Approach Warning System
The approach warning system addresses GPS and communication delays by estimating jib positions to accurately notify workers of approaching loads, enhancing crane safety.
Patent Information
- Application Number
- JP2020187530
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2020-11-10
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2040-11-10
AI Technical Summary
Existing crane safety monitoring systems fail to account for GPS and wireless communication delays, leading to inaccurate warnings when a load and a worker approach each other closer than a preset distance due to poor reception of radio waves at construction sites.
An approach warning system that includes a crane with position information acquisition means for the jib tip, base end, and worker, and a management PC to estimate the jib's position considering delays, determining a warning area and notifying workers or operators based on estimated positions.
Accurately determines the proximity of a suspended load to workers even in environments with communication delays, ensuring timely warnings are issued.
Smart Images

Figure 0007591783000001 
Figure 0007591783000002 
Figure 0007591783000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a proximity warning system. [Background technology]
[0002] Crane safety monitoring is carried out with the utmost care to prevent accidents involving the falling of a crane's suspended load. Crane safety monitoring is generally carried out, for example, by assigning a dedicated monitor to monitor the crane, who notifies workers when the crane's suspended load approaches. Also, various technologies have been developed to make crane work safer (for example, see Patent Document 1). The technology described in Patent Document 1 involves providing a location information acquisition means (e.g., a GPS (Global Positioning System) receiver) that acquires location information at the tip or hook of the crane's boom (also called a "jib"), and generating an alarm when the crane's suspended load and a worker come within a specified distance range in a plan view. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2015-005152 A Summary of the Invention [Problem to be solved by the invention]
[0004] However, the technology of Patent Document 1 does not take into consideration the delay in GPS reception or the delay in wireless communication. Therefore, at construction sites where the reception of GPS signals or wireless communication signals is poor, a warning may be issued only when the load suspended by the crane and the worker are closer than a preset distance. From this perspective, the present invention provides an approach warning system that can notify workers of the approach of a suspended load with greater accuracy than ever before. [Means for solving the problem]
[0005] The approach warning system according to the present invention is an approach warning system that warns of an approach between a load suspended by a crane and a worker. This approach warning system includes a crane having a jib, a first position information acquisition means for acquiring position information of the worker, an approach determination device for determining whether the load is approaching the worker, and a notification means for notifying at least one of the worker and the operator of the crane of the determination result. The crane includes: Means of transportation; A second position information acquiring means for acquiring position information of the tip of the jib. and a third position information acquisition means for acquiring position information of the base end portion of the jib. The approach determination device includes: and the base end From the time-dependent change in the position information, the position of the jib at a time after the time when the position information was last acquired To the base end The robot has a position estimation means for estimating the position of the tip, and an approach determination means for setting a warning area in a horizontal plane based on the estimated position of the tip and determining whether the position of the worker on the horizontal plane is included in the warning area.
[0006] In the approach warning system of the present invention, whether or not to issue a warning is determined based on the calculated estimated position, so that the approach of a suspended load and a worker can be appropriately determined even at a construction site where various delays (e.g., GPS reception delays and wireless communication delays) occur before the position information of the crane jib is obtained. In particular, even in the case of a mobile crane, the proximity of a suspended load to a worker can be appropriately determined.
[0008] When the jib is capable of rotating, the position estimation means may calculate the angular velocity or angular acceleration of the jib from the change over time in the acquired position information of the tip, and estimate the position of the tip of the jib in the horizontal plane based on the calculated angular velocity or angular acceleration. In addition, when the jib is capable of any of raising, lowering, extending and bending movements, the position estimation means may calculate the speed or acceleration of the tip from the change over time in the acquired position information of the tip, and estimate the position of the tip of the jib on the horizontal plane based on the calculated speed or acceleration. In this way, the proximity of the load and the worker can be appropriately determined depending on the type of jib the crane has.
[0009] The warning region may be a circular region centered on the estimated position of the tip. In this way, the approach of workers around the suspended load can be detected without fail. In addition, the position estimation means may further estimate the positions of the jibs of other cranes present around the crane, and the proximity determination means may determine whether the cranes are approaching each other or not. In this way, the proximity of the cranes to each other can be appropriately determined. Effect of the Invention
[0010] According to the present invention, it is possible to provide an approach warning system that can notify workers of the approach of a suspended load with greater accuracy than ever before. [Brief description of the drawings]
[0011] [Figure 1] 1 is a schematic configuration diagram of an approach warning system according to a first embodiment of the present invention. [Diagram 2] 1A and 1B are diagrams for explaining the configuration of a crane, in which FIG. 1A is a schematic external view of the crane, and FIG. 1B is a schematic plan view of the crane. [Diagram 3] FIG. 2 is a schematic external view showing a configuration example of a worker terminal. [Figure 4] 1 is a block diagram of an approach warning system according to a first embodiment of the present invention. [Diagram 5] 3 is an example of a flowchart showing the operation of the approach warning system according to the first embodiment of the present invention. [Figure 6] FIG. 5 is a schematic configuration diagram of an approach warning system according to a second embodiment of the present invention. [Figure 7] FIG. 5 is a block diagram of an approach warning system according to a second embodiment of the present invention. [Figure 8]10 is an example of a flowchart showing the operation of the approach warning system according to the second embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0012] Hereinafter, the embodiment of the present invention will be described in detail with reference to the drawings. Each drawing is merely a schematic illustration to allow a sufficient understanding of the present invention. Therefore, the present invention is not limited to the illustrated examples. In each drawing, common or similar components are denoted by the same reference numerals, and duplicated explanations thereof will be omitted.
[0013] [First embodiment] <Configuration of the approach warning system according to the first embodiment> The configuration of an approach warning system 1 according to the first embodiment will be described with reference to Fig. 1. Fig. 1 is a schematic configuration diagram of the approach warning system 1 according to the first embodiment. The approach warning system 1 is a system that monitors and warns of the approach of a worker to an object (sometimes called a "suspended load") suspended by a crane 2. Note that there is no particular limitation on the type of crane 2 or the type of suspended load used in the approach warning system 1.
[0014] As shown in FIG. 1, the approach warning system 1 mainly includes a crane 2 that hoists and carries an object, a worker terminal 3 carried by a worker, and a management PC 4 that monitors the distance (proximity) between the suspended load and the worker. The crane 2 and the management PC 4 are capable of communicating with each other, and the worker terminal 3 and the management PC 4 are also capable of communicating with each other. Although details will be described later, the crane 2 and the worker terminal 3 have position information acquisition means (first position information acquisition means 5A, second position information acquisition means 5B, third position information acquisition means 5C (see FIG. 2 and FIG. 3)), and the management PC 4 uses the position information acquired by the position information acquisition means to determine the distance (proximity) between the suspended load and the worker. The position information acquisition means is, for example, a GPS (Global Positioning System) receiver. The management PC 4 may be mounted on the crane 2.
[0015] The configuration of the crane 2 will be described with reference to Fig. 2. Fig. 2(a) is a schematic external view of the crane 2, and Fig. 2(b) is a schematic plan view of the crane 2. Note that the crane 2 shown in Fig. 2 is merely an example. The crane 2 can change the position of a lifted object (suspended load) in the front-rear, up-down, left-right directions by, for example, a slewing motion, a raising and lowering motion, a telescopic motion, or a bending motion, or a combination of these motions. The crane 2 according to this embodiment is assumed to be a mobile crane having a moving means 2d, but may also be a fixed crane that does not have the moving means 2d.
[0016] The crane 2 shown in FIG. 2(a) mainly comprises a main body 2a, a jib 2b, and a hook 2c. The main body 2a includes an operation room where an operator performs operations, a power source that generates power to hoist a load, and the like. A monitor and a speaker are installed in the operation room to notify the operator of information necessary for performing operations. The main body 2a is rotatable (pivotable) around a vertical axis. The monitor and the speaker installed in the operation room are examples of notification means. The jib 2b has a long shape. One end (base end) of the jib 2b is connected to the main body 2a. The jib 2b can move up and down with the base end as a fulcrum. The structure of the jib 2b is not particularly limited, and the jib 2b may be composed of multiple parts (e.g., a first jib, a second jib, etc.). The jib 2b may have a structure that allows it to expand and contract in the extension direction, or a structure that allows it to bend in a direction in which the tip and base ends of the jib 2b approach each other. The jib 2b is sometimes called a "boom." The hook 2c is connected to the power source of the main body 2a by a metal rope and hangs down from the tip of the jib 2b. The hook 2c has a structure capable of lifting an object. With these configurations, the crane 2 can lift an object (load) using power generated by the power source, and transport the lifted load horizontally.
[0017] As shown in Fig. 2(a) and (b), the crane 2 has a second position information acquisition means 5B and a third position information acquisition means 5C. The second position information acquisition means 5B and the third position information acquisition means 5C have an antenna that receives radio waves (positioning signals) from a positioning satellite (not shown), and are devices that calculate a position (latitude, longitude, altitude) using the received radio waves. The positioning satellite periodically transmits, for example, its own position information (orbital position information) and time information. The positioning satellite may be, for example, a GPS (Global Positioning System) satellite, a GLONASS (Global Navigation Satellite System) satellite, a Galileo satellite, a global navigation satellite system (GNSS: Global Navigation Satellite System), a quasi-zenith satellite, or the like. Note that the second position information acquisition means 5B and the third position information acquisition means 5C may not calculate the position by themselves, but may have another device or another device calculate the position.
[0018] The second position information acquisition means 5B is attached to the tip of the jib 2b and acquires position information of the tip of the jib 2b. The third position information acquisition means 5C is attached to the base end of the jib 2b and acquires position information of the base end of the jib 2b. Since the base end of the jib 2b is connected to the main body 2a, the third position information acquisition means 5C may be attached to the main body 2a (preferably in the vicinity of the jib 2b).
[0019] The worker terminal 3 shown in Fig. 1 is carried by a worker working at a construction site. The worker terminal 3 is a device equipped with a means for communicating with other devices, a means for notifying workers, and a means for acquiring location information. The worker terminal 3 may be composed of multiple devices, in which case each device does not necessarily have to have all three of the above-mentioned means. For example, when the worker terminal 3 is composed of two devices, one device may have the communication means and the location information acquisition means, and the other device may have the communication means and the notification means.
[0020] A specific configuration of the worker terminal 3 in this embodiment will be described with reference to Fig. 3. Fig. 3 is a schematic external view showing an example of the configuration of the worker terminal 3. As shown in Fig. 3, the worker terminal 3 in this embodiment is composed of a first worker terminal 3A and a second worker terminal 3B. The first worker terminal 3A is, for example, a smartphone or a mobile phone, and includes a communication means and a location information acquisition means (herein referred to as "first location information acquisition means 5A"). The first worker terminal 3A is carried by a worker, and the first location information acquisition means 5A acquires location information of the worker. The second worker terminal 3B is, for example, a wristwatch-type wearable device (sometimes called a "smart watch"), and includes a communication means and a notification means.
[0021] 1 is a terminal used to manage construction work, and is, for example, a PC (Personal Computer) having an application program for construction work. The management PC 4 according to this embodiment is an example of an "approach determination device" and determines whether or not a suspended load is approaching a worker. With reference to FIG. 4, the main data flow in the approach warning system 1 will be described. FIG. 4 is a block diagram of the approach warning system 1 according to the first embodiment of the present invention. As shown in FIG. 4, the crane 2 includes a calculation means 2e and a communication means 2f. The communication means 2f of the crane 2 transmits the position information of the tip of the jib 2b acquired by the second position information acquisition means 5B and the position information of the base end of the jib 2b acquired by the third position information acquisition means 5C to the management PC 4. Similarly, the first worker's terminal 3A transmits the worker's position information acquired by the first position information acquisition means 5A to the management PC 4. These position information may be associated with some kind of time information. The time information associated with the position information may be, for example, time information included in the radio wave transmitted from a positioning satellite, or time information when the crane 2 (or the first worker's terminal 3A) transmits the position information to the management PC 4.
[0022] As shown in Fig. 4, the management PC 4 includes a communication unit 4a, a position estimation unit 4b, and an approach determination unit 4c. The communication unit 4a is, for example, a module that realizes wireless communication, and the wireless communication method used by the communication unit 4a is not particularly limited. The position estimation unit 4b and the approach determination unit 4c are realized, for example, by a CPU (Central Processing Unit) reading and executing a predetermined program from a ROM (Read Only Memory) (not shown) or the like.
[0023] The management PC 4 acquires (receives) position information of the tip and base ends of the jib 2b from the crane 2 via the communication means 4a. The management PC 4 also acquires (receives) position information of the worker from the first worker terminal 3A via the communication means 4a. The position information acquired by the management PC 4 is affected by communication delays due to wireless communication, and there may be some deviation from the actual position at the time when the management PC 4 acquires the position information.
[0024] The position estimation means 4b estimates the position of the suspended load. The estimated position of the suspended load here is information that serves as a reference for determining whether the worker and the suspended load are close to each other, and is, for example, the position of the suspended load at the present time or in the near future (for example, several seconds later). The position estimation means 4b calculates the position of the suspended load taking into account various delays, and may also calculate the position of the jib 2b at the present time or in the near future (for example, several seconds later) by assuming that the position of the tip of the jib 2b is the position of the suspended load. In this embodiment, it is also assumed that the position of the tip of the jib 2b is calculated as the position of the suspended load, and the position estimation means 4b estimates the position of the tip of the jib 2b at a time later than the time when the position information was last acquired from the change over time in the acquired position information of the tip of the jib 2b. The position of the suspended load to be calculated may be either a two-dimensional position (latitude, longitude) or a three-dimensional position (latitude, longitude, altitude). When warning a worker not to go under a suspended load in consideration of the load falling, the positional relationship between the load and the worker only needs to be considered in two dimensions, so the two-dimensional position of the load may be calculated. In this embodiment, a warning is given to the worker based on the two-dimensional positional relationship.
[0025] For example, assume that the crane 2 is capable of rotating the jib 2b. In this case, the position estimation means 4b calculates the angular velocity or angular acceleration of the jib 2b from, for example, a change over time in the acquired position information of the tip of the jib 2b, and estimates the position of the tip of the jib 2b on the horizontal plane based on the calculated angular velocity or angular acceleration. Also, assume that the crane 2 is capable of raising, lowering, extending and bending the jib 2b. In this case, the position estimation means 4b calculates the speed or acceleration of the tip of the jib 2b on a horizontal plane from the time-dependent change in the acquired position information of the tip of the jib 2b, and estimates the position of the tip of the jib 2b on the horizontal plane based on the calculated speed or acceleration. Also, assume that the crane 2 is a mobile crane having a moving means 2d. In this case, it is preferable that the position estimation means 4b estimates the position of the tip end of the jib 2b relative to the base end of the jib 2b on the horizontal plane from the time-dependent change in the acquired position information of the tip end and base end of the jib 2b.
[0026] The approach determination means 4c sets a warning area K (see FIG. 1) in a horizontal plane based on the estimated position of the tip of the jib 2b, and determines whether the position of the worker on the horizontal plane is included in the warning area K. The approach determination means 4c issues a warning to workers who are within the warning area K, and does not issue a warning to workers who are outside the warning area K. The approach determination means 4c transmits a warning to, for example, a second worker terminal 3B carried by the target worker, and the notification means of the second worker terminal 3B transmits a warning to the worker by a message, a warning sound, vibration, or the like. The transmission of the warning to the second worker terminal 3B may be performed via the first worker terminal 3A, which is a smartphone. The warning to the worker may be any warning that allows the worker to recognize the approach of the suspended load.
[0027] The shape and size of the warning area K are not particularly limited. The warning area K is, for example, a circular area centered directly below the estimated tip of the jib 2b (the position where the tip of the jib 2b is projected onto the work surface). The warning area K may be composed of a plurality of divided areas, and may be composed of a first warning area K1 and a second warning area K2 as shown in FIG. 1. When notifying a worker of the approach of a suspended load by vibration, it is preferable to make the vibration interval shorter in the first warning area K1 than in the second warning area K2, for example.
[0028] <Operation of the approach warning system according to the first embodiment> The operation of the approach warning system 1 according to the first embodiment will be described with reference to Fig. 5. Fig. 5 is an example of a flowchart showing the operation of the approach warning system 1 according to the first embodiment. The series of operations shown in Fig. 5 is executed, for example, at predetermined intervals. Note that, when the crane 2 does not move and the position of the base end of the jib 2b (i.e., the crane 2 itself) does not change, the position information of the base end of the jib 2b (or the main body 2a of the vehicle) may be registered in advance without being acquired each time.
[0029] (Step S1) The third position information acquisition means 5C acquires position information (latitude, longitude) of the base end of the jib 2b (or the main body 2a of the vehicle). The second position information acquisition means 5B acquires position information (latitude, longitude) of the tip of the jib 2b (i.e., the second position information acquisition means 5B). The first position information acquisition means 5A acquires position information (latitude, longitude) of the worker. The acquired position information is then transmitted to the management PC 4. (Step S2) The position estimation means 4b of the management PC 4 calculates the angle (two-dimensional orientation) and distance (two-dimensional distance) of the jib 2b from the position information of the base end of the jib 2b (or the vehicle body 2a) and the position information of the tip of the jib 2b (i.e., the second position information acquisition means 5B). The angle of the jib 2b may be an angle relative to a reference orientation set on a horizontal plane, for example. The distance of the jib 2b may be a distance from a reference position of the tip of the jib 2b set on a horizontal plane, for example.
[0030] (Step S3) The position estimation means 4b of the management PC 4 calculates the angular velocity of the jib 2b from the previous calculation values (i.e., position information of the base end of the jib 2b (or the main body 2a of the vehicle), position information of the tip end of the jib 2b (i.e., the second position information acquisition means 5B), the estimated position of the jib 2b) and the angle and distance of the jib 2b calculated in step S2, and calculates the estimated position of the jib 2b based on the calculated angular velocity of the jib 2b. Note that here, the estimated position of the jib 2b is calculated from the angular velocity assuming the rotation of the jib 2b, but if movements other than rotation are included, it is preferable to calculate information other than the angular velocity. Note that angular acceleration may be calculated instead of or in addition to the angular velocity. (Steps S4 and S5) The position estimation means 4b of the management PC 4 may further perform a process to correct the delay when a GPS reception delay occurs. For example, in addition to the position estimation described above, the position may be corrected using a Kalman filter or the like based on past latitude and longitude information. This correction may be performed at a timing different from the position estimation described above. When the delay correction is performed, the position estimation means 4b recalculates the estimated position of the jib 2b from, for example, the angular velocity amount after the correction.
[0031] (Step S6) When the estimated position of the jib 2b and the position of the worker acquired in step S1 are closer than a preset distance, the approach determination means 4c of the management PC 4 issues a warning to the corresponding worker or the operator of the crane 2. Note that in this embodiment, considering that workers often stay within a specific work area and do not move significantly in a short time, and that the moving speed of the suspended load often exceeds the walking speed of the worker, only the position of the tip of the jib 2b is estimated, but the position of the worker may also be estimated.
[0032] As described above, the approach warning system 1 of the first embodiment determines whether to issue a warning based on the calculated estimated position, so that it can appropriately determine the approach of a suspended load and a worker even at a construction site where various delays (e.g., GPS reception delays and wireless communication delays) occur before obtaining position information of the jib 2b of the crane 2.
[0033] [Second embodiment] In the first embodiment, the approach between the load suspended by the crane 2 and the worker is monitored and a warning is issued. In the second embodiment, the approach between the cranes 2 (for example, two cranes 2) is further monitored and a warning is issued.
[0034] <Configuration of approach warning system according to the second embodiment> The configuration of an approach warning system 101 according to the second embodiment will be described with reference to Fig. 6. Fig. 6 is a schematic configuration diagram of the approach warning system 101 according to the second embodiment. The approach warning system 101 is a system that monitors and warns of approach between a load suspended by a crane 2 and a worker, and approach between cranes 2. 6, the approach warning system 101 mainly comprises a plurality of cranes 2A, 2B for lifting and carrying an object, a worker terminal 3 carried by a worker, and a management PC 104 for monitoring the distance (proximity) between the load and the worker and the distance (proximity) between the cranes 2A, 2B. The following mainly describes the differences from the first embodiment.
[0035] The jib 2b of the cranes 2A and 2B of this embodiment is composed of a first jib on the main body 2a side and a second jib on the hook 2c (see FIG. 2) side. Hereinafter, the first jib on the main body 2a side will be referred to as the "boom 2b1," and the second jib on the hook 2c (see FIG. 2) side will be referred to as the "jib 2b2." The second position information acquisition means 5B is attached to the tip of the jib 2b2, and the third position information acquisition means 5C is attached to the base end of the boom 2b1.
[0036] With reference to FIG. 7, the main data flow in the approach warning system 101 will be described. FIG. 7 is a block diagram of the approach warning system 101 according to the second embodiment of the present invention. As shown in FIG. 7, the communication means 2f of the cranes 2A and 2B transmits the position information of the tip of the jib 2b2 acquired by the second position information acquisition means 5B and the position information of the base end of the boom 2b1 acquired by the third position information acquisition means 5C to the management PC 104. These position information are preferably associated with some kind of time information. The time information associated with the position information may be, for example, time information included in radio waves transmitted from a positioning satellite, or time information when the crane 2 (or the first worker's terminal 3A) transmits the position information to the management PC 4.
[0037] 7, the management PC 104 includes a communication unit 104a, a position estimation unit 104b, and an approach determination unit 104c. The position estimation unit 104b and the approach determination unit 104c are realized, for example, by a CPU (Central Processing Unit) reading and executing a predetermined program from a ROM (Read Only Memory) (not shown) or the like. The communication means 104a is the same as the communication means 4a in the first embodiment, and realizes communication with the cranes 2A and 2B and the worker terminal 3. The position estimation means 104b estimates the position of the suspended load and also estimates the position of the jib 2b of the cranes 2A and 2B. In this embodiment, it is assumed that the jib 2b is composed of a boom 2b1 and a jib 2b2, but in estimating the position of the jib 2b, the positions of the boom 2b1 and the jib 2b2 may be calculated as one rod-shaped member rather than being calculated separately. In other words, when warning the worker based on the two-dimensional positional relationship, the angle and distance of the jib 2b may be obtained from two points, namely, the position information of the base end of the jib 2b (i.e., the main body 2a) and the position information of the tip of the jib 2b. The approach determination means 104c determines the approach between a suspended load and an operator, and also determines the approach between the cranes 2A, 2B.
[0038] <Operation of the approach warning system according to the second embodiment> The operation of the approach warning system 101 according to the second embodiment will be described with reference to Fig. 8. Fig. 8 is a flowchart illustrating the operation of the approach warning system 101 according to the second embodiment. The series of operations shown in Fig. 8 is executed, for example, at predetermined intervals.
[0039] (Step S11) When the accuracy of the position information (latitude, longitude) of the base end portion of the boom 2b1 (i.e., the main body portion 2a) acquired by the third position information acquisition means 5C is poor, the position information (latitude, longitude) of the base end portion of the boom 2b1 (i.e., the main body portion 2a) may be fixed at the discretion of the manager (e.g., the crane operator) who manages the crane 2. Since the crane 2 does not move (or moves little) during the operation of the crane 2, it is possible to fix the position information (latitude, longitude) of the base end portion of the boom 2b1 (i.e., the main body portion 2a). Fixing of the position information is realized by operating the management PC 104 or a manager's terminal (e.g., a tablet terminal) (not shown) held by the manager. For example, by specifying a location on a map of the construction site displayed on the screen of these devices, the position information (latitude, longitude) of the base end portion of the boom 2b1 is fixed to the specified location. (Step S12) The third position information acquisition means 5C of the cranes 2A, 2B acquires position information (latitude, longitude) of the base end of the boom 2b1 (i.e., the main body 2a). The second position information acquisition means 5B acquires position information (latitude, longitude) of the tip of the jib 2b2. The first position information acquisition means 5A acquires position information (latitude, longitude) of the worker. The acquired position information is then transmitted to the management PC 104.
[0040] (Step S13) The position estimation means 104b of the management PC 104 calculates the angle (two-dimensional orientation) and distance (two-dimensional distance) of the jib 2b from the position information of the base end of the boom 2b1 (i.e., the main body 2a) and the position information of the tip of the jib 2b2 (i.e., the second position information acquisition means 5B). The angle of the jib 2b may be an angle relative to a reference orientation set on a horizontal plane, for example. The distance of the jib 2b may be a distance from a reference position of the tip of the jib 2b2 (i.e., the second position information acquisition means 5B) set on a horizontal plane, for example.
[0041] (Step S14) The position estimation means 104b of the management PC 4 calculates the angular velocity of the jib 2b from the previous calculation value (i.e., the estimated position of the jib 2b) and the angle and distance of the jib 2b calculated in step S13, and calculates the estimated position of the jib 2b based on the calculated angular velocity of the jib 2b. Note that, although the estimated position of the jib 2b is calculated from the angular velocity assuming the rotation of the jib 2b here, it is preferable to calculate information other than the angular velocity when an operation other than rotation is included. Note that, instead of the angular velocity, or in addition to the angular velocity, the angular acceleration may be calculated. (Steps S15 and S16) The position estimation means 104b of the management PC 104 performs a process to correct the delay when a GPS reception delay occurs. The process to correct the delay is the same as that in the first embodiment. When the delay correction is performed, the position estimation means 104b recalculates the estimated position of the jib 2b from the angular velocity amount after the correction.
[0042] (Steps S17 and S18) The approach determination means 104c of the management PC 104 determines whether the estimated position of the jib 2b and the position of the worker acquired in step S12 are closer than a preset distance. The approach determination means 104c also determines whether the distance between the cranes 2A and 2B is closer than a preset distance based on the estimated positions of the jib 2b of the crane 2A and the estimated positions of the jib 2b of the crane 2B. Also, the approach determination means 104c may determine whether the position of the worker is closer than a preset distance or whether the distance between the cranes 2A and 2B is closer than a preset distance based on the current positions of the jib 2b of the crane 2A and the jib 2b of the crane 2B. This determination based on the current position may be auxiliary, and when the delay is, for example, n seconds or more or n seconds or less (n is a preset value), the approach determination may be performed based on the current position. Also, in addition to the approach determination based on the estimated position, the approach determination may be performed based on the actual position (for example, the range of the approach determination may be expanded by including the warning region K based on the actual position in the warning region K based on the estimated position).
[0043] (Step S19) The approach determination means 104c of the management PC 104 issues a warning to the relevant worker or the operator of the cranes 2A, 2B when the distance between the suspended load and the worker is close, or when the cranes 2A, 2B are close to each other.
[0044] The approach warning system 101 according to the second embodiment described above can also achieve substantially the same effects as the first embodiment. Moreover, the approach warning system 101 according to the second embodiment can appropriately determine the approach of the cranes 2A, 2B to each other.
[0045] Although the embodiment of the present invention has been described above, the present invention is not limited to this, and can be practiced within the scope of the claims. The shape of the warning area K in the first and second embodiments was a circular area centered on the tip of the estimated jib 2b. However, the warning area K may be an ellipse, and in particular, it is preferable that the warning area K is an ellipse elongated in the traveling direction of the jib 2b. The size of the warning area K may be adjusted according to the speed at which the jib 2b moves. For example, the size of the warning area K may be increased when the speed at which the jib 2b moves is fast compared to when the speed is slow. [Explanation of symbols]
[0046] 1,101 Approach Warning System 2,2A,2B クレーン 2a Main body 2b ジブ 2b1 ブーム 2b2 ジブ 2c フック 2d mobile means 3 Operator terminal 3A First operator terminal 3B Second operator terminal 4,104 Management PC (Approach Detection Device) 4a,104a Means of communication 4b,104b Position estimation means 4c,104c Approach determination method 5A First location information acquisition method 5B Second location information acquisition method 5C Third location information acquisition method K Warning Area
Claims
1. A proximity warning system that warns of the approach of a worker to a load suspended by a crane, A crane having a jib; A first position information acquisition means for acquiring position information of the worker; an approach determination device that determines whether the suspended load is approaching the worker; and a notification means for notifying at least one of the worker and the crane operator of the determination result, The crane has a moving means, a second position information acquisition means for acquiring position information of a tip end of the jib, and a third position information acquisition means for acquiring position information of a base end of the jib, The approach determination device includes: A position estimation means for estimating the position of the tip end relative to the base end of the jib at a time point after the time point at which the position information was last acquired based on the time-dependent change in the position information of the tip end and base end of the jib; and an approach determination means for determining whether or not the position of the operator on the horizontal plane is included in the warning area, the approach determination means being configured to determine whether or not the position of the operator on the horizontal plane is included in the warning area. The approach warning system is characterized by:
2. The jib is capable of rotating, The position estimation means calculates an angular velocity or an angular acceleration of the jib from a time-dependent change in the position information of the tip of the jib, and estimates a position of the tip of the jib on a horizontal plane based on the calculated angular velocity or angular acceleration.
2. The approach warning system according to claim 1.
3. The jib can perform any one of a raising and lowering motion, a telescopic motion, and a bending motion, The position estimation means calculates a speed or acceleration of the tip from a time-dependent change in the acquired position information of the tip, and estimates a position of the tip of the jib on a horizontal plane based on the calculated speed or acceleration.
3. The approach warning system according to claim 1 or 2.
4. 4. The approach warning system according to claim 1, wherein the warning area is a circular area having a center on the estimated position of the tip portion.
5. The position estimation means further estimates positions of the jibs of other cranes present around the crane, The approach determination means determines whether the cranes are approaching each other.
5. The approach warning system according to claim 1, wherein the approach warning system comprises a first detecting means for detecting an approaching object.
Citation Information
Patent Citations
Location correcting device
JP2002350157A
Jib operation monitoring device of construction machine, jib operation monitoring method of construction machine and operation monitoring system of construction machine
JP2007276996A
Navigation apparatus and estimation method
JP2010096647A
Approach warning system for hanging load of crane and worker
JP2015005152A
Working area management system of mobile crane and working area management method of mobile crane
JP2020111433A