Arc Furnace Equipment
The arc furnace system uses image and operational data analysis to predict and prevent arc breakage by adjusting electrode position, addressing the unpredictability of scrap collapse and reducing shutdowns.
Patent Information
- Application Number
- JP2023518529
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-11-08
- Publication Date
- 2024-09-18
- Estimated Expiration
- 2041-11-08
AI Technical Summary
The occurrence of arc breakage due to scrap collapse during melting in arc furnaces is unpredictable, leading to unstable operations and frequent shutdowns, as the internal state of the furnace is unclear and current methods fail to prevent scrap falling and resulting short circuits.
An arc furnace system equipped with a camera and information processing device that analyzes scrap input state through image data and operational data to predict arc breakage using an arc breakage prediction model, incorporating brightness and density indices, and potentially height indices, to prevent short circuits by adjusting electrode position.
The system effectively predicts arc breakage occurrences, allowing for proactive intervention to prevent circuit breaker disconnections and reduce operational stoppages by automatically adjusting electrode position.
Smart Images

Figure 0007552883000030 
Figure 0007552883000026 
Figure 0007552883000027
Abstract
Description
[Technical field]
[0001] The present disclosure relates to an electric arc furnace facility that melts scrap by utilizing heat generated by arc discharge between the scrap and an electrode. [Background technology]
[0002] In an electric furnace, scrap inserted into the furnace is heated and melted by supplying electricity. There are three types of electric furnace: resistance furnaces, which heat the scrap by Joule heat, induction furnaces, which use electromagnetic induction to induce a current in the scrap and heat it by its own resistance heating, and arc furnaces, which use the heat generated by the arc and electrodes.
[0003] In particular, electric arc furnaces have the advantages of being able to use cheap scrap iron as the main raw material, being able to be easily started and stopped, giving flexibility in facility operation, and being able to produce relatively large quantities with less investment than blast furnaces.
[0004] In an electric arc furnace, an arc is generated between the scrap and the electrodes or between the electrodes, and the scrap is melted by the heat. The arc can be generated by manipulating the power supplied to the electrodes and the distance between the electrodes and the scrap. Patent Document 1 discloses that in order to stably generate an arc, constant impedance control is performed and the elevation position of the electrodes is controlled.
[0005] It usually takes 2 hours from the time scrap is charged to the time the melted scrap (molten metal) is discharged. Scrap is added 3 times, and then goes through processes such as adjusting the composition. This series of operations is called "charging." When adding scrap, the electric arc furnace operator adds a predetermined amount of scrap at a predetermined time, while imagining the conditions inside the furnace based on experience.
[0006] In addition, in order to generate a stable arc, the electrode may be raised and lowered by the operator separately from the automatic control. During the melting operation, the electrode may be moved far away from the scrap by the operator due to some factor. For example, the electrode and scrap may come close to each other, causing the current value to exceed the allowable range. If the electrode is not raised even when the current value exceeds the allowable range, an overcurrent occurs, causing a short circuit between the electrode and the scrap. When a short circuit occurs, the circuit breaker is usually tripped. Here, this phenomenon is called arc interruption.
[0007] Once the breaker is tripped, it takes time to restore operation, which results in a shutdown and reduced production. To prevent this, operators raise and lower the electrodes based on experience. [Prior art documents] [Patent documents]
[0008] [Patent Document 1] Japanese Patent Publication No. 2006-85936 [Patent Document 2] Japanese Patent Publication No. 2018-28421 [Patent Document 3] Japanese Patent Publication No. 2008-116066 Summary of the Invention [Problem to be solved by the invention]
[0009] One of the reasons why the current value exceeds the allowable range is that the condition of the scrap that is charged is unclear. The amount of scrap charged is determined based on the operating conditions, but the condition of the scrap, such as the density or uneven distribution of the scrap when it is charged, cannot be controlled. In addition, after the scrap is charged, the lid is closed to maintain the temperature inside the furnace and prevent the molten metal from scattering to the surrounding area. Therefore, the operator cannot grasp the condition inside the furnace during melting.
[0010] Depending on the scrap loading condition, part of the scrap may collapse during melting and come into contact with the electrodes. In this case, an unexpected short circuit causes the arc to break, and there is currently no way to prevent this. Thus, there is a need for a method to grasp the loading condition of the scrap and the state inside the furnace during melting, or to predict and avoid the occurrence of unsteady phenomena such as the collapse of scrap.
[0011] As a method for grasping the state inside the furnace, for example, Patent Document 2 discloses a method for predicting the length of the electrodes consumed by melting and appropriately grasping the distance between the scrap and the electrodes. However, this is only a prediction of the length of the electrodes and cannot prevent operation stoppages due to unsteady factors such as the collapse of scrap.
[0012] As a method for grasping the state inside the furnace, for example, Patent Document 3 discloses an operating method in which thermometers are installed at various points on the furnace wall and the state inside the furnace is grasped from the temperature around the furnace periphery. According to this, it is possible to visualize the state inside the furnace from the melting point of the steel type of the scrap fed in and the temperature of the entire furnace. However, by only obtaining the state of the scrap near the periphery of the furnace and the temperature history information of the molten scrap, it is not necessarily possible to grasp the state of the scrap during melting. Therefore, it is difficult to prevent operation stoppages due to unsteady factors such as the collapse of scrap.
[0013] The present disclosure has been made to solve the above-mentioned problems, and an object of the present disclosure is to provide an electric arc furnace facility capable of predicting the occurrence of a circuit breaker tripping (arc interruption) caused by a short circuit due to the collapse of scrap during melting. [Means for solving the problem]
[0014] The first aspect relates to an electric arc furnace installation. The arc furnace facility includes an arc furnace, a camera, and an information processing device. The arc furnace melts the scrap by utilizing heat generated by arc discharge between the scrap and electrodes. The camera photographs the scrap fed into the arc furnace. The information processing device includes a memory and a processor. The memory stores information including image data obtained from the camera at the time of scrap input, control performance data regarding the electrode after melting has started, and an arc interruption prediction model. The processor processes the information stored in the memory. The processor is configured to input the arrangement and density of the scrap based on the image data and the control performance data into the arc interruption prediction model and perform a predictive process to predict the occurrence of arc interruption due to a short circuit between the scrap and the electrode.
[0015] The second aspect has the same features as the first aspect, as well as the following features. The placement and density of the scraps is based on a brightness index of each pixel of the image data. The control performance data includes operation time-series data and operation attribute data. The operation time series data includes current values, voltage values, and elevation speed values for the electrodes at each sampling time. The operation attribute data includes the input time and input amount of the scrap.
[0016] The third aspect has the following features in addition to those of the second aspect. The memory stores learning data. The learning data includes the image data, the operation time-series data, the operation attribute data, and an arc interruption occurrence label relating to scrap previously discharged from the arc furnace, The arc interruption occurrence label indicates an occurrence of an arc interruption associated with a sampling time at which a current value is higher than a short circuit correlation value among each sampling time of the operation time-series data. The processor is configured to perform a learning process for constructing the arc interruption prediction model based on the learning data.
[0017] A fourth aspect has the following features in addition to any one of the first to third aspects. The camera takes three-dimensional images of the scrap fed into the arc furnace. The image data includes a brightness index and a height index for each pixel. The placement and density of the scraps is based on a brightness index and a height index of each pixel of the image data.
[0018] A fifth aspect has the following features in addition to any one of the first to fourth aspects. The processor is configured to perform a short circuit prevention process that outputs a command to lift the electrode when the prediction process predicts that an arc interruption will occur. Effect of the Invention
[0019] According to the present disclosure, the arc furnace facility obtains information on the arrangement and density of scrap when the scrap is input from image data acquired from a camera. After melting starts, the arc furnace facility can predict the occurrence of arc interruption from the information and current control performance data. This allows the arc furnace facility to predict the occurrence of a circuit breaker tripping (arc interruption) caused by a short circuit due to the collapse of scrap during melting. [Brief description of the drawings]
[0020] [Figure 1] FIG. 1 is a diagram for explaining a configuration example of an arc furnace facility according to a first embodiment. [Diagram 2] 3 is a diagram showing an imaging range of a scrap photography camera in accordance with the first embodiment; FIG. [Diagram 3] 1 is a block diagram illustrating an example of an outline of functions of an arc interruption prediction device according to a first embodiment. [Figure 4] 3 is a diagram showing an outline of operation time-series data and operation attribute data according to the first embodiment. FIG. [Diagram 5] 10 is a flowchart for explaining a procedure for acquiring scrap image data in a camera image acquiring unit according to the first embodiment. [Figure 6] FIG. 2 is a diagram showing an example of scrap image data according to the first embodiment. [Figure 7] 10 is a diagram showing an outline of how brightness indices of scrap image data are stored according to the first embodiment. FIG. [Figure 8] 4 is a flowchart for explaining a procedure for constructing an arc interruption prediction model in an arc interruption learning unit according to the first embodiment. [Figure 9] 10 is a flowchart for explaining a procedure for assigning an arc interruption label in an arc interruption learning unit according to the first embodiment. [Figure 10] 10 is a diagram for explaining the procedure for assigning an arc interruption label in the arc interruption learning unit according to the first embodiment. FIG. [Figure 11] FIG. 4 is a diagram showing an outline of input values in the first embodiment. [Figure 12] 4 is a flowchart for explaining an arc interruption prediction procedure in an arc interruption predicting unit according to the first embodiment. [Figure 13] FIG. 11 is a diagram showing an outline of a brightness index and a height index of scrap image data in the second embodiment. [Figure 14] 11 is a block diagram illustrating an example of an outline of functions of an arc interruption prediction device according to a third embodiment. FIG. [Figure 15] 2 is a conceptual diagram showing an example of the hardware configuration of a processing circuit included in the arc interruption prediction device. FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0021] Hereinafter, embodiments of the present disclosure will be described in detail with reference to the drawings. In addition, elements common to the various drawings will be designated by the same reference numerals and duplicated explanations will be omitted.
[0022] Embodiment 1 1. Arc furnace FIG. 1 is a diagram for explaining a configuration example of an arc furnace facility 1 according to the first embodiment. An electric arc furnace melts steel pieces (scrap 2) containing various alloys that are placed in the furnace to form molten metal 3. The electric arc furnace is equipped with a furnace body 4 into which the scrap 2 is placed and which stores the molten metal 3, a lid 5 for preventing heat loss during melting and scattering of the molten metal 3 to the surrounding area, and a tap hole 6 for discharging the molten metal 3.
[0023] During melting, the temperature inside the furnace is high enough to melt the steel pieces (scrap 2), so firebricks are attached to the inner surfaces of the furnace body 4 and lid 5. A hole is made in the lid 5, and an electrode 7 for generating an arc is inserted into the furnace body 4. Generally, the electrode 7 is made of carbon and multiple electrodes are provided.
[0024] Electric power is supplied to these electrodes 7, generating an arc between the electrodes 7 and the scrap 2 placed inside, and the scrap 2 is melted by the heat of the arc to obtain molten metal 3. The electrodes 7 are raised and lowered by an electrode lifting device 8 to maintain an appropriate distance between the electrodes 7 and the scrap 2 for generating an arc. The power supplied to the electrodes 7 and the raised and lowered positions of the electrodes 7 are controlled by a control device 9. The output device 10 includes, for example, a power source and a circuit breaker.
[0025] At this time, command values such as the current and voltage for obtaining the power supplied to the electrode 7, and the lifting speed for obtaining the lifting position of the electrode 7 are set based on information such as the steel type of the scrap 2 and the input amount of the scrap 2. Although automatic operation is possible based on these settings, as described above, since the generation of the arc is unstable, usually an operator manually operates each time. This manual operation is mainly applied to the lifting speed for changing the lifting position of the electrode 7.
[0026] Moreover, performance information during actual melting operation may be input to the control device 9 and used for feedback control or the like.
[0027] A melting number is assigned to each molten metal 3 produced in one charge from the initial input of scrap 2 to the discharge of the melted molten metal 3, and this number is used for product management and quality control.
[0028] The arc furnace facility 1 according to this embodiment further includes a camera (scrap photographing camera 20) for photographing the inside of the furnace body 4, and an information processing device (arc interruption prediction device 30) for predicting arc interruption.
[0029] 2. Scrap Shooting Camera The scrap photography camera 20 photographs the state of scrap 2 each time it is fed. The imaging range of the scrap photography camera 20 is shown in FIG. 2. It is desirable that the scrap photography camera 20 is placed directly above the furnace body 4 so that it can photograph the entire inside of the furnace as shown in FIG. 2. Since the inside of the furnace body 4 becomes very hot during melting and the radiant heat is also transmitted to the outside, it is desirable that the scrap photography camera 20 be equipped with a water-cooling mechanism. Furthermore, since the steam and gas generated by melting rise directly above, it is desirable that the scrap photography camera 20 be placed at a distance from the furnace body 4 so that it is not affected by them.
[0030] In addition, when photographing the inserted state of the scraps 2, it is desirable to adjust the contrast, brightness, exposure, etc. so that the scraps 2 can be properly viewed. These adjustments may be processed by the scrap photographing camera 20 or by the camera image acquisition unit 32 described later.
[0031] 3. Arc interruption prediction device Fig. 3 is a block diagram illustrating an outline of functions of the arc interruption prediction device 30 according to the first embodiment. The configuration shown in Fig. 3 is an example, and is not limited thereto. The arc interruption prediction device 30 predicts arc interruption based on the input state of the scrap 2 obtained each time the scrap 2 is input and data on the operation during melting, and outputs the result.
[0032] (Operational Data Collection Division) The operation data collection unit 31 collects control performance data. The control performance data includes operation time-series data and operation attribute data.
[0033] The operation time series data is information on the control output during melting. The operation time series data includes, for example, the set and actual current values, actual voltage values, elevation speed reference values, and flag signals indicating whether the actual current value has reached an overcurrent level for each electrode 7. The operation time series data further includes flag signals indicating whether manual operation has been performed by the operator, as well as elevation speed command values, and flag signals indicating the on / off of a circuit breaker in response to the occurrence of a problem such as arc interruption. The operation time series data is data at each sampling point (sampling time) of these J signals acquired at a fixed sampling interval Δt.
[0034] The operation attribute data is information associated with other melting operations. The operation attribute data includes, for example, the time and amount of scrap 2 charged, the wear state of the electrodes 7, the temperature inside the furnace after melting, the steel type and composition of the charged scrap 2, the amount of elements charged when adjusting the composition, etc. The operation attribute data is information summarizing the melting status.
[0035] The information collected by the operation data collection unit 31 is stored in a database 33, for example, as shown in FIG. 4, with the operation time series data and operation attribute data linked by the melting number and the start time of each process.
[0036] (Camera image acquisition section) The camera image acquisition unit 32 acquires image data (imaging data) capturing an image of the input state of the scrap 2 (the arrangement and density state of the scrap 2) from the scrap photographing camera 20. Thereafter, the camera image acquisition unit 32 generates scrap image data to be used by the arc interruption learning unit 34 and the arc interruption prediction unit 35.
[0037] FIG. 5 is a flowchart for explaining a procedure for generating scrap image data in the camera image acquisition unit 32. As shown in FIG.
[0038] In step S100, the camera image acquisition unit 32 determines whether or not it is the timing when the scrap 2 is charged into the furnace body 4. If it is not the timing when the scrap 2 is charged, the camera image acquisition unit 32 waits for the timing to charge the scrap.
[0039] On the other hand, if it is the timing when the scrap 2 is inserted, in step S110, the camera image acquisition unit 32 acquires image data (image capture data) from the scrap photographing camera 20 at the time of the scrap insertion.
[0040] In step S120, the camera image acquisition unit 32 converts the captured image data into a grayscale image. The grayscale image conversion provides a brightness value that represents the density of the scrap 2 at the time of input. As a method for converting the captured image into a grayscale image, for example, the following conversion method is available.
[0041]
number
[0042]
number
[0043]
number
[0044]
number
[0045] where img is the color space numeric array of the image data. w is the number of pixels in the horizontal direction of the image. h is the number of pixels in the vertical direction of the image. I is the pixel value at horizontal pixel position x and vertical pixel position y. img_gray is the grayscale numeric array. I'(x,y) is the grayscale pixel value at horizontal pixel position x and vertical pixel position y.
[0046] As an example, the color space of I(x,y) is described in RGB space, but this is not limiting. Also, each coefficient for calculating I'(x,y) is defined in ITU-R BT.601 (Studio encoding parameters of digital television for standard 4:3 and wide screen 16:9 aspect ratios International Telecommunication Union), which is an international standard related to conversion between analog and digital signals, and may be based on other standards.
[0047] Depending on the facility environment, the scraps 2 may not always be visible. Therefore, after the scraps are charged and before the lid 5 is closed, image data may be obtained multiple times, and the grayscale image obtained by the above-mentioned processing may be obtained from the average value at each pixel position (equation (5)).
[0048]
number
[0049] Here, N cap is the number of image data acquired after the scraps are charged and before the lid 5 is closed.
[0050] Next, in step S130, the camera image acquisition unit 32 changes the number of pixels of the grayscale data.
[0051] The camera image acquisition unit 32 smoothes the grayscaled image, and then adjusts it to a predetermined number of pixels (number of data) to be used by the arc interruption learning unit 34 and the arc interruption prediction unit 35, thereby obtaining scrap image data. For example, the Gaussian filter weights neighboring pixel values by a Gaussian distribution g to smooth the image (equation (6)).
[0052]
number
[0053] This is just one example, and smoothing by average filtering or median filtering is also possible. The number of pixels in the smoothed image is adjusted. The number of pixels can be adjusted by the following procedure (equation (7)).
[0054]
number
[0055] where img_resize is the numeric array of the smoothed image. x is the horizontal pixel position of the smoothed image. y is the vertical pixel position of the smoothed image. α is the scaling factor. The symbol [ ] is rounding. R is the smoothed pixel value (brightness index). w' is the number of horizontal pixels of the smoothed image. h' is the number of vertical pixels of the smoothed image.
[0056] The brightness of a pixel is used as an index showing the input state of the scraps 2. The arrangement and density of the scraps 2 are expressed based on the brightness index of each pixel of the scrap image data. Fig. 6 is a diagram showing an example of the scrap image data.
[0057] In step S140, the camera image acquisition unit 32 stores the scrap image data in the database 33. The numerical sequence of the scrap image data is stored as a brightness index in the database 33. The scrap image data is saved in association with the dissolution number and the photographed date and time, as shown in FIG.
[0058] (Arc interruption learning section) Next, the arc interruption learning unit 34 will be described. The arc interruption learning unit 34 constructs an arc interruption prediction model based on the learning data and evaluation data stored in the database 33. The learning data and evaluation data include scrap image data, operation time series data, operation attribute data, and arc interruption occurrence labels related to scrap 2 previously discharged from the arc furnace. The arc interruption occurrence labels indicate the occurrence of arc interruption associated with a sampling time at which the current value is higher than the short circuit correlation value for each sampling time of the operation time series data. The procedure for constructing the arc interruption prediction model will be described with reference to FIG. 8.
[0059] FIG. 8 is a flowchart for explaining the procedure for constructing an arc interruption prediction model in arc interruption learning unit 34.
[0060] In step S200, the arc interruption learning unit 34 calculates the total number of melting numbers stored in the database 33, that is, the number of charges M charge The number of times required for model training is M Learning Determine whether it is greater than or equal to.
[0061] M charge M Learning If the number of pieces is greater than the number of pieces of scrap, in step S210, the arc interruption learning unit 34 acquires operation time series data, operation attribute data, and scrap image data from the database 33 based on the melting number and date and time. charge M Learning If it is equal to or less, the number of data used for learning the arc interruption prediction model is insufficient, so arc interruption learning unit 34 re-executes the process of step S200 after the current charge ends.
[0062] In step S220, the arc interruption learning unit 34 acquires an arc interruption label. Here, the procedure for assigning the arc interruption label in step S220 will be described with reference to FIG. 9. FIG. 9 is a flowchart for explaining the procedure for assigning the arc interruption label in the arc interruption learning unit 34. The process in FIG. 9 is executed for each operation time-series data stored in the database 33.
[0063] In step S300 of FIG. 9, the arc interruption learning unit 34 acquires operation time-series data.
[0064] In step S310, the arc interruption learning unit 34 calculates the actual current value I Act(n) is the given current value I ARC Check whether it is smaller than I Act(n) I ARC If it is smaller than , the process of step S320 is executed.
[0065] In step S320, the arc interruption learning unit 34 calculates the circuit breaker ON / OFF signal S of the data at the sampling point n. VCB(n) Determine whether S is off. VCB(n) If it is off, the process proceeds to step S330.
[0066] In step S330, the arc interruption learning unit 34 outputs a signal S MAN(n) Determine whether S is off. MAN(n) If the check signal is OFF, the process proceeds to step S340. That is, if all of the determination conditions in steps S310 to S330 are satisfied, the process proceeds to step S340.
[0067] In step S340, the arc interruption learning unit 34 performs a predetermined number of sampling points N from the sampling point n. OC The number of sampling points (nN OC ,nN OC +1,nN OC +2,…,n-1,n,n+1,…,n+N OC -2,n+N OC -1,n+N OC ) operation time series data will be obtained.
[0068] In step S350, the arc interruption learning unit 34 outputs a signal S indicating whether or not the actual current value has reached the level of the overcurrent (short circuit correlation value) in the operation time-series data acquired in step S340. Overcurrent Determine whether there is a time when S is on. Overcurrent When there is a time when the arc interruption learning unit 34 is turned on, the arc interruption label L ARC Mark (L ARC =1).
[0069] A given number of sampling points N at sampling point n OC is a predetermined number of points that specifies a short range in the melting process of the operation time series data. At this time, since it is necessary to catch the sign before the arc break occurs, the arc break label is a desired time T aim The number of sampling points N is calculated using equation (8) based on the sampling interval Δt. aim That is, the arc interruption learning unit 34 is given at a sampling point nN aim Arc out label L ARC(n-Naim) Mark the .
[0070]
number
[0071] That is, if all the determination conditions of steps S310 to S350 are satisfied, in step S360, the arc interruption learning unit 34 reads the arc interruption label L ARC(n-Naim) Mark (L ARC(n-Naim) On the other hand, if any of the determination conditions in steps S310 to S350 is not satisfied, in step S370, the arc interruption learning unit 34 determines whether the arc interruption label L ARC(n-Naim) Do not mark (L ARC(n-Naim) =0).
[0072] The above-mentioned method of assigning the arc break label is one example, and the arc break label may be generated according to other conditions or procedures, or the operator may generate the arc break label from some input terminal. The arc break label is associated with the melting number and sampling point of the operation time series data and stored in the database 33.
[0073] Returning to Fig. 8, we will continue to explain the procedure for building the arc interruption prediction model. In step S220, the arc break label stored in the database 33 by the process of FIG. 9 described above is obtained.
[0074] In step S230, the arc break learning unit 34 calculates the total number of arc break labels N Label However, the number of times that arc interruption occurs is N Label ' Determine whether it is greater than the total number of arc-broken labels N Label is the number of charges M charge This is the total number of arc interruptions that occurred at each sampling point of the operational time series data.
[0075] N Label N Label If N' is more than N, in step S240, the arc interruption learning unit 34 acquires learning data from the database 33. The learning data is a part of the set of scrap image data, operation time series data, operation attribute data, and arc interruption label stored in the database 33. Label N Label In the following cases, the number of data used to learn the arc interruption prediction model is insufficient, so arc interruption learning unit 34 re-executes the process of step S210 after the current charge ends.
[0076] In step S250, the arc interruption learning unit 34 uses the acquired learning data to learn an arc interruption prediction model, which will be described later.
[0077] In step S260, the arc interruption learning unit 34 acquires evaluation data from the database 33. The evaluation data is a part of the data group stored in the database 33, which is made up of sets of scrap image data, operation time-series data, operation attribute data, and arc interruption labels, excluding the learning data.
[0078] In step S270, the arc interruption learning unit 34 evaluates an arc interruption prediction model, which will be described later, using the evaluation data.
[0079] In step S280, arc interruption learning unit 34 determines whether or not to apply the arc interruption prediction model. If the evaluation value is equal to or greater than a predetermined value, the arc interruption prediction model is stored in database 33. On the other hand, if the evaluation value is less than the predetermined value, the accuracy of the learned arc interruption prediction model is insufficient, so arc interruption learning unit 34 re-executes the process of step S210 after the current charge ends.
[0080] In step S290, the arc interruption learning unit 34 updates or saves the arc interruption prediction model. If there is an already learned arc interruption prediction model, the arc interruption learning unit 34 may update or save it. The arc interruption prediction model is stored in the database 33.
[0081] The learning of the arc interruption prediction model in step S250 and the evaluation of the arc interruption prediction model in step S270 will be described in more detail below.
[0082] The arc interruption prediction model can be expressed, for example, by the following linear regression model.
[0083]
number
[0084]
number
[0085]
number
[0086]
number
[0087] Here, L pred is the arc interruption prediction, I pred is the predicted current value, X is the explanatory variable (input value) of the prediction model, β is the coefficient, ε is the disturbance term, N L is the total number of learning data, and p is the number of explanatory variables. In equation (9), the arc interruption prediction L pred i = 1 means that the number of sampling points N aim Time after i+N aim It is predicted that arc interruption will occur at
[0088] The arc interruption prediction model is constructed by determining β and ε so as to satisfy equations (10) and (11) using the learning data. The arc interruption prediction model is then evaluated using the evaluation data and equation (12). It is desirable to construct the arc interruption prediction model so that equation (12) is minimized using the learning data and evaluation data. Here, N V is the total number of data used for evaluation. In step S280 described above, the evaluation value based on equation (12) can be used.
[0089] The linear regression model is one example, and a non-linear model such as machine learning may be used to construct an arc breakage prediction model. For example, a classifier using XGBoost (Extreme Gradient Boosting), which is an ensemble learning model using decision trees, or a similar Random Forest, etc. may be applied as the arc breakage model. Here, the concept of XGBoost is shown below as an example. In XGBoost, a prediction value is obtained by ensembling the results of multiple parallelized decision trees. The input value X i The predicted value y obtained for pred i is obtained by the following formula:
[0090]
number
[0091] Here, X i is the input value, K is the number of trees, T is the number of leaves, ω is the leaf weight, and F is the regression tree space. In the initial stage of model construction, the number of trees K=1. When the difference between the obtained predicted value and the target value is minimized, the model has good accuracy. The accuracy of the model is evaluated by calculating the loss function L(φ) as follows:
[0092]
number
[0093] where y iis the objective value, l is the residual between the predicted value and the objective value, Ω is the regularization term, and γ and λ are parameters. A model that minimizes the loss function L(φ) is sought. In order to generate a model that minimizes the loss function L(φ), we aim to minimize L(φ) by increasing the number of decision trees using Gradient Boosting. When using such a classifier, the predicted value y pred i Arc interruption prediction L pred Alternatively, if the regression model is used to predict the current value, the predicted value y pred i The predicted current value I pred In addition, arc interruption may be determined based on a condition such as equation (9).
[0094] Arc interruption prediction L at sampling point i pred i The explanatory variables to be input to the arc interruption prediction model in order to output the above can be, for example, as follows:
[0095]
number
[0096] Here, R w’h’ is the brightness index of the scrapped image data, P K is operation attribute data, O i (j) is the j-th component (j=1,2,...,J) of the operation time series data at sampling point i. For the operation time series data, only the component at sampling point i may be used as the explanatory variable, or the component at a given sampling point N from sampling point i may be used as the explanatory variable. Buff You can add components from sampling points going back N to the explanatory variables. Buff is the number of points in a short range in the melting process as shown in Figure 11. The brightness index R of the scrap image data w’h’ and operation attribute data P K In other words, when the arc interruption prediction model is a linear regression model, for example, p (the number of explanatory variables) in formula (10) is expressed as follows:
[0097]
number
[0098] (Arc interruption prediction section) Next, the arc interruption prediction unit 35 will be described. The arc interruption prediction unit 35 inputs the arrangement and density of the scrap 2 based on the scrap image data, and the control performance data into an arc interruption prediction model, and predicts the occurrence of arc interruption due to a short circuit between the scrap 2 and the electrode 7.
[0099] FIG. 12 is a flowchart for explaining the procedure of arc interruption prediction in arc interruption predictor 35.
[0100] In step S400, the arc interruption prediction unit 35 determines whether or not it is the timing when the scrap 2 is charged into the furnace body 4. If it is not the timing when the scrap 2 is charged, the arc interruption prediction unit 35 waits for the timing of scrap charging.
[0101] On the other hand, if it is the timing when the scrap 2 is input, the scrap image data is generated by the camera image acquisition unit 32 before the start of melting by the same process as that shown in FIG. 5 described above.
[0102] In step S410, the arc interruption prediction unit 35 acquires the latest scrap image data. The scrap image data may be acquired directly from the camera image acquisition unit 32, or may be acquired after being stored in the database 33.
[0103] In step S420, the arc interruption prediction unit 35 determines whether or not melting has started. If melting has not started, the arc interruption prediction unit 35 waits for the start of melting.
[0104] After melting is started, in step S430, the arc interruption prediction unit 35 acquires operation time-series data and operation attribute data for the current charge. The operation time-series data collected by the operation data collection unit 31 may be acquired directly from the operation data collection unit 31 every moment according to a sampling period, or may be acquired after being stored in the database 33.
[0105] In step S440, scrap image data, operation time series data, and operation attribute data are input values, and arc interruption is predicted using an arc interruption prediction model. The input values of the arc interruption prediction model are explanatory variables, just as when the model was constructed (Equation (15)). Therefore, the latest sampling point n Now From N Buff The sampling points going back by 10 ...
[0106] In step S450, the arc interruption prediction unit 35 detects the latest sampling point n Now For example, the arc interruption prediction result is stored in the database 33. pred When the value of the arc interruption forecast becomes 1, the arc interruption forecast output unit 36 issues a forecast of the occurrence of an arc interruption by using images, sounds, vibrations, etc. The operator who receives the forecast can perform an operation to raise the electrode 7 to avoid an arc interruption. This can reduce the downtime caused by the circuit breaker tripping.
[0107] In step S460, arc interruption prediction unit 35 determines whether or not melting has been completed. If melting has not been completed, arc interruption prediction unit 35 returns to the process of step S430 again and predicts arc interruption based on the latest control performance data.
[0108] 4.Effects As described above, the arc interruption prediction device 30 according to this embodiment can predict the occurrence of circuit breaker tripping (arc interruption) caused by a short circuit due to the collapse of scrap during melting. In addition, by issuing a forecast of the occurrence of arc interruption, the operator can raise the electrode 7 to prevent a short circuit due to contact between the scrap 2 and the electrode 7. This makes it possible to avoid operation stoppage due to the tripping of the circuit breaker.
[0109] 5. Variations In the arc furnace equipment 1 according to the above-mentioned first embodiment, the arc interruption prediction unit 35 predicts the occurrence of arc interruption by using the arc interruption prediction model constructed in the arc interruption learning unit 34. However, when an appropriate arc interruption prediction model exists in advance, the arc interruption prediction unit 35 may predict the occurrence of arc interruption by using the prediction model. This point is the same in the following embodiments.
[0110] In addition, in FIG. 3, arc interruption prediction output unit 36 is disposed outside arc interruption prediction device 30, but it may be included in arc interruption prediction device 30.
[0111] Embodiment 2 Next, a second embodiment of the present disclosure will be described with reference to Fig. 13. Descriptions that overlap with the above-mentioned embodiment will be omitted.
[0112] In the second embodiment, in addition to pixel brightness, height is used as an index indicating the feeding state of the scrap 2. The arrangement and density of the scrap 2 are expressed based on the brightness index and height index of each pixel of the scrap image data. This provides a more accurate feeding state of the scrap 2 as an explanatory variable of the arc interruption prediction model, making it possible to predict with high accuracy whether or not an arc interruption will occur.
[0113] The scrap photographing camera 20 according to the second embodiment is capable of photographing an object in three dimensions. The arrangement of the scrap photographing camera 20 is the same as that of the first embodiment. The image data captured by the scrap photographing camera 20 includes information on the height at which the scrap was inserted.
[0114] There are several types of cameras capable of capturing images in 3D, including the stereo camera method, the ToF (Time of Flight) method, and the projector method. The stereo camera method uses multiple cameras to derive the distance between an object and the stereo camera based on the installation interval, focal length, and image difference (parallax). The ToF method derives the distance between an object and the camera based on the speed at which pulsed or continuous light emitted from the camera is reflected from the object. The projector method derives the difference in elevation of an object based on the distortion of a striped pattern illuminated on the object.
[0115] The three-dimensional imaging method shown here is merely an explanation of the principle, and any method may be used. In addition, any method not shown here may be used as long as it is capable of imaging in three dimensions. If there is information on the structure of the furnace body 4 and the location where the scrap imaging camera 20 is to be installed, information on the height of the scrap 2 in the furnace can be obtained based on the height information of the three-dimensional camera after the scrap has been charged and the height difference of the scrap 2.
[0116] The brightness value array img according to the scrap input state mentioned above resize and the height array of scrap input state (img) height can be obtained, for example, as follows:
[0117]
number
[0118] Here, H is a height value (height index) in the number of horizontal pixels w' and the number of vertical pixels h'. The camera image acquisition unit 32 stores the scrap image data including these pieces of information in the database 33 in the format shown in FIG. 13, as in the first embodiment.
[0119] Based on the scrap image data thus obtained, an arc interruption prediction model is constructed, and the arc interruption is predicted using the prediction model, as in the first embodiment. At this time, the input values (explanatory variables) used in constructing the arc interruption prediction model and in the prediction are configured as follows:
[0120]
number
[0121] As described above, in the arc furnace equipment 1 according to the second embodiment, information including the brightness index and the height index is used as an explanatory variable of the arc interruption prediction model. By adding the height index, the occurrence of arc interruption can be predicted with higher accuracy than in the first embodiment.
[0122] Embodiment 3 Next, a third embodiment will be described with reference to Fig. 14. Descriptions that overlap with the above-mentioned embodiments will be omitted.
[0123] The third embodiment is characterized by having a short circuit prevention output unit 37 in addition to an arc interruption forecast output unit 36 that issues an arc interruption forecast when an arc interruption is predicted to occur. When an arc interruption is predicted to occur, the short circuit prevention output unit 37 automatically controls the elevation of the electrodes, thereby preventing the breaker from tripping due to a short circuit caused by contact between the scrap and the electrodes.
[0124] The input value in the third embodiment may be in the form of either the first embodiment or the second embodiment. predWhen becomes 1, the short circuit prevention output unit 37 outputs a command value to raise the electrode 7. The command value is output to the control device 9, and the electrode 7 is raised to a predetermined avoidance height. Therefore, it is possible to prevent the breaker from being tripped without waiting for an operation by an operator.
[0125] Although short circuit prevention output unit 37 is arranged outside arc interruption prediction device 30 in FIG. 14, it may be included in arc interruption prediction device 30.
[0126] (Hardware configuration example) Fig. 15 is a conceptual diagram showing an example of a hardware configuration of a processing circuit included in the arc interruption prediction device 30 according to each of the above-mentioned embodiments. Each unit in the arc interruption prediction device 30 in Figs. 3 and 14 shows a part of the function, and each function is realized by the processing circuit. In one aspect, the processing circuit includes at least one processor 91 and at least one memory 92. In another aspect, the processing circuit includes at least one dedicated hardware 93.
[0127] When the processing circuit includes a processor 91 and a memory 92, each function is realized by software, firmware, or a combination of software and firmware. At least one of the software and firmware is written as a program. At least one of the software and firmware is stored in the memory 92. The processor 91 realizes each function by reading and executing the program and various data stored in the memory 92. The memory 92 includes a main storage device and an auxiliary storage device. The memory 92 stores various data to be saved in the database 33.
[0128] Where the processing circuitry comprises dedicated hardware 93, the processing circuitry may be, for example, a single circuit, multiple circuits, a programmed processor, or a combination thereof. Each function is implemented by the processing circuitry.
[0129] Although the embodiments of the present disclosure have been described above, the present disclosure is not limited to the above embodiments, and can be modified in various ways without departing from the spirit of the present disclosure. In the above-mentioned embodiments, when the number, quantity, amount, range, etc. of each element is mentioned, the present invention is not limited to the mentioned number, unless otherwise specified or clearly specified in principle. Furthermore, the structures, etc. described in the above-mentioned embodiments are not necessarily essential to the present invention, unless otherwise specified or clearly specified in principle. [Explanation of symbols]
[0130] 1. Arc furnace equipment 2. Scrap 3 Molten metal 4. Furnace body 5 Lid 6 Tapped holes 7 electrodes 8 Electrode lifting device 9. Control Device 10 Output Devices 20 Scrap Shooting Camera 30 Arc interruption prediction device 31 Operational Data Collection Division 32 Camera image acquisition section 33 Database 34 Arc interruption learning unit 35 Arc interruption prediction section 36 Arc interruption forecast output unit 37 Short circuit prevention output section 91 Processor 92 Memory 93 Hardware
Claims
1. 1. An electric arc furnace facility for melting scrap by utilizing heat generated by arc discharge between scrap and electrodes, A camera for photographing the scrap fed into an arc furnace; an information processing device including: a memory in which information including image data acquired from the camera at the time of scrap input, control performance data after the start of melting related to the electrode, and an arc interruption prediction model is stored; and a processor for processing the information stored in the memory; The processor, The arrangement and density of the scrap based on the image data and the control performance data are input to the arc interruption prediction model to perform a prediction process for predicting the occurrence of arc interruption due to a short circuit between the scrap and the electrode. The electric arc furnace equipment is characterized by:
2. The arrangement and density of the scraps are determined based on a brightness index of each pixel of the image data, The control performance data includes operation time-series data and operation attribute data, The operation time series data includes a current value, a voltage value, and a lifting speed value for the electrodes at each sampling time, The operation attribute data includes a time and an amount of the scrap input. The electric arc furnace installation according to claim 1 .
3. The memory stores learning data; The learning data includes the image data, the operation time-series data, the operation attribute data, and an arc interruption occurrence label indicating an arc interruption occurrence associated with a sampling time at which a current value is higher than a short circuit correlation value for each sampling time of the operation time-series data, regarding scrap previously discharged from the arc furnace; The processor is configured to perform a learning process for constructing the arc interruption prediction model based on the learning data; The electric arc furnace installation according to claim 2 .
4. The camera takes a three-dimensional image of the scrap fed into the arc furnace, the image data includes a brightness index and a height index for each pixel; The arrangement and density of the scraps are based on a brightness index and a height index of each pixel of the image data; The arc furnace facility according to any one of claims 1 to 3,
5. the processor is configured to perform a short circuit prevention process of outputting a command to raise the electrode when the prediction process predicts that an arc interruption will occur; The arc furnace facility according to any one of claims 1 to 4,
Citation Information
Patent Citations
Arc furnace closing power control device
JP1993174965A
Vaporization equipment for liquid raw material
JP1999006066A
Electrode lifting device
JP2017216216A
Electric furnace operation control system, electric furnace, and electric furnace operation control method
JP2018070926A
JP28421A