Excavation information processing device, work machine, excavation support device, and excavation information processing method
The excavation information processing device addresses the challenge of adjusting excavated soil volume by using position and attitude control, enabling precise and efficient soil volume management.
Patent Information
- Application Number
- JP2020134559
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2020-08-07
- Publication Date
- 2024-10-03
- Estimated Expiration
- 2040-08-07
AI Technical Summary
Existing excavation devices struggle to adjust the amount of excavated soil to an arbitrary value accurately.
An excavation information processing device that includes an acquisition unit for object and bucket position information, an excavated soil amount estimating section, and a control system to adjust the bucket's position and attitude, allowing precise control of the excavated soil volume.
Enables easy adjustment of the excavated soil amount to a desired value, enhancing operational efficiency and accuracy in excavation operations.
Smart Images

Figure 0007560973000001 
Figure 0007560973000002 
Figure 0007560973000003
Abstract
Description
[Technical field]
[0001] The present invention relates to an excavation information processing device, a work machine, an excavation support device, and an excavation information processing method. [Background technology]
[0002] In the excavation device described in Patent Document 1, the bucket, the ground, and the excavated material are recognized from images captured by a stereo camera, and the excavation point is determined based on the recognition result. The excavation point is the position where the bucket first comes into contact with the excavated material during excavation operation, and in this excavation device, it is determined so that the excavation amount (excavated soil amount) is large, the ground is not scraped, and the excavated material does not collapse. Then, in this excavation device, excavation is performed by scooping up the bucket from this excavation point. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] International Publication No. 2015 / 162710 Summary of the Invention [Problem to be solved by the invention]
[0004] In the excavation device described in Patent Document 1, the excavation material is excavated by scooping up the bucket from an excavation point determined so that the amount of excavated soil is large. The excavation device described in Patent Document 1 has a problem that it is difficult to adjust the amount of excavated soil to an arbitrary value, for example.
[0005] The present invention has been made in consideration of the above-mentioned circumstances, and aims to provide an excavation information processing device, a work machine, an excavation support device, and an excavation information processing method that can easily adjust the amount of excavated soil to any value. [Means for solving the problem]
[0006] One aspect of the present invention is an excavation information processing device that includes an acquisition unit that acquires object position information indicating multiple points of position information for an excavation object, bucket position and attitude information indicating the position and attitude of the bucket, and an excavation volume estimation unit that sequentially estimates and outputs the amount of excavated soil that would be obtained by the bucket if the bucket were to be loaded at that time based on the object position information. Effect of the Invention
[0007] According to the excavation information processing device, work machine, excavation support device, and excavation information processing method of the present invention, the amount of excavated soil can be easily adjusted to any value. [Brief description of the drawings]
[0008] [Figure 1] 1 is a perspective view showing a configuration example of a hydraulic excavator according to an embodiment of the present invention. FIG. [Diagram 2] 2 is a block diagram showing an example of the configuration of a work machine position and attitude measuring unit 30, a work machine control device 110, and an excavation information processing device 120 shown in FIG. [Diagram 3] FIG. 2 is a side view showing in a simplified form the hydraulic excavator 1 shown in FIG. [Figure 4] 3 is a system flow diagram showing an example of the operation of the work machine control device 110 and the excavation information processing device 120 shown in FIG. 2. [Diagram 5] 3 is a flowchart showing an example of the operation of an excavation volume estimating unit 122 shown in FIG. 2. [Figure 6] 4 is a schematic diagram showing an example of point cloud data 400 measured by the three-dimensional position information measuring unit 19 shown in FIG. [Figure 7] FIG. 2 is a side view diagrammatically showing the bucket 8 shown in FIG. [Figure 8] 4 is a side view showing a schematic example of point cloud data 400 measured by the three-dimensional position information measuring unit 19 shown in FIG. [Figure 9] FIG. 4 is a schematic diagram showing an example of point cloud data 400 in this embodiment. [Figure 10]4 is a side view showing a schematic example of point cloud data 400 measured by the three-dimensional position information measuring unit 19 shown in FIG. [Figure 11] 4 is a side view showing a schematic example of point cloud data 400 measured by the three-dimensional position information measuring unit 19 shown in FIG. [Figure 12] 10 is a schematic diagram showing an example of a time transition of an excavated soil amount in this embodiment. FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0009] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. In each drawing, the same or corresponding components are designated by the same reference numerals and the description thereof will be omitted as appropriate.
[0010] Fig. 1 is a perspective view showing a configuration example of a hydraulic excavator 1 as a work machine according to an embodiment of the present invention. Fig. 2 is a block diagram showing configuration examples of a work machine position and attitude measuring unit 30, a work machine control device 110, and an excavation information processing device 120 shown in Fig. 1. Fig. 3 is a side view showing a simplified view of the hydraulic excavator 1 shown in Fig. 1.
[0011] The hydraulic excavator 1 shown in FIG. 1 has a vehicle body 1B as a main body and a working machine 2. The vehicle body 1B has an upper rotating body 3 as a rotating body and a traveling device 5 as a traveling body. The upper rotating body 3 accommodates devices such as an engine and a hydraulic pump as a power generating device inside an engine room 3EG. In this embodiment, the hydraulic excavator 1 can use an internal combustion engine such as a diesel engine as the engine as the power generating device. However, the power generating device is not limited to an internal combustion engine. The power generating device of the hydraulic excavator 1 may be, for example, a so-called hybrid type device that combines an internal combustion engine, a generator motor, and a power storage device. Furthermore, the power generating device of the hydraulic excavator 1 may be a device that does not have an internal combustion engine and combines a power storage device and a generator motor, etc.
[0012] The upper rotating body 3 has a cab 4. An operator of the hydraulic excavator 1 gets in the cab 4 and operates the hydraulic excavator 1. That is, the operator of the hydraulic excavator 1 operates the working equipment 2, rotates the upper rotating body 3, and travels the hydraulic excavator 1 using the traveling device 5 from within the cab 4. The cab 4 is provided with a display device 40 for displaying various information, a control device for the working equipment 2 operated by the operator, a control device for the traveling device 5, and the like (not shown). In the example shown in FIG. 1, the cab 4 is provided on the side opposite to the side where the engine room 3EG of the upper rotating body 3 is provided. However, the positional relationship between the cab 4 and the engine room 3EG is not limited to this example. A handrail 9 is provided above the upper rotating body 3.
[0013] The traveling device 5 mounts the upper rotating body 3 so as to be rotatable relative to the traveling device 5 about a rotation axis RZ. The traveling device 5 has tracks 5a and 5b. The traveling device 5 is driven by one or both of hydraulic motors 5c provided on the left and right sides. The tracks 5a and 5b of the traveling device 5 rotate to cause the hydraulic excavator 1 to travel. The work machine 2 is attached to the lateral side of the operator's cab 4 of the upper rotating body 3. The traveling device 5 is equipped with a sensor that measures the rotation angle of the upper rotating body 3.
[0014] The hydraulic excavator 1 may be provided with tires instead of the tracks 5a and 5b, and may be provided with a traveling device capable of traveling by transmitting the driving force of the engine to the tires via a transmission. An example of a hydraulic excavator 1 having such a configuration is a wheeled hydraulic excavator.
[0015] The side of the upper rotating body 3 where the working machine 2 and the cab 4 are arranged is the front, and the side where the engine room 3EG is arranged is the rear. The front-rear direction of the upper rotating body 3 is the y direction. The left side facing the front is the left of the upper rotating body 3, and the right side facing the front is the right of the upper rotating body 3. The left-right direction of the upper rotating body 3 is also called the width direction or x direction. In the hydraulic excavator 1 or the vehicle body 1B, the traveling gear 5 side is the bottom with respect to the upper rotating body 3, and the upper rotating body 3 side is the top with respect to the traveling gear 5. The up-down direction of the upper rotating body 3 is the z direction. When the hydraulic excavator 1 is installed on a horizontal plane, the bottom is the vertical direction, that is, the side in the direction of gravity, and the top is the opposite side to the vertical direction. This xyz coordinate system is a coordinate system based on the hydraulic excavator 1 (upper rotating body 3), and is called a local coordinate system in this embodiment. Note that the x, y, and z arrows shown in FIG. 1 and other figures indicate the respective directions in the local coordinate system, but do not specify the position of the origin.
[0016] The working machine 2 has a boom 6, an arm 7, a bucket 8 as a working tool, a boom cylinder 10, an arm cylinder 11, and a bucket cylinder 12. The base end of the boom 6 is rotatably attached to the front of the upper rotating body 3 via a boom pin 13. The base end of the arm 7 is rotatably attached to the tip of the boom 6 via an arm pin 14. The bucket 8 is attached to the tip of the arm 7 via a bucket pin 15. The bucket 8 rotates around the bucket pin 15. The bucket 8 has a plurality of blades 8B attached to the side opposite the bucket pin 15. The blade tip 8T is the tip of the blade 8B. In this embodiment, the scraping surface by the bucket upper edge 8E is called the bucket surface 8S. The bucket 8 does not have to have a plurality of blades 8B. In other words, the bucket may not have the blade 8B as shown in FIG. 1, and the blade tip may be formed in a straight shape by a steel plate.
[0017] The boom cylinder 10, arm cylinder 11, and bucket cylinder 12 shown in Fig. 1 are hydraulic cylinders driven by the pressure of hydraulic oil discharged from a hydraulic pump. The boom cylinder 10 drives the boom 6 to raise and lower it. The arm cylinder 11 drives the arm 7 to rotate it around the arm pin 14. The bucket cylinder 12 drives the bucket 8 to rotate it around the bucket pin 15.
[0018] The work machine 2 also includes a work machine position and orientation measuring unit 30. As shown in FIG. 2, the work machine position and orientation measuring unit 30 includes a first stroke sensor 31, a second stroke sensor 32, a third stroke sensor 33, and a work machine position and orientation information generating unit 34. The first stroke sensor 31 is provided on the boom cylinder 10, the second stroke sensor 32 on the arm cylinder 11, and the third stroke sensor 33 on the bucket cylinder 12. The first stroke sensor 31 detects a boom cylinder length, which is the length of the boom cylinder 10, and outputs it to the work machine position and orientation information generating unit 34. The second stroke sensor 32 detects an arm cylinder length, which is the length of the arm cylinder 11, and outputs it to the work machine position and orientation information generating unit 34. The third stroke sensor detects a bucket cylinder length, which is the length of the bucket cylinder 12, and outputs it to the work machine position and orientation information generating unit 34.
[0019] Once the boom cylinder length, arm cylinder length, and bucket cylinder length are determined, the posture of the work machine 2 is determined. Note that the first stroke sensor 31, the second stroke sensor 32, and the third stroke sensor 33 may be angle detectors or the like.
[0020] The work machine position and attitude information generating unit 34 calculates the inclination angle of the boom 6 in the direction (z-axis direction) perpendicular to the horizontal plane in the local coordinate system from the boom cylinder length detected by the first stroke sensor 31. The work machine position and attitude information generating unit 34 also calculates the inclination angle of the arm 7 relative to the boom 6 from the arm cylinder length detected by the second stroke sensor 32. The work machine position and attitude information generating unit 34 also calculates the inclination angle of the bucket 8 relative to the arm 7 from the bucket cylinder length detected by the third stroke sensor 33. The work machine position and attitude information generating unit 34 also generates and outputs work machine position and attitude information, which is information indicating the attitude and position of the work machine 2 in the local coordinate system, based on the three-dimensional shape information (dimension information) of the work machine 2 and the respective inclination angles of the boom 6, the arm 7, and the bucket 8. The work machine position and attitude information includes information indicating the position and angle (attitude) of the bucket 8.
[0021] Antennas 21 and 22 are attached to the upper part of the upper rotating body 3. The antennas 21 and 22 are used to detect the current position of the hydraulic excavator 1. The antennas 21 and 22 are connected to, for example, a work machine control device 110 (or its peripheral circuitry). The work machine control device 110 (or its peripheral circuitry) receives radio waves by RTK-GNSS (Real Time Kinematic-Global Navigation Satellite Systems, GNSS stands for Global Navigation Satellite Systems) using the antennas 21 and 22, and detects the current position of the hydraulic excavator 1. Signals corresponding to the GNSS radio waves received by the antennas 21 and 22 are input to the work machine control device 110, which calculates the installation positions of the antennas 21 and 22 in a global coordinate system. An example of a global navigation satellite system is the Global Positioning System (GPS), but the global navigation satellite system is not limited to this.
[0022] As shown in Fig. 1, the antennas 21 and 22 are preferably installed on the upper rotating body 3 at both ends separated in the left-right direction, i.e., in the width direction, of the hydraulic excavator 1. In this embodiment, the antennas 21 and 22 are attached to handrails 9 attached to both sides in the width direction of the upper rotating body 3. The positions at which the antennas 21 and 22 are attached to the upper rotating body 3 are not limited to the handrails 9, but it is preferable to install the antennas 21 and 22 as far apart as possible, as this improves the accuracy of detecting the current position of the hydraulic excavator 1. In addition, the antennas 21 and 22 are preferably installed in positions that do not obstruct the operator's view as much as possible.
[0023] The hydraulic excavator 1 also includes a three-dimensional position information measuring unit 19. The three-dimensional position information measuring unit 19 is installed, for example, above the cab 4, and measures the three-dimensional position of an object (target) present within a measurement range SA including the bucket 8 and an excavation target 300 such as soil, sand, and earth and stones, at multiple points (multiple measurement points), as shown in FIG. 3, converts the three-dimensional position of each measurement point into point cloud data, and outputs the point cloud data as target position information. Here, the three-dimensional position information measuring unit 19 outputs point cloud data indicating the three-dimensional position of each measurement point, for example, in x, y, and z coordinates of a local coordinate system, as target position information. Note that in this embodiment, the point cloud data and target position information are synonymous. However, the target position information is not limited to point cloud data, and may be information indicating a three-dimensional model such as a solid model. This point cloud data includes information indicating the shape (topography) of the excavation target 300 before and after excavation, and also includes information indicating the shape of the excavation target 300 inside and outside the bucket 8 during excavation. The three-dimensional position information measuring unit 19 can be configured using, for example, a three-dimensional laser range finder, a three-dimensional laser scanner, a three-dimensional distance sensor, a stereo camera, or the like. The three-dimensional laser range finder, or the like, is also called LiDAR (Light Detection and Ranging), and irradiates a laser light emitting in a pulsed manner while sequentially scanning a plurality of measurement directions (x, y, z directions) over a certain range, and measures distance and direction based on, for example, the time until the reflected scattered light returns and the irradiation direction. In this embodiment, it is assumed that the three-dimensional position information measuring unit 19 is configured using LiDAR. In this case, the three-dimensional position information measuring unit 19 sequentially stores and updates point cloud data indicating the measurement results of each measurement point (each reflection point) for each scanning period, and outputs it as object position information. The object position information is information indicating the excavation object 300 by the position information of multiple points. This object position information indicates, for example, each position of each measurement point by each coordinate information of the multiple measurement points, and indicates the shape of the multiple measurement points by lines and surfaces connecting adjacent measurement points. 6 shows an example of point cloud data 400 measured by the three-dimensional position information measuring unit 19 of this embodiment. The point cloud data 400 includes three-dimensional position information of a plurality of measurement points 401.The point cloud data 400 also includes three-dimensional position information of a plurality of measurement points 401 corresponding to the boom 6, the arm 7, the bucket 8, and the excavation target 300. The point cloud data output by the three-dimensional position information measuring unit 19 is not limited to point cloud data indicating the three-dimensional coordinate values of each measurement point, and may be point cloud data indicating the distance to and direction of each measurement point. When the three-dimensional position information measuring unit 19 is configured using a stereo camera, for example, a plurality of predetermined feature points recognized by image recognition can be the measurement points 401.
[0024] Moreover, the hydraulic excavator 1 shown in FIG. 1 includes a work machine control device 110 and an excavation information processing device (excavation support device) 120 shown in FIG. 1 and FIG. 2. The work machine control device 110 controls the boom cylinder 10, the arm cylinder 11, and the bucket cylinder 12 of the work machine 2 to control, for example, the position and attitude of the bucket 8. In this embodiment, the work machine control device 110 manually controls the position and attitude of the bucket 8 according to instructions from an operator using a predetermined operation device, or automatically controls the position and attitude of the bucket 8 based on a preset position and trajectory. Furthermore, in this embodiment, the work machine control device 110 has a function of automatically controlling excavation work. The automatic control of excavation work can be configured, for example, by a combination of a plurality of controls as follows. That is, the automatic control of excavation work can be composed of, for example, movement control of bucket 8 to an excavation start position, excavation control (FIG. 3) which is control of the operation of digging up excavation target 300 with bucket 8, embracing control (FIG. 3) which is control of the operation of embracing excavation target 300 with bucket 8, movement control of bucket 8 to a soil discharge position (or loading position), and soil discharge control (loading control). Of these controls, the work machine control device 110 of this embodiment automatically performs at least the excavation control, the embracing control, and the control of switching from excavation control to the embracing control.
[0025] 2 can be configured using, for example, a computer such as a microcomputer or a field programmable gate array (FPGA), or a computer and its peripheral circuits or peripheral devices, etc. The work machine control device 110 at least includes a position and orientation information acquisition unit 111, an excavation control unit 112, and an embracing control unit 113 as a functional configuration configured by a combination of hardware such as a computer, peripheral circuits, and peripheral devices, and software such as a program executed by the computer.
[0026] The position and orientation information acquisition unit 111 repeatedly acquires, for example, at a predetermined period, the work machine position and orientation information generated and output by the work machine position and orientation information generation unit 34 from the work machine position and orientation measurement unit 30. In addition, the position and orientation information acquisition unit 111 outputs the acquired work machine position and orientation information to the excavation information processing device 120.
[0027] The excavation control unit 112 controls the position and attitude of the bucket 8, for example, so that the trajectory of the blade tip 8T of the bucket 8 matches a target trajectory in the operation of digging up the excavation target 300 with the bucket 8, based on the work machine position and attitude information acquired by the position and attitude information acquisition unit 111. The target trajectory in the digging operation can be determined by the excavation control unit 112 or another control unit (not shown), for example, based on a target value for the excavation volume, a target value for the excavation shape, the topographical shape, etc. Furthermore, the excavation control unit 112 performs switching control from excavation control to embracing control, based on embracing determination information output by the excavation information processing device 120.
[0028] The embracing control unit 113 controls the position and attitude of the bucket 8 in response to instructions from the excavation control unit 112 so that, for example, the trajectory of the blade tip 8T of the bucket 8 coincides with a target trajectory in the operation of embracing the excavation target 300 with the bucket 8. The target trajectory in the embracing operation can be, for example, a trajectory in which the bucket surface 8S moves to a predetermined height in an attitude perpendicular to the vertical direction so that the bucket 8 does not further excavate the excavation target 300.
[0029] The excavation information processing device 120 can be configured using, for example, a microcomputer, a computer such as an FPGA, or a computer and its peripheral circuits or peripheral devices, either as a standalone device like the work machine control device 110, or as an integrated device with the work machine control device 110 or another control device of the hydraulic excavator 1. The excavation information processing device 120 includes a three-dimensional position information acquisition unit (acquisition unit) 121, an excavation soil volume estimation unit 122, a determination unit 123, and a display unit 124 as a functional configuration configured by a combination of hardware such as a computer, peripheral circuits, and peripheral devices, and software such as a program executed by the computer.
[0030] The three-dimensional position information acquisition unit 121 repeatedly acquires object position information (point cloud data 400) indicating the position information of multiple points of the excavation object from the three-dimensional position information measurement unit 19, for example at a predetermined period, and outputs it to the excavation volume estimation unit 122.
[0031] The excavation volume estimation unit 122 estimates and outputs the excavation volume SVA that the bucket 8 will acquire when it is loaded with the bucket 8 at that time, based on the bucket position and attitude information that is input from the position and attitude information acquisition unit 111 and the target position information acquired by the three-dimensional position information acquisition unit 121. The excavation volume estimation unit 122 may output the result of estimating the excavation volume SVA, for example, expressed as a value of the volume of the excavation volume SVA, may output as a value of the weight of the excavation volume SVA, or may output as a value indicating the ratio of the volume or weight of the excavation volume SVA to a predetermined reference value. The conversion from volume to weight can be performed, for example, as follows. That is, for example, the weight of the excavation volume after the first excavation work (scooped up state) can be calculated based on the cylinder pressure or the working machine attitude, and the relationship (specific gravity, etc.) between the calculated weight and the estimated excavation volume can be calculated, and the volume can be converted to weight using the relationship.
[0032] In this embodiment, the excavation volume estimating unit 122 estimates the volume of soil in the bucket SVI, which is the volume of soil stored inside the bucket 8, as shown in Fig. 7, and estimates the volume of soil outside the bucket SVO, which is the volume of soil predicted to be scooped up by the bucket 8 in the future, and calculates the excavation volume SVA by adding up the volume of soil in the bucket SVI and the volume of soil outside the bucket SVO. That is, the excavation volume estimating unit 122 calculates the excavation volume SVA by the formula: excavation volume SVA = volume of soil in the bucket SVI + volume of soil outside the bucket SVO. Note that Fig. 7 is a side view (viewed from the x direction) that shows a schematic diagram of the bucket 8 during excavation operation. Fig. 7 shows a state in which the excavation target 300 (topography) in front of the bucket 8 is raised from the topography before excavation due to the excavation operation by the bucket 8.
[0033] Furthermore, as shown in Figures 7 and 9, the excavated soil volume estimation unit 122 extracts measurement points 402 located within the width 8W of the bucket 8 and inside the circle 8A traced by the bucket cutting edge 8T when the bucket 8 is rotated around the bucket pin 15 from the target object position information (point cloud data 400), and estimates the excavated soil volume based on the position information of the extracted measurement points 402.
[0034] Here, an example of the operation of the excavation volume estimating unit 122 when estimating the excavation volume will be described with reference to Figs. 5 to 11. Fig. 5 is a flow chart showing an example of the operation for one cycle when the excavation volume estimating unit 122 repeatedly estimates the excavation volume at a predetermined cycle during excavation operation. That is, the excavation volume estimating unit 122 repeatedly executes the process shown in Fig. 5 at a predetermined cycle during excavation operation. Figs. 8, 10 and 11 are side views (viewed from the x direction) that typically show an example of point cloud data 400 that was actually acquired during excavation control. Fig. 9 is a schematic diagram showing an example of point cloud data 400.
[0035] As shown in FIG. 5, the excavation volume estimation unit 122 first acquires the position and angle information of the bucket 8 from the work machine position and attitude information acquired from the position and attitude information acquisition unit 111 (step S101). Next, the excavation volume estimation unit 122 extracts a point cloud within the bucket width 8W from the target object position information (point cloud data 400) (step S102), and further extracts a point cloud inside the circle 8A of the bucket blade tip 8T at the center of the bucket pin 15 and in front of the bucket surface 8S (step S103). FIG. 9 shows an example of the point cloud (multiple measurement points 402) extracted in steps S102 and S103 from the point cloud data 400 (multiple measurement points 401). Here, within the bucket width 8W is a range sandwiched between two straight lines 501 and 502 extending the width 8W of the bucket 8 along the y direction of the local coordinate system as shown in FIG. 9. 7. The range inside the circle 8A of the bucket cutting edge 8T at the center of the bucket pin 15 and in front of the bucket surface 8S is the range inside the circle 8A shown in FIG.
[0036] Next, the excavation volume estimation unit 122 deletes the point cloud (part of the measurement points 402) obtained from the work machine 2 such as the arm 7, bracket, link mechanism, etc. based on the work machine position and posture information and drawing information (dimension information) (step S104).
[0037] Next, the excavation volume estimation unit 122 estimates the volume of soil SVI in the bucket (step S105). In step S105, the excavation volume estimation unit 122 estimates the volume of soil SVI in the bucket, for example, as follows. That is, for example, the excavation volume estimation unit 122 first determines two measurement points 402 (representative point A) on the front side (operator cab 4 side) and measurement point 402 (representative point B) on the back side as shown in FIG. 9 from the multiple measurement points 402 extracted from the point cloud data 400 in the processing of steps S102 to S104. Next, the excavation volume estimation unit 122 estimates the lower (vertical lower side) area (depth: butt width 8W) surrounded by the straight line LAB connecting the representative points A and B, the bucket surface 8S, and the bucket contour 8C as the volume of soil SVI in the bucket, as shown in FIG. 8.
[0038] Next, the excavation volume estimating unit 122 estimates the volume of soil SVO outside the bucket (step S106). In step S106, for example, the excavation volume estimating unit 122 estimates the volume of soil SVO outside the bucket as follows. That is, the excavation volume estimating unit 122 estimates the volume of soil SVO outside the bucket by two different calculation methods, for example, when viewed from the x direction, the straight line LAB connecting the representative points A and B determined in step S105 intersects with the bucket surface 8S (FIG. 10) and when it does not intersect with the bucket surface 8S (FIG. 11). First, when the straight line LAB intersects with the bucket surface 8S, the excavation volume estimating unit 122 estimates the volume of soil SVO outside the bucket to be an area (depth: butt width 8W) surrounded by the straight line LAB connecting the representative points A and B, the bucket surface 8S, and the straight line LABT extending vertically upward from the cutting edge 8T toward the straight line LAB, as shown in FIG. 10, when viewed from the x direction. In addition, when the straight line LAB does not intersect with the bucket surface 8S, the excavation volume estimation unit 122 estimates the amount of soil outside the bucket SVO to be a rectangular area (depth: butt width 8W) with vertices at representative point A, representative point B, the bucket pin 15, and the cutting edge 8T, as viewed from the x direction, as shown in Figure 11.
[0039] Next, the excavation volume estimation unit 122 calculates the excavation volume SVA by summing the bucket soil volume SVI estimated in step S105 and the bucket soil volume SVO estimated in step S106 (step S107). Through the above process, the excavation volume estimation unit 122 successively estimates the excavation volume SVA that will be obtained by the bucket 8 when the bucket 8 is loaded at that point during the excavation operation.
[0040] Furthermore, the determination unit 123 determines whether the excavation volume estimated by the excavation volume estimation unit 122 has reached the target excavation volume, and outputs the determination result to the excavation control unit 112 as embracing determination information. The target excavation volume is a target value of the volume or weight of the excavation target 300 acquired by the bucket 8 in one excavation operation. For example, it can be set by an operator or automatically set by the excavation control unit 112. Furthermore, for example, when excavation and loading are repeated multiple times in the case of loading the excavation target 300 onto a dump truck or the like, the loading volume can be accurately controlled by adjusting the excavation volume of the last one time.
[0041] The display unit 124 displays the value of the excavation volume estimated by the excavation volume estimating unit 122 as numerical values or a time-series graph on the display device 40 installed in the operator's cab 4. When the operator manually performs excavation work, the operator can, for example, perform a switching operation from excavation to embracing by referring to the estimated result of the excavation volume displayed on the display device 40. In this case, the excavation information processing device 120 including the three-dimensional position information acquiring unit (acquiring unit) 121, the excavation volume estimating unit 122, and the display unit 124 has an aspect as an excavation support device.
[0042] Next, referring to Fig. 4, an example of the operation of the work machine control device 110 and the excavation information processing device 120 shown in Fig. 2 will be described. Fig. 4 is a system flow diagram showing an example of the operation of the work machine control device 110 and the excavation information processing device 120 shown in Fig. 2 when excavation control and enveloping control are automatically performed once. The operation shown in Fig. 4 is started, for example, when a target excavation volume is set in advance and the operator instructs the start of excavation control with the bucket 8 moved to the excavation start position. When the operation shown in Fig. 4 is started, the excavation control unit 112 in the work machine control device 110 performs excavation control (step S11) and repeatedly determines at a predetermined cycle whether or not to switch to enveloping control based on enveloping determination information (step S12). In addition, in the excavation information processing device 120, when the operation shown in Figure 4 is started, the excavation soil volume estimation unit 122 estimates the excavation soil volume repeatedly at a predetermined period (step S21), and the judgment unit 123 judges whether the excavation soil volume estimated by the excavation soil volume estimation unit 122 has reached the target excavation soil volume (step S22).
[0043] When the excavation soil volume reaches the target excavation soil volume, the determination unit 123 outputs the envelopment determination information indicating that the excavation soil volume has reached the target excavation soil volume (if "YES" in step S22). When the excavation control unit 112 receives the envelopment determination information indicating that the excavation soil volume has reached the target excavation soil volume, it determines to switch to the envelopment control (if "YES" in step S12), and the envelopment control unit 113 performs the envelopment control (step S13).
[0044] Fig. 12 is a schematic diagram showing an example of the time transition of the excavation volume in the operation shown in Fig. 4. The horizontal axis is time, and the vertical axis is the excavation volume. When excavation starts, the volume of soil in the bucket SVI gradually increases, and when the volume of soil in the bucket SVI has increased to a certain extent, the volume of soil outside the bucket SVO begins to increase. Then, when the volume of soil excavated SVA reaches the target volume of soil excavated, the control is switched to the embracing control.
[0045] As described above, according to this embodiment, the excavation volume can be successively estimated during excavation work, so that the excavation volume can be easily adjusted to any value.
[0046] Although an embodiment of the present invention has been described above with reference to the drawings, the specific configuration is not limited to the above embodiment, and also includes design modifications and the like within the scope of the gist of the present invention.
[0047] For example, the hydraulic excavator 1 may be an unmanned type that automatically controls the vehicle body 1B and the work machine 2, may be a type that is remotely operated, or may be a type that is controlled by a combination of automatic control, remote control, and manual control by an operator. In addition, although the above embodiment has been described as an example in which coordinate information in a local coordinate system is mainly used, coordinate information converted into a global coordinate system may also be used.
[0048] Furthermore, a part or all of the programs executed by the computer in the above-described embodiments can be distributed via a computer-readable recording medium or a communication line. [Explanation of symbols]
[0049] 1...hydraulic excavator, 2...work machine, 8...bucket, 8T...cutting edge, 15...bucket pin, 19...three-dimensional position information measuring unit, 30...work machine position and orientation measuring unit, 110...work machine control device, 111...position and orientation information acquisition unit, 112...excavation control unit, 113...embracing control unit, 120...excavation information processing device, 121...three-dimensional position information acquisition unit (acquisition unit), 122...excavation soil volume estimation unit, 123...determination unit, 124...display unit
Claims
1. An acquisition unit that acquires object position information indicating a plurality of position information points of an excavation object; an excavation volume estimating unit that estimates and outputs an excavation volume that will be obtained by the bucket when the bucket is loaded at that time based on bucket position and attitude information indicating the position and attitude of the bucket and the target object position information; Equipped with The excavation volume estimation unit estimates an inner soil volume, which is the volume of soil stored inside the bucket, and estimates an outer soil volume, which is the volume of soil predicted to be scooped up by the bucket in the future, and calculates the excavation volume by adding up the inner soil volume and the outer soil volume. Drilling information processing device.
2. The apparatus further includes a determination unit that outputs a determination result as to whether the excavated soil volume has reached a target excavated soil volume. The excavation information processing device according to claim 1 .
3. The excavation volume estimation unit extracts, from the target object position information, the point located within the width of the bucket and inside a circle drawn by the bucket blade tip when the bucket is rotated around a bucket pin, and estimates the excavation volume based on the position information of the extracted point. The excavation information processing device according to claim 1 or 2.
4. The excavation information processing device according to any one of claims 1 to 3, The bucket; A work machine comprising:
5. An excavation information processing device according to claim 2, The bucket; a work machine control device that moves the bucket to a predetermined height when the excavated soil volume reaches the target excavated soil volume; A work machine comprising:
6. An acquisition unit that acquires object position information indicating a plurality of position information points of an excavation object; an excavation volume estimation unit that estimates the volume of excavated soil that would be obtained by the bucket when the bucket is loaded at that time based on bucket position and orientation information indicating the position and orientation of the bucket and the target object position information; A display unit that displays the excavated soil volume; Equipped with The excavation volume estimation unit estimates an inner soil volume, which is the volume of soil stored inside the bucket, and estimates an outer soil volume, which is the volume of soil predicted to be scooped up by the bucket in the future, and calculates the excavation volume by adding up the inner soil volume and the outer soil volume. Drilling support equipment.
7. A step of acquiring object position information indicating a plurality of position information points of an excavation object; a step of estimating and outputting an amount of excavated soil that would be obtained by the bucket when the bucket is loaded at that time, based on bucket position and attitude information indicating a position and attitude of the bucket and the object position information; In the step of estimating the amount of excavated soil, an amount of soil inside the bucket, which is the amount of soil stored inside the bucket, is estimated, and an amount of soil outside the bucket, which is the amount of soil predicted to be scooped up by the bucket in the future, is estimated, and the amount of soil inside the bucket and the amount of soil outside the bucket are summed to calculate the amount of excavated soil. A drilling information processing method comprising:
Citation Information
Patent Citations
Load measurement system of construction machine
JP2019039207A
Control system of work vehicle, method, and work vehicle
JP2019039280A
Work machine
JP2020020153A
Vehicle Payload Weight Display Method and System
US20140167971A1
Excavation device
WO2015162710A1