Supply and demand planning device and supply and demand planning method
The supply and demand planning device and method address the challenge of generating accurate and efficient verification scenarios by using past performance and constraint information to create scenarios that reflect actual system operation states, enhancing power system planning efficiency.
Patent Information
- Application Number
- JP2023083410
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-05-19
- Publication Date
- 2024-11-29
AI Technical Summary
Existing supply and demand planning systems struggle to generate comprehensive verification scenarios that accurately reflect actual system operation states, leading to increased processing times or the omission of critical scenarios due to excessive or insufficient scenario settings, especially with the integration of renewable energy sources and unpredictable power fluctuations.
A supply and demand planning device and method that utilizes past performance and constraint information to generate verification scenarios by comparing and evaluating operational constraints, incorporating a scenario generation unit to create scenarios that reflect actual system operation states, reducing processing time while ensuring comprehensive evaluation.
The solution enables the generation of comprehensive verification scenarios that account for operational constraints, reflecting actual system operation status, thereby reducing processing time and improving the accuracy of power system planning.
Smart Images

Figure 2024166962000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a supply and demand planning device and a supply and demand planning method. [Background technology]
[0002] A power system is composed of many generators, loads, power transmission and distribution equipment, and control devices. In order to operate the power system stably and at low cost, it is necessary to formulate a supply-demand plan to keep the balance of the power supply against the ever-changing power demand. In order to realize highly efficient system operation while introducing a large amount of renewable energy sources, whose output varies greatly depending on the weather, countries are moving toward a market-driven power system operation.
[0003] Necessary functions for realizing power system operation include the Security Constrained Unit Commitment (SCUC) and Security Constrained Economic Dispatch (SCED) functions in the next-generation central load dispatching center, which make it possible to formulate power generation start-up and stop plans and output allocations that satisfy wide-area merit orders and various operational constraints. In the optimization problem for obtaining a power generation plan in the above-mentioned SCUC / SCED functions, the objective function is set to minimize operational costs, and the operational constraints to be observed are power generation unit constraints (upper and lower output limits, output change rate, minimum start-up and stop times, etc.) and system constraints (power flow constraints, etc.).
[0004] Recently, there are issues of tight supply and demand (kWh constraints) due to fuel stockpile shortages and unexpected demand fluctuations, as well as long-term reductions in renewable energy output due to sudden weather changes (Dark Doldrums: DDD, or freezing of wind turbines, etc.). In addition, with the increase in the introduction of renewable energy, distributed power sources, EVs, and BESSs, it is becoming more difficult to predict trends in power consumption and fluctuations, and the impact of accidents is becoming more complex.
[0005] With the above two points as a background, in order for the person responsible for the long-term stable operation of the grid (general electricity transmission and distribution business operators in Japan) to invest in and be accountable for long-term stable operation, it is necessary to formulate plans that consider long-term constraints of at least a month or year, and to verify measures in advance by formulating plans that take into account multiple verification scenarios that take into account various unexpected fluctuations. Here, the verification scenario refers to information that defines the constraints that must be met in the operation of the power grid, based on the power supply and demand situation and the characteristics of facility operation. An optimal supply and demand plan is formulated based on indicators such as cost minimization, while satisfying the constraints defined by the above verification scenario.
[0006] In light of the above background, a supply and demand planning technique has been devised for a power system operator to determine an optimal power system operation method while assuming various possible system states. For example, Patent Document 1 states that "the priority calculation device includes a configuration change reflecting unit that selects one facility as a selected facility from a plurality of evaluation target facilities evaluated for the formulation of a power system equipment plan, and creates changed system configuration information indicating a system configuration in which the presence or absence of the selected facility is changed using system configuration information indicating the system configuration of the power system. The priority calculation device includes a power flow calculation unit that performs a power flow calculation using the changed system configuration information and the load amount, and a priority calculation unit that uses the result of the power flow calculation to calculate the degree of influence on other facilities that are facilities that constitute the power system and are facilities other than the selected facility as a priority for updating the selected facility, and the priority calculation device calculates the priority of each of the plurality of evaluation target facilities by changing the selected facility." [Prior art documents] [Patent documents]
[0007] [Patent Document 1] Patent Publication No. 2021-191112 Summary of the Invention [Problem to be solved by the invention]
[0008] In recent years, renewable energy sources such as solar and wind power are being introduced into the grid in large quantities. These renewable energies are accompanied by sudden fluctuations in power output that are difficult to predict in advance, and as a result, the power supply and demand situation may change significantly. In addition, in the operation of thermal power generators, events have occurred in which the amount of power generation possible is affected in terms of kWh restrictions due to the political situation in resource-producing countries such as natural gas and oil, problems in fuel transportation and storage facilities, and rising fuel prices and difficulties in procurement. Furthermore, when unexpected weather conditions that deviate from weather forecasts cause an increase in power demand and the timing of generator work stoppages overlap, there is a possibility that a supply shortage will cause a tight supply and demand situation.
[0009] Considering the above system operation status, it is necessary to take preventive measures based on comprehensive scenario verification, and to update the scenarios assumed for future system operation as needed in accordance with the actual operating state. If verification scenarios are set mechanically, there is a risk that the scenarios will be excessive for the purpose, increasing the calculation time for planning, or that important scenarios will not be verified due to insufficient scenarios. From the above perspective, it is necessary to generate and extract verification scenarios that are neither excessive nor insufficient, and that reflect the verification purpose and the actual operating state.
[0010] In the technology described in Patent Document 1, since the impact of the presence or absence of a failure of a certain piece of equipment is evaluated, it is difficult to evaluate system conditions that are not specified in advance, such as combinations of multiple equipment failures or severe events other than equipment failures, and the effort required to input evaluation cases increases, making it difficult to realize comprehensive scenario verification.In addition, since constraint conditions based on the actual operation state are not reflected in the scenario settings, there is a risk that scenarios that require verification due to changes in the system operation state may not be verified, or that computational resources may be consumed in verifying unnecessary scenarios that do not reflect the actual situation.
[0011] An object of the present invention is to provide a supply and demand planning device and a supply and demand planning method that can simultaneously generate comprehensive verification scenarios that take into account operational constraints that reflect the actual system operation state and reduce processing time. [Means for solving the problem]
[0012] In order to achieve the above object, the supply and demand planning device of the present invention is a supply and demand planning device that formulates an operation plan after satisfying various operation constraint conditions, and is characterized by comprising a past performance evaluation unit that compares and evaluates past performance information including information on operation performance at a past point in time and past constraint information including information on constraint information set at a past point in time, and a scenario generation unit that generates a verification scenario defined as a combination of various operation constraint conditions based on a past performance evaluation result of the past performance evaluation unit. Other aspects of the present invention will be described in the embodiments described later. Effect of the Invention
[0013] According to the present invention, it is possible to generate comprehensive evaluation scenarios that take into account operational constraints that reflect the actual system operation state, while also reducing the processing time. [Brief description of the drawings]
[0014] [Figure 1] FIG. 2 is a diagram illustrating an example of a functional configuration of the supply and demand planning device according to the present embodiment. [Diagram 2] 1 is a diagram illustrating an example of a hardware configuration of a supply and demand planning system according to an embodiment of the present invention. [Diagram 3] FIG. 13 illustrates an example of an overall process of verification scenario generation. [Figure 4] FIG. 11 is a diagram illustrating an example of constraint information. [Figure 5A] FIG. 13 is a diagram showing an example of constraint extension information (targeting an increase / decrease in constraint-subject equipment and an increase / decrease in constraint amount). [Figure 5B] FIG. 13 is a diagram showing an example of constraint extension information (targeting an increase or decrease in a constraint period). [Figure 6] FIG. 11 is a diagram illustrating an example of past performance information. [Figure 7A] FIG. 11 is a diagram showing an example of past plan information (power generation amounts at each time interval for a plurality of power generators). [Figure 7B]FIG. 13 is a diagram showing an example of past constraint information (whether the constraint condition of each constraint item is valid or invalid in each time interval). [Figure 8] FIG. 13 is a diagram illustrating an example of evaluation index information of past performance information. [Figure 9] FIG. 13 is a diagram illustrating an example of estimated constraint information at a past point in time. [Figure 10A] FIG. 13 is a diagram illustrating an example of estimated constraint information for a future period. [Figure 10B] 10B is a diagram showing an example in which the past constraint information and the future estimated constraint information shown in FIG. 10A are displayed on a time series graph. FIG. [Figure 11A] FIG. 13 is a diagram showing constraint change information at a future point in time, and is a diagram showing an example of constraint extension information in the case where the increase / decrease in the constraint target equipment or the increase / decrease in the constraint amount is targeted. [Figure 11B] 13 is a diagram showing constraint change information at a future point in time, and is a diagram showing an example of constraint extension information in the case where an increase or decrease in the constraint subject period is targeted. FIG. [Figure 12] FIG. 11 illustrates an example of verification scenario information. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0015] Hereinafter, embodiments of the present invention will be described. Note that the following is merely an example, and the invention itself is not intended to be limited to the specific contents described below. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will now be described with reference to the drawings.
[0016] Fig. 1 is a diagram showing an example of a functional configuration of a supply and demand planning device 200 according to this embodiment. The supply and demand planning device 200 includes a supply and demand plan determination unit 10, a plan formulation unit 18, and an information storage unit 30. The supply and demand plan determination unit 10 may be connected to a measuring device 21 (see Fig. 2). The measuring device 21 measures measurement information of measuring devices 21a, 21b, ... at a plurality of points. The information storage unit 30 stores a constraint information DB 31, a constraint extension information DB 32, a past performance DB 33, and a past plan DB 34.
[0017] The supply and demand plan determination unit 10 includes a constraint information acquisition unit 11, a past performance acquisition unit 12, a past plan acquisition unit 13, a past performance evaluation unit 14, a constraint condition estimation unit 15, a constraint change condition generation unit 16, and a scenario generation unit 17.
[0018] The constraint information acquisition unit 11 acquires constraint information and constraint extension information from the constraint information DB 31 and the constraint extension information DB 32. The past performance acquisition unit 12 acquires past performance information from the past performance DB 33. The past plan acquisition unit 13 acquires past information including either a past power generation plan or constraint information related to the past power generation plan from the past plan DB 34.
[0019] The past performance information and past plan information include at least one of the power output of various power generators and the power flow in various system facilities including transmission lines and substations.
[0020] An embodiment in which the power generation output of a generator is used as past performance information and past plan information will be described below.
[0021] The past performance evaluation unit 14 calculates constraint information and statistical information thereof based on past power generation results as an evaluation value, based on the past performance information acquired by the past performance acquisition unit 12. The past performance evaluation unit 14 calculates constraint information and statistical information thereof based on past power generation results, based on the past performance information acquired by the past performance acquisition unit 12 and the past plan information acquired by the past plan acquisition unit 13, and calculates a difference by comparing it with the past power generation plan and the constraint information related to the past power generation plan, which are included in the past plan information.
[0022] That is, the past performance evaluation unit 14 compares and evaluates the past performance information and the past constraint information based on the past performance information including information on operation performance at a past point in time and the past constraint information including information on constraint information set at a past point in time. The past performance evaluation unit 14 compares and evaluates the past performance information and the past constraint information with respect to constraint conditions including one or more constraint items of a kWh constraint in a specified period and a planned stoppage constraint in a specified period.
[0023] The constraint condition estimation unit 15 estimates constraint information in the past operation results using the evaluation value of the past performance information calculated by the past performance evaluation unit 14 and the past power generation plans and constraint information related to the past power generation plans included in the past plan information. Also, the constraint condition estimation unit 15 calculates an estimate value of constraint information in the future using the estimation result of the constraint information in the past operation results.
[0024] That is, the constraint condition estimation unit 15 calculates estimated constraint information including operation constraints at a past time point reflecting the past operation performance, based on the evaluation value of the past performance information and the past constraint information calculated by the past performance evaluation unit 14. The constraint condition estimation unit 15 calculates estimated constraint information at a future time point, based on the calculated estimated constraint information at a past time point.
[0025] The constraint change condition generating unit 16 generates constraint change information based on the estimated value of the future constraint information calculated by the constraint condition estimating unit 15 and the constraint extension information.
[0026] The scenario generation unit 17 generates a scenario defined by a combination of setting values for each constraint condition item based on the constraint information and constraint extension information acquired by the constraint information acquisition unit 11 from the constraint information DB 31 and the constraint extension information DB 32, the estimated constraint information calculated by the constraint condition estimation unit 15, and the constraint change information calculated by the constraint change condition generation unit 16.
[0027] The plan formulation unit 18 formulates a supply and demand plan that takes into account the constraint information included in the verification scenario generated by the scenario generation unit 17. Here, as a plan formulation method, known mathematical programming methods called the Security Constrained Unit Commitment (SCUC) and Security Constrained Economic Dispatch (SCED) functions may be applied, and the operation cost minimization may be set as an objective function, and power generation unit constraints (upper and lower output limits, output change rate, minimum start and stop time) and system constraints (power flow constraints) may be set as operation constraints to be observed. In addition, the applied objective functions and operation constraints are not limited to those described above, and various objective functions and operation constraints applied in the current power system operation may be set.
[0028] Fig. 2 is a diagram showing an example of a hardware configuration of the supply and demand planning system according to the present embodiment. As shown in Fig. 2, the supply and demand planning system according to the present embodiment includes a generator 101, a substation 102, a phase modifying device 103, a power load 104, an external power system 105, measurement devices 21a, 21b, ..., an information and communication network 108, and a supply and demand planning device 200. Hereinafter, the power system including the generator 101, the substation 102, the phase modifying device 103, the power load 104, and the measurement devices 21a, 21b, ... may be referred to as the own system.
[0029] The generator 101 is a generator that generates electric power by any power generation method including thermal power generation, hydroelectric power generation, nuclear power generation, solar power generation, wind power generation, biomass power generation, and tidal power generation.
[0030] The generator 101a is a large-scale generator including a thermal power plant, a hydroelectric power plant, a nuclear power plant, or the like, that is installed on the high-voltage side of a substation 102 in a power system, and transmits system state quantities including the amount of power generated to the supply and demand planning device 200 via the measuring device 21a and the information and communication network 108. The generator 101a also receives control command information transmitted from the supply and demand planning device 200 via the measuring device 21a and the information and communication network 108, and changes the system state quantities including the amount of power generated in accordance with the control command information.
[0031] The generator 101b is a small- to medium-sized generator including solar power generation, wind power generation, cogeneration, etc., that is installed on the low-voltage side of a substation 102 in the power system, and transmits system state quantities including the amount of power generation to the supply and demand planning device 200 via a measuring device 21b and an information and communication network 108.
[0032] A substation 102 is installed between power transmission lines in a power system, changes the voltage value of power transmitted from the high-voltage side where a generator 101a, which is a large-scale generator, is installed, and transmits the power to a low-voltage side where a power load 104 is installed. A phase modifying device 103 such as a power capacitor and a shunt reactor is connected to the substation 102.
[0033] The phase modifying devices 103 are devices that control the voltage distribution in the power system by changing the reactive power in the power system, and include a power capacitor, a shunt reactor, a STATCOM (Static Synchronous Compensator), an SVC (Static Var Compensator), etc. Some of the phase modifying devices 103 receive control command information transmitted from the supply and demand planning device 200 via the measurement device 21c and the information and communication network 108, and change the system state quantities including the power generation amount according to the control command information.
[0034] The power load 104 is a facility that consumes power and includes electric motors, lighting fixtures, and the like, and represents facilities such as homes, factories, and buildings.
[0035] The external power system 105 is an external power system that cannot be controlled by the supply and demand planning device 200, and is connected to the self-system by an interconnection line.
[0036] The measuring devices 21a, 21b, ... include sensors that measure system state quantities such as the power generation amount in the generator 101a, the phase modification amount in the phase modifying device 103, the power flow value in the transmission line, and the voltage value, and transmit the measured system state quantities to the supply and demand planning device 200 via the information and communication network 108.
[0037] The information and communication network 108 is a network capable of transmitting data in both directions. The information and communication network 108 is, for example, a wired network, a wireless network, or a combination thereof. The information and communication network 108 may be the so-called Internet, or may be a dedicated line network.
[0038] The supply and demand planning device 200 is a device for realizing the supply and demand planning function shown in Fig. 1. The supply and demand planning device 200 receives system state quantities measured by the measuring devices 21a, 21b, ..., via the information and communication network 108. In addition, the supply and demand planning device 200 transmits control command information calculated using the transmitted system state quantities of the system and information accumulated inside to the measuring devices 21 via the information and communication network 108.
[0039] The supply and demand planning device 200 includes an internal configuration including a CPU (Central Processing Unit) 201, a display device 202, a communication means 203, an input means 204, a memory 205, and a storage device 206, which are connected to a bus line 211. The CPU 201 executes a calculation program stored in the storage device 206 to calculate the system state, generate a control signal, generate image data, and display the image data on the display device 202. The memory 205 is a memory that temporarily stores image data for display, calculation result data of the system state, and the like, and is, for example, a RAM (Random Access Memory). The communication means 203 acquires system state quantities such as power flow values and voltage values from the measurement devices 21 through the information and communication network 108. The constraint information acquisition unit 11 receives time-series measurement information measured by the multiple measurement devices 21 using the communication means 203.
[0040] A user (administrator) of the supply and demand planning device 200 can set or change parameters such as various thresholds through a predetermined interface of the input means 204, and appropriately set the operation of the supply and demand planning device 200 for its own system. In addition, the user can select the type of data he or she wishes to check through a predetermined interface of the input means 204, and display it on the display device 202.
[0041] The storage device 206 holds various programs and data. The storage device 206 is, for example, a hard disk drive (HDD) or a flash memory. The storage device 206 holds, for example, programs and data that can realize various functions described below. The programs and data stored in the storage device 206 are read out and executed by the CPU 201 as necessary. The storage device 206 realizes the information storage unit 30 and stores various databases (DB).
[0042] The measurement equipment 21 measures measurement information at measurement points in the system and transmits the information to the constraint information acquisition unit 11. The measurement information includes at least one type of information among active power flow, reactive power flow, system voltage, system current, and voltage phase. The measurement equipment 21 includes measurement equipment 21a, 21b, ..., 21n that are respectively arranged at a plurality of measurement points. The measurement equipment 21 is, for example, a PMU (Power Monitoring Unit), and performs periodic measurements related to power and transmits time-series measurement information.
[0043] Returning to FIG. 1, the information storage unit 30 includes a constraint information DB 31 that stores constraint information to be considered in a supply and demand plan, and a constraint extension information DB 32 that stores parameters for generating a verification scenario by extending the constraint information.
[0044] The constraint information DB31 stores constraint information including various data items such as constraint target equipment indicating the target equipment on which various constraint items are reflected, constraint upper limit amounts specifying the upper limit values of the operation amounts of various equipment, constraint lower limit amounts specifying the lower limit values of the operation amounts of various equipment, constraint specified amounts specifying the specified values of the operation amounts of various equipment, and constraint target periods indicating the periods on which various constraint items are reflected.
[0045] In addition, the constraint extension information DB32 stores constraint extension information including various data items such as lower and upper limits when increasing or decreasing a quantity when any of the values of various constraint upper limits, constraint lower limits, or constraint specified amounts can be changed within a certain range, a change increment when increasing or decreasing a quantity that specifies the increment when the constraint value is changed within the range of the lower and upper limits when increasing or decreasing the quantity, lower and upper limits when the start and end times when the period is increased or decreased when the constraint period can be changed within a certain range, a change increment when the period is increased or decreased that specifies the increment when the constraint value is changed within the range of the lower and upper limits when increasing or decreasing the period, and a constraint period type that indicates the type of period in which various constraint items are reflected (time of day, daytime / nighttime, weekdays / holidays, day of the week, month, etc.).
[0046] As an example of constraint information, the constraint information related to constraint item 2 shown in FIG. 4 indicates that the power transmission lines A-1 and A-2 are set as the constrained facilities, 300 MW is set as the constraint upper limit amount, and each time is set as the constraint period, and that the constraint lower limit amount and the constraint specified amount are not specified.
[0047] As an example of constraint extension information, the constraint upper limit amount in FIG. 5A is explained. The constraint extension information indicates that the constraint amount can be set in increments of 10% within the range of 50% to 200% of the original constraint information.
[0048] Here, when the constraint information shown in constraint item 2 in Figure 4 is used as the base constraint, a verification scenario is created in which, based on the constraint extension information, the lower limit is 300[MW] x 50[%] = 150[MW], the upper limit is 300[MW] x 200[%] = 600[MW], and the increment is 300[MW] x 10[%] = 30[MW], with the constraint upper limit amount for the constrained equipment set to any of 150, 180, ..., 570, or 600[MW].
[0049] As another example of constraint extension information, when the constraint extension information shown in Figure 5B is used for the constrained period and constraint information that sets the constrained period from April 2023 to March 2035 as the base constraint, a verification scenario is created in which the start time of the constrained period is set in one-month increments from April 2023 to April 2028 and the end time is set in one-month increments from March 2032 to March 2035, and the type of constrained period is set to one of all days, holidays only, or weekdays from midnight to 7:00 and from 19:00 to 23:00.
[0050] <Verification scenario generation process S300> The verification scenario generation process S300 performed by the supply and demand planning device 200 will be described. Figure 3 shows the overall process of the verification scenario generation process S300. One of the purposes of this process is to evaluate the application status of operational constraints set when a previous plan was formulated by comparing them with actual values based on actual or estimated values of the operational constraints set when a previous plan was formulated and actual operation values (power generation output values of generators, power flow values of transmission and distribution facilities such as transmission lines, control command value information of transmission and distribution facilities such as generators and transformers, etc.) acquired from the time when the previous plan was formulated to the current time when this function is used.
[0051] Another purpose of this process is to estimate future operational constraints from the present time based on the above evaluation information, and to calculate a future operational plan based on the estimated future operational constraints.
[0052] The background to the need for this processing is that as the liberalization of the electricity business progresses through changes to the business system such as unbundling of transmission and distribution, it will become necessary for transmission and distribution operators to estimate the operational status of various operators based on limited publicly available information in order to achieve stable operation of the power grid.
[0053] (Step S301) First, the constraint information acquisition unit 11 acquires constraint information that needs to be considered in formulating a supply and demand plan from the constraint information DB 31 included in the information storage unit 30 (step S301). Here, the constraint information may be acquired by manual input by a user using an analysis tool / software, importing a file in which the constraint information is stored, or by DB linkage with another system.
[0054] (constraint information) Fig. 4 is a diagram showing an example of the constraint information 31A. Fig. 4 shows an example of the constraint information 31A stored in the constraint information DB 31. For each constraint item represented in each row of Fig. 4, setting values of the constraint target facility 311, the constraint upper limit amount 312, the constraint lower limit amount 313, the constraint specified amount 314, and the constraint target period 315 are stored. Here, for the constraint target facility 311 and the constraint target period 315, settings are required for all constraint items, and for the constraint upper limit amount 312, the constraint lower limit amount 313, and the constraint specified amount 314, settings of at least one of them are required.
[0055] Target facilities to which the constraint applies are set as the constraint target facilities 311. The type of facility to be set may be any one of a generator, a transmission line, a substation, a power load, and a grid-connection node, or a combination of these facilities.
[0056] The constraint upper limit amount 312 means that a value equal to or greater than a specified set value must be maintained for the constraint item. As the constraint upper limit amount, active power [kW] or [MW], reactive power [kvar] or [Mvar], active energy [kWh] or [MWh], system voltage [V] or [kV], power factor [%], current phase or voltage phase [deg] or [rad] may be set.
[0057] The constraint lower limit amount 313 means that a value must be kept equal to or less than a specified set value in the constraint item. As the constraint lower limit amount, active power [kW] or [MW], reactive power [kvar] or [Mvar], active energy [kWh] or [MWh], system voltage [V] or [kV], power factor [%], current phase or voltage phase [deg] or [rad] may be set.
[0058] The constraint specified quantity 314 means that the value must be kept equal to the specified setting value in the constraint item. As the constraint specified quantity, active power [kW] or [MW], reactive power [kvar] or [Mvar], active energy [kWh] or [MWh], system voltage [V] or [kV], power factor [%], current phase or voltage phase [deg] or [rad] may be set.
[0059] The constraint period 315 is set as a period for determining whether or not a constraint can be complied with. A period including a plurality of time intervals may be set as the constraint period. Also, for a constraint item in which an individual constraint value is set for each time interval, each individual time interval may be set as the constraint period. Also, a period that satisfies certain conditions may be set as the constraint period. As the conditions, any one of the fiscal year, season, day of the week, weekday / holiday type, and time may be used to set the conditions for the constraint period.
[0060] (Step S302) Next, the constraint information acquisition unit 11 acquires constraint extension information, which stores parameters used to change the constraint information in generating a verification scenario, from the constraint extension information DB included in the information storage unit 30 (step S302).
[0061] Here, the method of acquiring the constraint extension information may be one of the following: manual input by the user using analysis tools / software, importing a file in which the constraint extension information is stored, or database integration with another system.
[0062] (Constraint extension information) Fig. 5A is a diagram showing an example of constraint extension information 32A (targeting an increase or decrease in constraint-target equipment and an increase or decrease in constraint amount). Fig. 5B is a diagram showing an example of constraint extension information 32B (targeting an increase or decrease in constraint-target period). Figs. 5A and 5B show an example of constraint extension information stored in the constraint extension information DB 32.
[0063] Fig. 5A shows an example of constraint extension information 32A for the case of increasing or decreasing the constraint target facility 321 or increasing or decreasing the constraint amount (constraint upper limit amount 322, constraint lower limit amount 323). For the increase or decrease of the constraint target facility 321, a combination condition of system facilities subject to each constraint item that can be set as a verification scenario may be specified. Fig. 5A shows an example of specifying the upper and lower limits of the number of facilities that can be set as the constraint target facility by using the ratio of the system facilities subject to the constraint item in the base constraint condition to the number of facilities.
[0064] Regarding the increase or decrease of the constraint amount, the upper and lower limits and the fluctuation range of the constraint amount that can be set as a verification scenario may be specified for any of the constraint upper limit amount 312, the constraint lower limit amount 313, and the constraint specified amount 314 shown in Fig. 4. Fig. 5A shows an example in which the upper and lower limits of the range that can be set as the constraint amount are specified using the ratio of the constraint item in the base constraint condition to the constraint amount.
[0065] Specifically, it is shown that the constraint target equipment 321 ranges from 50% of the number of equipment of the base constraint to all interconnected equipment of the target system, whereas the constraint upper limit amount 322 ranges from 50% of the constraint amount of the base constraint to 200% of the constraint amount of the base constraint, and the constraint lower limit amount 323 ranges from 80% of the constraint amount of the base constraint to 120% of the constraint amount of the base constraint.
[0066] Fig. 5B shows an example of constraint extension information 32B in the case of increasing or decreasing the constraint period 324. For the increase or decrease of the constraint period 324, an applicable period for each constraint item that can be set as a verification scenario may be specified. Fig. 5B shows an example of specifying a constraint period that can be set as a verification scenario using the start time, upper and lower limits of the end time, the range of change, and the period type for the applicable period of the constraint item in the base constraint condition. Here, the period type may be set to fiscal year, season, day of the week, weekday / holiday type, or time of day.
[0067] (Step S303) Next, the past performance acquisition unit 12 acquires past performance information consisting of past power system operation performance including at least one of power generation output from various generators, or power flows in various system facilities including transmission lines and substations, from the past performance DB 33 included in the information storage unit 30 (step S303). Here, the past performance information may be acquired by manual input by a user using an analysis tool / software, importing a file in which constraint extension information is stored, or by DB linkage with another system.
[0068] FIG. 6 is a diagram showing an example of past performance information 33A. FIG. 6 shows an example of past performance information 33A stored in past performance DB 33. Past performance information 33A includes past information that satisfies one or more conditions of a specified data period of past information, acquisition date and time of past information, target equipment of past information, and target area of past information. FIG. 6 shows the power generation amount at each time interval for multiple generators (generators a-1, a-2, b-1, b-2) as an example of past performance information 33A of each system equipment included in the supply and demand plan. As the type of system equipment included in the past performance information, various facilities other than generators, i.e., transmission lines, substations, power loads, and power flow rates at interconnection nodes may be acquired as past plan information.
[0069] (Step S304) Next, the past plan acquisition unit 13 acquires past plan information consisting of a power system operation plan formulated at a past time including at least one of the power generation output of various generators, or the power flow in various system facilities including transmission lines and substations, from the past plan DB 34 included in the information storage unit 30 (S304). Here, the past plan information may be acquired by manual input by a user using an analysis tool / software, importing a file in which constraint extension information is stored, or by DB linkage with another system.
[0070] Fig. 7A is a diagram showing an example of past plan information 34A (power generation amount for each time interval for multiple generators). Fig. 7B is a diagram showing an example of past plan information 34B (whether the constraint condition of each constraint item is valid or invalid in each time interval). Figs. 7A and 7B show an example of past plan information stored in the past plan DB 34.
[0071] 7A shows the amount of power generated at each time interval for multiple generators (generators a-1, a-2, b-1, b-2) as an example of past plan information 34A for each system facility included in the supply and demand plan. As the type of system facility included in the past plan information, various facilities other than generators, i.e., transmission lines, substations, power loads, and power flow rates at interconnection nodes, may be acquired as past plan information.
[0072] 7B shows, as an example of past plan information 34B taken into account in formulating a supply and demand plan, whether the constraint conditions of each constraint item (kWh constraint of generator group A, planned shutdown constraint of generator b-1, planned shutdown constraint of generator b-2, kWh constraint of generator group B) are valid or invalid in each time interval. In the figure, items marked with a check mark indicate that they are valid.
[0073] Here, as the past constraint information, in addition to the valid / invalid state of the constraint condition, the constraint amount set in each constraint item, i.e., the constraint upper limit amount, the constraint lower limit amount, and the constraint specified amount, may be acquired. Furthermore, for constraint items related to multiple pieces of system equipment, which system equipment is subject to each constraint item in each time interval may be acquired as the past constraint information.
[0074] When the past constraint information of the kWh constraint of the generator group A shown in Fig. 7B is used and reflected as constraint item 1 shown in Fig. 4, the generator group A is set as the constraint target facility in Fig. 4, and the information of the time frame in which the constraint condition is valid is set as the constraint target period in Fig. 4. Furthermore, when the upper limit value of the kWh constraint of the generator group A is included in the past constraint information in addition to the information described in Fig. 7B, the constraint upper limit amount 312 in Fig. 4 is set based on the information on the left.
[0075] (Step S305) Next, the past performance evaluation unit 14 calculates an evaluation index based on the past performance information (step S305). Here, the evaluation index is calculated as a statistical index value, for example, an average value, a maximum value, a minimum value, or a frequency distribution (histogram), based on the past performance information for a certain period of time.
[0076] Fig. 8 is a diagram showing an example of evaluation index information 35A of past performance information 33A. Fig. 8 shows an example of evaluation indexes calculated in past performance evaluation unit 14. In the example of evaluation index information 35A of past performance shown in Fig. 8, examples of calculated types of evaluation indexes include power generation output 351 indicating the output of the generator at each time, startup time length 352 indicating the time interval from when the generator is started to when it is stopped next, shutdown time length 353 indicating the time interval from when the generator is stopped to when it is started next, and startup / shutdown count 354 indicating the number of times the generator is started or stopped in a certain period of time are shown.
[0077] For each of these evaluation index types, statistical index values such as average value, maximum value, minimum value, and frequency distribution (histogram) are calculated from the past performance information 33A. Here, the period for calculating each statistical index value is set by a preset fixed value, a manual setting by the user of this device, or other means.
[0078] The past performance evaluation unit 14 compares and evaluates the past performance information and the past constraint information using a statistical evaluation index value including one or more of an average value, an upper limit value, a lower limit value, and a frequency distribution calculated from the past performance information.
[0079] (Step S306) Next, based on the evaluation index of the past performance information 33A calculated by the past performance evaluation unit 14 in step S305, the constraint condition estimation unit 15 estimates the constraint condition applied in the past operation of the power system (step S306).
[0080] Here, the constraint conditions applied in past power system operations may be estimated by comparing and evaluating the evaluation indexes of the past performance information 33A and the past constraint information 31AP (past constraint information among constraint information 31A) included in the past plan information 34A, 34B (see Figure 9).
[0081] At this time, for each constraint item defined in the past constraint information 31AP (see FIG. 9), the degree of conformance with the evaluation index of the past performance information 33A is calculated. For constraint item 1 shown in the example of FIG. 4, the equipment subject to the constraint is the power output of generators a-1, a-2, and b-1, a constraint lower limit amount 313 is set as the content of the constraint, and the constraint period 315 is a fixed period including multiple time intervals (1.5 years in the example of FIG. 4). When calculating the degree of conformance of such a constraint item with the past performance information 33A, the actual value EN of the power generation amount [Wh] for a period equivalent to the constraint period 315 is calculated. R is extracted from the past performance information 33A, and the power amount lower limit EN in the past constraint information 31AP is low At this time, the conformity r1 with the past performance information 33A in this constraint item may be calculated from formula (1). Here, α low is a preset fixed parameter.
number
[0082] Similarly, the power consumption limit EN high When is specified in the past constraint information, the conformance r2 of this constraint item with the past performance information may be calculated using formula (2). high is a preset fixed parameter.
number
[0083] In addition, in the example of constraint item 2 shown in FIG. 4, the equipment subject to the constraint is the power flow of transmission lines A-1 and A-2, the content of the constraint is a power flow upper limit, and the period subject to the constraint is each time. When calculating the degree of conformity of such a constraint item with the past performance information, the average value PN Ravg is extracted from the evaluation index of the past performance information, and the power flow upper limit PN high In this case, the degree of conformity r3 with the past performance information in this constraint item may be calculated using formula (3). Here, β high is a preset fixed parameter.
number
[0084] Another method for calculating the degree of conformance with respect to the constraints is to use the frequency distribution f(PN R ) is extracted from the evaluation index of the past performance information, and the power flow upper limit PN high At this time, the degree of conformity r4 with the past performance information in this constraint item can be calculated using formula (4). Here, f % (PN R ) is the frequency distribution f(PN R ) and the relative frequency calculated from high is a preset fixed parameter.
number
[0085] In addition, in the example of constraint item 3 shown in FIG. 4, the equipment subject to the constraint is the power output of the generator a-1, a power output designation value is set as the content of the constraint, and the period subject to the constraint is each time. When calculating the conformity of such a constraint item with the past performance information, the past performance value P R (t) is extracted from the past performance information, and the output specification value P fix In this case, the degree of conformity r5 with the past performance information in this constraint item can be calculated using equation (5). Here, γ is a fixed parameter set in advance, g(P R Let (t) be the degree of conformance at time t, and n be the time span or number of time frames of past performance information for which conformance is evaluated.
number
[0086] As shown in the above example, the degree of conformance r n Calculate.
[0087] Next, the fitness value r calculated above n The estimated constraint information 31E is calculated using the above. Fig. 9 is a diagram showing an example of estimated constraint information 31E at a past point in time. Fig. 9 shows estimated constraint information 31E estimated based on evaluation indexes of past performance information 33A and past constraint information 31AP included in past plan information 34A and 34B.
[0088] 9 shows an example in which constraint item 1, constraint item 2, and constraint item 3 are specified as past constraint information 31AP, and 0.5 is specified as the judgment threshold for the degree of conformance. In this case, for constraint item 2, the degree of conformance calculated from the past performance information is 0.3, which is below the judgment threshold. From the judgment result, it is determined that the information needs to be updated for the constraint upper limit amount 300 [MW] stored in the past constraint information, and this represents that the evaluation index of the past performance information 33A shown in FIG. 8, for example 400 [MW] which is the average value of the operational performance of the target equipment over a certain period of time in the past, is set as the new constraint upper limit amount.
[0089] Here, for constraint item 1 and constraint item 3, the degree of conformance is above the judgment threshold, so the estimated constraint information is equivalent to the past constraint information. Also, for constraint item 2, the degree of conformance is below the judgment threshold, so it is presumed that the impact of applying operational constraints different from those assumed at the time of past planning is reflected in past performance.
[0090] In such a case, a value different from the past constraint information 31AP is set as the estimated constraint information 31E. Here, since constraint item 2 is a constraint item related to the constraint upper limit, the upper limit value in the evaluation index of the past performance information for a certain period of time may be set as the estimated constraint information. Similarly, when setting estimated constraint information different from the past constraint information for a constraint item related to the constraint lower limit, the lower limit value in the evaluation index of the past performance information for a certain period of time may be set as the estimated constraint information. Furthermore, when setting estimated constraint information different from the past constraint information for a constraint item related to a constraint specified amount, the average value or median value in the evaluation index of the past performance information for a certain period of time may be set as the estimated constraint information.
[0091] (Step S307) Next, the constraint condition estimation unit 15 calculates future estimated constraint information to be applied in the future operation of the power system (step S307). Here, the future estimated constraint information may be calculated using estimated constraint information at the time of past plan formulation and at one or more time points in the future from the time of past plan formulation.
[0092] Fig. 10A is a diagram showing an example of estimated constraint information 31E for a future period. Fig. 10B is a diagram showing an example in which past estimated constraint information 31EP (thick dashed line) and future estimated constraint information 31EF (thick solid line) shown in Fig. 10A are displayed on a time series graph.
[0093] Fig. 10A shows an example of future estimated constraint information 31EF calculated by the constraint condition estimation unit 15. The example of Fig. 10A shows the result of calculating past estimated constraint information 31EP for each of constraint items 1, 2, and 3 using past performance information in past period 1, past period 2, and past period 3. Furthermore, an example is shown in which future estimated constraint information 31EF for future period 4 and future period 5 is calculated using past estimated constraint information 31EP for those past periods.
[0094] Here, using the estimated constraint information 31E for the past period, changes in the constraint condition values in the time series direction may be modeled using a linear time series analysis method such as autoregression (AR), moving average (MA), autoregressive moving average (ARMA), etc., to calculate future estimated constraint information for the future period. Also, correlations with external factors that affect the operation of the power system, such as power demand, power market transactions, and power transmission capacity, may be modeled using a method such as multivariate linear regression and nonlinear regression, and future predicted values of the above external factors may be input to the above model to calculate future estimated constraint information for the future period.
[0095] (Step S308) Next, the constraint change condition generating unit 16 calculates constraint change information 31M using the constraint extension information 32A, 32B, past performance information 33A, past estimated constraint information 31EP at the past time point, and future estimated constraint information 31EF (step S308).
[0096] FIG. 11A is a diagram showing constraint change information 31M at a future time point, and is a diagram showing an example of constraint extension information 32AM when the increase / decrease of the constraint target equipment or the increase / decrease of the constraint amount is the target. FIG. 11B is a diagram showing constraint change information 31M at a future time point, and is a diagram showing an example of constraint extension information 32BM when the increase / decrease of the constraint target period is the target. FIG. 11A is an example of constraint change information 31M calculated in the constraint change condition generating unit 16 for the constraint extension information 32A of FIG. 5A. Also, FIG. 11B is an example of constraint change information 31M calculated in the constraint change condition generating unit 16 for the constraint extension information 32B of FIG. 5B. Note that the constraint change information 31M clearly indicates changes from the past constraint information.
[0097] Regarding the increase or decrease of the constraint target equipment in Fig. 11A, a combination condition of the system equipment targeted by each constraint item that can be set as a verification scenario may be specified. Fig. 11A shows an example of specifying the upper and lower limits of the number of facilities that can be set as the constraint target equipment by using the ratio of the system equipment targeted by the constraint item in the base constraint condition to the number of facilities. Regarding the increase or decrease of the constraint amount, the upper and lower limits and the fluctuation range of the constraint amount that can be set as a verification scenario may be specified for either the constraint upper limit amount, the constraint lower limit amount, or the constraint specified amount.
[0098] Regarding the increase or decrease of the constraint period in Fig. 11B, the applicable period of each constraint item that can be set as a verification scenario may be specified. Fig. 11B shows an example of specifying the constraint period that can be set as a verification scenario using the start time, upper and lower limits of the end time, the range of change, and the period type for the applicable period of the constraint item in the base constraint condition. Here, the period type may be set to fiscal year, season, day of the week, weekday / holiday type, or time of day.
[0099] For the constraint extension information used in the past planning, a statistical index may be calculated from the past performance information, and the calculation result may be reflected in the past constraint extension information. At this time, for the constraint item related to the kWh constraint, the integrated energy generation value for a certain period may be calculated using the past plan information, and the above integrated energy value may be calculated for each of multiple periods or conditions, and the past constraint information and the past constraint extension information may be set as the upper or lower constraint limit for the kWh constraint using any of the statistical information for the set of the integrated energy values for the multiple periods obtained, that is, the average value, median value, variance, standard deviation, or sample value at a quantile based on a predefined threshold value.
[0100] Similarly, for constraints related to planned shutdowns, a predefined equipment shutdown period may be extracted from past planning information, and past constraint information and past constraint extension information may be set as upper and lower constraint limits in the work shutdown constraints based on statistical information using the same integrated values as above. For constraint items other than those mentioned above, past constraint information and past constraint extension information may be set by calculating feature amounts of past planning information related to various constraints and applying statistical analysis.
[0101] In addition, past constraint extension information may be set using estimated constraint information at a past time point and estimated constraint information in the future. As an example, if the constraint upper limit value included in the estimated constraint information at a future time point is greater than the setting value of the past constraint information assumed at a past time point, it is assumed that the constraint upper limit will be relaxed in the future. In such a case, by further increasing the setting value of "constraint upper limit amount" of "upper limit when increasing or decreasing quantity" shown in the example of FIG. 11A by 200%, a verification scenario including a condition in which the constraint upper limit will be relaxed more than expected at a future time point can be set.
[0102] The constraint change condition generation unit 16 generates constraint change information 31M based on estimated constraint information for past and future points in time, which includes one or more of the upper and lower limits and ranges of change for increasing or decreasing the setting value of each constraint item, the upper and lower limits and ranges of change for the start time, end time, and period length for increasing or decreasing the period that is the subject of the constraint, and the year, season, day of the week, weekday / holiday type, and time of day for the period that is the subject of the constraint.
[0103] (Step S309) Next, the scenario generation unit 17 generates verification scenario information 37 based on the estimated constraint information and the constraint change information (step S309). Here, for each constraint item included in the estimated constraint information 31E, possible combinations of constraint setting values may be calculated based on the variation range, i.e., upper variation limit, lower variation limit, and variation width, of each constraint item included in the constraint change information 31M calculated in step S308, and a verification scenario may be generated by selecting one of the combinations of constraint setting values for all selected constraint items and specifying all combination conditions of the setting values.
[0104] Fig. 12 is a diagram showing an example of verification scenario information 37. Fig. 12 shows an example of verification scenario information 37 generated by the scenario generation unit 17. In the example of Fig. 12, for each verification scenario (scenario a-0, scenario a-1, scenario b-0) shown in each row, the application or non-application of constraint items 371 (constraint item 1) and 372 (constraint item 2), the equipment constrained by each constraint item, the constraint amount of each constraint item, the period constrained by each constraint item, and the scenario generation conditions are stored as verification scenario information.
[0105] In the example of Fig. 12, a verification scenario is generated by setting the constraint application status, the equipment subject to the constraint, the constraint amount, and the constraint period within the range based on the constraint extension information shown in Fig. 11 using the kWh constraint and the planned shutdown constraint, which are the constraint items shown in Fig. 10, and combining the constraint conditions of each constraint item. Here, as the scenario generation condition 373, information on what operations were applied to the base constraint conditions to set the constraint conditions in the verification scenario based on the constraint information 31A and the constraint extension information 32A and 32B may be stored. In the example of Fig. 12, information on the increase or decrease in the constraint amount in the base constraint conditions, and which of the conditions set within the range based on the constraint extension information shown in Fig. 11 among the multiple constraint items were combined to set the constraint conditions in the verification scenario is stored as the scenario generation condition.
[0106] (Step S310) The plan formulation unit 18 uses the verification scenario generated in step S309 to calculate a power generation plan based on the verification scenario (step S310). At this time, an optimization problem reflecting the constraint conditions defined by the verification scenario may be formulated as shown in the following example, and a power generation plan including the start / stop state and power generation output of the generator may be calculated based on the calculation result of the optimization problem. Here, the optimization problem is defined as a problem of minimizing an objective function while satisfying the following constraint conditions.
[0107] An example of the objective function is expressed by the following formula (6). Here, each symbol in the formula is t: index representing time, i: index representing a generator, C i (p): Operating cost for power output p of generator i, SUC i : Start-up cost of generator i, D i (r): Operating cost of generator i for adjustment capacity contribution r, and PC: Penalty cost associated with constraint violation.
number
[0108] The constraint conditions include one or more of the following: (a) supply-demand balance constraint: the power demand to be allocated matches the total power generation output, (b) upper and lower limit constraint on generator output: each generator takes an output value within the range from the lower limit to the upper limit of output, (c) generator output change rate constraint: the change in the output value of each generator between different times is within the upper limit of the output change rate, (d) minimum start-up time / minimum stop time constraint: the generator is operated so that its continuous start-up or stop time is equal to or longer than a specified minimum time, (e) designated start / stop period: the generator is forcibly stopped or operated during a period designated by the operator, and (f) operating reserve / required adjustment capacity constraint: the necessary amount of generator spare capacity is secured to correct the difference between the power demand during actual operation and the supply-demand plan.
[0109] Here, constraint conditions that are not specified in the verification scenario may also be set as constraint conditions in the optimization problem. In this case, a certain period may be extracted from the past planning information, constraint conditions other than those specified in the verification scenario may be extracted from the constraint information set in that period, and the constraint conditions in the optimization problem may be set using the set values.
[0110] The supply and demand planning device 200 and the supply and demand planning method of this embodiment have the following features. (1) A supply and demand planning device 200 that formulates an operation plan after satisfying various operational constraint conditions includes a past performance evaluation unit 14 that compares and evaluates past performance information 33A including information on operation performance at a past time point and past constraint information 31AP including information on constraint information set at a past time point, and a scenario generation unit 17 that generates a verification scenario defined as a combination of various operational constraint conditions based on a past performance evaluation result of the past performance evaluation unit 14. This makes it possible to achieve both the generation of comprehensive verification scenarios that take into account operational constraint conditions that reflect the actual system operation state and the reduction of processing time.
[0111] In other words, in order to verify preventive measures against supply-demand tightness due to supply capacity shortages, it is necessary to formulate plans that take into account multiple scenarios that take into account various unexpected fluctuations. At this time, in addition to preventive measures based on comprehensive scenario verification that takes into account the system operation status, it is necessary to update the scenarios assumed for future system operation in accordance with the actual operation status as needed. Here, if verification scenarios are set mechanically, there is a risk that the scenarios will be excessive for the purpose, which will increase the calculation time for planning, or that important scenarios will not be verified due to insufficient scenarios. For this reason, by formulating a generator start-up and shutdown plan and output allocation that takes into account operational constraints that reflect the actual system operation status, it is possible to generate comprehensive evaluation scenarios and reduce processing time at the same time.
[0112] (2) In (1) above, past performance information 33A includes past information that satisfies one or more conditions of the specified data period of the past information, the acquisition date and time of the past information, the target equipment of the past information, and the target area of the past information.
[0113] (3) In (1) above, the past performance evaluation unit 14 compares and evaluates the past performance information 33A and the past constraint information 31AP with respect to constraint conditions including at least one of the kWh constraint in the designated period and the planned outage constraint in the designated period.
[0114] (4) In (1) above, the past performance evaluation unit 14 compares and evaluates the past performance information 33A and the past constraint information 31AP using a statistical evaluation index value including one or more of an average value, an upper limit value, a lower limit value, and a frequency distribution calculated from the past performance information 33A.
[0115] (5) In the above (1), the supply and demand planning device 200 further includes a constraint condition estimation unit 15 that calculates estimated constraint information 31E including operational constraints at a past point in time reflecting past operational performance, based on the evaluation value of the past performance information 33A calculated by the past performance evaluation unit 14 and the past constraint information 31AP, and the scenario generation unit 17 generates a verification scenario defined as a combination of various operational constraint conditions, based on the estimated constraint information 31E calculated by the constraint condition estimation unit 15.
[0116] (6) In (5) above, the constraint condition estimation unit 15 calculates estimated constraint information at a future point in time (future estimated constraint information 31EF) based on the calculated estimated constraint information at a past point in time 31E (past estimated constraint information 31EP).
[0117] (7) In the above (5), the constraint condition estimation unit 15 calculates estimated constraint information 31E including operational constraints at a past time point, using the degree of conformity with past performance information of the constraint items.
[0118] (8) In (6) above, the supply and demand planning device 200 further includes a constraint change condition generation unit 16 that generates constraint change information 31M based on estimated constraint information 31E at past and future points in time, the constraint change information 31M including upper and lower limits and change ranges for increasing and decreasing the setting value of each constraint item, upper and lower limits and change ranges for the start time, end time, and period length for increasing and decreasing the period for which the constraint is taken into consideration, and one or more of the year, season, day of the week, weekday / holiday type, and time of day for the period for which the constraint is taken into consideration, and the scenario generation unit 17 formulates a supply and demand plan based on the estimated constraint information 31E and the constraint change information 31M, taking into account the estimated constraint information 31E and the constraint change information 31M.
[0119] (9) In the above (6), the supply and demand planning device 200 further includes a plan formulation unit 18 that formulates a supply and demand plan that takes into account the constraint information, based on the constraint information included in the verification scenario.
[0120] (10) A supply and demand planning method for formulating an operation plan while satisfying various operation constraint conditions, comprising: The method includes a past performance evaluation step (see step S306) of comparing and evaluating the past performance information 33A and the past constraint information 31AP based on the past performance information 33A including information on the operation performance at a past time point and the past constraint information 31AP including information on the constraint information set at a past time point, a constraint condition estimation step (see step S307) of calculating estimated constraint information 31E including the operation constraint at a past time point reflecting the past operation performance based on the evaluation value of the past performance information 33A calculated in the past performance evaluation step and the past constraint information 31AP, a scenario generation step (see step S309) of generating a verification scenario defined as a combination of various operation constraint conditions based on the estimated constraint information calculated in the constraint condition estimation step, and a plan formulation step (see step S310) of formulating a supply and demand plan taking into account the constraint information based on the constraint information included in the verification scenario. This makes it possible to achieve both the generation of a comprehensive verification scenario taking into account the operation constraint conditions reflecting the actual system operation state and the reduction of the processing time.
[0121] (11) In the above (10), the supply and demand planning method further includes a constraint change condition generation step (see step S308) for generating constraint change information based on the estimated constraint information, the constraint change information including upper and lower limits and change ranges for increasing and decreasing the setting value of each constraint item, upper and lower limits and change ranges for the start time, end time, and period length for increasing and decreasing the period for which the constraints are taken into consideration, and one or more of the year, season, day of the week, weekday / holiday type, and time of day for the period for which the constraints are taken into consideration, and in the scenario generation step, a supply and demand plan is formulated based on the estimated constraint information 31E and the constraint change information 31M, taking into account the estimated constraint information 31E and the constraint change information 31M. [Explanation of symbols]
[0122] 10. Supply and Demand Planning Department 11 Constraint information acquisition section 12 Past Performance Acquisition Department 13 Past Plan Acquisition Department 14 Past Performance Evaluation Department 15 Constraint estimation section 16 Constraint change condition generation unit 17 Scenario Generation Section 18 Planning Department 21 Measuring Equipment 30 Information storage section 31 Constraint information DB 31A Constraint information 31AP past constraint information 31E Estimated constraint information 31EF Future Estimated Restrictions Information 31EP Past estimation constraint information 31M Restriction Change Information 32 Constraint Extension Information DB 32A,32B Constraint extension information 32AM, 32BM restriction extension information 33 Past performance DB 33A Past performance information 34 Past Plan DB 34A, 34B Past planning information 35A Evaluation Index Information 37 Verification scenario information 101 Generator 102 Substation 103 Phase adjustment equipment 104 Power load 105 External power system 108 Information and Communication Networks 200 Supply and Demand Planning Device
Claims
1. A supply and demand planning device that formulates an operation plan while satisfying various operation constraint conditions, a past performance evaluation unit that compares and evaluates the past performance information and the past constraint information based on past performance information including information on operation performance at a past point in time and past constraint information including information on constraint information set at a past point in time; a scenario generation unit that generates a verification scenario defined as a combination of various operational constraint conditions based on a past performance evaluation result of the past performance evaluation unit. A supply and demand planning device comprising:
2. The past performance information includes past information that satisfies one or more of the following conditions: a data period of the specified past information, an acquisition date and time of the past information, a target facility of the past information, and a target area of the past information.
2. The supply and demand planning device according to claim 1 .
3. The past performance evaluation unit compares and evaluates the past performance information and the past constraint information with respect to constraint conditions including at least one of a kWh constraint in a specified period and a planned stoppage constraint in a specified period.
2. The supply and demand planning device according to claim 1 .
4. The past performance evaluation unit compares and evaluates the past performance information and the past constraint information using a statistical evaluation index value including one or more of an average value, an upper limit value, a lower limit value, and a frequency distribution calculated from the past performance information.
2. The supply and demand planning device according to claim 1 .
5. The supply and demand planning device further includes a constraint condition estimation unit that calculates estimated constraint information including operation constraints at a past time point that reflect the past operation performance, based on the evaluation value of the past performance information calculated by the past performance evaluation unit and the past constraint information, The scenario generator generates a verification scenario defined as a combination of various operational constraint conditions based on the estimated constraint information calculated by the constraint condition estimator.
2. The supply and demand planning device according to claim 1 .
6. The constraint condition estimation unit calculates estimated constraint information at a future time point based on the estimated constraint information at a past time point calculated.
6. The supply and demand planning device according to claim 5.
7. The constraint condition estimation unit calculates estimated constraint information including operational constraints at a past time point using a degree of conformity with past performance information of the constraint items.
6. The supply and demand planning device according to claim 5.
8. the supply and demand planning device further includes a constraint change condition generating unit that generates constraint change information based on the estimated constraint information for the past time point and the future time point, the constraint change information including one or more of upper and lower limits and change ranges for increasing and decreasing the set value of each constraint item, upper and lower limits and change ranges for the start time, end time, and period length for increasing and decreasing the period subject to the constraint consideration, and the year, season, day of the week, weekday / holiday type, and time of day for the period subject to the constraint consideration, The scenario generation unit formulates a supply and demand plan based on the estimated constraint information and the constraint change information, the supply and demand plan taking into account the estimated constraint information and the constraint change information.
7. The supply and demand planning device according to claim 6.
9. The supply and demand planning device further includes a planning unit that formulates a supply and demand plan that takes into account constraint information included in the verification scenario.
7. The supply and demand planning device according to claim 6.
10. A supply and demand planning method for formulating an operation plan while satisfying various operation constraint conditions, a past performance evaluation step of comparatively evaluating the past performance information and the past constraint information based on past performance information including information on operation performance at a past point in time and past constraint information including information on constraint information set at a past point in time; a constraint condition estimation step of calculating estimated constraint information including operational constraints at a past time point that reflect the past operational performance, based on the evaluation value of the past performance information calculated in the past performance evaluation step and the past constraint information; a scenario generation step of generating a verification scenario defined as a combination of various operational constraint conditions based on the estimated constraint information calculated in the constraint condition estimation step; and a planning step of formulating a supply and demand plan that takes into account the constraint information based on the constraint information included in the verification scenario. A supply and demand planning method comprising:
11. The supply and demand planning method further includes a constraint change condition generating step of generating constraint change information based on the estimated constraint information, the constraint change information including upper and lower limits and change ranges for increasing and decreasing the set value of each constraint item, upper and lower limits and change ranges for the start time, end time, and period length for increasing and decreasing the period subject to the constraint consideration, and one or more of the year, season, day of the week, weekday / holiday type, and time of day for the period subject to the constraint consideration, In the scenario generation step, a supply and demand plan is formulated based on the estimated constraint information and the constraint change information, taking into account the estimated constraint information and the constraint change information. The supply and demand planning method according to claim 10 .
Citation Information
Patent Citations
Power system planning device and method
JP2020188619A
Energy management system
US20120010757A1
Priority calculation device and priority calculation program
JP2021191112A
Cited By
System for designing specification for gas separation device, method for designing specification for gas separation device, and program
WO2026163553A1