Forecasting apparatus, forecasting method, and forecasting program
The landing prediction device forecasts project outcomes by incorporating expected order changes and budget adjustments, addressing uncertainties in uncontracted projects, enhancing budgeting and profit estimation in industries such as construction and IT.
Patent Information
- Application Number
- JP2023069312
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-20
- Publication Date
- 2024-10-31
- Estimated Expiration
- 2043-04-20
AI Technical Summary
Existing systems fail to predict project outcomes accurately when there are no contracts but expected orders, leading to uncertainties in budgeting and profit estimation.
A landing prediction device and method that includes contract information, project budget data, and cost details, allowing for the input of expected increases or decreases in contract amounts, estimated budget amounts, and future costs, even in the absence of contracts, to calculate project outcomes.
Enables accurate forecasting of project outcomes by considering uncontracted orders, facilitating better budgeting and profit estimation, applicable to industries like construction and IT.
Smart Images

Figure 2024154998000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a landing prediction device, a landing prediction method, and a landing prediction program. [Background technology]
[0002] For example, in the construction industry, there are situations where an increase in construction work is expected for an ongoing construction project even though no contract has been signed, and the work will proceed even though no purchase order has been received. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2019-21081 A Summary of the Invention [Problem to be solved by the invention]
[0004] However, the above-mentioned Patent Document 1 does not state anything about making a final outcome forecast that takes into account uncontracted orders for an ongoing project when further orders (e.g., additional construction) are expected, even though they have not yet been contracted.
[0005] The present invention has been made in consideration of the above, and aims to provide a landing prediction device, a landing prediction method, and a landing prediction program that are capable of making landing predictions taking into account uncontracted orders for an ongoing project when further orders are expected although not yet contracted. [Means for solving the problem]
[0006] In order to solve the above-mentioned problems and achieve the object, the present invention is characterized in that the control unit is configured to be able to access contract information data including project identification information, order identification information, and contract amount, project budget data including project identification information, order identification information, cost item classification, and budget amount, and project cost detail data including voucher number, project identification information, order identification information, cost item classification, and cost amount, and is equipped with an end-of-life forecast input means for inputting a planned increase / decrease amount relative to the contract amount, an estimated budget amount and future planned costs for each cost item classification, in the case where a contract has not been signed but further orders are expected, for the target project identification information and order identification information in response to an operator's operation on the end-of-life forecast screen, and creating project end-of-life forecast data including the project identification information, order identification information, cost item classification, budget amount, estimated budget amount, accumulated incurred costs which are the accumulation of cost amounts, future planned costs, and a final expected amount calculated as the accumulated incurred costs + future planned costs, in accordance with the contract information data, the project budget data, and the project cost detail data.
[0007] According to another aspect of the present invention, the project end forecast data may include a difference between the actual and forecast amounts calculated by adding the budget amount to the estimated budget amount and subtracting the final end forecast amount.
[0008] According to another aspect of the present invention, the end result forecast input means may output a profit amount calculated by summing up the contract amount+the expected increase / decrease amount-the final end result forecast.
[0009] According to another aspect of the present invention, the planned increase / decrease amount and the estimated budget amount for each cost item category may be input in a plurality of patterns.
[0010] According to another aspect of the present invention, the planned increase / decrease amount and the estimated budget amount for each cost item category may be configured to allow input of negative amounts.
[0011] In addition, according to one aspect of the present invention, the final forecast input means may create project final forecast estimated budget data including project identification information, order identification information, estimated budget identification information, planned increase / decrease amount, cost item classification, and estimated budget amount.
[0012] In order to solve the above-mentioned problems and achieve the object, the present invention provides a method for forecasting a project outcome executed by an information processing device having a control unit, the control unit being configured to be able to access contract information data including project identification information, order identification information, and a contract amount, project budget data including project identification information, order identification information, cost item classification, and budget amount, and project cost detail data including a slip number, project identification information, order identification information, cost item classification, and cost amount, and the control unit being configured to access a target project's cost detail data in response to an operator's operation on a project outcome forecast screen executed by the control unit. For the project identification information and order identification information, when a contract has not been signed but further orders are expected, a planned increase / decrease in the contract amount, an estimated budget amount for each cost item category, and future planned costs are input, and a project end forecast input process may be included in which, by referring to the contract information data, the project budget data, and the project cost detail data, project end forecast data is created that includes the project identification information, the order identification information, the cost item category, the budget amount, the estimated budget amount, the accumulated incurred costs which are the accumulation of the cost amounts, the future planned costs, and a final expected amount calculated as the accumulated incurred costs + the future planned costs.
[0013] In order to solve the above-mentioned problems and achieve the object, the present invention provides a performance forecasting program to be executed by an information processing device having a control unit, the control unit being configured to be able to access contract information data including project identification information, order identification information, and a contract amount, project budget data including project identification information, order identification information, cost item classification, and budget amount, and project cost detail data including a voucher number, project identification information, order identification information, cost item classification, and cost amount, and the control unit is configured to access target project identification information and The program is characterized in that it is an outcome forecast program for executing an outcome forecast input step for inputting the planned increase / decrease in the contract amount and the estimated budget amount and future planned costs for each cost item category for order identification information when a contract has not yet been awarded but further orders are expected, and creating project outcome forecast data including project identification information, order identification information, cost item category, budget amount, estimated budget amount, accumulated incurred costs which are the accumulation of cost amounts, future planned costs, and a final expected outcome calculated as accumulated incurred costs + future planned costs by referring to the contract information data, the project budget data, and the project cost detail data. Effect of the Invention
[0014] According to the present invention, when further orders are expected for an ongoing project even though they have not yet been contracted, it is possible to make a forecast of the outcome taking into account the uncontracted orders. [Brief description of the drawings]
[0015] [Figure 1] FIG. 1 is a block diagram showing an example of the configuration of a landing prediction device according to the present embodiment. [Diagram 2] FIG. 2 is a diagram showing a flow for explaining an outline of the overall processing of the landing prediction device according to the present embodiment. [Diagram 3] FIG. 3 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. [Figure 4]FIG. 4 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. [Diagram 5] FIG. 5 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. [Figure 6] FIG. 6 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. [Figure 7] FIG. 7 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. [Figure 8] FIG. 8 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. [Figure 9] FIG. 9 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. [Figure 10] FIG. 10 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. [Figure 11] FIG. 11 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. [Figure 12] FIG. 12 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. [Figure 13] FIG. 13 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. [Figure 14] FIG. 14 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. [Figure 15] FIG. 15 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. [Figure 16] FIG. 16 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. [Figure 17] FIG. 17 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. [Figure 18]FIG. 18 is a diagram for explaining a specific example of the processing of the control unit of the landing prediction device according to the present embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0016] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described in detail with reference to the drawings. However, the present invention is not limited to the embodiment.
[0017] [1. Overview] For example, in the construction industry, there are situations where an increase in work is expected for an ongoing project even though no contract has been signed, and the work will proceed even though no purchase order has been received. Since no purchase order has been received, the order and budget do not include the increase in work, but there is a demand to understand the final amount including the increase in work.
[0018] However, in the past, it was only possible to register forecasts for contracts that had already been ordered and budgeted. This resulted in issues such as (1) when estimating costs for construction work that has not yet been contracted and has no budget, it is not possible to grasp profits because there is no budget, (2) when managing indirect costs of the completed work calculated from the contract amount, it is not possible to accurately estimate them because there is no contract, and (3) it is not possible to forecast revenues that take into account orders that have not yet been contracted.
[0019] Therefore, in this embodiment, we propose a system that can make a final forecast taking into account the planned increase / decrease in the amount of increase or decrease and the estimated budget, for example, when an increase in construction work is already expected for an ongoing construction project, even if no contract has been signed.
[0020] According to the present embodiment of the device for predicting final results, (1) the order amount for uncontracted items can be registered as the expected increase / decrease amount, (2) an estimated budget for the expected increase / decrease amount can be registered, (3) a final result that takes into account the expected increase / decrease amount and the estimated budget can be registered, and (4) multiple patterns of expected increase / decrease amount and estimated budget can be registered. This makes it possible to manage expected costs, including the amount of orders to be received in the future, and to predict income and expenditure.
[0021] The landing prediction device of this embodiment is widely applicable to industries such as the construction industry and the IT industry.
[0022] [2. Configuration] An example of the configuration of the landing prediction device 100 according to this embodiment will be described with reference to Fig. 1. Fig. 1 is a block diagram showing an example of the configuration of the landing prediction device 100.
[0023] The landing prediction device 100 is a commercially available desktop personal computer. The landing prediction device 100 is not limited to a stationary information processing device such as a desktop personal computer, but may be a portable information processing device such as a commercially available notebook personal computer, a PDA (Personal Digital Assistant), a smartphone, or a tablet personal computer.
[0024] The landing prediction device 100 includes a control unit 102, a communication interface unit 104, a storage unit 106, and an input / output interface unit 108. The units included in the landing prediction device 100 are connected to each other so as to be able to communicate with each other via any communication path.
[0025] The communication interface unit 104 communicably connects the landing prediction device 100 to the network 300 via a communication device such as a router and a wired or wireless communication line such as a dedicated line. The communication interface unit 104 has a function of communicating data with other devices via a communication line. Here, the network 300 has a function of connecting the landing prediction device 100 and the server 200 so that they can communicate with each other, and is, for example, the Internet or a LAN (Local Area Network).
[0026] An input device 112 and an output device 114 are connected to the input / output interface unit 108. The output device 114 may be a monitor (including a touch panel), a speaker, or a printer. The input device 112 may be a keyboard, a mouse, a microphone, or a monitor that cooperates with a mouse to realize a pointing device function. In the following, the output device 114 may be referred to as the monitor 114 or the printer 114, and the input device 112 may be referred to as the keyboard 112 or the mouse 112.
[0027] The storage unit 106 stores various databases, tables, files, and the like. The storage unit 106 records computer programs for cooperating with an OS (Operating System) to give instructions to a CPU (Central Processing Unit) to perform various processes. For example, memory devices such as RAM (Random Access Memory) and ROM (Read Only Memory), fixed disk devices such as hard disks, flexible disks, and optical disks can be used as the storage unit 106. The storage unit 106 also stores contract information data, project budget data, project cost details data, project completion forecast data, project completion forecast approximate budget data, and the like.
[0028] The contract information data may include project identification information (project number and / or project name), order identification information (order number, line number), department, order date, construction period, and contract amount (eg, contract price).
[0029] The project budget data may include project identification information (project number and / or project name), order identification information (order number, line number), registration date, project cost item classification, and budget amount.
[0030] Project cost detail data may include document identification information (document number, line number), project identification information (project number and / or project name), order identification information (order number, line number), accounting date, project cost account classification, and cost amount.
[0031] The project completion forecast data may include project identification information (project number and / or project name), order identification information (order number, line number), project cost item classification, budget amount, estimated budget amount, cumulative incurred costs, future planned costs, final completion forecast, and actual / budget variance.
[0032] The project completion estimated budget data may include project identification information (project number and / or project name), order identification information (order number, line number), estimated budget identification information (estimated budget name and / or estimated budget code), estimated budget year and month, expected increase / decrease amount, project cost item classification, and estimated budget amount.
[0033] The control unit 102 is a CPU or the like that comprehensively controls the landing prediction device 100. The control unit 102 has an internal memory for storing control programs such as an OS, programs that define various processing procedures, and required data, and executes various information processing based on these stored programs.
[0034] The control unit 102 is configured to be able to access the contract information data, project budget data, project cost detail data, project end-of-life forecast data, and project end-of-life forecast approximate budget data stored in the storage unit 106. These data may be stored in other locations (e.g., the server 200) as long as they are accessible by the control unit 102.
[0035] The control unit 102 conceptually includes, in terms of functions, a contract information input unit 102a, a budget input unit 102b, a cost appropriation input unit 102c, a final result forecast input unit 102d, and a screen display control unit 102e.
[0036] The contract information input unit 102a inputs contract information data in response to, for example, an operator's operation on a contract information input screen (not shown) displayed on the monitor 14, and stores the data in the storage unit .
[0037] The budget input unit 102b inputs project budget data in response to, for example, an operator's operation on a budget input screen (not shown) displayed on the monitor 14, and stores the data in the storage unit .
[0038] The cost appropriation input unit 102c inputs project cost detail data in response to, for example, an operator's operation on a cost appropriation input screen (not shown) displayed on the monitor 14, and stores the data in the storage unit 106.
[0039] The final forecast input unit 102d, for example, in response to the operator's operations on the final forecast list screen and final forecast input screen (see Figures 6 to 12) displayed on the monitor 14, inputs the planned increase / decrease in the contract amount, the estimated budget amount and future planned costs for each cost item category for the target project identification information and order identification information, when a contract has not been signed but further orders are expected, and creates project final forecast data including the project identification information, order identification information, cost item category, budget amount, estimated budget amount, accumulated incurred costs which are the accumulation of cost amounts, future planned costs, and a final forecast amount calculated as the accumulated incurred costs + future planned costs, by referring to the contract information data, project budget data, and project cost detail data, and stores the data in the memory unit 106.
[0040] The project end forecast data may include the difference between the actual and forecast amounts, which is calculated by adding the budget amount to the estimated budget amount and subtracting the final end forecast amount.
[0041] The arrival forecast input unit 102d may display and output a profit amount calculated by summing up the contract amount+the expected increase / decrease amount-the final arrival forecast.
[0042] The planned increase / decrease amount and the estimated budget amount for each cost item category may be input in multiple patterns.
[0043] The planned increase / decrease amount and the estimated budget amount for each cost item category may be set to allow negative amounts to be input.
[0044] In addition, the final forecast input unit 102d may create project final forecast estimated budget data including project identification information, order identification information, estimated budget identification information, planned increase / decrease amount, cost item classification, and estimated budget amount, and store the data in the memory unit 106.
[0045] The screen display control unit 102e controls the display and input of various screens (eg, contract information input screen, budget input screen, cost accounting input screen, estimated arrivals list screen, estimated arrivals input screen, etc.) displayed on the monitor 114.
[0046] [3. Specific Examples] A specific example of the processing of the control unit 102 of the landing prediction device 100 in this embodiment will be described with reference to FIGS.
[0047] (3-1. Overall processing) FIG. 2 is a diagram showing a flow for explaining an outline of the overall processing of the control unit 102 of the landing prediction device 100 in this embodiment.
[0048] An outline of the overall processing of the control unit 102 of the landing prediction device 100 in this embodiment will be described with reference to Fig. 2. In Fig. 2, the contract information input unit 102a executes a contract information input process (step S1). Specifically, in the contract information input process, the contract information input unit 102a inputs contract information data in response to an operator's operation on a contract information input screen (not shown) displayed on the monitor 14, for example, and stores the data in the storage unit 106.
[0049] The budget input unit 102b executes a budget input process (step S2). Specifically, in the budget input process, the budget input unit 102b inputs project budget data in response to, for example, an operator's operation on a budget input screen (not shown) displayed on the monitor 14, and stores the data in the storage unit 106.
[0050] The cost appropriation input unit 102c executes a cost appropriation input process (step S3). Specifically, in the cost appropriation input process, the cost appropriation input unit 102c inputs project cost detail data in response to, for example, an operation by an operator on a cost appropriation input screen (not shown) displayed on the monitor 14, and stores the data in the storage unit 106.
[0051] The arrival forecast input unit 102d executes the arrival forecast input process (step S4). Specifically, in the arrival forecast input process, the arrival forecast input unit 102d, for example, in response to the operator's operation on the arrival forecast list screen and the arrival forecast input screen (see Figs. 6 to 12) displayed on the monitor 14, inputs the planned increase / decrease amount with respect to the contract amount, the estimated budget amount and the future planned cost for each cost item classification when the target project identification information and order identification information are not yet contracted but further orders are expected, and creates project arrival forecast data including the project identification information, order identification information, cost item classification, budget amount, estimated budget amount, accumulated incurred cost which is the accumulation of the cost amount, future planned cost, and the final estimated amount calculated by the accumulated incurred cost + future planned cost by referring to the contract information data, project budget data, and project cost detail data, and stores the data in the storage unit 106. In addition, the final forecast input unit 102d may create project final forecast estimated budget data including project identification information, order identification information, estimated budget identification information, planned increase / decrease amount, cost item classification, and estimated budget amount, and store the data in the memory unit 106.
[0052] In this case, the project end result forecast data may include the difference between the budget amount, the estimated budget amount, and the final end result forecast. The end result forecast input unit 102d may display and output the profit amount calculated by the sum of the contract amount, the estimated increase / decrease amount, and the final end result forecast. The estimated increase / decrease amount and the estimated budget amount for each cost item category may be input in multiple patterns. The estimated increase / decrease amount and the estimated budget amount for each cost item category may be input as negative amounts.
[0053] (3-2. Sample data) 3 to 18 are diagrams showing sample data for explaining a specific example of the processing of the control unit 102 of the landing prediction device 100 in this embodiment. A specific example of the processing of the control unit 102 of the landing prediction device 100 in this embodiment will be explained with reference to Figs. 3 to 18. In the following explanation, the unit of monetary amount is always "yen", and the notation thereof will be omitted.
[0054] (S1: Contract information input process) A specific example of the contract information input process will be described with reference to Fig. 3. Project information is registered by the contract information input process. The contract information input unit 102a inputs contract information data in response to, for example, an operator's operation on a contract information input screen (not shown) displayed on the monitor 14, and stores the data in the storage unit 106.
[0055] FIG. 3 is a diagram showing an example of contract information data. The contract information data includes the following items: project number, order number, line number, project name, department, order date, construction period, and contract amount (contract amount). In the example shown in the figure, the first line includes project number "PJ0001", order number "JU0001", line number "1", project name "New Factory B Area Installation Work", department "B001: First Construction Department", order date "2022 / 6 / 1", construction period "2022 / 6 / 1~2024 / 3 / 31", and contract amount "10,000,000".
[0056] Regarding this project number "PJ0001", it has not yet been contracted (ordered), however, an additional order for "3,000,000" is planned for May 1, 2023, and an additional order for "1,000,000" is planned for December 1, 2023.
[0057] (S2: Budget input process) A specific example of the budget input process will be described with reference to Fig. 4. The budget input process is used to register a budget. The budget input unit 102b inputs project budget data in response to, for example, an operator's operation on a budget input screen (not shown) displayed on the monitor 14, and stores the data in the storage unit 106.
[0058] FIG. 4 is a diagram showing an example of project budget data. The project budget data includes the following items: project number, order number, line number, project name, registration date, PJ cost item classification, and budget amount. In the example shown in the figure, the first line is project number "PJ0001", order number "JU0001", line number "1", project name "new factory B area installation work", registration date "2022 / 6 / 1", PJ cost item classification "material cost", budget amount "1,000,000", and the fifth line is project number "PJ0001", order number "JU0001", line number "1", project name "new factory B area installation work", registration date "2022 / 6 / 1", PJ cost item classification "indirect cost", and budget amount "500,000". The budget amount for indirect expenses will be automatically calculated as 5% of the contract amount (500,000 = 10,000,000 x 5%).
[0059] (S3: Cost entry processing) A specific example of the cost accounting input process will be described with reference to Fig. 5. The cost accounting input process is used to account for costs. The cost accounting input unit 102c inputs project cost detail data in response to, for example, an operator's operation on a cost accounting input screen (not shown) displayed on the monitor 14, and stores the data in the storage unit 106.
[0060] FIG. 5 is a diagram showing an example of project cost detail data. The project cost detail data includes the following items: slip number, line number, project number, order number, line number, accounting date, PJ cost item classification, and cost amount. In the example shown in the figure, the first line includes the slip number "GK001", line number "1", project number "PJ0001", order number "JU0001", line number "1", accounting date "2023 / 2 / 1", PJ cost item classification "material cost", and cost amount "900,000", while the fifth line includes the slip number "GK001", line number "1", project number "PJ0001", order number "JU0001", line number "1", accounting date "2023 / 2 / 1", PJ cost item classification "indirect cost", and cost amount "300,000". The overhead costs in the cost amount are automatically calculated as 60% of the completed amount, out of 5% of the contract amount (300,000 = 10,000,000 x 5% x 60%).
[0061] (S4: Landing cost entry processing) A specific example of the final cost calculation input process will be described with reference to Figures 6 to 18. For example, in response to an operator's operation on the final cost forecast list screen and final cost forecast input screen displayed on the monitor 114, the final cost forecast input unit 102d inputs the planned increase / decrease amount for the contract amount, the estimated budget amount for each cost item category, and the future planned cost for the target project identification information and order identification information, when a contract has not been signed but further orders are expected, and creates project final cost forecast data including the project identification information, order identification information, cost item category, budget amount, estimated budget amount, accumulated incurred cost which is the accumulated total of the cost amount, future planned cost, and the final estimated amount calculated by the accumulated incurred cost + future planned cost, with reference to the contract information data, project budget data, and project cost detail data, and stores the data in the storage unit 106. In addition, the final estimate input unit 102d creates project final estimate budget data including project identification information, order identification information, estimated budget identification information, estimated increase / decrease amount, cost item classification, and estimated budget amount, and stores it in the memory unit 106.
[0062] FIG. 6 is a diagram showing a display example of the arrival forecast list screen 400. A project for which arrival forecast input is to be performed is selected from the arrival forecast list screen 400. The arrival forecast list screen 400 includes an extraction condition designation area for designating extraction conditions such as the fiscal year and month, department, project number, and order number, a project list display area in which details of projects that meet the extraction conditions are displayed, and a display button. The project list display area displays data for the items of project number, order number, project name, and department. When the extraction conditions are designated in the extraction condition designation area and the display button is pressed, contract information data is extracted using the extraction conditions as a key, and data for the project number, order number, project name, and department are displayed in the project list display area. When a target is selected in the project list display area and double-clicked, the arrival forecast input screen 500 is displayed.
[0063] In the example shown in FIG. 6, the data shown in the figure is displayed in the project list display area from the contract information data using the accounting year and month "2023 / 3" and department "B001" as keys. The first line displays the project number "PJ0001", order number "JU0001", line number "1", project name "New Factory B Area Installation Work", and department "B001: 1st Construction Department". When the first line is selected and double-clicked, the expected end result input screen 500 as shown in FIG. 7 is displayed.
[0064] 7 is a diagram showing a display example of a final forecast input screen 500. The final forecast input screen 500 includes a header area 501 that displays the accounting year and month, project number, order number-line number, and a details area 502 that displays the final forecast or rough estimate according to a switching button.
[0065] Figure 7 shows the case where final forecast is selected with the switch button in the details area 502, and displays the final forecast header area 510 of the contract amount, planned increase / decrease amount, and initial amount, the final forecast detail area (row number, project cost item classification, budget amount, estimated budget, budget total, accumulated costs incurred, future planned costs, final forecast, variance between forecast and actual) 511, and the total profit amount.
[0066] Figure 8 shows the case where estimate forecast is selected with the switch button in the details area 502, and an estimate budget header area 520 including the estimate budget code, estimate budget name, estimate budget year and month, and planned increase / decrease amount, an estimate budget details area (row number, project cost item classification, estimate budget) 521, and a confirm button are displayed.
[0067] In the landing prediction input screen 500, hatched cells are ones that the operator cannot input (automatic input / display), and non-hatched cells are ones that the operator can input.
[0068] 7, the header area 501 of the arrival forecast input screen 500 displays the fiscal year specified on the arrival forecast list screen 400, and the project number, order number-line number of the contract information data of the line selected in the project list display area. In the example shown in the figure, the fiscal year and month "2023 / 3", project number "PJ0001", and order number-line number "JU0001-1" are displayed.
[0069] Furthermore, when forecasted end result is selected in the details area 502 shown in FIG. 7, the forecasted end result header area 510 displays the contract amount of the contract information data for the row selected in the project list display area. The planned increase / decrease amount is displayed as "0 yen" as the initial value. The head amount is displayed as the contract amount + planned increase / decrease amount. In the example shown in the figure, the contract amount "10,000,000", the planned increase / decrease amount "0", and the head amount "10,000,000" are displayed.
[0070] In the estimated end result details area 511, using the selected project number and order number-line number as keys, the project budget data and project cost detail data are referenced to display the project cost item category, budget amount, estimated budget amount, budget total (= budget amount + estimated budget amount), accumulated incurred costs, future planned costs, final end result (= accumulated incurred costs + future planned costs), and actual / budget variance (= budget total - final end result). For the estimated budget amount, the data entered in the estimated budget details area 521 is set. For the future planned costs, the operator enters them excluding indirect costs.
[0071] Also, as shown in Fig. 8, when the estimated budget is selected in the detail area 502, the estimated budget detail area 521 displays the same project cost item classification as the final forecast detail area 511. As shown in Fig. 9, the operator inputs data in the estimated budget header area 520, inputs data on the general budget other than indirect costs in the estimated budget detail area 521 (indirect costs are automatically displayed), and presses the Confirm button, whereupon the data input in the estimated budget header area 520 and the estimated budget detail area 521 are displayed in the Confirm area 522 (see Fig. 9). When the Reflect button is checked, the planned increase / decrease amount and the estimated budget amount in the Confirm area 522 are reflected in the planned increase / decrease amount in the final forecast header area 510 of the detail area 502 and the estimated budget amount in the final forecast detail area 511.
[0072] 9, the operator enters the estimated budget code "A", the estimated budget name "Estimated A Angle Height", the estimated budget year and month "2023 / 5", and the planned increase / decrease amount "3,000,000" in the estimated budget header area 520. In addition, in the estimated budget details area 521, the operator enters "800,000", "1,300,000", "500,000", and "200,000" in the project cost item categories "material costs", "subcontract costs", "labor costs", and "expenses", respectively. The overhead cost of "150,000" (calculated as 5% of the planned increase / decrease amount (150,000 = 3,000,000 x 5%) and the total of "2,950,000" are automatically entered (displayed). When the operator presses the Confirm button, the data about the estimated budget "A" entered in the estimated budget header area 520 and the estimated budget details area 521 are displayed in the Confirmation area 522, as shown in FIG. 9.
[0073] In addition, the planned increase / decrease amount and the estimated budget can be registered (input) in multiple patterns, and multiple patterns of the estimated budget can be set as the estimated budget of the final forecast details. FIG. 10 is a diagram showing an example of the case where multiple patterns of the planned increase / decrease amount and the estimated budget are registered. The example shown in FIG. 10 shows an example in which an estimated budget "B" (planned increase / decrease amount "1,000,000") is registered in addition to the estimated budget "A" (planned increase / decrease amount "3,000,000"). As shown in FIG. 10, in the estimated budget header area 520, the operator inputs the estimated budget code "B", the estimated budget name "Estimate B Angle Height", the estimated budget year / month "2023 / 12", and the planned increase / decrease amount "1,000,000". In addition, in the estimated budget details area 521, the operator enters "200,000," "400,000," "200,000," and "100,000" into the project cost item categories of "material costs," "subcontract costs," "labor costs," and "expenses," respectively. Indirect costs of "50,000" and the total of "950,000" are automatically entered (displayed). When the operator presses the Confirm button, the data about the estimated budget "B" entered in the estimated budget header area 520 and estimated budget details area 521 is displayed in the Confirm area 522, as shown in FIG. 10.
[0074] Then, when the operator checks the reflect button for estimated budget "A" as shown in Figure 12, the expected increase / decrease amount of "3,000,000" is reflected in the final result header area 510 of the details area 502, and the estimated budget in the final result detail area 511 (cost item categories of "materials", "outsourcing", "labor", "expenses", and "overhead" of "800,000", "1,300,000", "500,000", "200,000", and "150,000", totaling "2,950,000") is reflected as shown in Figure 11. The total budget (= budget amount + estimated budget) is also updated.
[0075] In FIG. 11, the operator inputs the future planned costs in the estimated final cost details area 511. In the example shown in FIG. 11, the operator inputs "1,000,000", "2,800,000", "950,000", and "400,000" into the project cost item categories of "material costs", "outsourcing costs", "labor costs", and "expenses", respectively. Indirect costs of "350,000" and a total of "5,500,000" are automatically input (displayed). Indirect costs are calculated as the final estimated final cost minus the accumulated cost incurred. In this example, the calculation is the final estimated final cost of "650,000 (indirect costs taking into account the estimated budget) - accumulated cost incurred of "300,000 (60% of the budget amount of "500,000")" = 350,000. The final forecast (= accumulated costs incurred + future planned costs), the difference between the budget and actual results (= total budget - final forecast), and the profit amount (= sum of initial amount - final forecast) are updated. In the example shown in the figure, the difference between the budget and actual results for material costs is updated to "-100,000 (= 1,800,000 - 1,900,000)" and the profit amount is updated to "1,100,000 (= 13,000,000 - 11,900,000)."
[0076] When a registration button (not shown) is pressed, the project arrival forecast data and the project arrival forecast estimated budget data corresponding to the input contents of the arrival forecast input screen 500 are registered in the storage unit 206. In the case of the input contents of Figures 11 and 12, the project arrival forecast data and the project arrival forecast estimated budget data as shown in Figures 13(A) and 13(B) are registered.
[0077] Fig. 13(A) is a diagram showing an example of project end forecast data. The project end forecast data includes the following items: project number, order number, line number, project cost item category, budget amount, estimated budget amount, accumulated incurred costs, future planned costs, final end forecast, and actual / budgeted difference. In the example shown in the figure, the first line contains project number "PJ0001", order number "JU0001", line number "1", project cost item category "material cost", budget amount "1,000,000", estimated budget amount "800,000", accumulated incurred costs "900,000", future planned costs "1,000,000", final end forecast "1,900,000", and actual / budgeted difference "-100,000".
[0078] 13B is a diagram showing an example of estimated project end-of-year budget data. The estimated project end-of-year budget data includes the following fields: project number, order number, line number, estimated budget name, estimated budget year and month, expected increase or decrease amount, project cost item classification, and estimated budget amount. In the example shown in the same figure, the first line has the project number "PJ0001", order number "JU0001", line number "1", estimated budget name "Estimated A, high angle", estimated budget year and month "2023 / 5", planned increase / decrease amount "3,000,000", project cost item category "material costs", and estimated budget amount "800,000". The sixth line has the project number "PJ0001", order number "JU0001", line number "1", estimated budget name "Estimated B, high angle", estimated budget year and month "2023 / 12", planned increase / decrease amount "1,000,000", project cost item category "material costs", and estimated budget amount "200,000".
[0079] Figure 15 shows the case where the operator checks the reflect button for both estimated budget "A" and estimated budget "B" in the confirmation area 522 of the details area 502. In this case, as shown in Figure 14, the expected final result header area 510 of the details area 502 reflects the planned increase / decrease amount of "4,000,000" as the sum of estimated budget "A" and estimated budget "B", and the expected final result detail area 511 reflects the cost item categories of "material costs", "subcontract costs", "labor costs", "expenses", and "indirect costs" of "1,000,000", "1,700,000", "700,000", "300,000", and "200,000", totaling "3,900,000". From now on, the planned costs will be the same as those in Figure 11 for "material costs," "outsourcing costs," "labor costs," and "expenses," and the overhead costs will be automatically entered as "400,000 (= final estimated cost of 700,000 - cumulative cost of 300,000)." The total budget, final estimated cost, actual cost difference, and profit amount will also be updated.
[0080] When a registration button (not shown) is pressed, the project arrival forecast data and the project arrival forecast estimated budget data corresponding to the input contents of the arrival forecast input screen 500 are registered in the storage unit 206. In the case of the input contents of Figures 14 and 15, the project arrival forecast data and the project arrival forecast estimated budget data as shown in Figures 16(A) and 16(B) are registered.
[0081] It is possible to input negative amounts for the planned increase / decrease amount and the estimated budget. Figures 17 and 18 are diagrams showing a display example of the details area 502 of the arrival forecast input screen 500 when negative amounts are input for the planned increase / decrease amount and the estimated budget.
[0082] As described above, according to this embodiment, in response to an operator's operation on the arrival forecast screen, the arrival forecast input unit 102d is provided which inputs the planned increase / decrease amount with respect to the contract amount, the estimated budget amount and future planned costs for each cost item category for the target project identification information and order identification information in response to an operation by an operator on the arrival forecast screen, when an order is not yet contracted but further orders are expected, and creates project arrival forecast data including the project identification information, order identification information, cost item category, budget amount, estimated budget amount, accumulated incurred costs which are the accumulation of cost amounts, future planned costs, and a final arrival forecast amount calculated as the accumulated incurred costs + future planned costs, by referring to the contract information data, the project budget data, and the project cost detail data. Therefore, when an order is not yet contracted but further orders are expected for an ongoing project, it is possible to make an arrival forecast that takes into account uncontracted orders.
[0083] [4. Contribution to the United Nations-led Sustainable Development Goals (SDGs)] This embodiment can contribute to improving business efficiency and promoting appropriate management decisions by companies, thereby contributing to goals 8 and 9 of the SDGs.
[0084] Furthermore, this embodiment can contribute to reducing waste and promoting paperless and electronic systems, thereby contributing to the achievement of goals 12, 13, and 15 of the SDGs.
[0085] Furthermore, this embodiment can contribute to strengthening control and governance, making it possible to contribute to Goal 16 of the SDGs.
[0086] 5. Other embodiments The present invention may be embodied in various different embodiments other than those described above within the scope of the technical concept set forth in the claims.
[0087] For example, among the processes described in the embodiments, all or part of the processes described as being performed automatically can be performed manually, or all or part of the processes described as being performed manually can be performed automatically using known methods.
[0088] In addition, the processing procedures, control procedures, specific names, information including parameters such as registered data and search conditions for each process, screen examples, and database configurations shown in this specification and drawings may be changed as desired unless otherwise specified.
[0089] Furthermore, with regard to the landing prediction device 100, each of the illustrated components is a functional concept, and does not necessarily have to be physically configured as illustrated.
[0090] For example, the processing functions of the landing prediction device 100, particularly the processing functions performed by the control unit, may be realized in whole or in part by a CPU and a program interpreted and executed by the CPU, or may be realized as hardware using wired logic. The program is recorded in a non-transient computer-readable recording medium that includes programmed instructions for causing an information processing device to execute the processes described in this embodiment, and is mechanically read by the landing prediction device 100 as necessary. That is, a computer program for giving instructions to the CPU in cooperation with the OS and performing various processes is recorded in a storage unit such as a ROM or HDD (Hard Disk Drive). This computer program is executed by being loaded into a RAM, and cooperates with the CPU to form a control unit.
[0091] In addition, this computer program may be stored in an application program server connected to the landing prediction device 100 via any network, and it is also possible to download all or part of it as needed.
[0092] In addition, the program for executing the process described in this embodiment may be stored in a non-transient computer-readable recording medium, or may be configured as a program product. Here, the "recording medium" includes any "portable physical medium" such as a memory card, a Universal Serial Bus (USB) memory, a Secure Digital (SD) card, a flexible disk, a magneto-optical disk, a ROM, an Erasable Programmable Read Only Memory (EPROM), an Electrically Erasable and Programmable Read Only Memory (EEPROM (registered trademark)), a Compact Disk Read Only Memory (CD-ROM), a Magneto-Optical disk (MO), a Digital Versatile Disk (DVD), and a Blu-ray (registered trademark) Disc.
[0093] Moreover, a "program" is a data processing method written in any language or description method, and may be in any form, such as source code or binary code. Note that a "program" is not necessarily limited to a single configuration, but also includes a distributed configuration as multiple modules or libraries, and a program that achieves its function by working with a separate program, such as an OS. Note that the specific configuration and reading procedure for reading a recording medium in each device shown in the embodiments, as well as the installation procedure after reading, may use well-known configurations and procedures.
[0094] The various databases etc. stored in the memory unit are storage means such as memory devices such as RAM and ROM, fixed disk devices such as hard disks, flexible disks, and optical disks, and store various programs, tables, databases, and web page files etc. used for various processes and providing websites.
[0095] The landing prediction device 100 may be configured as an information processing device such as a known personal computer or a workstation, or may be configured as the information processing device to which any peripheral device is connected. The landing prediction device 100 may be realized by implementing software (including programs or data, etc.) that causes the device to realize the processing described in this embodiment.
[0096] Furthermore, the specific form of distribution and integration of the devices is not limited to that shown in the drawings, and all or part of them can be functionally or physically distributed and integrated in any unit according to various additions or functional loads. In other words, the above-mentioned embodiments can be implemented in any combination, or the embodiments can be implemented selectively. [Explanation of symbols]
[0097] 100 Landing Prediction Device 102 Control section 102a Contract information input section 102b Budget input section 102c Cost Accounting Input Section 102d Landing prediction input section 102e Screen display control unit 104 Communication interface section 106 Storage section 108 Input / Output Interface Section 112 Input Devices 114 Output Device 200 Servers 300 Network 400 Landing forecast list screen 500 Landing prediction input screen 501 Header Area 502 Details Area 510 Landing Prediction Header Area 511 Landing forecast details area 520 Estimated Budget Header Area 521 Estimated Budget Details Area 522 Confirmed Area
Claims
1. A landing prediction device including a control unit, The control unit is Contract information data including project identification information, order identification information, and contract amount; Project budget data including project identification information, order identification information, cost item classification, and budget amount; Project cost detail data including document number, project identification information, order identification information, cost item classification, and cost amount; is configured to be accessible to a final forecast input means for inputting the planned increase or decrease in the contract amount, the estimated budget amount and future planned costs for each cost item category for the target project identification information and order identification information in response to an operator's operation on a final forecast screen when a contract has not yet been signed but further orders are expected, and creating project final forecast data including the project identification information, order identification information, cost item category, budget amount, estimated budget amount, accumulated costs incurred which are the accumulation of cost amounts, future planned costs, and a final forecast amount calculated as the accumulated costs incurred + future planned costs by referring to the contract information data, the project budget data, and the project cost detail data.
2. 2. The project outcome prediction device according to claim 1, wherein the project outcome prediction data includes a difference between actual and forecast results calculated by adding a budget amount to an estimated budget amount and subtracting a final outcome prediction.
3. 2. The apparatus for predicting sales revenue according to claim 1, wherein the means for inputting prediction of sales revenue outputs a profit amount calculated by summing up a contract amount + a planned increase / decrease amount - a final prediction of sales revenue.
4. 2. The device for predicting results according to claim 1, wherein a plurality of patterns can be input for the planned increase / decrease amount and the estimated budget amount for each cost item category.
5. 2. The device for predicting a result according to claim 1, wherein negative amounts can be input for the planned increase / decrease amount and the estimated budget amount for each cost item category.
6. The project arrival prediction device according to any one of claims 1 to 5, characterized in that the project arrival forecast input means creates project arrival forecast estimated budget data including project identification information, order identification information, estimated budget identification information, planned increase / decrease amount, cost item classification, and estimated budget amount.
7. A landing prediction method executed by an information processing device having a control unit, The control unit is Contract information data including project identification information, order identification information, and contract amount; Project budget data including project identification information, order identification information, cost item classification, and budget amount; Project cost detail data including document number, project identification information, order identification information, cost item classification, and cost amount; is configured to be accessible to Executed in the control unit: a final forecast input step of inputting a planned increase or decrease in the contract amount, an estimated budget amount and future planned costs for each cost item category for the target project identification information and order identification information in response to an operator's operation on a final forecast screen, when a contract has not yet been signed but further orders are expected, and creating project final forecast data including project identification information, order identification information, cost item category, budget amount, estimated budget amount, accumulated costs incurred which are the accumulation of cost amounts, future planned costs, and a final forecast amount calculated as the accumulated costs incurred + future planned costs by referring to the contract information data, the project budget data, and the project cost detail data.
8. A landing prediction program to be executed by an information processing device having a control unit, The control unit is Contract information data including project identification information, order identification information, and contract amount; Project budget data including project identification information, order identification information, cost item classification, and budget amount; Project cost detail data including document number, project identification information, order identification information, cost item classification, and cost amount; is configured to be accessible to Executed in the control unit: A program for executing a final forecast input step which, in response to an operator's operation on a final forecast screen, inputs a planned increase / decrease in the contract amount, an estimated budget amount for each cost item category, and future planned costs for each cost item category for the target project identification information and order identification information when a contract has not yet been signed but further orders are expected, and creates project final forecast data including project identification information, order identification information, cost item category, budget amount, estimated budget amount, accumulated costs incurred which are the accumulation of cost amounts, future planned costs, and a final forecast amount calculated as the accumulated costs incurred + future planned costs by referring to the contract information data, the project budget data, and the project cost detail data.
Citation Information
Patent Citations
Management improvement supporting device
JP2020077424A
Project management device, project management method, and project management program
JP2022027168A
Budget accounting system, program and recording medium
JP2019021081A