Lifting equipment for building renovation

The lifting device with vertically rolling guide rollers on circumferentially extending rails stabilizes the platform against wind and earthquake-induced shaking, reducing construction time and costs by eliminating scaffolding, and improving work efficiency.

JP7553348B2Active Publication Date: 2024-09-18FUJITA CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2020215658
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2020-12-24
Publication Date
2024-09-18
Estimated Expiration
2040-12-24

AI Technical Summary

Technical Problem

Existing lifting platforms installed in buildings for renovation or demolition can shake sideways due to strong winds or earthquakes, potentially damaging the building or disrupting work, and the installation and removal of scaffolding is time-consuming and costly.

Method used

A lifting device with a lifting platform and elevator unit, featuring guide rollers that roll vertically on rails extending vertically around the building's circumference, and a roller support mechanism to adjust the distance and position of the rollers, ensuring stability and engagement with rails of various sizes.

Benefits of technology

The device prevents horizontal shaking of the lifting platform, maintaining stability during strong winds or earthquakes, reduces construction time by eliminating the need for scaffolding, and enhances work efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007553348000004
    Figure 0007553348000004
  • Figure 0007553348000005
    Figure 0007553348000005
  • Figure 0007553348000010
    Figure 0007553348000010
Patent Text Reader

Abstract

To provide an ascending / descending device for repairing a building which securely prevents rolling of an ascending / descending base with a simple and inexpensive configuration and which is advantageous in improving workability.SOLUTION: In an ascending / descending device 14 for repairing a building, an ascending / descending base 16 is provided with guide rollers 30 which cannot move in a horizontal direction and roll in a vertical direction on each vertically extending rail 12 for preventing a work gondola from swinging at a plurality of places with an interval in a circumference direction of a peripheral face of a building 10. Even when strong wind or an earthquake occurs, rolling of the ascending / descending base 16 is securely prevented with a simple and inexpensive configuration, to keep the ascending / descending base 16 in a stable state and become advantageous in improving workability of work performed by workers on the ascending / descending base 16.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a lifting device for building renovation. [Background technology]

[0002] When renovating or demolishing a building, scaffolding must be set up around the building, the renovation work must be carried out using the scaffolding, and then the scaffolding must be dismantled and removed, which increases costs and lengthens the construction period. Incidentally, when carrying out demolition work on tower-shaped structures such as chimneys, a technology has been proposed in which a lifting platform is provided around the periphery of the structure, this lifting platform is raised and lowered using a lifting section, and workers carry out demolition work on the lifting platform (see Patent Document 1). Therefore, by installing such a lifting platform and lifting section in an existing building and carrying out renovation or demolition work on the building, it is possible to eliminate the need for scaffolding, reduce costs, and shorten the construction period. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2005-68757 A Summary of the Invention [Problem to be solved by the invention]

[0004] However, if such a lifting platform and lifting unit are installed in an existing building, if the lifting platform sways sideways due to strong winds or an earthquake, the lifting platform may interfere with the building and cause damage to the building or may be detrimental to the smooth carrying out of work. On the other hand, for cleaning the glass windows of buildings such as high-rise buildings, a window-cleaning gondola is installed that is suspended by a wire that is paid out from a lifting device installed on the roof of the building and raised and lowered along the perimeter of the building. In such high-rise buildings, rails are provided in advance that extend vertically around the periphery of the building and engage with the gondolas to prevent them from swaying in the wind. The present invention was made with a focus on the anti-sway rails of the glass window cleaning gondola, and the object of the present invention is to provide a lifting device for building renovation that has a simple and inexpensive configuration and reliably prevents lateral vibration of the lifting platform, thereby being advantageous in improving workability. [Means for solving the problem]

[0005] In order to achieve the above-mentioned object, one embodiment of the present invention is a lifting device for building renovation, comprising a lifting platform arranged opposite the peripheral surface of a building, and a lifting section which raises and lowers the lifting platform along the building, and in which rails for preventing a gondola for cleaning glass windows are provided extending in the vertical direction at multiple locations spaced circumferentially on the peripheral surface, and which is characterized in that the lifting platform is provided with guide rollers which cannot move horizontally on the rails but can roll in the vertical direction. In one embodiment of the present invention, the guide roller is configured with a pair of roller bodies arranged to sandwich the rail from the circumferential direction of the peripheral surface. In one embodiment of the present invention, the guide rollers are provided on the rail at at least two locations spaced apart in the circumferential direction of the peripheral surface. Moreover, one embodiment of the present invention is characterized in that the building has a rectangular shape when viewed from above, the lifting platform has a rectangular frame shape when viewed from above that surrounds the entire periphery of the building, and the guide rollers are provided on each of the four sides of the building. In one embodiment of the present invention, a roller body distance adjustment unit is provided to adjust the distance between the pair of roller bodies sandwiching the rail in the direction in which the rail is sandwiched. In one embodiment of the present invention, the guide rollers are provided in plurality at intervals in the vertical direction. In one embodiment of the present invention, a roller height adjustment unit is provided for adjusting the vertical position of the guide roller. Furthermore, one embodiment of the present invention is characterized in that the work performed using the lifting platform is repair work on damaged portions of the exterior wall of the building, painting work on the exterior wall, or demolition work on the building. Effect of the Invention

[0006] According to one embodiment of the present invention, a guide roller that cannot move horizontally but rolls vertically is provided on the lift platform and is attached to anti-sway rails for a glass window cleaning gondola that extends vertically at multiple locations spaced circumferentially around the periphery of a building. Therefore, even in the event of strong winds or earthquakes, by utilizing the anti-sway rails of the glass window cleaning gondola, it is possible to reliably prevent lateral shaking of the platform with a simple and inexpensive configuration and maintain the platform in a stable state, which is advantageous in improving the workability of workers on the platform. In addition, compared to constructing scaffolding around the perimeter of a building to carry out renovation or demolition work, this method does not require the time-consuming task of setting up and removing scaffolding, which is advantageous in shortening construction time and reducing construction costs. Furthermore, if the guide rollers are configured as a pair of rollers arranged to sandwich the rail from the circumferential direction of the outer periphery of the building, lateral vibration of the lifting platform can be more reliably prevented and the lifting platform can be maintained in a stable state, which is more advantageous in improving workability. Furthermore, providing guide rollers on at least two rails spaced circumferentially around the periphery of the building makes it possible to more reliably prevent lateral shaking of the platform and maintain the platform in a stable state, compared to providing guide rollers on a single rail, which is more advantageous in improving workability. In addition, if the building has a rectangular shape when viewed from above, the lifting platform has a rectangular frame shape when viewed from above that surrounds the entire periphery of the building, and guide rollers are provided on each of the four side surfaces of the building, the guide rollers provided on the four side surfaces can more reliably prevent lateral shaking of the lifting platform and maintain the lifting platform in a stable state, which is more advantageous in improving workability. Furthermore, by providing a roller body spacing adjustment section which adjusts the spacing in the direction in which the rail is sandwiched between a pair of roller bodies which sandwich the rail, the guide rollers can reliably engage the rail to accommodate rails of various sizes, thereby more reliably preventing lateral vibration of the lifting platform and maintaining the lifting platform in a stable state, which is more advantageous in improving workability. In addition, by providing multiple guide rollers spaced apart in the vertical direction, the rails can be engaged with the multiple guide rollers spaced apart in the vertical direction, which more reliably prevents the lifting platform from swaying sideways and maintains the lifting platform in a stable state, which is more advantageous in improving workability. In addition, by providing a roller height adjustment unit that adjusts the vertical position of the guide roller, when positioning the lifting platform at the top of the building, the lifting platform can be positioned at a higher position by adjusting the vertical position of the guide roller, which is advantageous in improving workability in high places on the building. In addition, if the work performed using the lift platform is repair work on damaged parts of the exterior walls of a building, or painting work on the exterior walls, or building demolition work, it is advantageous for workers on the lift platform to efficiently carry out building renovation or demolition work. [Brief description of the drawings]

[0007] [Figure 1] 1 is a plan view showing a state in which a lifting device for building renovation according to an embodiment is installed on the periphery of a building. [Diagram 2] 2 is a view taken along line AA in FIG. 1, showing the state in which the lift platform is positioned at a low position. [Diagram 3] 2 is a view taken along the line BB in FIG. 1, showing a state in which the lift platform is positioned at a low position. [Figure 4] 2 is a view taken along line AA in FIG. 1, showing the lift platform in a raised state. [Diagram 5] 2 is a view taken along line BB in FIG. 1, showing the lift platform in a raised state. [Figure 6] 1 is a plan view showing a state in which the rollers of a lifting device for building renovation are engaged with rails installed on a wall surface of a building. [Figure 7] 7 is a view taken along the line CC in FIG. 6. [Figure 8]FIG. 7 is a view taken along line DD in FIG. 6. [Figure 9] 4 is a front view showing the configuration of a roller body interval adjustment unit and a roller height adjustment unit. FIG. [Figure 10] FIG. 10 is a view taken along the arrow B in FIG. [Figure 11] 10 is a view taken along the line CC in FIG. 9 . DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0008] Hereinafter, a lifting device for building renovation according to an embodiment of the present invention will be described with reference to the drawings. First, a building 10 to which the lifting device for building renovation is applied will be described. As shown in Figs. 1 to 3, in this embodiment, a case will be described in which a building 10 is a high-rise building with a rectangular cross section. The cross-sectional shape of the building 10 is not limited, and the lifting device for building renovation of the present invention can be applied to buildings 10 of various cross-sectional shapes that are conventionally known. The building 10 has a peripheral surface, and in this embodiment, the peripheral surface has a pair of long side surfaces 1002 corresponding to a pair of long sides of the rectangle, and a pair of short side surfaces 1004 corresponding to a pair of short sides of the rectangle. Each of the side surfaces 1002, 1004 is formed of a flat surface having a vertical height and a width perpendicular to the height, and each of the side surfaces 1002, 1004 is provided with a glass window (not shown). In addition, the symbol G in the figure indicates the ground.

[0009] A building 10 such as a high-rise building is provided with a gondola for cleaning glass windows, which is suspended by a wire drawn from a lifting device installed on the roof of the building 10 and moves up and down along the periphery of the building 10, and the gondola is usually stored on the roof. In addition, vertically extending rails 12 for preventing work gondolas from swaying are provided in advance on the periphery of the building 10, and rollers on the gondola are engaged with the rails 12 so as to be able to roll but not move horizontally, thereby preventing the gondola from swaying in the wind. In this embodiment, the rails 12 are pre-installed at multiple locations spaced circumferentially around the periphery of the building 10, i.e., at multiple locations spaced apart in the width direction of each side 1002, 1004, with the rails 12 extending vertically. The rails 12 are provided over almost the entire height of the building 10 .

[0010] As shown in FIG. 6, in this embodiment, an H-shaped steel is used for the rail 12, and the rail 12 includes a pair of flanges 1202 and a web 1204 connecting the pair of flanges 1202. The rail 12 is attached to the building 10 by embedding one flange 1202 into the periphery of the building 10, i.e., the long side surface 1002 and the short side surface 1004, and the other flange 1202 is located at a position spaced outward from the periphery of the building 10. Therefore, the portion of the rail 12 that engages with the guide roller 30 (described later) has a T-shape. In addition, the cross-sectional shape of the rail 12 is not limited to a T-shape, and rails 12 of various cross-sectional shapes known in the art can be used, and various guide rollers 30 known in the art that correspond to the cross-sectional shapes of the rail 12 can be used. For example, if the rail is formed by a pair of opposing rail bodies each having a U-shaped cross section, and a groove portion extending in the vertical direction is formed between the pair of rail bodies, a single guide roller may be inserted into the pair of groove portions and the guide roller may be guided by the inner surfaces of the pair of rail bodies. The rail 12 can be attached to the building 10 using a variety of conventionally known attachment structures, such as a mounting bracket.

[0011] As shown in FIGS. 1 to 3, the building renovation lifting device 14 includes a lifting platform 16, a lifting section 18, and a vibration prevention section 20. As shown in FIG. The lift platform 16 is where workers board to carry out repair work on the building 10 or demolition work on the building 10, and is also where equipment and materials to be used in the repair work or demolition work are loaded. The repair work includes conventionally known work such as repairing damaged parts of the exterior walls of the building 10 and painting the exterior walls. The lift platform 16 is disposed facing the peripheral surface of the building 10, and in this embodiment, the lift platform 16 has a rectangular frame shape in plan view that surrounds the entire peripheral surface of the building 10. In this embodiment, the lift platform 16 includes a rectangular frame-shaped bottom wall 1602 and a side wall 1604 standing upright from the outer edge of the bottom wall 1602 . As shown in FIG. 1, the inner edge of bottom wall 1602 forms an opening 1606 that is slightly larger than the cross-sectional shape of building 10, and a gap S of a predetermined dimension is secured between the inner edge of bottom wall 1602 and the outer periphery of building 10.

[0012] As shown in FIGS. 1 to 3, the lifting section 18 lifts and lowers the lift platform 16 along the building 10. As shown in FIG. The lifting section 18 includes a plurality of guide rods 22 and a plurality of lifting jacks 24 . The guide rods 22 are installed at intervals along the outer periphery of the building 10 on the ground G based on a rod base not shown, and each guide rod 22 extends in the vertical direction through a through hole 1608 (see Figures 2 and 3) provided in the bottom wall 1602 of the lifting platform 16. In this embodiment, as shown in FIG. 1, four guide rods 22 are provided at equal intervals along each of a pair of long side surfaces 1002 of the building 10. One end of each guide rod 22 is male threaded and the other end is female threaded, so that the guide rods 22 can be extended in the axial direction by fastening the male thread of one guide rod to the female thread of another guide rod. One end of each guide rod 22 is male threaded and the other end is female threaded, so that the guide rods 22 can be extended in the axial direction by fastening the male thread of one guide rod to the female thread of another guide rod. Alternatively, both ends of each guide rod 22 may be male threaded, and the male threaded portions may be fastened together via a connecting jig having female threads, thereby allowing the guide rods 22 to be extended in the axial direction. Therefore, the total length of the multiple guide rods 22 connected in units of guide rods 22 can be extended, and the total length of the multiple guide rods 22 can be shortened by removing the guide rods 22 connected to each other. The operation of adding or removing the guide rod 22 is performed by a worker standing on the lift platform 16. By increasing or decreasing the length of the guide rod 22 in this manner, the range of movement in the height direction of the lift platform 16 raised and lowered by the lift jack 24 can be changed. As shown in FIG. 3, each guide rod 22 is detachably attached to the outer periphery of the building 10 via stays 26 arranged at equal intervals in the axial direction of the guide rod 22 to prevent buckling.

[0013] The lifting jacks 24 are provided on the underside of the bottom wall 1602 of the lifting platform 16 for each of the through holes 1608 and are coupled to each of the guide rods 22 . The lifting jack 24 includes upper and lower holding means for the guide rod 22 that are arranged at intervals above and below, and a hydraulic cylinder that changes the vertical interval between the upper and lower holding means. By the upper and lower holding means gripping and releasing the guide rods 22 and the hydraulic cylinder extending and retracting, the lift platform 16 is raised and lowered along the guide rods 22 while being supported by the lift jacks 24 . The amount by which the lifting platform 16 rises with one extension of the lifting jack 24, and the amount by which the lifting platform 16 falls with one contraction of the lifting jack 24, is, for example, 10 cm. By repeating this extension and contraction movement of the lifting jack 24, the lifting platform 16 rises and falls like an inchworm. The operation of each lifting jack 24 is controlled by a control device (computer) (not shown) installed at a location away from the lifting unit 18, for example, on the ground or in the building 10. Of course, such a control device may be mounted on the lift section 18.

[0014] As shown in FIG. 1, the anti-sway portion 20 prevents the lift platform 16 from swaying sideways due to strong winds, earthquakes, and the like. A vibration prevention portion 20 is provided for each rail 12. As shown in FIGS. 6 to 8, the vibration prevention unit 20 includes a housing 28, a guide roller 30, and a roller support mechanism 32 (see FIGS. 9 to 11). The housing 28 is erected on the upper surface of the bottom wall 1602 corresponding to each rail 12, and has a vertical height, a width in a direction perpendicular to the vertical direction and parallel to the circumferential surface of the building 10 which is a dimension smaller than the height, and a thickness in the vertical direction and in the direction perpendicular to the circumferential surface of the building 10 which is a dimension smaller than the width, and is elongated in the vertical direction. As shown in Figures 6 to 8, housing 28 comprises a bottom plate 2802 which is attached by being overlapped on the upper surface of bottom wall 1602, a pair of end plates 2804 which rise from both longitudinal ends of bottom plate 2802 and face each other in the width direction of housing 28, a pair of side plates 2806 which rise from both longitudinal ends of bottom plate 2802 and face each other in the thickness direction of housing 28, and an upper plate 2808 which connects the upper ends of the pair of end plates 2804 and the pair of side plates 2806.

[0015] The guide rollers 30 are immovable in the horizontal direction on the rails 12 but roll in the vertical direction, and are provided on the lift table 16 via a roller support mechanism 32 and a housing 28 . In this embodiment, the guide rollers 30 are provided on the rails 12 at at least two locations spaced apart in the circumferential direction of the peripheral surface of the building 10. More specifically, a guide roller 30 is provided on each of the four sides 1002, 1004 of the building 10. The guide roller 30 is composed of a pair of roller bodies 30A arranged to sandwich the rail 12 from the circumferential direction of the peripheral surface of the building 10. As shown in Figures 6 to 8, in this embodiment, the roller body 30A comprises a spindle 3002 having a male thread 3002A (see Figure 10) formed at one end, and a roller body 3004 rotatably supported at the other end of the spindle 3002, and a groove 3006 is formed on the outer circumferential surface of the roller body 3004 to engage with the flange 1202 of the rail 12. In this embodiment, two guide rollers 30 are provided at a distance from each other in the vertical direction. Therefore, a total of four roller bodies 30A are provided for one rail 12. It should be noted that the number of roller bodies 30A provided for one rail 12 is not limited to four, and may of course be two, six or more. The grooves 3006 of the pair of roller bodies 30A engage with both sides of the flanges 1202 of the rail 12, so that each roller body 30A is immovable in the horizontal direction relative to the rail 12 but is capable of rolling in the vertical direction. The roller body 3004 is located on the outside of one of the pair of side panels 2806 of the housing 28 that faces the peripheral surface of the building 10 (side surface 1002 or side surface 1004), and the support shaft 3002 passes through an opening 2810 (see Figure 7) provided in the side panel 2806 and is supported by a roller support mechanism 32 (see Figures 9 to 11) inside the housing 28.

[0016] As shown in FIGS. 9, 10 and 11, the roller support mechanism 32 supports the support shaft 3002 of the roller body 30A, and is provided in the housing . The roller support mechanism 32 includes a roller body interval adjustment unit 34, a roller height adjustment unit 36, and a control unit 38. In addition, Figure 9 shows the roller support mechanism 32 corresponding to the upper pair of roller bodies 30A of the two pairs of roller bodies 30A arranged above and below, but the roller support mechanism 32 corresponding to the lower pair of roller bodies 30A is also configured in the same way.

[0017] The roller body gap adjustment parts 34 adjust the gap between the pair of roller bodies 30A in the direction in which the rail 12 is sandwiched between them, and one is provided corresponding to each of the pair of roller bodies 30A. The roller height adjustment unit 36 ​​adjusts the vertical position of the guide roller 30, and in this embodiment, adjusts the vertical position of multiple guide rollers 30 spaced apart in the vertical direction, with one provided corresponding to each of the pair of roller bodies 30A. The control unit 38 controls the roller body interval adjustment unit 34 and the roller height adjustment unit 36 ​​.

[0018] The roller support mechanism 32 will now be described in detail. As shown in FIGS. 9, 10 and 11, the roller support mechanism 32 includes an attachment base 3202 . The mounting base 3202 has a rectangular plate shape, and its outer surface 3202A located on one side of the thickness direction is superimposed on and attached to the inner surface of the side surface 2804 of the pair of side surfaces 2804 of the housing 28 that is away from the building 10, and its inner surface 3202B located on the other side of the thickness direction faces the circumferential surface of the building 10.

[0019] As shown in FIGS. 9, 10, and 11, the roller height adjustment unit 36 ​​includes a first table 3602, a first stage 3604, a first feed screw 3606, and a first motor 3608. The first table 3602 is attached by overlapping it on the inner surface 3202B of the mounting base 3202, and a first guide groove (not shown) extending in the vertical direction is formed on the inner surface of the first table 3602 opposite the mounting base 3202. The first stage 3604 is provided with a first guide rail (not shown) that is guided by the first guide groove of the first table 3602, and is arranged in a superimposed manner on the inner surface of the first table 3602, so that the first guide rail is guided by the first guide groove and is movable in the vertical direction. The first stage 3604 is formed with a first female screw (not shown) that extends in the vertical direction parallel to the first guide rail. The first lead screw 3606 is threadedly engaged with the first female thread. The first motor 3608 is attached to the inner surface 3202B of the mounting base 3202, and its drive shaft is coupled to the end of the first lead screw 3606 to rotate the first lead screw 3606 in both forward and reverse directions, thereby moving the first stage 3604 up and down.

[0020] As shown in FIGS. 9, 10, and 11, the roller body interval adjustment unit 34 includes a bracket 3402, a second table 3404, a second stage 3406, a second feed screw 3408, and a second motor 3410. As shown in FIG. 11, bracket 3402 includes mounting portion 3402A where first stage 3604 is attached by superimposing it on the inner surface facing the circumferential surface of building 10, and support portion 3402B which protrudes from the lower end of mounting portion 3402A toward the circumferential surface of building 10 and is parallel to the horizontal plane. The second table 3404 is attached by stacking it on the upper surface of the support part 3402B, and on the upper surface opposite the bracket 3402, a second guide groove 3404A is formed extending in the direction in which the pair of roller bodies 30A move toward and away from each other (horizontal direction). The second stage 3406 is provided with a second guide rail 3406A guided by the second guide groove 3404A of the second table 3404, and is arranged superimposed on the upper surface of the second table 3404. The second guide rail 3406A is guided by the second guide groove 3404A3404A, so that the pair of roller bodies 30A can move in the direction of moving closer and farther apart. The second stage 3406 is formed with a second female screw 3406B extending in a direction (horizontal direction) in which the pair of roller bodies 30A move toward and away from each other in parallel with the second guide rail 3406A. The second lead screw 3408 is threadedly engaged with the second female thread 3406B. The second motor 3410 is attached to the upper surface of the support portion 3402B of the bracket 3402, and its drive shaft is coupled to the end of the second feed screw 3408 to rotate the second feed screw 3408 in forward and reverse directions, thereby moving the second stage 3406 in a direction (horizontal direction) in which the pair of roller bodies 30A move closer and farther apart.

[0021] As shown in FIGS. 9, 10 and 11, a shaft support portion 40 for supporting the shaft 3002 of the roller body 30A is provided on the upper surface of the second stage 3406 located on the opposite side to the second table 3404. The shaft support portion 40 includes a main body portion 42 and a cylindrical portion 44 . As shown in FIG. 10, the main body 42 is formed with a support hole 4202 through which the support shaft 3002 of the roller body 30A is inserted. The tubular portion 44 protrudes toward the building 10 from a portion of the main body 42 facing the peripheral surface of the building 10, and has a hole 4402 concentric with the support hole 4202, and a screw hole (not shown) is formed through the tubular portion 44 in the radial direction. As shown in Figures 10 and 11, one end of the spindle 3002 is inserted through the hole 4402 of the tubular portion 44 with the male thread 3002A of the spindle 3002 protruding from the main body portion 42, and the tip of the screw B screwed into the threaded hole of the tubular portion 44 presses against the outer circumferential surface of the spindle 3002. In addition, a nut N is fastened to the male thread 3002A of the spindle 3002 protruding from the main body portion 42, thereby attaching the spindle 3002 to the spindle support portion 40 so that it cannot move axially or rotate.

[0022] As shown in FIG. 9, the control unit 38 controls the direction and amount of rotation of the first motor 3608 and the second motor 3410 based on the operation of a switch 39 that is manually operated. The control unit 38 controls the direction and amount of rotation of the first motor 3608, so that the pair of roller bodies 30A sandwiching the rail 12 therebetween is moved in the vertical direction. Furthermore, the control unit 38 controls the direction and amount of rotation of the second motor 3410, whereby the pair of roller bodies 30A sandwiching the rail 12 are moved in the direction in which the rail 12 is sandwiched. Incidentally, one control unit 38 may be provided for each roller support mechanism 32, or one control unit 38 may control all the roller support mechanisms 32. The roller body interval adjustment unit 34 is not limited to the embodiment and may be any of various conventionally known mechanisms as long as it can adjust the interval between the pair of roller bodies 30A in the direction sandwiching the rail 12. The roller height adjustment unit 36 ​​is not limited to the embodiment and may be any of various conventionally known mechanisms as long as it can adjust the vertical position of the guide roller 30.

[0023] Next, a method of using the building renovation lifting device 14 will be described. As shown in Figures 1, 2 and 3, the lift platform 16 is assembled on the ground G around the periphery of the building 10. Next, the lifting platform 16 is lifted using heavy machinery such as a crane (not shown), and the lifting platform 16 is positioned parallel to the horizontal plane at a location above the ground G and a predetermined distance away, and multiple guide rods 22 are installed on the ground G and each guide rod 22 is connected to a lifting jack 24. At this time, the installed guide rod 22 is inserted from the lifting jack 24 through the through hole 1608 in the bottom wall 1602 of the lifting platform 16 , and the middle portion of the guide rod 22 is inserted through the roller support mechanism 32 . Each guide rod 22 is detachably attached to the outer periphery of the building 10 via stays 26 at multiple locations equally spaced in the axial direction. In addition, the control unit 38 controls the roller body spacing adjustment unit 34 to engage the grooves 3006 of the pair of roller bodies 30A with both sides of the flange 1202 of the rail 12, and the control unit 38 controls the roller height adjustment unit 36 ​​to adjust the vertical spacing between the pair of roller bodies 30A provided above and the pair of roller bodies 30A provided below to an appropriate value. As a result, the lift platform 16 is engaged with the rail 12 via a plurality of guide rollers 30, preventing horizontal movement, thereby suppressing lateral shaking due to strong winds, earthquakes, and the like.

[0024] When the lifting jacks 24 are connected to the guide rods 22 and the lifting platform 16 is supported on the ground G via each lifting jack 24 and each guide rod 22, the heavy machinery is detached from the lifting platform 16 and the lifting platform 16 is made capable of being raised and lowered by the operation of the lifting jacks 24. Then, the lifting jack 24 is used to raise or lower the lifting platform 16 to a height required for work, and then the lifting jack 24 is stopped to determine the height position of the lifting platform 16. At this time, as the lift platform 16 rises or falls, the guide rollers 30 roll on the rails 12, so that the lift platform 16 rises or falls smoothly. Once the height position of the platform 16 has been determined, the workers on the platform 16 carry out repair work over a certain range in the vertical direction of the building 10 that is workable at that height position of the platform 16.

[0025] When the workers have completed work on a certain area of ​​the building 10, the lifting jack 24 is extended to raise the lifting platform 16 so that the next area of ​​work can be completed, and the height of the lifting platform 16 is then determined, and the workers then carry out the repair work.

[0026] Furthermore, if it is necessary to add guide rods 22 to further raise the lift platform 16, additional guide rods 22 are added to each guide rod 22 as shown in Figures 4 and 5, and the added guide rods 22 are removably attached to the outer periphery of the building 10 via stays 26.

[0027] By repeatedly raising the platform 16 and extending the guide rods 22 in this manner, the platform 16 is raised from the bottom to the top of the building 10 while the renovation work on the building 10 is carried out.

[0028] Eventually, the platform 16 reaches a height equivalent to the top of the building 10. At this time, the roller height adjustment unit 36 ​​ensures the spacing between the vertically separated guide rollers 30 while lowering the height position of each guide roller 30, thereby allowing the lift platform 16 to be positioned higher. Therefore, by positioning the platform 16 at a higher position, a working range in the vertical direction of the building 10 can be secured for the worker on the platform 16.

[0029] When the repair work at the height position corresponding to the top of the building 10 is completed, the lifting platform 16 is lowered by the lifting jack 24, while the added guide rods 22 are removed one by one and collected on the lifting platform 16. Additionally, the stays 26 connecting the guide rods 22 to be removed and the building 10 are removed one by one and collected onto the lift platform 16. In this manner, the lift platform 16 is lowered while the guide rod 22 and the stay 26 are withdrawn.

[0030] When the lift platform 16 is lowered to the lowest position, for example, to the ground G, and all of the guide rods 22 and stays 26 are retrieved, the guide rods 22 and stays 26 are removed from the lift platform 16, and the renovation work is completed. In this embodiment, the case has been described where renovation work on building 10 is carried out while moving lift platform 16 toward the top of building 10. However, when demolition work on building 10 is being carried out, lift platform 16 can be raised to a height equivalent to the top of building 10 and then lowered as the work progresses.

[0031] As described above, according to the building renovation lifting device 14 of this embodiment, the lifting platform 16 is provided with guide rollers 30 which are immovable horizontally but roll vertically on each of the rails 12 for preventing the glass window cleaning gondola from swinging upward and downward at multiple locations spaced circumferentially around the periphery of the building 10. Therefore, even in the event of strong winds, earthquakes, etc., the use of the anti-sway rails 12 for the glass window cleaning gondola allows the platform 16 to be reliably prevented from swaying sideways with a simple and inexpensive configuration, thereby maintaining the platform 16 in a stable state, which is advantageous in improving the workability of workers on the platform 16. In addition, compared to constructing scaffolding around the periphery of the building 10 to carry out renovation or demolition work on the building 10, this method does not require the time-consuming task of setting up and removing scaffolding, which is advantageous in shortening the construction period and reducing construction costs.

[0032] Furthermore, in this embodiment, the guide rollers 30 are composed of a pair of rollers 30A arranged to sandwich the rail 12 from the circumferential direction of the peripheral surface of the building 10, so that lateral vibration of the lift platform 16 can be more reliably prevented and the lift platform 16 can be maintained in a stable state, which is more advantageous in improving workability. Furthermore, in this embodiment, the guide rollers 30 are provided on the rails 12 at at least two locations spaced apart circumferentially around the periphery of the building 10. This more reliably prevents lateral vibration of the lift platform 16 and maintains the lift platform 16 in a stable state, compared to the case in which the guide rollers 30 are provided on the rails 12 at one location, which is more advantageous in terms of improving workability.

[0033] In addition, in this embodiment, the building 10 has a rectangular shape when viewed from above, the lifting platform 16 has a rectangular frame shape when viewed from above that surrounds the entire periphery of the building 10, and the guide rollers 30 are provided on each of the four side surfaces 1002, 1004 of the building 10.Therefore, the guide rollers 30 provided on the four side surfaces 1002, 1004 more reliably prevent lateral vibration of the lifting platform 16, thereby maintaining the lifting platform 16 in a stable state, which is more advantageous in improving workability. It is possible to omit the roller body spacing adjustment section 34, but if a roller body spacing adjustment section 34 is provided to adjust the spacing in the direction in which the rail 12 is sandwiched between a pair of roller bodies 30A that sandwich the rail 12 as in the present embodiment, the rail 12 can be reliably engaged with the guide rollers 30 to accommodate rails 12 of various sizes, so that lateral vibration of the lifting platform 16 can be more reliably prevented and the lifting platform 16 can be maintained in a stable state, which is more advantageous in improving workability.

[0034] In addition, instead of providing multiple guide rollers 30 in the vertical direction, a single guide roller 30 may be provided. However, providing multiple guide rollers 30 at intervals in the vertical direction as in this embodiment allows the rail 12 to be engaged with the multiple guide rollers 30 spaced apart vertically, which more reliably prevents lateral vibration of the lift platform 16 and maintains the lift platform 16 in a stable state, which is more advantageous in terms of improving workability. In addition, the roller height adjustment unit 36 ​​may be omitted, but if a roller height adjustment unit 36 ​​is provided that adjusts the vertical position of multiple guide rollers 30 spaced apart in the vertical direction, as in the present embodiment, then when positioning the lifting platform 16 at the top of the building 10, the lifting platform 16 can be positioned at a higher position by adjusting the vertical position of the guide rollers 30, which is advantageous in improving workability at high points of the building 10. In addition, in this embodiment, the work performed using the lifting platform 16 is repair work on damaged parts of the exterior wall of the building 10, or painting work on the exterior wall, or demolition work on the building 10, which is advantageous for workers on the lifting platform 16 to efficiently carry out renovation work or demolition work on the building 10.

[0035] In the present embodiment, the guide roller 30 is configured by a pair of roller bodies 30A that sandwich the rail 12 therebetween. However, it goes without saying that the roller height adjustment section 36 can be provided even if a single guide roller is inserted into a groove formed inside the rail and the guide roller is guided by the inner surface of the groove, and in that case too, the same effect as this embodiment can be achieved.

[0036] In this embodiment, the case has been described in which the lifting device for building renovation 14 is used to carry out renovation work on a building 10. However, it goes without saying that the lifting device for building renovation 14 can be used for various purposes that have been conventionally known, such as using the lifting device for building renovation 14 to diagnose deterioration or damage to the building 10 prior to renovation work, or using the lifting device for building renovation 14 to carry out demolition work on the building 10. [Explanation of symbols]

[0037] 10. Building 1002 Long side surface (periphery) 1004 Short side surface (periphery) 12 Rail 1202 Flange 1204 Web 14 Lifting equipment for building renovation 16 Lift platform 1602 Bottom wall 1604 Side wall 1606 Opening 1608 Through hole 18 Lifting section 20 Anti-vibration part 22 Guide Rod 24 Lifting Jack 26 Stay 28 Case 2802 Bottom plate 2804 A pair of end plates 2806 Pair of side panels 2808 Upper plate 2810 Opening 30 Guide roller 30A roller body 3002 Support shaft 3002A Male thread 3004 Roller body 3006 Groove 32 Roller support mechanism 3202 Mounting Base 3202A Exterior 3202B Inside 34 Roller body interval adjustment section 3402 Bracket 3402A mounting part 3402B Support part 3404 Table 2 3404A 2nd guide groove 3406 2nd Stage 3406A Second Guide Rail 3406B 2nd female thread 3408 Second feed screw 3410 Second Motor 36 Roller height adjustment unit 3602 Table 1 3604 1st Stage 3606 First feed screw 3608 First motor 38 Control Unit 40 Spindle support part 42 Main body 4202 Support hole 44 barrel 4402 Hole

Claims

1. A lift platform disposed opposite to the periphery of the building; a lifting unit that raises and lowers the lift platform along the building, A lifting device for building renovation, comprising: a plurality of rails for preventing the swinging of a glass window cleaning gondola extending in the vertical direction at a plurality of circumferentially spaced locations on the peripheral surface; A guide roller that cannot move horizontally on the rail but can roll vertically is provided on the lift platform, The guide roller is composed of a pair of roller bodies arranged to sandwich the rail from the circumferential direction of the circumferential surface, a roller body interval adjustment unit that adjusts the interval between the pair of roller bodies that sandwich the rail in the direction in which the rail is sandwiched; A lifting device for building renovation characterized by the above.

2. A lift platform disposed opposite to the periphery of the building; a lifting unit that raises and lowers the lift platform along the building, A lifting device for building renovation, comprising: a plurality of rails for preventing the swinging of a glass window cleaning gondola extending in the vertical direction at a plurality of circumferentially spaced locations on the peripheral surface; A guide roller that cannot move horizontally on the rail but can roll vertically is provided on the lift platform, a roller height adjustment unit that adjusts the vertical position of the guide roller with respect to the lift platform is provided. A lifting device for building renovation characterized by the above.

3. The guide rollers are provided on the rail at at least two locations spaced apart in the circumferential direction of the peripheral surface.

3. The lifting device for building renovation according to claim 1 or 2.

4. The building has a rectangular shape in plan view, The lift platform has a rectangular frame shape in a plan view that surrounds the entire periphery of the building, The guide rollers are provided on each of the four sides of the building. A lifting device for building renovation according to any one of claims 1 to 3.

5. The guide rollers are provided in a plurality of positions spaced apart in the vertical direction. A lifting device for building renovation according to any one of claims 1 to 4.

Citation Information

Patent Citations

  • Car gondola for work and work method using the same

    JP2003268968A

  • Method and device for demolishing chimney

    JP2005068757A

  • Temporary passage system and repairing method of high-rise structure

    JP2019002248A

  • Guide rail for moving body and guide rail system

    JP2019190156A