Construction method using temporary scaffold
The temporary scaffolding method addresses the inefficiency of repeated scaffolding assembly by installing a cross-shaped pedestal and extending the structure using temporary scaffolding across retaining walls, reducing assembly times and shortening the construction period for pier-type pneumatic caisson foundations.
Patent Information
- Application Number
- JP2023068355
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-19
- Publication Date
- 2024-10-31
AI Technical Summary
Existing methods for constructing pier-type pneumatic caisson foundations require repeated assembly and removal of external scaffolding due to ground settlement, which is time-consuming and inefficient, especially during limited construction periods in rivers.
A construction method using temporary scaffolding that involves installing a cross-shaped pedestal on the lower part of the structure, assembling scaffolding on this pedestal, and extending the upper part of the structure using the scaffolding across temporary earth retaining walls, allowing continuous use during subsidence and backfilling processes.
Reduces the number of times scaffolding needs to be assembled and removed, thereby shortening the construction period and optimizing the construction process for pier-type pneumatic caisson foundations.
Smart Images

Figure 2024154520000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a construction method using a temporary scaffold, and more particularly to a construction method for a bridge pier using a temporary scaffold such as a pier-type pneumatic caisson foundation construction. [Background technology]
[0002] Conventionally, the outer scaffolding required for the construction of the pier section of a pier-type pneumatic caisson foundation requires backfilling of the area around the pier before the next pier section is constructed, as the soil around the pier sinks when the caisson is lowered. This requires the assembled outer scaffolding to be removed and reassembled. This assembly and removal work of the outer scaffolding is repeated the number of times that the pier is lifted to be constructed as a caisson foundation. For piers in rivers, the construction period is limited during non-flooding periods, which greatly affects the number of days required for the assembly and removal of the outer scaffolding. Therefore, there is a strong demand for a construction method for a scaffolding platform that can reduce the number of times that the outer scaffolding needs to be assembled and removed for pier-type pneumatic caisson foundation construction.
[0003] For example, Patent Document 1 describes a temporary scaffolding 2 for water's edge construction, which comprises a barge 3 arranged in a floating state on the water surface near the floating structure 1 or 20, a mobile body 4 arranged so as to be movable along the floating structure 1 or 20, and a work stage 8 having one end connected and supported by a support 5 provided on the barge 3 and the other end connected and supported by the mobile body 2, and which makes it possible to move the barge 3, the mobile body 4 and the work stage 8 as a unit along the floating structure 1 or 20 with heavy machinery, equipment, etc. installed on the work stage 8 (see claim 1 in the claims of Patent Document 1, paragraphs
[0014] to
[0024] of the specification, Figures 1 and 2 of the drawings, etc.).
[0004] However, the temporary scaffolding 2 for water's edge construction described in Patent Document 1 had the problem that it could not be applied to structures such as pier-type pneumatic caisson foundation construction, in which the pier foundation and pier are constructed in succession and the width of the structure being constructed narrows along the way.
[0005] Patent Document 2 also describes a scaffolding structure 100 for constructing an underground structure, which comprises a retaining wall 10 constructed so as to slope downward toward the excavation area 1, and scaffolding 20 supported on the retaining wall 10 at a distance from the bottom of the excavation area 1 and used to construct an underground structure in the excavation area 1, and a method of installing the scaffolding for constructing an underground structure (see claims 1 and 3 of Patent Document 2, paragraphs
[0011] to
[0022] of the specification, Figures 1 and 2 of the drawings, etc.).
[0006] However, the scaffolding structure for constructing underground structures and the method of installing scaffolding for constructing underground structures described in Patent Document 2, like the temporary scaffolding for water's edge construction described in Patent Document 1, had the problem that they could not be applied to structures such as pier-type pneumatic caisson foundation construction, where the pier foundation and pier are constructed in succession and the width of the structure to be constructed narrows along the way. [Prior art documents] [Patent documents]
[0007] [Patent Document 1] JP 2007-247359 A [Patent Document 2] JP 2014-148855 A Summary of the Invention [Problem to be solved by the invention]
[0008] Therefore, the present invention has been devised in consideration of the above-mentioned problems, and an object of the present invention is to provide a construction method for temporary scaffolding that can be applied to structures whose horizontal projection area is smaller at the top, and that can reduce the number of times that the scaffolding is assembled and disassembled, thereby shortening the construction period. [Means for solving the problem]
[0009] The construction method using the temporary scaffolding according to claim 1 is a construction method of the temporary scaffolding used when constructing a structure in a space surrounded by a temporary earth retaining wall, comprising: a structure lower part construction step of constructing the lower part of the structure; a scaffolding assembly step of assembling a base by combining steel materials in a grid pattern on the lower part of the structure constructed in the structure lower part construction step and assembling the temporary scaffolding on the base; a structure upper part construction step of constructing the upper part of the structure using the temporary scaffolding assembled in the scaffolding assembly step; The method comprises a subsidence process for subsiding the structure constructed in the upper part construction process, and a backfilling process for filling back soil around the structure that has sunk in the subsidence process, wherein in the subsidence process, the platform is placed on the upper ends of the temporary earth-retaining walls without removing the temporary scaffolding on the platform, and is installed by bridging the upper ends of the temporary earth-retaining walls, and then a structure upper part expansion process is performed to further expand the upper part of the structure that has sunk in the subsidence process using the temporary scaffolding on the platform bridged between the upper ends of the temporary earth-retaining walls.
[0010] The construction method using temporary scaffolding of claim 2 is characterized in that, in the construction method using temporary scaffolding of claim 1, the horizontal projection area of the lower part of the structure is larger than the horizontal projection area of the upper part, and in the process of constructing the upper part of the structure, an upper part having a smaller horizontal projection area than the lower part is constructed using the temporary scaffolding on the platform bridged between the upper ends of the temporary earth-retaining walls.
[0011] The construction method using temporary scaffolding of claim 3 is characterized in that, in the construction method using temporary scaffolding of claim 2, the lower part of the structure is a caisson foundation and the upper part of the structure is a bridge pier. Effect of the Invention
[0012] According to the inventions recited in claims 1 to 3, even in the case of a structure in which the horizontal projection area of the upper part is smaller, the number of times the temporary scaffolding is assembled and dismantled can be reduced, thereby shortening the construction period. [Brief description of the drawings]
[0013] [Figure 1]FIG. 1 is a process explanatory diagram showing a process for constructing a lower part of a structure in a construction method using temporary scaffolding according to an embodiment of the present invention. [Diagram 2] FIG. 2 is a process explanatory diagram showing a scaffolding assembly process of the construction method using the temporary scaffolding. [Diagram 3] FIG. 3 is a process explanatory diagram showing the process of constructing the upper part of a structure in the construction method using the temporary scaffolding described above. [Figure 4] FIG. 4 is a process explanatory diagram showing a subsidence process of the construction method using the temporary scaffolding. [Diagram 5] FIG. 5 is a process explanatory diagram showing a backfilling process of the construction method using the temporary scaffolding. [Figure 6] FIG. 6 is a process explanatory diagram showing the process of expanding the upper part of a structure in the construction method using the temporary scaffolding described above. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0014] Hereinafter, one embodiment of a construction method using a temporary scaffolding according to the present invention will be described in detail with reference to the drawings.
[0015] The construction method using temporary scaffolding according to the embodiment of the present invention is a construction method using temporary scaffolding for constructing a structure in a space surrounded by a temporary earth retaining wall, and will be described by taking as an example a case in which a caisson foundation in which the horizontal projection area of the lower part of the structure is larger than that of the upper part, and a bridge pier in which the horizontal projection area of the upper part is smaller than that of the caisson foundation, are continuously constructed as a structure to be constructed, such as in the case of pier-type pneumatic caisson foundation construction. Note that the temporary earth retaining wall refers to a temporary earth retaining wall that does not require a curing period until the concrete hardens, excluding soil cement wall construction methods such as the parent pile horizontal sheet pile construction method, the steel sheet pile construction method, or the steel pipe sheet pile construction method, and cast-in-place reinforced concrete wall construction methods, and in the illustrated form, a steel sheet pile (sheet pile) SP, which is a temporary earth retaining wall for the steel sheet pile construction method, is exemplified.
[0016] (Structure lower part construction process) In the construction method using the temporary scaffold according to the embodiment of the present invention, first, a structure lower part construction step is performed to construct the lower part of the structure C1, which is a concrete structure. Specifically, as shown in FIG. 1, in this step, rebar assembly, formwork installation, concrete pouring, etc. are performed in a dry area on water, on land, or underground in a space surrounded by a steel sheet pile SP, which is a temporary earth retaining wall, to construct a caisson foundation CF made of reinforced concrete, which is the lower part of the structure. FIG. 1 is a process explanatory diagram showing the structure lower part construction step of the construction method using the temporary scaffold according to the embodiment of the present invention. Note that the reference character CL is a crawler crane CL, which is a lifting machine, and the reference character WG is a work platform WG.
[0017] (Scaffolding assembly process) Next, in the construction method using temporary scaffolding according to this embodiment, a scaffolding assembly process is carried out in which a platform is installed on top of the lower part of the structure constructed in the lower part of the structure construction process by combining steel materials in a crisscross pattern, and then temporary scaffolding is assembled on top of the platform.
[0018] Specifically, as shown in Fig. 2, in this process, steel materials 20 stiffened and reinforced by welding stiffeners and end plates to H-shaped steel are assembled in a grid pattern on the top of the caisson foundation CF constructed in the structure lower part construction process, and the steel materials are fixed to each other with steel frame clamps (crank vises), bolts, etc. to prevent lateral shifting, and a platform 2 is installed. Then, a temporary scaffolding 1 is assembled on the installed platform 2, and the platform 2 and the temporary scaffolding 1 are joined and fixed with steel frame clamps, etc. Fig. 2 is a process explanatory diagram showing the scaffolding assembly process of a construction method using temporary scaffolding according to an embodiment of the present invention.
[0019] Of course, the temporary scaffolding 1 to be assembled may be any general temporary scaffolding such as a wedge-tightened scaffolding (bamboo scaffolding), frame scaffolding, or single-pipe scaffolding, and may be appropriately selected according to the shape of the superstructure (pier P1) to be constructed. It is also possible to construct a combination of multiple types of scaffolding. This temporary scaffolding 1 is not only used as a work scaffolding for constructing the pier P1, which is the superstructure, but is also used as a work passage for entering the attached shaft AS, which is equipped with material locks and manlocks.
[0020] (Structure upper construction process) Next, in the construction method using temporary scaffolding according to the present embodiment, a structure upper part construction step is performed in which the upper part of the structure is constructed using the temporary scaffolding 1 assembled in the previous step. Specifically, as shown in Fig. 3, the temporary scaffolding 1 is used to construct rebar assembly, formwork installation, concrete pouring, etc., to construct a pier P1 made of reinforced concrete, which is the upper part of the structure. Fig. 3 is a process explanatory diagram showing the structure upper part construction step of the construction method using temporary scaffolding according to the embodiment of the present invention.
[0021] (Subsidence process) Next, in the construction method using the temporary scaffolding according to the embodiment, a subsidence process is carried out to subside the structure constructed in the structure lower part construction process and the structure upper part construction process. Specifically, as shown in Fig. 4, the caisson foundation CF and the pier P1, which is the upper structure of the caisson foundation CF, are excavated by the pneumatic caisson construction method and subsided. Fig. 4 is a process explanatory diagram showing the subsidence process of the construction method using the temporary scaffolding according to the embodiment of the present invention.
[0022] A high-pressure work chamber HW is provided below this caisson foundation CF, as shown in Figure 4, and a caisson shovel CE installed in this high-pressure work chamber HW is remotely operated from the ground to excavate the soil and lower the caisson foundation CF and the pier P1. Of course, the caisson shovel CE may be operated automatically and independently to excavate and lower the foundation, or it may be excavated and lowered manually as in the past.
[0023] In addition, as mentioned in the Background Art section, in conventional pier-type pneumatic caisson foundation construction, the soil around the pier P1 also sinks when the caisson is submerged (sinks), so it was necessary to backfill the area around the pier P1 with soil before adding the upper part of the pier P1. For this reason, the outer scaffolding required for the construction of the pier P1 had to be removed once and then reassembled. In addition, this assembly and removal work of the outer scaffolding had to be repeated the number of times the structure was submerged, which caused construction delays.
[0024] In addition, in this process, when the caisson foundation CF and pier P1, which are structure C1, sink, the temporary scaffolding 1 on the platform 2 is placed on the top of the steel sheet piles SP and installed across the top ends of the steel sheet piles SP without having to be removed, making it possible to continue using the temporary scaffolding 1 as a work scaffold. This is to shorten the construction period for the temporary work by eliminating the need to assemble and remove the temporary scaffolding 1 every time structure C1 sinks and is backfilled.
[0025] (backfilling process) Next, in the construction method using the temporary scaffolding according to this embodiment, as shown in Fig. 5, a backfilling process is performed to backfill soil around the caisson foundation CF and pier P1 of the structure C1 that have sunk in the previous process. This is to prevent the steel sheet pile SP from collapsing due to earth pressure or water pressure caused by the surrounding ground subsiding due to the settlement of the structure C1. Fig. 5 is a process explanatory diagram showing the backfilling process of the construction method using the temporary scaffolding according to this embodiment.
[0026] In addition, at this time, the spacing between the steel members 20 of the base 2 is sufficiently secured, so that even with the temporary scaffolding 1 in place, backfilling with soil using a bucket or the like is not impeded, and backfilling can be done in a short time. In other words, the construction period can be shortened in this respect as well.
[0027] (Upper part of structure expansion process) Next, in the construction method using the temporary scaffolding according to this embodiment, as shown in Fig. 6, a structure upper part expansion process is performed to further expand the upper part of the structure C1 that has been lowered in the lowering process, using the temporary scaffolding 1 on the pedestal 2 that has been spanned between the upper ends of the steel sheet piles SP in the previous process. Fig. 6 is a process explanatory diagram showing the structure upper part expansion process of the construction method using the temporary scaffolding according to this embodiment.
[0028] Specifically, in accordance with the settlement of the pier P1, which is the upper part of the structure C1, rebar assembly, formwork installation, concrete pouring, etc. are carried out to expand the part above the pier P1 constructed in the upper part construction process of the structure C1. Also, in accordance with the settlement plan for the structure C1, if necessary, the temporary scaffolding 1 is also extended to the required height.
[0029] Thereafter, the subsidence process, the backfilling process, and the structure upper part extension process are repeated to construct the structure C1, which is then submerged to a predetermined depth and installed. This completes the construction method using the temporary scaffold according to this embodiment, and the structure C1 can be constructed.
[0030] According to the construction method of the temporary scaffolding of this embodiment described above, even in the case of consecutive construction of a caisson foundation CF with a large horizontal projection area and a pier P1 with an upper portion having a smaller horizontal projection area than the caisson foundation CF, as in pier-type pneumatic caisson foundation construction, the number of times the temporary scaffolding 1 is assembled and dismantled can be reduced, thereby shortening the construction period.
[0031] The construction method using the temporary scaffolding according to the embodiment of the present invention has been described in detail above. However, the above-mentioned or illustrated embodiments are merely one embodiment embodied in carrying out the present invention. Therefore, the technical scope of the present invention should not be interpreted as being limited by these. In particular, although the steel sheet pile SP has been described as an example of a temporary earth retaining wall, the temporary earth retaining wall is not limited to the steel sheet pile SP, and the temporary scaffolding 1 may be installed on the top end of the parent H-shaped steel of another dry-type temporary earth retaining wall by bridging the frame 2. However, the steel sheet pile SP has the advantage that the frame 2 can be installed regardless of the installation interval of the H-shaped steel. [Explanation of symbols]
[0032] 1: Temporary scaffolding 2: Stand 20: Steel material C1: Structure CF: Caisson foundation (lower part of structure) P1: Pier (upper part of structure) AS: Attached shaft HW: High pressure work chamber CE: Caisson shovel SP: Steel sheet pile (temporary retaining wall) WG: Work platform CL: Crawler crane (lifting machine)
Claims
1. A construction method using temporary scaffolding to construct a structure in a space surrounded by a temporary earth retaining wall, The method comprises a lower part of a structure construction step of constructing a lower part of the structure, a scaffolding assembly step of assembling steel materials in a lattice pattern on the lower part of the structure constructed in the lower part of the structure construction step to set a platform on the platform and assembling a temporary scaffolding on the platform, an upper part of a structure construction step of constructing an upper part of the structure using the temporary scaffolding assembled in the scaffolding assembly step, a subsidence step of subsiding the structure constructed in the lower part of the structure construction step and the upper part of the structure construction step, and a backfilling step of filling back soil around the structure that has sunk in the subsidence step, In the subsidence step, the temporary scaffolding on the platform is not removed, and the platform is placed on the upper end of the temporary earth retaining wall and is installed between the upper ends of the temporary earth retaining walls. Then, a structure upper part expansion step is performed to further expand the upper part of the structure that has been submerged in the subsidence step using the temporary scaffolding on the platform that has been spanned between the upper ends of the temporary earth retaining walls. A construction method using temporary scaffolding characterized by the above.
2. The structure has a lower portion having a larger horizontal projection area than an upper portion, and in the upper portion construction step, the upper portion having a smaller horizontal projection area than the lower portion is constructed using the temporary scaffolding on the platform bridged between the upper ends of the temporary earth retaining walls. A construction method using the temporary scaffolding according to claim 1.
3. The lower part of the structure is a caisson foundation, and the upper part of the structure is a bridge pier. A construction method using the temporary scaffolding according to claim 2.