FRP temporary pavement slab
FRP temporary pavement slabs made of fiber-reinforced resin address the challenge of securing traffic during concrete slab renewal by providing a lightweight, easy-to-install solution that allows simultaneous waterproofing and paving, enhancing durability and reducing construction time.
Patent Information
- Application Number
- JP2023078720
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-05-11
- Publication Date
- 2024-11-21
AI Technical Summary
Existing concrete slab renewal on expressways with heavy traffic requires securing traffic in a short construction period, which is challenging due to the need for installing new slabs, pouring concrete, and curing before waterproofing and paving, often done at night with traffic restrictions.
The use of FRP temporary pavement slabs, composed of fiber-reinforced resin components, which are lightweight and can be quickly installed across gaps between concrete slabs to secure traffic, allowing for simultaneous waterproofing and paving, eliminating the need for temporary paving and reducing construction time.
The FRP slabs enable secure traffic before permanent paving, reduce construction time, and enhance slab durability by preventing water seepage and joint formation, while being lightweight and easy to install.
Smart Images

Figure 2024162809000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to an FRP temporary pavement slab that is temporarily placed in place of the pavement on the top surface of a concrete deck. [Background technology]
[0002] Many of Japan's expressways have been in operation for several decades and are becoming increasingly dilapidated. As highways age, safety and driving performance decline, so as a countermeasure, highway renewal work is being carried out. The road surface on which automobiles travel on expressways is constructed by applying pavement on top of a concrete deck. For this reason, the renewal of the concrete deck and the paving of the top surface are extremely important steps in expressway renewal construction.
[0003] A typical highway concrete deck renewal project is carried out in the following steps: (1) Removal of existing concrete deck (2) Installation of new concrete deck (3) Pouring concrete into the gap between adjacent concrete slabs (4) After the concrete in the filling section has hardened, waterproofing and paving are applied to the top surface of the new concrete slab. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2007-239365 A Summary of the Invention [Problem to be solved by the invention]
[0005] Concrete decks support the road surface of expressways, and the renewal of concrete decks is directly linked to the safety and comfort of the expressway, so precise construction is required. However, renovation work in areas with heavy traffic volume is usually carried out from late at night to early in the morning, involving traffic restrictions, so it is necessary to ensure traffic flow within a short construction period. In the general renovation work mentioned above, traffic cannot be restored until new concrete decks are installed, concrete is poured and cured in the gaps between adjacent concrete decks, and waterproofing and paving of the top surface are carried out.
[0006] The present invention provides an FRP temporary pavement slab that allows traffic to be secured before paving the top surface of a concrete slab during concrete slab renewal work. [Means for solving the problem]
[0007] The FRP temporary pavement slab of the present invention comprises a rectangular lower plate, end reinforcements arranged on the upper surface of the lower plate at both longitudinal ends of the lower plate, longitudinal reinforcements arranged on the upper surface of the lower plate along both transverse ends of the lower plate, a plurality of transverse reinforcements arranged on the upper surface of the lower plate between the two longitudinal reinforcements and perpendicular to the longitudinal reinforcements, and a rectangular upper plate arranged on top of the end reinforcements, the longitudinal reinforcements and the transverse reinforcements, wherein the lower plate, the end reinforcements, the longitudinal reinforcements, the transverse reinforcements and the upper plate are all made of fiber-reinforced resin. The structure may further include an upper plate reinforcing plate disposed between the end reinforcement, the longitudinal reinforcement, the transverse reinforcement and the upper plate, and the upper plate reinforcing plate may be made of fiber reinforced resin. The upper surface of the upper plate may be provided with a thin layer of paving. The lower plate may have a rubber bearing disposed in the longitudinal direction of the lower surface thereof. A fulcrum reinforcement may be provided between the end reinforcement and the end of the longitudinal reinforcement, and the fulcrum reinforcement may be a member having a strength greater than that of fiber-reinforced resin, and may have a through hole passing through the fulcrum reinforcement and the rubber bearing. Effect of the Invention
[0008] The present invention provides at least one of the following effects by solving the above-mentioned problems. (1) By placing a temporary FRP pavement slab in place of paving on the top surface of the concrete deck, traffic can be secured before paving is carried out. (2) By making most of the constituent components out of fiber-reinforced resin, the pavement slab can be made lightweight. (3) By applying a thin layer of pavement on top of the FRP temporary pavement slab, traffic can be ensured without the need for temporary pavement by simply arranging them in parallel. (4) By placing an FRP temporary pavement slab over the top of the gap between adjacent concrete slabs, traffic can be ensured without pouring concrete into the gap. In addition, traffic can be maintained even during curing after pouring. (5) By carrying out waterproofing and paving work on multiple concrete slabs at once, joints can be eliminated, preventing water from seeping into the concrete slabs and improving the durability of the concrete slabs. [Brief description of the drawings]
[0009] [Figure 1] A perspective view of the FRP temporary pavement slab of the present invention. [Diagram 2] Exploded perspective view of the FRP temporary pavement slab of the present invention (1) [Diagram 3] Exploded perspective view of the FRP temporary pavement slab of the present invention (2) [Figure 4] Cross-sectional view of the FRP temporary pavement slab of the present invention DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0010] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. EXAMPLES
[0011] [1] FRP temporary pavement <1> Usage of FRP temporary pavement The FRP temporary pavement slab 1 of the present invention is placed on a concrete deck S of an expressway or the like in place of pavement (FIG. 1). The FRP temporary pavement slabs 1 are arranged in parallel so that the short side direction is the direction of vehicle traffic. There is a filling section F between adjacent concrete decks S, and the FRP temporary pavement slabs 1 are arranged over the top of the filling section F. By simply arranging the FRP temporary pavement slabs 1 of the present invention in parallel on the concrete floor slab S, it is possible to ensure traffic flow before paving is performed. Furthermore, by arranging it across the top of the filling section F, it is possible to drive on the FRP temporary pavement slab 1 even before concrete is poured into the filling section F (when gaps are open) or when concrete has been poured into the filling section F and is being cured. Since the number of concrete slabs S that can be installed in one day is limited, traffic is ensured using the FRP temporary pavement slab 1 until the specified number of concrete slabs S are installed, and then waterproofing and paving are performed simultaneously across multiple concrete slabs S, eliminating joints over a specified construction distance, preventing water from entering the concrete slabs S and improving the durability of the concrete slabs S. When waterproofing and paving are applied on the concrete deck S to construct the permanent road surface, the FRP temporary pavement slab 1 in that area can be removed, making it possible to complete the work in a short period of time.
[0012] <2> composition The FRP temporary pavement slab 1 is composed of a lower plate 2, end reinforcements 3, longitudinal reinforcements 4 and transverse reinforcements 5 which are placed on the upper surface of the lower plate 2, and an upper plate 6 which is placed on top of the end reinforcements 3, longitudinal reinforcements 4 and transverse reinforcements 5 (Figure 2). The bottom plate 2, end reinforcement 3, longitudinal reinforcement 4, transverse reinforcement 5 and top plate 6 that constitute the FRP temporary pavement slab 1 are all made of fiber reinforced plastic (FRP).
[0013] <3> Lower plate, upper plate The lower plate 2 and the upper plate 6 are rectangular flat plates, and form the lower and upper surfaces of the FRP temporary pavement slab 1 . The dimensions of the lower plate 2 and the upper plate 6 are, for example, 5.2 m in length and 0.7 m in width, which become the plan dimensions of the FRP temporary pavement slab 1. The thickness of the lower plate and the upper plate is 5 mm. In addition, a thin layer pavement 61 is applied to the upper surface of the upper plate 6 by a conventional neat method or the like. By applying the thin layer pavement 61, traffic can be ensured without temporary pavement by simply arranging the FRP temporary pavement slabs 1 in parallel.
[0014] <4> End reinforcement, longitudinal reinforcement, transverse reinforcement The end reinforcement 3, the longitudinal reinforcement 4 and the transverse reinforcement 5 are columnar members, and the two opposing faces of each are joined to the lower plate 2 and the upper plate 6, respectively, by rivets (not shown) or adhesive. The end reinforcement members 3, the longitudinal reinforcement members 4 and the transverse reinforcement members 5 may be structural members such as square tubes or H-shaped members. The end reinforcement members 3 are disposed at both longitudinal ends between the lower plate 2 and the upper plate 6. The dimensions of the end reinforcement members 3, for example, in the case of a rectangular tube, are 50 mm square, 4 mm thick, and the length is 0.7 m, the same as the short-side length of the lower plate 2 and the upper plate 6. In this embodiment, two end reinforcement members 3 are disposed at each longitudinal end. The longitudinal reinforcement 4 is placed along both ends in the short direction between the lower plate 2 and the upper plate 6. For example, in the case of a rectangular tube, the dimensions of the longitudinal reinforcement 4 are 50 mm square and 4 mm thick, the same as the end reinforcement 3, and its length is 4.85 m, which is shorter than the longitudinal length of the lower plate 2 and upper plate 6 by the width of the number of end reinforcements 3 and the width of the support reinforcement 8 described below. The short side reinforcements 5 are arranged between the lower plate 2 and the upper plate 6, between the longitudinal reinforcements 4, and are arranged side by side without any gaps, perpendicular (parallel to the short side direction) to the longitudinal reinforcements 4. For example, in the case of a rectangular tube, the length of the short side reinforcements 5 is 50 mm square and 4 mm thick, the same as the end reinforcements 3 and the longitudinal reinforcements 4, and the length is 0.6 m, which is shorter than the short side length of the lower plate 2 and the upper plate 6 by the width of the number of longitudinal reinforcements 4. These end reinforcements 3, longitudinal reinforcements 4, and transverse reinforcements 5, as well as the lower plate 2 and upper plate 6 which also make up the FRP temporary pavement slab 1, are all made of FRP, making the FRP temporary pavement slab 1 lighter than if it were all made of steel.
[0015] <5> Rubber bearing A rubber bearing 7, which is a rubber plate, is arranged along the longitudinal direction on the lower surface of the lower plate 2. The rubber bearings 7 may be arranged over the entire length, or may be arranged at predetermined intervals. The rubber bearings 7 absorb vibrations and shocks acting on the FRP temporary pavement slab 1 .
[0016] <6> Support reinforcement In this embodiment, a support point reinforcement 8 is disposed along the end reinforcement 3 between the end reinforcement 3 and the end of the longitudinal reinforcement 4 . The support point reinforcement 8 has an insertion hole 81, and the FRP temporary pavement slab 1 is fixed onto the concrete floor slab S via a fixing bolt 82 inserted into the insertion hole 81 and a washer 83 attached to the lower part of the fixing bolt 82 (Figures 3 and 4). The fulcrum reinforcement 8 is made of high-strength steel since it is the portion where the fixing bolt 82 is fixed. The dimensions of the support reinforcement 8, for example in the case of an angle bar, are 75 mm in width and 50 mm in height, and its length is 0.7 m, the same as the short-side length of the lower plate 2 and the upper plate 6. In addition, the lower plate 2 and the upper plate 6 are each provided with through holes 21, 62 through which a fixing bolt 82 can be inserted, and in this embodiment, an insertion hole 71 is provided in the rubber support 7 below the fulcrum reinforcement 8, through which the fixing bolt 82 can be inserted.
[0017] <7> Upper plate reinforcement plate An upper plate reinforcing plate 63 may be disposed between the lower surface of the upper plate 6 and the upper surfaces of the end reinforcement members 3, the longitudinal reinforcement members 4 and the transverse reinforcement members 5. The upper plate 6 and the upper plate reinforcing plate 63 are made of FRP and are formed by pultrusion molding. Therefore, by disposing the upper plate reinforcing plate 63 in multiple pieces so that the pultrusion direction is perpendicular to the upper plate 6, the strength of the FRP temporary pavement slab 1 is increased. The upper plate 6 is provided with a through hole 631 through which the fixing bolt 82 can be inserted, in accordance with the arrangement position of the fixing bolt 82. [Explanation of symbols]
[0018] 1: FRP temporary pavement 2: Lower plate, 21: Through hole 3: Edge reinforcement 4: Longitudinal reinforcement 5: Short side reinforcement 6: upper plate, 61: thin layer pavement, 62: through hole, 63: upper plate reinforcement, 631: through hole 7: Rubber bearing 8: Support reinforcement, 81: Through hole, 82: Fixing bolt, 83: Washer
Claims
1. A rectangular lower plate; end reinforcements disposed on the upper surface of the lower plate at both longitudinal ends of the lower plate; A longitudinal reinforcement member is disposed on the upper surface of the lower plate along both ends of the lower plate in the short direction; A plurality of short reinforcements are arranged on the upper surface of the lower plate between the two long reinforcements and perpendicular to the long reinforcements; A rectangular upper plate is disposed on the end reinforcement, the longitudinal reinforcement, and the short reinforcement, The lower plate, the end reinforcement, the longitudinal reinforcement, the short reinforcement and the upper plate are all made of fiber reinforced resin. FRP temporary pavement.
2. An upper plate reinforcing plate is disposed between the end reinforcement member, the longitudinal reinforcement member, the short reinforcement member, and the upper plate, The upper reinforcing plate is made of fiber reinforced resin.
2. The FRP temporary pavement plate according to claim 1.
3. The upper surface of the upper plate is provided with a thin layer of paving. The FRP temporary pavement plate according to claim 2.
4. The lower plate has a rubber bearing arranged in the longitudinal direction of the lower surface thereof. The FRP temporary pavement slab according to any one of claims 1 to 3.
5. A support reinforcement is disposed along the end reinforcement between the end reinforcement and an end of the longitudinal reinforcement, The support point reinforcement material is a member having a strength higher than that of fiber reinforced resin, The support portion reinforcing material and the rubber bearing have a through hole passing through them.
5. The FRP temporary pavement plate according to claim 4.