of this embodiment, the work space width B is a space width in which, for example, a unit box 16 and the equipment 27 for pushing it out can be installed, and by working only in the narrow starting shaft 31 on the starting side with a space width of, for example, about 10 m, it is possible to efficiently form an underground space 26 that crosses the ground below the existing structure 30 by using the box structure 15 obtained by connecting and integrating multiple underpass box pieces 16, without providing a work shaft on the arrival side.
[0041] In this manner, in this embodiment, the box structure 15 is advanced into the ground, and the tip of the box structure 15 reaches, for example, the improved ground 34 at the destination side mirror section on the forward side in the advancing direction across the existing structure 30, thereby forming an underground space 26 by the box structure 15 installed across the portion directly below the existing underground structure 30 (see Figs. 8 and 9). The formed underground space 26 can be used in communication with the existing facility structure 40, for example, by removing the side wall 40a of the other existing facility structure 40 at a portion corresponding to the underground space 26 (see Fig. 9).
[0042] The present invention is not limited to the above embodiment and may be modified in various ways. For example, the existing structure in which an underground space is formed in the ground below by a box structure may be an existing structure for a subway or road, or may be various other existing structures such as a building or a sewer pipe. In addition, the existing structure does not necessarily have to be an underground structure.
[0043] 11 Roof support steel shell 12 Roof side rectangular frame 12a Upper steel material 13 Rectangular frame on box side 13a Upper steel material 14 Connecting steel 15 Box structure 15a Top section 16 Unit box (Underpass box piece) 16a Top section 16b Precast piece 17,17',17” Box pipe members 18,18',18" Unit Box Pipe 18a Unit U-shaped upper flat piece 18b Unit U-shaped lower piece 18c Height adjustment hardware 20 Box Roof 21 Box-shaped roof on top 22 Box roof on the side 23 Box roof at bottom 26 Underground space 27 Propulsion equipment (pushing equipment) 28 Face 30 Existing Structures 31 Working shaft (narrow starting shaft) 32 Earth retaining wall 33 Improved ground for the launch mirror 34 Reach side mirror section improved ground 40 Existing structures on the approaching side 40a Side walls of the part corresponding to the underground space B Working space width
Claims
1. An underpass construction method for forming an underground space by a box structure having a rectangular cross-sectional shape in the ground below an existing structure by working only from a narrow starting shaft formed in the ground on one side of a planned installation area of a box structure and having a work space width shorter than the extension of the planned installation area, the method comprising: The box structure is obtained by connecting and integrating a plurality of precast concrete unit boxes in the extrusion direction, a mirror part ground improvement process for forming an improved ground for the mirror part by ground improvement in the ground at both ends of the planned installation area in a direction crossing the bottom of the existing structure; a box-shaped roof formation process for forming a box-shaped roof of at least the top surface part crossing the part directly below the existing structure by pushing each of a plurality of box-shaped pipe members from the narrow starting shaft into the ground below the existing structure so as to be connected in the width direction along at least the top surface part in the planned installation area of the box structure; a box piece extrusion process in which each of the constituent unit boxes is installed one by one in the narrow starting shaft and the installed unit box is pushed forward as a unit together with the unit box pushed out previously; and a pipe member removal process in which the ground below the box-shaped roof of the top surface portion formed in the box-shaped roof forming process is excavated at the face on the narrow starting shaft side to expose and protrude rearward, and at least the portion of the rear end portion of the box-shaped pipe member facing the top surface portion of the unit box is sequentially removed. In the pipe member removal process, at least the portion of the rear end portion of the box-shaped pipe member that faces the top surface of the unit box is removed, and in the box piece extrusion process, the unit box is pushed forward as a single unit.By repeating these two processes, at least the top surface is replaced with the box-shaped roof of the top surface, and an underpass construction method in which the underground space is formed by the box structure obtained by connecting and integrating a plurality of the unit boxes.
2. 2. An underpass construction method according to claim 1, wherein the working space width, which is shorter than the extension of the planned installation area of the narrow starting shaft, is a space width capable of installing the unit box and equipment for pushing it out.
3. 3. An underpass construction method according to claim 1 or 2, wherein the unit box has a thickness of 1 m or more.
4. The underpass construction method according to claim 1 or 2, wherein the box-shaped pipe member is formed by axially connecting and integrating a plurality of the unit box-shaped pipes having an approximately quadrilateral hollow cross-sectional shape, and these unit box-shaped pipes are formed by axially connecting and detachably connecting a plurality of unit U-shaped lower pieces having an axial length shorter than that of a unit U-shaped upper flat piece of a predetermined length below the unit U-shaped upper flat piece, the unit U-shaped lower pieces being axially connected and integrated together, and wherein, in the pipe member removal process, the box-shaped pipe member is sequentially removed by the unit U-shaped lower pieces at the rear end portions.
5. An underpass construction method as described in claim 1 or 2, wherein a roof supporting steel shell is installed at the tip of the unit box in the extrusion direction, and the roof supporting steel shell is interposed between the box-shaped roof of the top surface and the roof supporting steel shell and has an outer circumferential shape that follows the front shape of the unit box, and in the pipe member removal process, at least the rear end portion of the box-shaped pipe member that is exposed by protruding rearward and faces the top surface of the unit box can be sequentially removed to the inside of the box structure through the gap between the pair of rectangular frames of the roof supporting steel shell.
6. An underpass construction method as described in claim 5, wherein the pair of rectangular frame bodies are installed so that the upper surface of the upper edge steel material is positioned at the same height position as the lower surface of the box-shaped roof of the top surface portion installed previously.
Citation Information
Patent Citations
Construction of underground structure and tubular body for roof therefor
JP2001073670A
Portal construction method
JP2003097179A
Protective method of starting or arrival face
JP2005113421A
Jacking method for tunnel
JP2005264552A
Construction method for underground structure
JP2007262679A