Towing type underpass construction method

JP2024143681APending Publication Date: 2024-10-11OKUMURA CORP +1
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2023056469
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-30
Publication Date
2024-10-11

AI Technical Summary

Benefits of technology

【0016】 本発明のけん引式アンダーパス工法によれば、発進基地の広大な広さの敷地を利用して、作業工程に改良を加えることによって、効率良く且つ効果的に、工事期間の短縮を図ることができる。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024143681000001_ABST
    Figure 2024143681000001_ABST
Patent Text Reader

Abstract

To provide a towing type underpass construction method capable of efficiently and effectively shortening the construction period by improving the work process at a vast starting base.SOLUTION: A temporary support wall 55 is erected at a starting base 51, and the starting base 51 is divided into a pushing work area 51A and a box body construction work area 51B in the towing direction X. A box roof formation process is carried out in the pushing work area 51A, and in parallel with this, a box body construction process is carried out in the box body construction work area 51B to construct a box body structure 20. After these processes, a temporary wall formation is removed in a dismantling and removal process, and the box body structure 20, which will become the underground space constructed in the box body construction process, is replaced with the box roof 22 formed on the ground directly below an expressway 50, so that it can be towed to an arrival base 52 side.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a tow-type underpass construction method, and more particularly to a tow-type underpass construction method for forming an underground space using a box structure by crossing the ground below an existing structure. [Background technology]

[0002] The underpass method is a method for forming an underground space that crosses the ground below existing structures such as railroad tracks and roads without interfering with the operation of railroads and vehicles, and examples of such methods include the SFT method (registered trademark) and the R&C method (registered trademark), which replace a box-shaped roof with a box-shaped roof, and the Frontejacking method. The SFT method and the R&C method form a box-shaped roof, preferably made of hollow pipe members having a rectangular cross-sectional shape, including a pipe roof (a row of pipes on the top surface) of the upper floor that supports existing structures such as railroad tracks and roads from below, on the ground in the planned installation area of ​​the box structure, which is the planned location for forming an underground space, and replace the box-shaped roof including the pipe roof of the upper floor, for example, made of concrete and having a rectangular cross-sectional shape, by driving or towing the box structure into the ground in the planned installation area to form an underground space by the box structure (see, for example, Patent Document 1 and Patent Document 2).

[0003] In addition, the Frontejacking method involves leaving a row of pipes, including a pipe roof on the upper floor formed on the ground in the planned installation area of ​​the box structure, in the ground, and towing the box structure at the departure base toward the arrival base while aligning the top surface of the left behind pipe row, particularly the pipe roof on the upper floor, to form an underground space made of the box structure inside the left behind pipe row (see, for example, Patent Documents 3 and 4).

[0004] Here, for example, if there is not enough space at the destination base to construct a box structure using cast-in-place concrete and it is necessary to construct the box structure at the starting base, generally, a propulsion facility installed at the starting base is used to propel each of the pipe components that make up the box roof into the ground, and then the propulsion facility is removed. In the space left by the removed propulsion facility, formwork etc. is assembled and concrete is poured, and the poured concrete is allowed to harden and cure to complete the construction. [Prior art documents] [Patent documents]

[0005] [Patent Document 1] JP 2007-177553 A [Patent Document 2] JP 2012-144942 A [Patent Document 3] Japanese Patent Application Publication No. 6-41996 [Patent Document 4] JP 2004-257025 A Summary of the Invention [Problem to be solved by the invention]

[0006] However, when constructing a box structure at a launch base using cast-in-place concrete, it takes a considerable number of days to install the formwork and reinforcing bars, pour the concrete, harden it, and then allow the required curing period to pass. Therefore, if the number of days required for the process of driving each of the multiple pipe members that make up the box roof into the ground is included, the construction period will be long, so it is desirable to be able to shorten this construction period.

[0007] In particular, for example, when the ground beneath the existing structure is an embankment and a large launch base site (space) can be secured on at least one side of the existing structure, or when the extension that crosses the existing structure is long, it will be necessary to divide the box structure into several unit box structures and construct them so that the weight can be easily moved, preferably by a propulsion jack, etc., which will extend the construction period even further.

[0008] On the other hand, if a towing-type underpass method is adopted as the underpass construction method, in which the box structure is moved by towing it with a towing wire, there is no need to install a support wall at the starting base to obtain a supporting reaction force when the box structure is pushed out by a thrust jack. Therefore, by adopting such a towing-type underpass method and making improvements to the work process by utilizing the vast area of ​​the starting base, it is thought that it will be possible to shorten the construction period more efficiently and effectively.

[0009] The present invention aims to provide a towed underpass construction method that can efficiently and effectively shorten the construction period by utilizing the vast area of ​​the departure base and improving the work process. [Means for solving the problem]

[0010] The present invention is a tow-type underpass construction method for forming an underground space by towing a box structure having a rectangular cross section across the ground below an existing structure while replacing the top surface with a previously formed top surface pipe row or while aligning the top surface with the top surface pipe row, the tow-type underpass construction method comprising the steps of: erecting a temporary support wall at a starting base on one side of a planned installation area of ​​the box structure in the ground below the existing structure where the box structure will be installed; and setting the starting base between the temporary support wall and the starting base; A temporary wall formation process is performed to divide the work area in the direction of towing into a driving work area on the existing structure side and a box construction work area on the opposite side. In the driving work area on the front side in the driving direction divided in the temporary wall formation process, a plurality of hollow pipe members are driven toward a destination base provided on the other side of the planned installation area while receiving a driving reaction force from the temporary support wall, so that the hollow pipe members are arranged in a line in the circumferential direction of the planned installation area and are pushed into the ground directly below the existing structure, thereby crossing the ground directly below the existing structure. a box roof forming step of forming a box roof including at least a top surface pipe row, the box roof including at least a top surface pipe row being formed by the box roof forming step; a box construction step of constructing the box structure made of reinforced concrete by assembling a formwork and pouring cast-in-place concrete, which is carried out in parallel with the box roof forming step in the box construction work area on the rear side in the towing direction separated by the temporary wall forming step; and a box construction step of constructing the box structure made of reinforced concrete by assembling a formwork and pouring cast-in-place concrete, which is carried out in parallel with the box roof forming step in the box roof forming step, after pushing all of the plurality of hollow pipe members into the ground directly below the existing structure in the box roof forming step, dismantling the advancing equipment and the temporary support wall in the advancing work area. a dismantling and removal process in which the box structure is removed from the box structure; and thereafter, a towing steel wire is used to tow the box structure toward the arrival base while replacing the top surface with the top surface pipe row or aligning the top surface with the top surface pipe row, the top surface being supported at one end by a rear portion in the towing direction of a towing support wall erected at the arrival base on the other side of the planned installation area and extending across the planned installation area and the other end being engaged with a rear end portion in the towing direction of the box structure constructed in the box construction work area of ​​the starting base.The above-mentioned object has been achieved by providing a towing-type underpass construction method including a box towing step of moving the box structure on the ground below the existing structure.

[0011] Furthermore, in the tow-type underpass method of the present invention, the box structure consists of a plurality of unit box bodies arranged in series at intervals in the towing direction, and a central push jack is interposed in the gap between adjacent unit box bodies, and it is preferable that the box towing process includes a self-propelled towing process in which the box structure is moved in the towing direction by an ESA method, which can tow each unit box body in one direction using the frictional resistance of the unit box body that is not being propelled as a reaction force.

[0012] In addition, in the tow-type underpass construction method of the present invention, it is preferable that the temporary support wall is formed by filling an interior area surrounded by a rectangular retaining member with soil and sand.

[0013] Furthermore, it is preferable that the towed underpass construction method of the present invention is implemented using the R&C construction method (registered trademark), in which the box structure is towed while excavation work is carried out at the face portion of the front portion in the towing direction of the box structure and the top surface portion is replaced with the top surface pipe row.

[0014] Furthermore, it is preferable that the tow-type underpass method of the present invention is implemented using a Frontejacking method (registered trademark), in which excavation work is carried out at the face of the front part of the box structure in the towing direction, while the top surface is aligned with the underside of the top surface pipe row, and the box structure is towed while leaving the top surface pipe row in the ground.

[0015] In addition, in the tow-type underpass construction method of the present invention, it is preferable that the ground below the existing structure is a banked ground. Effect of the Invention

[0016] According to the towed underpass construction method of the present invention, by utilizing the vast area of ​​the starting base and improving the work process, the construction period can be shortened efficiently and effectively. [Brief description of the drawings]

[0017] [Figure 1] 1(a) to 1(c) are schematic vertical cross-sectional views illustrating each step of a tow-type underpass construction method according to a preferred embodiment of the present invention. [Diagram 2] FIG. 1 is a schematic vertical cross-sectional view illustrating a tow-type underpass construction method according to a preferred embodiment of the present invention. [Diagram 3] A tow-type underpass construction method according to a preferred embodiment of the present invention will be described. [Figure 4] 1(a) to 1(d) are schematic vertical cross-sectional views illustrating each step of a tow-type underpass construction method according to a preferred embodiment of the present invention. [Diagram 5] 1(a) to 1(c) are schematic vertical cross-sectional views illustrating each step of a tow-type underpass construction method according to a preferred embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0018] The tow-type underpass construction method according to a preferred embodiment of the present invention is adopted as a construction method for forming an underground space in which another road is laid by towing a hollow box structure 20 having a rectangular cross section to the ground directly below the expressway 50 as shown in Figs. 4(a)-(d) when a new road is constructed to cross the ground below a multi-lane expressway as an existing structure 50 and cross over it, as shown in Figs. 1(a)-(c). In this embodiment, the tow-type underpass construction method is preferably a well-known tow-type R&C construction method (registered trademark), and the box structure 20 is towed to the ground below the expressway 50 and installed to replace the box roof 22 made of hollow pipe members 23 preferably having a rectangular cross section, including a top pipe row 22a, which was formed in advance on the ground directly below the expressway 50, to form an underground space.

[0019] In this embodiment, the ground below the expressway 50, which is an existing structure, to which the box structure 20 is towed is a banked ground, and a large starting base 51 can be secured on one side of the site across the expressway 50. For this reason, in this embodiment, the concrete box structure 20 is constructed in the large starting base 51, preferably by connecting a plurality of divided unit box bodies 21 in the towing direction X, as a structure having a sufficient extension to cross the ground below the expressway 50 at one time. The towed underpass construction method of this embodiment utilizes the large site of such a starting base 51, and preferably enables the process of constructing a plurality of unit box bodies 21 constituting the box structure 20 to be performed in parallel with the process of pushing a plurality of hollow pipe members 23 into the ground directly below the expressway 50 to form a box-shaped roof 22, thereby enabling the construction period to be shortened more efficiently and effectively.

[0020] The tow-type underpass method of this embodiment is a tow-type R&C method (registered trademark) for forming an underground space by towing a box structure 20 having a rectangular cross section across the ground below an expressway 50, which is an existing structure, while replacing the previously formed top surface pipe row 22a and top surface 20a, and installing the box structure 20. A temporary support wall 55 is erected at a starting base 51 on one side of a planned installation area 24 (see FIG. 1(a)) of the box structure 20 in the ground below the expressway 50, where the box structure 20 will be installed. a temporary wall formation process for dividing the starting base 51 in the towing direction X into a driving work area 51A on the expressway 50 side with a temporary support wall 55 in between and a box construction work area 51B on the opposite side; and in the driving work area 51A on the forward side of the towing direction X divided in the temporary wall formation process, a plurality of hollow pipe members 23 are driven toward a destination base 52 provided on the other side across the planned installation area 24 while receiving a driving reaction force from the temporary support wall 55, so that the hollow pipe members 23 are aligned in a circumferential direction of the planned installation area 24 and are continuously installed, and are each pushed into the ground directly below the expressway 50. The box-shaped roof forming process forms a box-shaped roof 22 including at least a top surface pipe row 22a crossing the ground immediately below the expressway 50 by pushing the hollow pipe members 23 into the ground immediately below the expressway 50. The box-shaped roof forming process is performed in parallel with the box-shaped roof forming process in a box-shaped construction work area 51B on the rear side in the towing direction X separated by the temporary wall forming process, in which a formwork is assembled and in-situ concrete is poured to construct a reinforced concrete box structure 20. After all of the hollow pipe members 23 are pushed into the ground immediately below the expressway 50 in the box-shaped roof forming process, the box-shaped roof forming process is performed in the pushing work area 51A. a dismantling and removal process for dismantling and removing the advancement equipment 54 and the temporary support wall 55; and thereafter, a towing steel wire 12 having one end connected to and supported by a back portion 11a in the towing direction X of the towing support wall 11 erected at the arrival base 52 on the other side of the planned installation area 24 and the other end engaged with a rear end portion in the towing direction X of the box structure 20 constructed in the box construction work area 51B of the departure base 51, towing the box structure 20 toward the arrival base 52 while replacing the top surface portion 20a with the top surface pipe row 22a.and a box towing step of moving the box structure 20 on the ground below the expressway 50.

[0021] In addition, in this embodiment, the box structure 20 preferably consists of a plurality of unit box bodies 21 arranged in series at intervals in the towing direction X, and an intermediate push jack 25 is interposed in the gap between adjacent unit box bodies 21.Therefore, the box towing process includes a self-propelled towing process in which the box structure is moved in the towing direction by an ESA method, which can tow each unit box body 21 in one direction using the frictional resistance of the unit box body 21 that is not being propelled as a reaction force, without relying on external reaction force resistance.

[0022] In order to carry out the towed underpass method of this embodiment, as preparatory work, for example, removal and restoration of obstacles at the construction site, and chemical injection work 56a prior to excavation of the guide pit 56 are carried out, and then, as shown in FIG. 1(a), steel sheet piles for retaining soil are driven into both sides of the embankment ground below the expressway 50 to form mirror wall surfaces 53a, 53b on both sides of the expressway 50, and a temporary wall forming process is carried out to erect a temporary support wall 55 as a roof propulsion reaction body at a predetermined interval between the mirror wall surface 53b and the starting base 51. Since the temporary support wall 55 is erected at the starting base 51 and formed, the starting base 51 is divided in the towing direction X into a propulsion work area 51A on the expressway 50 side sandwiched between the temporary support wall 55 and a box construction work area 51B on the opposite side. Since the temporary support wall 55 needs to be removed after the box-shaped roof 22 is formed and before the box structure 20 is advanced, it is preferably formed by filling the interior of a rectangular area surrounded by, for example, steel sheet piles as an earth retaining member 55a with soil.

[0023] In addition, the towing support wall 11 is erected at the arrival base 52 with a predetermined distance between it and the mirror wall surface portion 53a. The towing support wall 11 is preferably formed by pouring concrete inside a rectangular area surrounded by, for example, steel sheet piles as the retaining members 11c so that it can bear at least a part of the reaction force during towing in the box towing process described later. The support wall 11 is formed with a through hole at a predetermined position between the opposing surface portion 11b and the back surface portion 11a in the towing direction X by the retaining members 11c. In addition, a guide pit 56 for inserting the towing wire 12 is formed in the area where the chemical grouting work 56a is performed at the bottom corner portion of the planned installation area 24 of the box structure 20.

[0024] Furthermore, in this embodiment, in the box towing process described later, a tie beam 13 can be erected and attached between the opposing surface 11b in the towing direction X of the towing support wall 11 and the mirror wall 53a on the arrival base 52 side of the embankment land so that the support reaction force when towing the box structure 20 is also borne by the wall 53a. The tie beam 13 is made of a retaining beam member made of, for example, H-shaped steel, and can be attached in an erected state between them by joining both ends to a wale member made of, for example, H-shaped steel installed on the opposing surface 11b and the mirror wall 53a. In this embodiment, the tie beam 13 is appropriately selected in a position so as not to interfere with the frame steel constituting the temporary hollow pipe removal facility 27 (see FIG. 3(b)) installed within the range surrounded by the box-shaped roof 22 at the arrival base 52, and is installed in two stages, for example, one above the other.

[0025] In this embodiment, after the temporary wall forming step, a box-shaped roof forming step is carried out to form a box-shaped roof 22 including at least a top surface pipe row 22a, as shown in Fig. 1(b). In the box-shaped roof forming step, a propulsion facility 54 similar to that of the conventional R&C construction method is provided between the formed temporary support wall 55 and the mirror wall surface portion 53b on the starting base 51 side in the propulsion work area 51A of the starting base 51, and a plurality of hollow pipe members 23, preferably a plurality of unit pipe members 23a, can be sequentially added from the starting base 51 to the arrival base 52, and each of them can be pushed into the ground directly below the expressway 50, so that they are arranged in a line in the circumferential direction of the planned installation area 24, while being sequentially connected to each other, in the same manner as in the conventional R&C construction method. This allows a box-shaped roof 22 having a U-shaped cross-sectional shape, preferably consisting of at least a top surface pipe row 22a and a pair of side surface pipe rows 22b on both sides, to be formed so as to span the mirror wall portion 53a on the departure base 51 side and the mirror wall portion 53b on the arrival base 52 side.

[0026] In this embodiment, in parallel with the box-shaped roof forming process in the advancing work area 51A, for example, five unit box bodies 21 constituting the box structure 20 are constructed in the box body construction work area 51B on the rear side of the temporary support wall body 55 of the starting base 51 in the towing direction X. That is, in the box body construction work area 51B on the vast site of the starting base 51, for example, formwork is assembled on a steel plate, and reinforcing bars are assembled, and then concrete is poured and hardened / cured, so that the five unit box bodies 21 can be constructed in a state in which they are connected at a predetermined interval in the towing direction X. Also, a known center push jack 25 is attached to each of the intervals between the five unit box bodies 21 connected in the towing direction X, and a cutting edge member 26 used when excavating the ground inside the box-shaped roof 22 is attached to the tip of the unit box 21 at the tip end in the towing direction X.

[0027] Meanwhile, at the arrival base 52, preferably in parallel with the above-mentioned box-shaped roof forming process, a temporary hollow pipe removal equipment 27 is installed in the area between the mirror wall surface portion 53a on the arrival base 52 side and the opposing surface portion 11b of the towing support wall 11. The temporary hollow pipe removal equipment 27 is used when removing the hollow pipe members 23 constituting the pipe rows 22a, 22b of the box-shaped roof 22, which have been pushed out by the box structure 20 in the towing process described below, one by one as unit pipe members 23a (see Figs. 4(a) to (d)). The temporary hollow pipe removal equipment 27 is formed by assembling the structural steel members constituting the equipment into a three-dimensional shape while avoiding interference with the above-mentioned tie beams 13 that have been previously installed within the area surrounded by the box-shaped roof 22.

[0028] In this embodiment, in the box-shaped roof forming process, all of the hollow pipe members 23 are pushed into the ground in the planned installation area 24 to form the box-shaped roof 22 including the top pipe row 22a crossing the ground directly below the expressway 50. In the dismantling and removal process, the propulsion equipment 54 and the temporary support wall 55 in the propulsion work area 51A are dismantled and removed at the starting base 51 as shown in Fig. 1(c). In addition, the traction steel wire 12 is arranged and attached so as to extend from the back part 11a in the towing direction X of the towing support wall 11 erected at the arrival base 52 to the rear end of the unit box 21 at the rear end of the box structure 20 constructed at the starting base 51, thereby making it possible to carry out the towing process of the box structure 20 described later.

[0029] That is, in the starting base 51, preferably in the portion from which the roof propulsion reaction body 55 and the propulsion equipment 54 have been removed, a steel sheet, for example, is laid so that the box structure 20 consisting of the five unit box bodies 21 can be smoothly slid in the towing direction X. Also, a known traction steel wire 12 made of, for example, a steel strand is inserted into a through hole formed in the towing support wall 11, and is inserted into a guide pit 56 formed in a bottom corner of the planned installation area 24 so as to cross the planned installation area 24 of the box structure 20, and further into an insertion hole provided in a bottom corner of the unit box body 21, and is arranged in a state of extending from the back part 11a of the support wall 11 in the towing direction X to the rear end of the box structure 20 in the towing direction X. In this state, one end of the installed traction steel wire 12 is fixed and connected to the back part 11a in the towing direction X of the support wall 11 via a known fastener 28a, and the other end of the installed traction steel wire 12 is fixed and connected to the rear end of the box structure 20 in the towing direction X of the multiple unit box bodies 21 connected together via a known front jack as an expansion jack 28b, for example, to be supported. As a result, in the box towing process described later, the box structure 20 can be towed toward the arrival base 52 while obtaining a support reaction force from the towing support wall 11 while expanding and contracting the expansion jack 28b.

[0030] In the box towing process of this embodiment, from a state in which both ends of the towing steel wire 12 shown in Fig. 1(c) are connected and supported to the back part 11a of the supporting wall 11 and the rear end part of the box structure 20, the expansion jack 28b is expanded and contracted, so that the box structure 20 made up of five unit box bodies 21 can be towed as a whole in the towing direction X while receiving a support reaction force during towing from the supporting wall 11, as shown in Fig. 2, and pulled toward the arrival base 52. In addition, when the box structure 20 is pulled toward the arrival base 52 and the tip of the box structure 20 made up of the unit box bodies 21 at the tip part abuts against the rear end of the box roof 22 previously installed on the ground of the planned installation area 24, the box structure 20 is further pulled toward the arrival base 52 while excavating the ground inside the box roof 22. This makes it possible to push the box structure 20 as a whole into the ground of the planned installation area 24 directly below the expressway 50, while replacing it with the box roof 22, as shown in Figure 4(a). Furthermore, each of the hollow pipe members 23 constituting the box roof 22 pushed out to the arrival base 52 in this way will be removed at the arrival base 52, one by one, by the unit pipe member 23a at the tip, using temporary hollow pipe removal equipment 27.

[0031] In this embodiment, in the box towing process in which the five unit box bodies 21 of the box structure 20 are towed as a whole, as shown in an enlarged view in Figure 3, a tie beam 13 is erected between the box structure 20 and the mirror wall portion 53a of the embankment land below the expressway 50.By using the erected tie beam 13, the support reaction force when towing the box structure 20 with the towing steel wire 12 can be borne not only by the supporting wall 11 but also by the mirror wall portion 53a of the embankment land. As a result, because the five unit box bodies 21 are integrated, the box structure 20 is constructed as a large structure with sufficient length to cross the ground below the existing structure, the expressway 50, in one go, and even if its weight is considerable, the support reaction force when towing the box structure 20 with the towing steel wire 12 is also borne by the mirror wall portion 53 of the embankment land, making it possible to tow the box structure 20 in a stable state by pulling it toward the arrival base 52.

[0032] In the box towing process of this embodiment, the support reaction force when towing the box structure 20 is borne not only by the supporting wall 11 but also by the mirror wall surface portion 53a of the embankment ground, and the box structure 20 is pushed into the ground of the planned installation area 24 directly below the expressway 50 while replacing the box roof 22. When the box structure 20 reaches a predetermined position, as shown in Fig. 4(b), one end of the towing steel wire 12 fixed to the back surface portion 11a of the supporting wall 11 in the towing direction X is replaced by the tip of the box structure 20 by the unit box 21 at the tip, and fixed by the fixing device 28a. Also, by attaching the ESA steel wire 29c to the upper portion of the box structure 20 via the fixing device 29a and the ESA jack 29b, the box structure 20 is changed over to a state in which it can be advanced by a known ESA construction method.

[0033] 4(c), the box structure 20 is further pushed into the ground of the planned installation area 24 directly below the expressway 50 by the ESA method, in which, for example, one of the five unit boxes 21 is used as a driving box and the remaining unit boxes 21 are used as reaction boxes, and the frictional resistance of the reaction boxes that are not being driven is used as a reaction force, without relying on external reaction resistance, by replacing the driving boxes and pushing in one direction. Also, each hollow pipe member 23 constituting the box roof 22 pushed out to the arrival base 52 by the pushing of the box structure 20 is removed at the arrival base 52 by the temporary hollow pipe removal equipment 27 for each unit pipe member 23a at the tip, as described above.

[0034] When the tip of the box structure 20 made of the unit pipe members 23a at the tip reaches the arrival base 52 by the ESA method, the tie beams 13 and the temporary hollow pipe removal equipment 27 installed between the support wall 11 and the mirror wall surface portion 53a of the embankment land below the expressway 50 are removed as shown in Fig. 4(d). Also, as shown in Fig. 5(a), while the center push jacks 25 between adjacent unit boxes 21 are sequentially removed, the unit box 21 at the rear end is pulled toward the arrival base 52 by the ESA method, whereby the box structure 20 having a rectangular cross section formed by five unit boxes 21 as one body is installed across the ground directly below the expressway 50 by the underpass method of this embodiment (see Fig. 5(b)).

[0035] Furthermore, once the box structure 20 has been installed across the ground directly below the expressway 50, as shown in Figures 5(b) and (c), the towing steel wires 12 and the ESA steel wires 29c, etc. will be removed, the cutting edge member 26 will be removed from the tip of the box structure 20, and the supporting wall 11 installed at the arrival base 52 will be removed. After that, the necessary waterproofing work, backfill grout injection work, road ancillary work, etc. will be carried out, and an underground space in which other roads will be laid will be formed by the box structure 20, with a multi-level intersection in the ground directly below the expressway 50.

[0036] Furthermore, according to the towed underpass construction method of this embodiment, by utilizing the vast area of ​​the starting base 51 site and improving the work process, it is possible to shorten the construction period efficiently and effectively.

[0037] In other words, in this embodiment, in the temporary wall formation process, the vast starting base 51 is divided into a propulsion work area 51A and a box construction work area 51B in the towing direction X, and the box-shaped roof formation process is carried out in the propulsion work area 51A while the box construction process is carried out in parallel in the box construction work area 51B. Once these processes are completed, the temporary support wall is removed in the dismantling and removal process, and the box structure 20 constructed in the box construction process can be towed as is to the arrival base 52 side, so that the construction period can be shortened efficiently and effectively by utilizing the vast area of ​​the starting base 51.

[0038] The present invention is not limited to the above embodiment and can be modified in various ways. For example, the present invention does not necessarily have to be implemented in the R&C method (registered trademark) in which the box structure is towed while replacing it with a box roof while performing excavation work at the face of the front part of the box structure, but can also be implemented in the SFT method (registered trademark) in which excavation work is performed at a reach base, or the Frontejacking method (registered trademark) in which the box structure is towed while leaving the box roof in the ground while performing excavation work at the face of the front part in the towing direction of the box structure and aligning the top surface part with the underside of the top surface pipe row of the box roof. [Explanation of symbols]

[0039] 11 Support wall 11a Rear part in towing direction 11b Facing surface in the towing direction 12 Towing wire 13 Tie beam 20 Box structure 20a Top section 21 Unit Box 22 Box roof 22a Top pipe row 22b Side pipe row 23 Hollow pipe components 23a Unit pipe member 24 Planned installation area 25 Center Jack 26 Blade mouth parts 27 Hollow pipe removal equipment 28a Fixture 28b Telescopic jack (fronte jack) 29a Fixtures 29b ESA jack 29c ESA steel wire 50 Expressway (Existing Structures) 51 Launch Base 51A Propulsion work area 51B Box construction work area 52 Base reached 53a,53b Mirror wall section 54 Propulsion mount 55 Temporary support wall (roof support reaction body) 56 Guide Tunnel 56a Chemical grouting work X Towing direction

Claims

1. A towing-type underpass construction method for forming an underground space by towing a box structure having a rectangular cross-sectional shape across the ground below an existing structure while replacing the top surface with a previously formed top surface pipe row or while aligning the top surface with the top surface pipe row, a temporary wall formation process in which a temporary support wall is erected at a starting base on one side of a planned installation area of ​​the box structure in the ground below the existing structure, where the box structure will be installed, and the starting base is divided in the towing direction into a driving work area on the existing structure side, sandwiched between the temporary support wall, and a box construction work area on the opposite side; a box-shaped roof forming process in which, in the advancing work area on the front side in the towing direction divided in the temporary wall forming process, a plurality of hollow pipe members are advanced toward a destination base provided on the other side of the planned installation area while receiving an advancing reaction force from the temporary support wall, so that the hollow pipe members are arranged in a line in the circumferential direction of the planned installation area and are pushed into the ground directly below the existing structure, thereby forming a box-shaped roof including at least a top surface pipe row that crosses the ground directly below the existing structure; A box construction process is carried out in parallel with the box roof formation process in the box construction work area on the rear side in the towing direction divided in the temporary wall formation process, in which a formwork is assembled and in-situ concrete is poured to construct the box structure made of reinforced concrete; a dismantling and removal process in which, after all of the plurality of hollow pipe members are pushed into the ground directly below the existing structure in the box-shaped roof forming process, the propulsion equipment and the temporary support wall body in the propulsion work area are dismantled and removed; Thereafter, a towing-type underpass construction method is provided which includes a box towing process in which the box structure is towed toward the arrival base side by a towing steel wire having one end connected and supported to the back end in the towing direction of the towing support wall erected at the arrival base on the other side of the planned installation area, and the other end engaged with the rear end in the towing direction of the box structure constructed in the box construction work area of ​​the starting base, while replacing the top surface with the top surface pipe row or aligning the top surface with the top surface pipe row, thereby moving the box structure on the ground below the existing structure.

2. The towed underpass method described in claim 1, wherein the box structure consists of a plurality of unit box bodies arranged in series at intervals in the towing direction, and a central push jack is interposed in the gap between adjacent unit box bodies, so that the box towing process includes a self-propelled towing process in which the box structure is moved in the towing direction by an ESA method that can tow each unit box body in one direction using the frictional resistance of the unit box body that is not being propelled as a reaction force.

3. 3. A tow-type underpass construction method according to claim 1 or 2, wherein the temporary support wall is formed by filling an interior area surrounded by a rectangular retaining member with soil and sand.

4. A towed underpass construction method as described in claim 1 or 2, implemented in the R&C construction method (registered trademark), in which the box structure is towed while replacing the top surface with the top surface pipe row while performing excavation work at the face portion of the front portion in the towing direction of the box structure.

5. A towed underpass construction method as described in claim 1 or 2, which is implemented in the Frontejacking method (registered trademark), in which excavation work is carried out at the face of the front part in the towing direction of the box structure, while the top surface is aligned with the underside of the top surface pipe row, and the box structure is towed while the top surface pipe row is left in the ground.

6. 3. A tow-type underpass construction method according to claim 1 or 2, wherein the ground below the existing structure is a fill ground.

Citation Information

Patent Citations

  • Building method for underground structure of large section

    JP1994041996A

  • Caisson body traction method and caisson body used therefor

    JP2004257025A

  • Construction method for underground passage

    JP2007177553A

  • Construction method of underpass

    JP2012144942A