A construction method for wear-resistant and non-slip integral suspended assembled shock-absorbing sports floor
Through the overall suspension assembled shock-absorbing sports floor construction method, the problem of high installation cost of leveling floor mats and skirting boards in the prior art is solved, efficient and environmentally friendly sports floor construction is achieved, and the sports performance and service life of the floor are improved.
Patent Information
- Application Number
- CN201910758238.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-08-16
- Publication Date
- 2025-01-17
- Estimated Expiration
- 2039-08-16
AI Technical Summary
The existing suspended sports wood floor construction method requires the installation of leveling floor mats, which increases construction costs. The installation of skirting boards is not mentioned, which affects the stability of floor performance.
A method of construction of a wear-resistant and non-slip integrated suspension assembled shock-absorbing sports floor, including base layer treatment, elastic rubber pad placement, wooden keel fixation, plywood laying, panel installation and skirting board fixation, etc., to form a suspended overall base structure, reducing the Traditional construction processes improve construction efficiency and floor performance.
It achieves high shock absorption, deformation resistance, and excellent load-bearing performance, reduces construction costs and process complexity, improves the overall motion performance and service life of the floor, and is suitable for rapid construction of new and old renovation venues.
Smart Images

Figure CN110552481B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a construction method of a wear-resistant and non-slip integrally suspended assembled shock-absorbing sports floor. Background Art
[0002] With the advent of the era of "national sports" for sports and fitness, the installation and use of wooden sports floors in sports venues has become more and more common. The overall suspended assembled sports floor is currently a more advanced floor installation construction technology. It is a construction process that separates the base of the sports floor from the building floor. The elastic rubber pad is used as the bottom structural layer. The elastic rubber pad, the wooden keel treated with special technology, and the multi-layer board are fixed with reinforced nails to form a suspended overall base structure. It subverts the construction process of fixing the traditional wooden keel system with rivets or expansion bolts on the building ground, and changes the characteristics of poor shock absorption, elasticity, and sports performance. The surface layer uses finished panels that have been completed in the production workshop through finger jointing and ultraviolet light curing paint technology, and is assembled with tongue and groove, reducing the traditional surface grinding, paint spraying and other construction processes, as well as the problem of poor operation. The suspended structure has the advantages of perfect sports performance, convenient construction, simple and convenient operation, and no process interruption. It is particularly suitable for the paving of new venues and the renovation of old venues. At the same time, it is not affected by climatic conditions and temperature, and can adapt to completing construction in a shorter time.
[0003] The suspended assembled floor adopts mature high-strength polypropylene environmentally friendly materials, which effectively solves the problem of thermal expansion and contraction of the floor while also having stable surface friction. Anti-UV additives are added to each piece of floor to ensure that the floor does not fade under long-term sunlight exposure. The suspended structural design plus the sturdy reinforced support foot structure create an excellent vertical shock absorption effect. The non-slip surface can effectively prevent sports injuries. Good ball rebound performance and ball speed ensure the excellent sports performance of the floor. It can be used to pave ideal high-performance basketball courts, tennis courts, five-a-side football fields, roller skating courts, table tennis courts, as well as volleyball, badminton and other multi-functional courts.
[0004] The overall suspended assembled solid wood sports floor adopts a production process that mainly adopts assembly line production in the production workshop and supplemented by on-site assembly. It changes the various uncertain factors affected by external construction conditions and working environment, and realizes the superiority and controllability of construction quality and construction progress. Compared with traditional fixed keel wood floors, it reduces many processes in on-site construction, and vigorously adapts to the requirements of factory processing and on-site assembly and installation advocated by the country. It not only embodies professionalism, environmental protection and safety, but also embodies the four savings and one environmental protection in the construction industry, and has been rapidly developed and applied.
[0005] CN 106499154 A discloses a suspended sports wooden floor system and a construction method, which comprises a leveling mat, a bottom keel, a shock-absorbing pad, an upper keel, a subfloor, a sound-absorbing and moisture-proof isolation layer and a surface floor arranged from bottom to top, wherein a leveling mat is arranged under the bottom keel and then laid on the ground, an upper keel is vertically arranged at the upper end of the bottom keel and a shock-absorbing pad is arranged at the intersection of the upper keel and the bottom keel, and then the three are fixed, the subfloor is fixed on the upper keel, the sound-absorbing and moisture-proof isolation layer is laid on the subfloor, and the surface floor is arranged on the sound-absorbing and moisture-proof isolation layer and fixed on the subfloor.
[0006] The above patent has good performances such as stable movement and moisture resistance and a long service life. However, the above patent requires the installation of a leveling mat, which increases the construction cost. The skirting board is also a part of the sports wooden floor. The skirting board and the floor must be installed at the same time to ensure the stable performance of the floor. The above patent does not mention the installation of the skirting board. Summary of the invention
[0007] In view of the shortcomings of the prior art, the technical problem to be solved by the present invention is to provide a construction method of an overall suspended assembled shock-absorbing sports floor which has excellent load-bearing performance, high shock absorption performance, anti-deformation performance, high overall motion performance, and is environmentally friendly, safe, wear-resistant and non-slip.
[0008] The technical solution adopted by the present invention to achieve the above-mentioned purpose is: a construction method of a wear-resistant and non-slip integral suspended assembled shock-absorbing sports floor, comprising the following construction steps:
[0009] (I) Construction preparation
[0010] Measure, lay out, and locate according to on-site construction conditions, and prepare construction materials, equipment, and tools;
[0011] (II) Base floor treatment
[0012] Clean up the debris and dust on the base floor, and deal with the uneven parts of the base floor to make the base floor smooth without sand or cracks;
[0013] (III) Marking, grid division, positioning, and precise leveling
[0014] (1) Take the longitudinal axis of the building as the reference line, find the square, divide it vertically with a spacing of 400 mm, and then perform grid positioning in sequence to form a positioning grid;
[0015] (2) Use plywood to accurately level the positioning grid and accurately grind the raised parts to form a leveling layer;
[0016] (IV) Elastic rubber pad placement
[0017] Place elastic rubber pads on the leveling layer according to the grid position, and the direction of placement of the elastic rubber pads should be consistent;
[0018] (V) Placement of wooden keels
[0019] (1) Place the wooden keel on the elastic rubber pad and keep it horizontal with the horizontal axis of the building and perpendicular to the elastic rubber pad;
[0020] (2) The joints of wooden keels are staggered and arranged at intervals;
[0021] (3) Use 30mm nails to fix the wooden keel from both sides of the elastic rubber pad so that the wooden keel and the elastic rubber pad are fixed as a whole;
[0022] (VI) Laying plywood
[0023] (1) Lay the plywood in a direction perpendicular to the wooden keel. The joints of the plywood should be staggered by one third and kept in the middle above the wooden keel.
[0024] (2) The laying sequence should be from one side to the other and fixed. When laying on the surrounding walls, a gap of 10 to 20 mm should be left between the walls.
[0025] (VII) Panel installation
[0026] (1) After laying a non-woven fabric isolation layer on the plywood, install the panel. The installation direction of the panel should be perpendicular to the direction of the plywood;
[0027] (2) During the panel installation process, the groove and the tenon must be completely fastened and fixed with U-shaped nails. The spacing between the U-shaped nails is 400mm. The panel installation width should not exceed 550mm and an expansion joint should be left;
[0028] (3) When encountering wall columns, the panel should maintain a distance of 10mm from the wall or column surface;
[0029] (8) Installation of skirting board
[0030] (1) Check the flatness of the wall surface and adjust the uneven parts of the wall surface;
[0031] (2) The thickness of the skirting board is 8-12mm, the height is 80-120mm, and there is a molding groove on the back. The skirting board surface should be vertical to the base floor, and the top should be kept horizontal;
[0032] (3) Use nails to fix the skirting board. The spacing between the nails should not exceed 500mm, and the nails should penetrate 1-2mm into the skirting board.
[0033] (4) The angle between the inner and outer corners of the skirting board at the inner and outer corners of the wall should be cut into 45°;
[0034] (IX) Panel cleaning and protection
[0035] Clean and protect the installed panels.
[0036] Furthermore, in the step (five), the wooden keel is an antiseptic wooden keel of 40mm*40mm.
[0037] Furthermore, in step (six), the gap between the plywood boards is no larger than 3 mm.
[0038] Furthermore, in step (seven) of step (1), the non-woven fabric is laid in the same direction as the panel installation direction, and the overlap is not less than 100 mm.
[0039] Furthermore, in step (seven) step (2), the width of the expansion joint is 3 mm.
[0040] Furthermore, in step (seven), a gap of 10 mm should be reserved between the first panel and the last panel and the wall when installing the first panel and the last panel.
[0041] The beneficial effects of the wear-resistant and non-slip integral suspended assembled shock-absorbing sports floor construction method of the present invention are:
[0042] As the most advanced sports floor installation and construction technology, the overall suspended assembly structure is a construction process that separates the base of the sports floor from the building floor. The elastic rubber pad is used as the bottom structural layer. By fixing the elastic rubber pad, the wooden keel treated with special technology, the multi-layer board, etc. with reinforced nails, a suspended overall base structure is formed, which subverts the traditional wooden keel system and the building ground with rivets or expansion bolts. The construction process has changed the characteristics of poor shock absorption, elasticity and sports performance; the panel layer uses the finished panel completed by the finger joint process and ultraviolet light curing paint process in the production workshop, and is assembled by combining the tongue and groove structure with U-shaped nails, reducing the traditional surface grinding, paint spraying and other construction processes and the difficulty of not being able to cross-operate; the suspended structure has the advantages of perfect sports performance, convenient construction, simple and convenient operation, no process interval, etc., which is particularly suitable for the paving of new venues with short construction period and fast progress requirements and the renovation of old venues. At the same time, it is not affected by climatic conditions and temperature, and can be more adapted to the application of projects completed in a short time, which can fully reflect the good effects of energy saving and environmental protection.
[0043] The overall suspended assembled solid wood sports floor adopts a unique overall suspended structure, which has no connection with the base of the venue, forming a unique load-bearing base of the overall suspended structure. It scientifically utilizes the principle of wood structural fibers to resist and absorb energy from the outside world, without any damage to the floor structure. At the same time, it ensures the overall elasticity of the sports floor. The elastic rubber pad serves as the bottom structural layer. The appearance and use of this structural layer not only makes the solid wood sports floor more practical, but also provides better shock absorption for the suspension structure of the entire sports floor; it provides higher security and safety factor for athletes' sports, and fully reflects the humanistic and scientific construction technology concept.
[0044] The panel of the overall suspended assembled solid wood sports floor is an important component of the sports floor. The raw materials are Northeast maple with moderate hardness, micro-deformation and long fiber structure. The finger-joining process is used in the production workshop to solve the fundamental problem of bending and deformation of the solid wood panel due to different environmental humidity. The surface board is subjected to the ultraviolet light-curing paint process to make the paint film form a three-dimensional structure with high hardness and good wear resistance. The anti-slip and wear resistance are three to five times that of on-site spray paint. The construction process reduces on-site grinding and paint spraying, shortens the overall construction period by about one-fifth, greatly reduces construction costs, and achieves green, environmental protection and energy saving.
[0045] It reduces the labor intensity of workers, improves work efficiency, and reduces the difficulty of operation. It improves the overall quality and progress of the project, saves materials, labor, and construction period. Compared with the traditional sports floor installation method, it can avoid the damage to the main structure caused by rivets or expansion bolts, extend the service life and maintenance cycle, and reduce the comprehensive cost by 10-20%.
[0046] The present invention enables the sports wooden floor to have better load-bearing performance, high shock absorption performance, and anti-deformation performance, thereby improving the overall sports performance of the sports floor. At the same time, the sports floor is developed in a more professional, environmentally friendly, and safer direction. It is economical, practical, and beautiful, and has good application and promotion prospects. BRIEF DESCRIPTION OF THE DRAWINGS
[0047] Figure 1 It is a flow chart of the construction method of the present invention;
[0048] Figure 2 It is a transverse cross-sectional structural diagram of the present invention. DETAILED DESCRIPTION
[0049] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments;
[0050] like Figure 1 , 2 As shown, a wear-resistant and non-slip integral suspended assembled shock-absorbing sports floor construction method includes the following construction steps:
[0051] (I) Construction preparation
[0052] (1) Construction technicians enter the site to fully understand the construction site conditions, familiarize themselves with the construction drawings, and prepare a special construction plan for the sports floor. After approval by the chief engineer of the construction unit, the plan is submitted to the supervision and construction unit for approval, and labor, supplies, and materials are organized according to the special plan;
[0053] (2) Measure, lay out and locate according to the on-site construction conditions, and check the base floor 1 conditions and various elevations. If any problems are found, they should be raised and solved in a timely manner, and the handover procedures between the various types of work should be completed.
[0054] (3) According to the on-site construction conditions, select appropriate transportation equipment and make all preparations for materials and machinery.
[0055] (4) The overall suspended assembled sports floor has relatively high requirements for materials. Therefore, all parties need to jointly confirm and seal the materials before the materials enter the site: two copies of the samples must be provided before the materials enter the site, and the manufacturer's qualification certificate, quality assurance book, and certificate of conformity must be provided. They must be reported to Party A and the supervision unit for review. After the materials are qualified, the project leaders of the reviewing parties shall sign and confirm on the display board or samples and seal them; the construction unit must inform the supervision unit one day in advance of the materials entering the site. After the materials enter the site, the supervision unit must check and accept the sealed samples before they can be used. Unqualified materials must be withdrawn; after the samples are sealed, the construction unit shall not change the brand, specification, model, or color of the supplied goods. If there are special circumstances, a written application must be made and the replacement can only be made after the consent of Party A.
[0056] (II) Base floor treatment
[0057] Before marking, dividing and positioning, the uneven parts of the base floor 1 should be processed to ensure that the flatness of the base floor 1 meets the construction requirements and there is no sanding or cracking. The integrated floor debris, dust, etc. must be cleaned up to ensure the accuracy of laying out and positioning.
[0058] (II) Marking, grid division, positioning, and precise leveling
[0059] (1) Take the longitudinal axis of the building as the reference line, find the square, divide it vertically with a spacing of 400 mm, and perform grid positioning in turn to form a positioning grid to control the accurate position of the elastic rubber pad 2 and keep the spacing of the wooden keel 3 consistent.
[0060] (2) Use a two-meter level ruler to accurately level the grid according to the positioning grid, and use plywood 4 to level each grid position with an accuracy of within 2 mm; and accurately grind the local raised parts to ensure that the elastic rubber pads 2 are placed on the same horizontal plane to form a leveling layer;
[0061] (IV) Elastic rubber pad placement
[0062] The elastic rubber pad 2 is placed on the leveling layer according to the position of the grid. The direction of placement of the elastic rubber pad 2 should be consistent. After the elastic rubber pad 2 is placed, other construction workers are prohibited from entering the construction area for construction, and the construction area must be kept clean.
[0063] (V) Placement of wooden keels
[0064] (1) Before placing the wooden keels 3, they should be carefully selected. Those that are warped, cracked, knotty, not properly treated with anti-corrosion and anti-insect treatment, and not up to standard in size specifications must be selected to ensure the quality of the project;
[0065] (2) Place the wooden keel 3 on the elastic rubber pad 2 and keep it horizontal with the horizontal axis of the building and perpendicular to the elastic rubber pad 2. The wooden keel 3 is an antiseptic wooden keel 3 of 40 mm*40 mm;
[0066] (3) The joints of the wooden keels are staggered and arranged at intervals, with a spacing of not less than 1000 mm;
[0067] (4) Use 30 mm nails to fix the wooden keel 3 from both sides of the elastic rubber pad 2 so that the wooden keel 3 and the elastic rubber pad 2 are fixed as a whole;
[0068] (VI) Laying plywood
[0069] (1) Before laying plywood 4, the specifications and quality of the incoming materials shall be sampled according to the sealed samples, and the relevant materials such as material test reports and certificates shall be checked to see whether they are complete and valid; the retest reports on the moisture content and formaldehyde content of the materials shall be checked to see whether they are qualified, etc., and only after these are confirmed can the plywood 4 construction be carried out;
[0070] (2) The plywood 4 is laid in a direction perpendicular to the wooden keel 3. The joints of the plywood 4 should be staggered by one third and kept in the middle above the wooden keel 3. The gap between the plywood 4 should not be larger than 3 mm to facilitate fixation and prevent the corners of the subfloor from warping and inequality.
[0071] (3) The laying sequence should be from one side to the other and fixed. When laying on the surrounding walls, a gap of 15 mm should be left between the walls.
[0072] (VII) Panel installation
[0073] (1) To prevent noise and moisture erosion during use, a non-woven fabric 5 is laid on the plywood 4 before installing the panel 6. The installation direction of the panel 6 should be perpendicular to the direction of the plywood 4. The non-woven fabric 5 is laid in the same direction as the panel 6, and the overlap is not less than 100 mm.
[0074] (2) During the installation of panel 6, the groove and the tenon must be completely fastened and fixed with U-shaped nails. The spacing between the U-shaped nails is 400mm. The installation width of panel 6 is not more than 550mm and an expansion joint is left. The width of the expansion joint is 3mm;
[0075] (3) When encountering a wall column, the panel 6 should be kept 10mm away from the wall and column. When installing the first panel 6 and the last panel 6, a 10mm gap should be reserved with the wall to avoid damage to the floor due to thermal expansion and contraction;
[0076] (8) Installation of skirting board
[0077] (1) Check the flatness of the wall surface and adjust the uneven parts of the wall surface;
[0078] (2) The thickness of the skirting board 7 is 10 mm, the height is 100 mm, and there is a molding groove on the back. The surface of the skirting board 7 should be vertical to the base floor 1, and the upper edge should be kept horizontal;
[0079] (3) Use nails to fix the skirting board 7, the spacing between the nails should not exceed 500mm, and the nails should penetrate 72mm into the skirting board;
[0080] (4) The intersection angle of the skirting board 7 at the corners of the wall should be cut into 45 degrees. At the same time, during the installation process, care should be taken not to connect skirting boards 7 with obvious color differences together, and those with scars should be removed.
[0081] (IX) Panel cleaning and protection
[0082] During the construction process, protective measures should be taken in time for the installed panels 6, and the sports floor of the entire floor that has been constructed should be cleaned in time. If other types of work are carried out on it, plywood 4 should be laid to prevent scratches on the panels 6, and it is prohibited to have loaded carts walking on it or heavy objects being dragged on the surface layer, etc., to ensure civilized construction and protection of finished products.
[0083] (X) On-site testing and acceptance
[0084] After the installation of the sports floor is completed, the following requirements should be met;
[0085] (1) Flatness ≤ 2.0 mm, the surface flatness of the site is less than or equal to 2 mm;
[0086] (2) Moisture content <12.8%, less than the local equilibrium moisture content of 12.8;
[0087] (3) Site appearance: Panel 6 assembly gap width ≤ 2.0 mm, Panel 6 joint straightness ≤ 3.0 mm, height difference between adjacent panels 6 ≤ 5.0 mm;
[0088] (4) Coating performance: The color of the coating should not affect the identification of the playing field markings, and the reflection should not affect the performance of athletes.
[0089] (5) Ventilation facilities: The sports floor structure should have ventilation facilities; the facilities should not only provide good ventilation but also be reasonably arranged; they should not be located in unobstructed areas, and their color should be the same or close to that of the 6th layer of panel.
[0090] (6) Anti-deformation measures: Anti-deformation measures should be taken on the 6th layer of the panel to prevent the floor from warping, sinking and other deformations that affect normal use due to changes in the external environment.
[0091] (7) Friction: parameter index: 0.4≤f≤0.7.
[0092] (8) Ball rebound force: Parameter index: ≥90%. When a 600g basketball falls freely on a horizontal cement floor, the rebound force measured is 1. Then the same ball is dropped on the floor for testing, and the minimum rebound force of the ball is 90%.
[0093] (9) Rolling load: When a load of 1500N is applied, the wooden floor should not have any damage such as cracks, breaks, splits, or paint film.
[0094] (XI) Quality requirements and control methods
[0095] (1) The types, specifications and performances of the panel 6, plywood 4, wooden keel 3, elastic rubber pad 2 and other materials shall comply with the design and specification requirements and shall have corresponding performance grade test reports.
[0096] Inspection methods: observation, measurement inspection, inspection of product certificates, on-site verification records, performance test reports and re-inspection reports
[0097] (2) Its supporting materials: non-woven fabric 5, U-shaped nails and other materials should comply with design requirements and relevant standards.
[0098] Inspection method: Check quality certification documents, random sampling of incoming materials for inspection, and review of re-inspection reports
[0099] (3) The base layer must be leveled to ensure that it is placed on the same horizontal plane with a levelness of less than 2 mm.
[0100] Inspection method: Based on the floor reference point, use an infrared level and a steel ruler to measure to ensure that the leveling layer is at the same level.
[0101] (4) The cross-sectional dimensions of the wooden keels 3 of the sports floor, the staggered dimensions of the keel installation joints, the keel spacing, the straightness, and the fixation of the keels to the elastic rubber pads 2 should comply with the design requirements and construction specifications.
[0102] Inspection methods: measurement, observation and on-site pull-out test, etc.
[0103] (5) The installation and laying direction, joint position, joint spacing, fixing position and spacing, material thickness, etc. of the sports floor stabilization layer plywood 4 must comply with the design and specification requirements.
[0104] Inspection method: observation; measurement and on-site inspection to ensure that the plywood 4 is laid vertically on the wooden keel 3, the joint is in the middle of the wooden keel 3, and the joint is staggered by no less than one third.
[0105] (6) The thickness of sports floor panels 6, the installation distance from the wall column and decorative surface, the width and spacing of expansion joints, the spacing of U-shaped nail fixing positions, the width of the board assembly gap, the straightness of the board joints, the height difference between adjacent boards, and the flatness of the finished surface shall comply with the design and specification requirements.
[0106] Inspection methods: observation; measurement and on-site testing
[0107] (7) Friction, ball rebound force, rolling load, coating performance, ventilation facilities, anti-deformation measures, etc. meet the design and specification requirements
[0108] Inspection method: On-site inspection by professional quality supervision and inspection agencies
[0109] (XII) Safety measures
[0110] (1) All construction workers must receive job education before taking up their posts, learn safety technical regulations and rules and regulations, the performance and application of safety protection facilities, the use and storage of personal protective equipment, etc., and can only take up their posts after passing the assessment.
[0111] (2) Personnel entering the construction site must wear work clothes, safety helmets, gloves, goggles, and other labor protection equipment.
[0112] (3) Hand-held power tools should comply with relevant regulations. The power cord, plug and socket should be intact. The power cord must not be extended or replaced at will. The external insulation of the tool must be intact. Maintenance and storage must be the responsibility of a designated person.
[0113] (4) Strictly implement relevant national safety and technical operating procedures and take various corresponding measures to ensure construction safety.
[0114] (XIII) Environmental protection measures
[0115] (1) During the construction process, consciously develop environmental awareness and minimize environmental pollution caused by construction.
[0116] (2) During each shift, designated personnel are assigned to promptly collect and clean up scraps, sawdust, etc., and place them in a centralized location to avoid littering and ensure civilized construction.
[0117] The above embodiments are only for illustrating the technical concept and features of the present invention, and their purpose is to enable ordinary technicians in the field to understand the content of the present invention and implement it accordingly, and they cannot be used to limit the protection scope of the present invention. Any equivalent changes or modifications made based on the essence of the content of the present invention should be included in the protection scope of the present invention.
Claims
1. A construction method for a wear-resistant and non-slip integral suspended assembled shock-absorbing sports floor, characterized in that: The construction steps include: Construction preparation Measure, lay out, and locate according to on-site construction conditions, and prepare construction materials, equipment, and tools; (II) Base floor treatment Clean up the debris and dust on the base floor, and deal with the uneven parts of the base floor to make the base floor smooth without sand or cracks; (III) Line drawing, grid division, positioning and precise leveling (1) Take the longitudinal axis of the building as the reference line, find the square, divide it vertically into equal parts with a spacing of 400 mm, and then perform grid positioning in sequence to form a positioning grid; (2) Use plywood to accurately level the positioning grid and accurately grind the raised parts to form a leveling layer; (IV) Elastic rubber pad placement Place elastic rubber pads on the leveling layer according to the grid position, and the direction of placement of the elastic rubber pads should be consistent; (V) Placement of wooden keels (1) Place the wooden keel on the elastic rubber pad and keep it horizontal with the horizontal axis of the building and perpendicular to the elastic rubber pad; (2) The joints of wooden keels are staggered and arranged at intervals; (3) Use 30mm nails to fix the wooden keel from both sides of the elastic rubber pad so that the wooden keel and the elastic rubber pad are fixed as a whole; 6. Laying plywood (1) Lay the plywood in a direction perpendicular to the wooden keel. The joints of the plywood should be staggered by one third and kept in the middle of the wooden keel. (2) The laying order should be from one side to the other and fixed. When laying on the surrounding walls, a gap of 10 to 20 mm should be left between the walls; the gap between the plywood boards should not be greater than 3 mm; (VII) Panel installation (1) After laying a layer of non-woven fabric isolation layer on the plywood, the panel should be installed. The installation direction of the panel should be perpendicular to the direction of the plywood; the laying of the non-woven fabric should be consistent with the installation direction of the panel, and the overlap should not be less than 100mm; when installing the first and last panels, a gap of 10mm should be reserved with the wall; (2) During the panel installation process, the groove and the tenon must be completely fastened and fixed with U-shaped nails. The spacing between the U-shaped nails is 400mm. The panel installation width is not more than 550mm and an expansion joint is left; the width of the expansion joint is 3mm; (3) When encountering a wall column, the panel should maintain a distance of 10 mm from the wall or column surface; (VIII) Installation of skirting board (1) Check the flatness of the wall surface and adjust the uneven parts of the wall surface; (2) The thickness of the skirting board is 8-12mm, the height is 80-120mm, and there is a molding groove on the back. The skirting board surface should be vertical to the base floor, and the top should be kept horizontal; (3) Use nails to fix the skirting board. The spacing between the nails should not exceed 500mm, and the nails should penetrate 1-2mm into the skirting board. (4) The angle between the inner and outer corners of the skirting board at the inner and outer corners of the wall should be cut into 45°; (IX) Panel cleaning and protection Clean and protect the installed panels.
2. The wear-resistant and non-slip integral suspended assembled shock-absorbing sports floor construction method according to claim 1 is characterized by: In the step (V), the wooden keel is an antiseptic wooden keel of 40mm*40mm.
Citation Information
Patent Citations
Suspension type sports wood floor system and construction method thereof
CN106499154A
Skirting board, skirting line unit and combination method of combined skirting line
CN108952086A
Movable floor
CN201265248Y