Demolishing and building integrated construction method for old rigid frame bridge and newly-built tied arch bridge
By assembling a new tie-tied arch bridge on the old bridge and using the new bridge to remove the old bridge, the cross-construction of the bridge demolition and the bridge construction has been achieved, solving the problems of long construction cycle, poor safety and high cost, and improving construction efficiency and safety avoids the impact on river navigation.
Patent Information
- Application Number
- CN202411132107.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-19
- Publication Date
- 2024-11-08
AI Technical Summary
In the prior art, the construction sequence of the demolition of old bridges and the construction of new bridges is to demolish and then build, resulting in a long construction period, poor safety, high costs, and affecting the navigation of the river.
The old rigid frame bridge is used to assemble the newly built arch bridge, and then the old rigid frame bridge is used to remove the old rigid frame bridge. Through the cross construction of the bridge demolition and the bridge construction, the old bridge is used as the bearing system for the new bridge arch ring assembly bracket, and The new bridge arch ring is used as the crane bearing system for dismantling old bridges.
It shortens the construction cycle, improves construction safety, reduces construction costs, and avoids the impact on river navigation.
Smart Images

Figure CN118911024A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of bridge construction, and relates to an integrated demolition and construction method for demolishing an old rigid frame bridge and building a new tied arch bridge in situ. Background Art
[0002] A rigid frame bridge is a type of bridge that uses piers to support the main beam. Due to its low construction difficulty, convenient maintenance, and low cost, this type of bridge was mostly used in early cross-river bridges. However, after a certain number of years of use, some old cross-river rigid frame bridges have developed defects that can no longer meet the requirements of safe operation through maintenance. Some old bridges cannot meet the current navigation needs due to their span and clear height under the bridge, and all need to be demolished and rebuilt. The tied arch bridge has the advantages of large span, strong bearing capacity, long service life, and easy maintenance, and is the preferred bridge type for bridge reconstruction.
[0003] At present, the conventional construction sequence for the demolition and reconstruction of old bridges is: demolish the old bridge - clear the site - build a new bridge. This construction sequence of demolition first and then construction is not only long, but also has poor safety and high costs, and has a great impact on river navigation. From the perspective of bridge demolition, the reverse demolition method is currently commonly used for the demolition of cross-river rigid frame bridges. According to the division of the old bridge hanging basket construction segments, the bridge deck crane or floating crane is used to cut and demolish them section by section. However, if the bridge deck crane is used for demolition, the concrete beam strength of the old bridge has not reached the strength when the bridge was built, and the T-structure cantilever of the old bridge is at risk of breaking or overturning. If a large floating crane is used for demolition, there is a problem of high floating crane rental costs. From the perspective of bridge construction, for the tied arch bridge across the river, the conventional construction methods include the bracket method, vertical rotation method, horizontal rotation method, cable crane method, large segment lifting method, etc. Among them, the cable crane method and horizontal rotation method do not affect navigation, but these two methods have problems such as long construction period, complex construction process, and difficult to control the arch ring line shape. Summary of the invention
[0004] The purpose of the present invention is to provide an integrated construction method for dismantling and rebuilding old rigid frame bridges and newly built tie arch bridges in order to shorten the construction period, ensure construction safety, reduce construction costs, and avoid affecting navigation during construction.
[0005] The present invention firstly uses the old rigid frame bridge to assemble the new tied arch bridge, and then uses the new tied arch bridge to dismantle the old rigid frame bridge, which has the following advantages:
[0006] 1. Bridge dismantling and bridge construction are carried out in parallel, and some processes can be carried out simultaneously, which can shorten the construction period of the entire project;
[0007] 2. The old rigid frame bridge is used as the bearing system for the new bridge arch ring assembly bracket, and the arch ribs are assembled using the bracket method, which not only avoids the impact of setting up brackets in the water on navigation, but also reduces the bracket height and saves bracket materials;
[0008] 3. Use the arch ring of the new bridge as the crane bearing system for dismantling the old rigid frame bridge, and use the crane on the arch to dismantle the old rigid frame bridge. This is not only safer, but also reduces the investment in conventional bridge dismantling equipment such as bridge deck cranes and floating cranes, thereby reducing construction costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0009] Figure 1 It is a side view of a rigid frame bridge to be demolished;
[0010] Figure 2 It is the overall construction flow chart of the present invention;
[0011] Figure 3 This is a state diagram of the dismantling of a span of beam slab at the connection between the approach bridge and the side span of the old bridge;
[0012] Figure 4 This is the state diagram of the newly built tied arch bridge pier after construction is completed;
[0013] Figure 5 It is a schematic diagram of the state of erecting a Bailey beam bridge between the approach bridge piers, the newly built tied arch bridge piers and the side span piers;
[0014] Figure 6 It is a schematic diagram of the status of temporary bridge deck system laid on the main span and side span bridge deck of the old bridge;
[0015] Figure 7 It is a cross-sectional view of the temporary bridge deck system;
[0016] Figure 8 This is a state diagram of the arch ring and arch foot section of the tied arch bridge being installed;
[0017] Fig. 9 It is a schematic diagram of the installation status of the connection section between the arch foot and the tie beam on the bottom surface of the tie beam of the temporary bridge deck;
[0018] Fig.10 This is a schematic diagram of the state along the bridge when the tie rods of a tied arch bridge are installed;
[0019] Fig.11 It is a schematic diagram of the transverse state of the tied arch bridge with the tied rods installed;
[0020] Fig.12 It is a schematic diagram of the state of erecting the arch ring assembly bracket and arch ring segments at the mid-span on the temporary bridge deck;
[0021] Fig.13 It is a schematic diagram of the cross-sectional structure of the arch ring assembly bracket;
[0022] Fig.14 This is a schematic diagram of the state of assembling the arch ring from the arch foot to the mid-span;
[0023] Fig.15 This is a schematic diagram of the state of installing the arch bridge hanger after the arch rings are assembled and closed;
[0024] Fig.16 It is a schematic diagram of the state of installing the arch crane on the arch ring;
[0025] Fig.17 This is a schematic diagram of the dismantling of the side span and the joint section of the middle span of the old bridge;
[0026] Fig.18 This is a schematic diagram of the state of dismantling the steel cantilever of the old bridge using an arch crane;
[0027] Fig.19 This is a schematic diagram of the status of two arch cranes cooperating to remove Block No. 0 on the top of the main pier of the old bridge;
[0028] Fig. 20 This is a schematic diagram of the state where two arch cranes are moving the demolished pier top block No. 0 below to the barge;
[0029] Fig.21 Schematic diagram of two cranes working together to dismantle the old bridge pier;
[0030] Fig. 22 This is a schematic diagram of the state where the main span and side span of the old bridge have been dismantled, the crawler crane is hoisting the bridge deck at the arch foot, and the arch crane is hoisting the bridge deck at the middle span;
[0031] Fig.23 It is a schematic diagram of the state in which two arch cranes symmetrically lift the remaining bridge deck of the arch bridge;
[0032] Fig.24 This is a schematic diagram of the status of the new tied-arch bridge when the construction is completed. DETAILED DESCRIPTION
[0033] The method of the present invention is described below in conjunction with a specific embodiment and the accompanying drawings.
[0034] like Figure 1 The figure shows an old river-crossing rigid frame bridge, the river-crossing part of the bridge includes a main span 101 and two side spans 102, and approach bridges 103 are arranged on both sides. The main span 101 and the side span 102 are concrete cast-in-place continuous box beam structures, and the approach bridge 103 is a multi-span simply supported beam structure. Due to the aging of the old bridge structure and the upgrading of the bridge and the river channel, it is necessary to dismantle the old bridge and rebuild a new bridge on the original site. The bridge type of the new bridge adopts a tied arch bridge, the bridge axis is the same as that of the old bridge, the bridge deck width is greater than the bridge deck width of the old rigid bridge, and the span is equivalent to the span of the main span and the side span of the old bridge. If the traditional construction method of dismantling first and then building is used, the construction period is long, and the main and side spans of the old bridge can only be dismantled by a bridge deck crane or a floating crane, which has low safety and high cost. In order to avoid affecting the waterway during the construction of the new bridge, the arch ring needs to be constructed by horizontal rotation or cable crane, which is difficult and expensive. Therefore, the integrated construction method of dismantling and building of the present invention is adopted.
[0035] Figure 2This is the overall construction flow chart of the present invention, which adopts the construction sequence of beams first, arches second, and then hangers. First, the piers of the newly built tied arch bridge are constructed, and then the main and side span decks of the old rigid frame bridge are used as platforms to build a temporary bridge deck system. The arch bridge tie rods are installed on the temporary bridge deck, and the arch ring and hangers are installed on the old bridge using the bracket method. After the construction of the newly built tied arch bridge is completed, two arch cranes are installed on the arch ring. According to the division of the original hanging basket construction sections of the rigid frame bridge, the arch cranes are used to symmetrically dismantle the old bridge sections in reverse section by section, and then the two arch cranes are used to cooperate to dismantle the No. 0 block, pier body, underwater pedestal and pile foundation of the rigid frame bridge in turn. Finally, the arch crane is used to lift and install the bridge deck of the newly built tied arch bridge, completing the dismantling of the old rigid frame bridge and the construction of the new tied arch bridge. The specific construction method is as follows:
[0036] (1) Figure 3 As shown, two crawler cranes 1 travel to the approach bridges 103 on both sides of the river respectively, and use the crawler cranes 1 to dismantle a span of beam slab 1031 connecting the approach bridge and the side span of the old bridge; the dismantled beam slab is transported away by a beam transport vehicle.
[0037] (2) Figure 4 As shown, the pier 2 of the newly built tied arch bridge is constructed between the approach bridge pier 1032 and the side span pier 1022 whose beam and slab are removed;
[0038] (3) Figure 5 As shown, a double-deck Bailey beam bridge 104 is erected between the pier 1031 of the approach bridge of the old bridge, the pier 2 of the newly built tied arch bridge and the pier 1022 of the side span of the old bridge by using a crawler crane 1;
[0039] (4) Figure 6 , Figure 7 As shown, the crawler crane 1 travels to the main span and the side span of the old bridge through the Bailey beam bridge 104, and lays a temporary bridge deck system on the main span 101 and the side span 102 of the old bridge. The temporary bridge deck system includes a crossbeam 3, a distribution beam 4 and a temporary bridge deck 5. The crossbeam 3 is supported on the bridge deck of the old bridge in the transverse direction of the bridge, and its two ends extend to a certain length outside the bridge deck of the old bridge respectively. The distribution beam 4 is laid on the crossbeam 3 along the bridge direction, and the temporary bridge deck 5 is laid on the distribution beam 4. The laying width of the distribution beam and the temporary bridge deck is smaller than the beam deck width of the old bridge.
[0040] The cross beam 3 also serves as the cross beam of the deck system of the newly built tied arch bridge, and its length and spacing are set according to the designed length and spacing of the cross beam of the deck system of the newly built tied arch bridge;
[0041] After the construction of the temporary bridge deck system is completed, crawler crane 1 returns to the approach bridge to dismantle the double-deck Bailey beam bridge between the side span pier and the newly built tied arch bridge pier, freeing up space for the construction of the arch ring and arch foot section of the tied arch bridge;
[0042] like Figure 7As shown in , during the specific construction of the present invention, when laying the temporary bridge deck system, in order to prevent the cross beam 3 from being displaced when the carrying vehicle is running, at least two high-quality rolled threaded steel bars 6 can be symmetrically anchored between the cross beam 3 and the box beams of the main span 101 and the side span 102 of the old bridge to position the cross beam 3. The upper end of the high-quality rolled threaded steel bar 6 passes through the cross beam and is anchored to the top surface of the cross beam, and the lower end passes through the top plate of the box beam of the old bridge and is anchored to the bottom surface of the top plate of the old bridge.
[0043] The deck of a rigid frame bridge is often provided with a certain transverse slope, and the height of the middle and sides of the deck are inconsistent. Therefore, after the cross beam is placed on the old bridge deck, there will be a certain gap between the two sides of the old bridge deck and the bottom of the cross beam. In order to prevent the cross beam from being deformed under pressure during construction, when there is a gap between the cross beam 3 and the two sides of the old bridge deck, a pad 7 can be set in the gap to level the cross beam.
[0044] (5) Figure 8 , Fig. 9 As shown, a crawler crane 1 is used to install an arch foot section 8 of an arch ring of a tied arch bridge on the piers 2 of two newly built tied arch bridges, and a connecting section of the arch foot and a tie beam 9 of the tied arch bridge is welded to the bottom surfaces of both ends of the adjacent cross beam 3. After the construction of the arch foot section is completed, a double-layer Bailey beam bridge is erected again between the side span pier and the newly built tied arch bridge pier for vehicle traffic.
[0045] (6) Fig.10 , Fig.11 As shown, the beam transporter transports the tie beam 9 of the tied arch bridge to the temporary bridge deck in sections, and uses a crawler crane to sequentially install the tie beam sections from the arch foot to the middle of the span, and each tie beam section is welded to the bottom surface of the cross beam 3 until the tie beam 9 is connected;
[0046] (7) Fig.12 As shown, after the tie beams are closed, the beam transporter transports the arch ring assembly bracket segments and the arch ring segments to the temporary bridge deck in sequence, and first installs the arch ring assembly bracket 10 at the mid-span using the boom crawler crane 1, and then installs the arch ring 11 at the mid-span on the bracket;
[0047] like Fig.13 As shown, since the width of the new bridge is greater than that of the old bridge, the spacing between the arch rings 11 on both sides of the new bridge is also greater than the width of the old bridge. Therefore, the cross-section of the arch ring assembly bracket 10 adopts an inverted isosceles trapezoid, and the bottom of the arch ring assembly bracket is supported on the surface of the old bridge. The width of the top of the arch ring assembly bracket is set according to the spacing between the arch rings 11 on both sides of the arch bridge.
[0048] (8) Fig.14 As shown, after the arch ring segment 11 at the mid-span is installed, two large-arm crawler cranes 1 are used to construct an assembly bracket 10 from the mid-span to the arch foot. After the bracket construction is completed, the arch ring segments 11 are sequentially constructed on the assembly bracket 10 from the arch foot to the mid-span until the arch ring is closed;
[0049] (9) Fig.15As shown, after the arch ring 11 is closed, concrete is poured into the arch ring steel pipe, the arch ring assembly bracket is removed, and the boom 12 of the newly built tied arch bridge is installed using the large arm crawler crane 1;
[0050] (10) Fig.16 As shown, after the installation of the suspension rod 12 is completed, the temporary bridge deck and distribution beam of the temporary bridge deck system are removed, and the anchorage between the cross beam and the box beam of the old bridge is removed at the same time; the first arch hoist 13 is installed at the arch foot of the left bank of the arch ring 11 by using a crawler crane, and the second arch hoist 14 is installed at the arch foot of the right bank. The arch hoist is an arch hoisting device that can walk on the arch ring, can walk along the top surface of the arch ring, and has a self-locking function. It is generally used in the arch-first-beam-later construction method of the arch bridge. After the arch ring is installed, the bridge deck system of the arch bridge is hoisted on the arch ring.
[0051] (11) Fig.17 As shown, two crawler cranes 1 are used to lift the closure sections 1021 of both side spans of the old bridge, and the closure sections of the side spans are transported to the storage yard by a beam transporter; at the same time, the second arch crane 14 moves to the middle span of the arch ring to lift the closure section 1011 of the middle span of the old bridge, and the second arch crane 14 is used to vertically lower the closure section 1011 to the barge for transportation.
[0052] (12) Fig.18 As shown, after the main side span joint section is removed, the side span 102 and the main span 101 form a cantilever beam. The cantilever beam sections of the left span 102 and the left main span 101 of the old bridge are symmetrically removed by two arch cranes 13 and 14, and the removed beam sections are lowered to the barge for transportation.
[0053] (13) Fig.19 , 20 As shown, the first arch crane 13 moves to the top of the left main pier 1012 connecting the left span and the main span of the old bridge, and the second arch crane 14 moves to the middle of the span; the block No. 0 1013 on the top of the left main pier 1012 is cut in layers, and the two arch cranes cooperate to lower the cut block No. 0 onto the barge for transportation.
[0054] The two arch cranes can cooperate in the following method to lower the cut block No. 0 onto the barge: the two arch cranes 13 and 14 are simultaneously connected to the cut block segment 1013 by a lifting rope, and first the first arch crane 13 lifts the block 1013 vertically, at which time the lifting rope of the second arch crane 14 is not under stress; after the first crane lifts the block 1013 vertically to a certain height, the second arch crane 14 tightens the lifting rope, and at the same time the first arch crane 13 gradually loosens the lifting rope, so that the block 1013 gradually moves toward the mid-span in the air, and when the lifting rope moved to the second arch crane 14 is vertically lifted, the lifting ropes of the two cranes are loosened at the same time, and the block 1013 is lowered to the barge below.
[0055] While removing block No. 0 on the top of pier, two crawler cranes 1 were used to remove the Bailey beam bridge on the piers of the tied arch bridge and the side span piers, which were transported away by the beam transporter. Then the cap beams on the piers 1022 on both side spans were removed and lowered by crawler cranes to the barge for transportation away.
[0056] (14) Fig.21 As shown, the two arch cranes 13 and 14 dismantle the pier body, the abutment and the pile foundation of the left main pier 1012 in turn according to the method of dismantling block No. 0, and lower them onto the barge for transportation; when dismantling the pile foundation, a rope saw can be used to cut it underwater along the riverbed line.
[0057] At the same time, crawler crane 1 is used to dismantle the piers 1022 on both sides of the old bridge, and the side span caps and pile foundations can be retained to stabilize the river slope.
[0058] (15) The two arch cranes dismantle the right span and main span cantilever, the pier body, the abutment and the pile foundation of the right main pier in turn according to the method of the above steps (12) to (14), thus completing the dismantling of the old bridge.
[0059] (16) Fig. 22 , 23 As shown, an arch crane 13 or 14 is used to vertically lift and install the bridge deck 15 at the mid-span of the newly built tied arch bridge from a barge, and two crawler cranes 1 are used to lay the bridge deck 15 at the arch foot; then the two arch cranes 13 and 14 are used to symmetrically install the remaining bridge decks 15 of the newly built tied arch bridge from the mid-span to the arch foot, thereby completing the paving of the bridge deck of the newly built tied arch bridge.
[0060] (17) Fig.24 As shown, finally, the crawler crane 1 is used to dismantle the arch hoists 13 and 14, completing the integrated construction of dismantling the old rigid frame bridge and building a new tied arch bridge.
Claims
1. A method for integrated construction of demolition and reconstruction of an old rigid frame bridge and a new tied arch bridge, wherein the old rigid frame bridge comprises a main span, two side spans and approach bridges on both sides, the main span and the side spans are concrete continuous box beam structures, the approach bridges are multi-span simply supported beam structures, the deck width of the new tied arch bridge is greater than the deck width of the old bridge, the bridge axis of the new tied arch bridge is the same as that of the old bridge, and the span of the new tied arch bridge is equivalent to the span of the main span and the side span of the old bridge, It is characterized in that The following steps are involved: (1) Two crawler cranes were driven to the approach bridges on both sides of the river, and the crawler cranes were used to dismantle the beam slab connecting the approach bridge and the side span of the old bridge; (2) Construction of the piers of the new tied arch bridge between the approach bridge piers and side span piers after the beam and slab have been removed; (3) Using crawler cranes, a double-deck Bailey beam bridge was erected between the piers of the approach bridge of the old bridge, the piers of the newly built tied arch bridge, and the piers of the side span of the old bridge; (4) The crawler crane travels to the main span and side span of the old bridge through the Bailey beam bridge, and lays a temporary bridge deck system on the main span and side span of the old bridge. The temporary bridge deck system includes a crossbeam, a distribution beam and a temporary bridge deck. The crossbeam is supported on the old bridge in the transverse direction of the bridge, and its two ends extend to a certain length outside the old bridge respectively. The distribution beam is laid on the crossbeam along the bridge direction, and the temporary bridge deck is laid on the distribution beam. The laying width of the distribution beam and the temporary bridge deck is less than the beam deck width of the old bridge. The cross beam also serves as the cross beam of the deck system of the newly built tied arch bridge, and its length and spacing are set according to the designed length and spacing of the cross beam of the deck system of the newly built tied arch bridge; After the construction of the temporary bridge deck system was completed, the crawler crane returned to the approach bridge and dismantled the double-deck Bailey beam bridge between the side span pier and the newly built tied arch bridge pier, freeing up space for the construction of the arch ring and arch foot section of the tied arch bridge; (5) Use crawler cranes to install the arch ring arch foot section of the tied arch bridge on the piers of the two newly built tied arch bridges, and weld the connecting section between the arch foot and the tie beam of the tied arch bridge to the bottom surfaces of both ends of the adjacent cross beams. After the construction of the arch foot section is completed, a double-deck Bailey beam bridge is erected again between the side span pier and the newly built tied arch bridge pier; (6) The beam transport vehicle transports the tie beam segments of the tied arch bridge to the temporary bridge deck, and uses a crawler crane to sequentially install the tie beam segments from the arch foot to the mid-span, and welds each tie beam segment to the bottom surface of the cross beam until the tie beams are connected; (7) After the tie beams are closed, the beam transporter transports the arch ring assembly bracket segments and arch ring segments to the temporary bridge deck in sequence, and uses the large arm crawler crane to first install the arch ring assembly bracket at the mid-span, and then installs the arch ring segments at the mid-span on the bracket; (8) After the arch ring segments at the mid-span are installed, two large-arm crawler cranes are used to construct the assembly bracket from the mid-span to the arch foot. After the bracket is constructed, the arch ring segments are constructed on the assembly bracket from the arch foot to the mid-span in sequence until the arch ring is closed; (9) After the arch ring is closed, concrete is poured into the arch ring steel pipe, the arch ring assembly bracket is removed, and the boom of the new tied arch bridge is installed using a large boom crawler crane; (10) After the installation of the suspender rod is completed, the temporary bridge deck and distribution beam of the temporary bridge deck system are removed; the first arch hoist is installed at the arch foot on the left bank of the arch ring using a crawler crane, and the second arch hoist is installed at the arch foot on the right bank; (11) Two crawler cranes are used to remove the side span closure section of the old bridge, which is then transported to the storage yard by a beam transporter. At the same time, the second arch crane moves to the middle span of the arch ring to remove the middle span closure section of the old bridge, and the second arch crane is used to vertically lower the middle span closure section onto a barge for transportation. (12) Use two overhead cranes to symmetrically dismantle the cantilever beam sections of the left span and the left main span of the old bridge, and lower the dismantled beam sections onto the barge for transportation; (13) The first arch crane moves to the top of the left main pier connecting the left span and the main span of the old bridge, and the second arch crane moves to the middle of the span; the No. 0 block on the top of the left main pier is cut in layers, and the two arch cranes cooperate to lower the cut No. 0 block to the barge for transportation; at the same time, two crawler cranes remove the Bailey beam bridge on the piers of the tied arch bridge and the side span piers, and transport them away by the beam transporter; then the cap beams on the piers of the two side spans are removed, and lowered by crawler cranes to the barge for transportation; (14) Two arch cranes cooperated to dismantle the pier body, cap and pile foundation of the left main pier in turn, and lowered them onto the barge for transportation. At the same time, crawler cranes were used to dismantle the pier bodies of the span piers on both sides of the old bridge; (15) Two arch cranes dismantle the right span and main span cantilever, the pier body, the cap and the pile foundation of the right main pier in sequence according to the method of the above steps (12) to (14), thus completing the dismantling of the old bridge; (16) Use an arch crane to vertically lift and install the bridge deck at the mid-span of the new tied arch bridge from a barge, and use two crawler cranes to lay the bridge deck at the arch foot. Then use two arch cranes to install the remaining bridge decks of the new tied arch bridge from the mid-span to the arch foot, and complete the deck paving of the new tied arch bridge; (17) Finally, the crawler crane was used to dismantle the arch crane, completing the integrated demolition and reconstruction of the old rigid frame bridge and the newly built tied arch bridge.
2. The integrated construction method for dismantling and reconstructing an old rigid frame bridge and a newly built tied arch bridge according to claim 1, Features: When laying the temporary bridge deck system in step (4), at least two high-quality rolled threaded steel bars are symmetrically anchored between the crossbeam and the old bridge box girder to position the crossbeam. The upper end of the high-quality rolled threaded steel bar passes through the crossbeam and is anchored to the top surface of the crossbeam, and the lower end passes through the top plate of the old bridge box girder and is anchored to the bottom surface of the top plate of the old bridge box girder.
3. The integrated construction method for dismantling and reconstructing an old rigid frame bridge and a newly built tied arch bridge according to claim 2, Features: If there is a gap between the crossbeam and the two sides of the old bridge deck, place pads in the gap to prevent the crossbeam from being deformed under pressure.
4. The integrated construction method for dismantling and reconstructing an old rigid frame bridge and a newly built tied arch bridge according to claim 1, Features: The cross section of the arch ring assembly bracket is an inverted isosceles trapezoid, the bottom of the arch ring assembly bracket is supported on the old bridge surface, and the width of the top of the arch ring assembly bracket is set according to the spacing of the arch rings on both sides of the arch bridge.
5. The integrated construction method for dismantling and reconstructing an old rigid frame bridge and a newly built tied arch bridge according to claim 1, Features: When removing the No. 0 block section of the pier top in step (13), the method of cooperating the two arch cranes to lower the cut No. 0 block onto the barge is as follows: The two arch cranes simultaneously connect the cut No. 0 block segment through the lifting ropes. First, the first arch crane lifts the No. 0 block segment vertically to a certain height, and the lifting rope of the second arch crane is not under stress; then the second arch crane tightens the lifting rope, and the first arch crane gradually loosens the lifting rope, so that the No. 0 block gradually moves toward the mid-span in the air. When the lifting rope moved to the second arch crane is vertically lifted, the lifting ropes of the two cranes are loosened at the same time, and the No. 0 block is lowered to the barge below.
Citation Information
Cited By
Demolition method of reinforced concrete arch bridge lower structure