A kind of assembled track structure and construction method thereof
The use of anchor bolt positioning fixtures solved the problem of difficult precast column installation, enabling rapid and accurate installation of track engineering, improving construction safety and efficiency, and meeting high-standard track acceptance requirements.
Patent Information
- Application Number
- CN202411162045.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-23
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-08-23
AI Technical Summary
In track engineering construction, the installation of prefabricated columns is difficult, with low positioning accuracy and low construction efficiency, making it difficult to meet the high standards of track geometry and position acceptance requirements. In addition, traditional construction tools have many parts and low precision, making it difficult to achieve rapid and accurate installation.
The anchor bolt positioning fixture structure includes a main frame, an anchoring mechanism, and a fine-tuning mechanism. Through pre-embedded corrugated sleeves and connecting anchor bolts, it achieves precise positioning and rapid installation of precast columns, integrating hoisting, measurement, fine-tuning, and grouting into one unit, simplifying the construction process.
It enables rapid and precise installation of prefabricated columns, meets the accuracy requirements for track acceptance, improves construction safety and efficiency, saves manpower and resources, simplifies construction processes, and reduces labor intensity and construction period.
Smart Images

Figure CN118668744B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of rail transportation, and in particular to an assembled track structure and a construction method thereof. Background Art
[0002] The acceptance standards for track gauge, level, track direction, height and other geometric positions in the track construction acceptance are very high, and the error is generally no more than 2mm. However, due to the narrow construction site in the warehouse, it is difficult to use large construction machinery, and the number of prefabricated columns is large, the volume and weight are large, and a single column can reach more than 300 kilograms, which leads to the problem of difficulty in column installation. At the same time, the prefabricated column track structure is higher than the traditional prefabricated track structure. A slight offset and tilt will have a great impact on the track geometry. It is difficult to install manually, the hoisting efficiency is low, and fine adjustment is difficult. After temporary positioning, the connection part still needs secondary concrete pouring. In addition, traditional track construction tools mostly use gauge rods, screw rods and other tools, which have many parts and low precision. It is difficult to meet the acceptance accuracy requirements and the work efficiency is low when used in forward construction.
[0003] Therefore, it is necessary to provide a prefabricated track structure with high positioning accuracy, lightness and efficiency and a construction method thereof to ensure the positioning accuracy of prefabricated columns and meet the acceptance requirements of track projects. Summary of the invention
[0004] The object of the present invention is to provide an assembled track structure and a construction method thereof, which has a simple structure and a reasonable design, can solve the problem of rapid and accurate installation of the columns of the assembled track structure in forward construction, ensure the basic accuracy of the column installation, thereby realizing the forward construction of the assembled track structure, saving the investment of construction personnel and the entire construction period, and improving construction safety.
[0005] In order to solve the above technical problems, the present invention specifically provides the following technical solutions:
[0006] A construction method for an assembled track structure comprises the following steps:
[0007] S100, after the foundation construction under the civil engineering line is completed, the pouring of the pit floor is inspected to form a cast-in-place floor, and a corrugated sleeve is pre-buried before pouring the concrete of the inspection pit floor, so that two rows of reserved holes are reserved on both sides of the top of the cast-in-place floor after pouring, and each row of reserved holes is divided into multiple groups, each group has four holes, and the four reserved holes are arranged diagonally;
[0008] S200, after the corrugated sleeve is embedded, pour the bottom slab concrete, and reserve the steel bars for the subsequent installation of the retaining wall on the cast-in-place bottom slab. After the civil engineering completes the above steps, re-measure and check the elevation of the cast-in-place bottom slab, the positioning of the embedded corrugated sleeve, and whether there is blockage and water accumulation on the inner wall of the corrugated sleeve;
[0009] S300, surround each group of reserved holes with a template, place a connecting anchor bolt in each reserved hole, and position and adjust the positions of all the connecting anchor bolts;
[0010] S400, after the adjustment is completed, the cement-based grouting material is mixed according to the material requirements, and the grout is poured into the formwork so that the grout fills the formwork and flows from the formwork to the inside of all the reserved holes. After the grouting is completed, the formwork is removed after the grout is filled and reaches the preset strength;
[0011] S500. After the grouting material is cured, the prefabricated columns are transported to the installation site, hoisted, accurately positioned and connected with the pre-buried connecting anchor bolts, and then the four connecting anchor bolts on the prefabricated columns are fixed with double nuts;
[0012] S600. After the prefabricated columns are installed, the iron pads of the fasteners are fixed on the top of the prefabricated columns and tightened, pads are placed on the iron pads, rails are installed on the iron pads on the top of the prefabricated columns and fasteners are installed to complete the installation of the track system.
[0013] As a preferred solution of the present invention, in S300, positioning and adjusting the position and height of the connecting anchor bolt specifically includes the following steps:
[0014] S301, hoisting the anchor bolt positioning tooling structure manufactured in advance to a position at one end of the inspection pit for installing the prefabricated column, and connecting the anchor bolt positioning tooling structure with the connecting anchor bolt;
[0015] S302, according to the measurement and setting out, adjust the height, left and right, front and back of the anchor bolt positioning tooling structure to a preset position;
[0016] S303. After the adjustment is completed, fix the connecting anchor bolts with nuts and start the template installation.
[0017] In order to solve the above technical problems, the present invention further provides the following technical solutions:
[0018] As a preferred embodiment of the present invention, it includes an anchor positioning tooling structure set on the cast-in-place base plate in the step S301, the anchor positioning tooling structure includes a main frame, multiple anchoring mechanisms and multiple fine-adjusting mechanisms for adjusting and supporting the main frame in vertical, horizontal and longitudinal directions, the main frame is detachably installed on the top of the cast-in-place base plate, the main frame includes two longitudinal beams and multiple cross beams, the two longitudinal beams are symmetrically set on the cast-in-place base plate, the multiple cross beams are evenly set between the two longitudinal beams, and the two ends of all the cross beams are respectively fixedly connected to the two longitudinal beams, each of the longitudinal beams is evenly set with multiple positioning steel plates along its length direction at the bottom, and the multiple positioning steel plates are respectively connected to the two ends of the bottom of the multiple cross beams, the multiple anchoring mechanisms are symmetrically set on the top of the two longitudinal beams in pairs, and the two adjacent anchoring mechanisms on each longitudinal beam are respectively located between the two positioning steel plates, the multiple fine-adjusting mechanisms are symmetrically set on the opposite side of the two longitudinal beams in pairs, and all the fine-adjusting mechanisms are located between the two cross beams, wherein the tops of the two cross beams are provided with lifting ears on both sides.
[0019] As a preferred solution of the present invention, anchor bolt connection holes are opened at the four corners of the inner walls of all the positioning steel plates, and connecting anchor bolts for positioning and connecting prefabricated columns are connected in all the anchor bolt connection holes, and all the connecting anchor bolts connected on the positioning steel plates correspond to multiple groups of reserved holes, and all the connecting anchor bolts are threadedly connected with two nuts.
[0020] As a preferred solution of the present invention, column base steel plates are provided at the bottom of all the prefabricated columns, and column positioning holes connected and fixed to all the connecting anchor bolts are opened at the four corners of the bottom of all the column base steel plates.
[0021] As a preferred solution of the present invention, the structures of all the fine-adjustment mechanisms are the same, and the fine-adjustment mechanisms include a supporting base, a connecting plate, a height adjustment screw, a lateral adjustment movable assembly and a longitudinal adjustment movable assembly, the connecting plate is fixed on the side wall of the longitudinal beam, the height adjustment screw passes through the connecting plate and is threadedly connected to the connecting plate, the lateral adjustment movable assembly is installed at the bottom end of the height adjustment screw, the longitudinal adjustment movable assembly is installed at the bottom end of the lateral adjustment movable assembly, and the supporting base is installed at the bottom of the longitudinal adjustment movable assembly.
[0022] As a preferred solution of the present invention, all the anchoring mechanisms have the same structure, and the anchoring mechanisms include a screw rod and a locking nut, the screw rod is threadedly connected to the longitudinal beam, and the locking nut is threadedly connected to the screw rod.
[0023] As a preferred solution of the present invention, all the longitudinal beams are provided with a prism mounting base matching the total station, a measuring prism can be installed on each prism mounting base, and the longitudinal centers of the prism mounting base and the positioning steel plate are located on the same axis.
[0024] As a preferred solution of the present invention, the cross-sectional shape of all the longitudinal beams is I-shaped, and fixed columns are fixedly connected inside two of the longitudinal beams, and the fixed columns are respectively located at the center positions of the connection points of all the longitudinal beams and the positioning steel plates, and grouting holes are opened inside all the fixed columns, and the upper and lower ends of the grouting holes respectively penetrate and connect the longitudinal beams and the positioning steel plates.
[0025] Compared with the prior art, the present invention has the following beneficial effects:
[0026] 1. Compared with the prior art, the construction accuracy of embedded connectors in traditional projects is often low, while the acceptance standards for track gauge, level, track direction, height and other geometric positions in track engineering are very high, and the error is generally not more than 2mm. The anchor bolt positioning tooling structure provided in the present invention can determine the coordinates, elevations and angular positioning in batches, quickly and accurately, thereby ensuring that the accuracy requirements of track acceptance are met.
[0027] 2. Compared with the prior art, traditional track construction tools mostly use gauge rods, screw rods and other tools, which have many parts and low precision. The present invention integrates lifting, measurement, fine adjustment, anchoring and grouting, and can complete multiple construction steps on one tool. It has high integration, simple structure and high reliability, which improves construction safety, enhances construction efficiency, reduces labor intensity, saves construction personnel input and the entire construction period.
[0028] 3. The present invention can realize bottom-up forward construction by using this embodiment. Through accurate pre-embedded connectors, dry construction without concrete operation is realized during the subsequent installation of prefabricated columns. The connection method is simple, which significantly improves the construction safety and convenience and realizes assembly construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] In order to more clearly illustrate the implementation methods of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for the implementation methods or the description of the prior art. Obviously, the drawings in the following description are only exemplary, and for ordinary technicians in this field, other implementation drawings can be derived from the provided drawings without creative work.
[0030] Figure 1 A three-dimensional structural schematic diagram of an assembled track structure is provided for an embodiment of the present invention;
[0031] Figure 2 A schematic diagram of the connection structure between a cast-in-place base plate and an anchor bolt positioning tooling structure is provided for an embodiment of the present invention;
[0032] Figure 3 A three-dimensional structural schematic diagram of an anchor bolt positioning tooling structure is provided for an embodiment of the present invention;
[0033] Figure 4 Provided for embodiments of the present invention Figure 3 A magnified view of the structure at A;
[0034] Figure 5 A schematic diagram of the connection structure of a prefabricated column and a column base steel plate is provided for an embodiment of the present invention;
[0035] Figure 6 A front structural cross-sectional view of an anchor bolt positioning tooling structure is provided for an embodiment of the present invention;
[0036] Figure 7 A schematic diagram of a use status of an assembled track structure is provided for an embodiment of the present invention.
[0037] The numbers in the figure represent the following: 1. Main frame; 101. Longitudinal beam; 102. Horizontal beam; 103. Lifting ear; 104. Prism mounting base; 105. Fixed column; 106. Grouting hole; 2. Fine adjustment mechanism; 201. Connecting plate; 202. Height adjustment screw; 203. Lateral adjustment moving assembly; 204. Longitudinal adjustment moving assembly; 3. Anchoring mechanism; 301. Screw rod; 302. Locking nut; 4. Positioning steel plate; 401. Anchor bolt connecting hole; 5. Track system; 6. Prefabricated column; 7. Connecting anchor bolt; 8. Cast-in-place base plate; 10. Column foot steel plate; 11. Reserved hole. DETAILED DESCRIPTION
[0038] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0039] like Figures 1 to 7 As shown, the present invention provides a construction method of an assembled track structure, comprising the following steps:
[0040] S100, after the foundation construction under the civil engineering line is completed, the pouring of the pit floor is checked to form a cast-in-place bottom plate 8, and a corrugated sleeve is pre-buried before pouring the concrete of the inspection pit floor plate, so that two rows of reserved holes 11 are reserved on both sides of the top of the cast-in-place bottom plate 8 after pouring, and each row of reserved holes 11 is divided into multiple groups, each group has four holes, and the four reserved holes 11 are diagonally arranged;
[0041] S200, after the corrugated sleeve is pre-embedded, the base plate concrete is poured, and at the same time, steel bars for the subsequent installation of the retaining wall are reserved on the cast-in-place base plate 8. After the above steps are completed in the civil construction, the elevation of the cast-in-place base plate 8, the positioning of the pre-embedded corrugated sleeve, and whether the inner wall of the corrugated sleeve is blocked or has water accumulation are re-measured;
[0042] S300, surrounding each group of reserved holes 11 with a template, placing a connecting anchor bolt 7 in each reserved hole 11, and positioning and adjusting the positions of all connecting anchor bolts 7;
[0043] S400, after the adjustment is completed, mix the cement-based grouting material according to the material requirements, and pour the grout into the template so that the grout fills the template and flows from the template to the inside of all the reserved holes 11. After the grouting is completed, the template is removed after the grout is filled and reaches the preset strength;
[0044] S500, after the grouting material is cured, the prefabricated column 6 is transported to the installation site, the prefabricated column 6 is hoisted, the prefabricated column 6 is accurately positioned and connected with the pre-buried connecting anchor bolts 7, and then the four connecting anchor bolts 7 on the prefabricated column 6 are fixed with double nuts;
[0045] S600, after the prefabricated column 6 is installed, the iron pad of the fastener is fixed on the top of the prefabricated column 6 and tightened, a pad is placed on the iron pad, the rail is installed on the iron pad on the top of the prefabricated column 6 and the fastener is installed to complete the installation of the track system 5.
[0046] Specifically, in S300, positioning and adjusting the position and height of the connecting anchor bolt 7 specifically includes the following steps:
[0047] S301, hoisting the anchor bolt positioning tooling structure manufactured in advance to a position at one end of the inspection pit for installing the prefabricated column 6, and connecting the anchor bolt positioning tooling structure with the connecting anchor bolt 7;
[0048] S302, according to the measurement and setting out, adjust the height, left and right, front and back of the anchor bolt positioning tooling structure to a preset position;
[0049] S303. After the adjustment is completed, the connecting anchor bolt 7 is fixed by a nut and the template installation begins.
[0050] Embodiment 2:
[0051] like Figure 2-Figure 4 , Figure 6As shown, a construction method of an assembled track structure of the present invention also includes an anchor bolt positioning tooling structure set on the cast-in-place bottom plate 8 in step S301, the anchor bolt positioning tooling structure includes a main frame 1, multiple anchoring mechanisms 3 and multiple fine adjustment mechanisms 2 for vertically, horizontally and longitudinally adjusting and supporting the main frame 1, the main frame 1 can be detachably installed on the top of the cast-in-place bottom plate 8, the main frame 1 includes two longitudinal beams 101 and multiple cross beams 102, the two longitudinal beams 101 are symmetrically arranged on the cast-in-place bottom plate 8, the multiple cross beams 102 are evenly arranged between the two longitudinal beams 101, and both ends of all the cross beams 102 are respectively It is fixedly connected to the two longitudinal beams 101, and multiple positioning steel plates 4 are evenly arranged at the bottom of each longitudinal beam 101 along its length direction, and multiple positioning steel plates 4 are respectively connected to the bottom ends of multiple cross beams 102, multiple anchoring mechanisms 3 are symmetrically arranged on the top of the two longitudinal beams 101, and two adjacent anchoring mechanisms 3 on each longitudinal beam 101 are respectively located between the two positioning steel plates 4, multiple fine adjustment mechanisms 2 are symmetrically arranged on the opposite side of the two longitudinal beams 101, and all fine adjustment mechanisms 2 are located between the two cross beams 102, and the tops of the two cross beams 102 are both provided with lifting ears 103. It is convenient to move the anchor bolt positioning tooling structure.
[0052] The main frame 1 is composed of two mutually parallel longitudinal beams 101 and multiple mutually parallel cross beams 102, and the longitudinal beams 101 and the cross beams 102 are in a horizontal plane and perpendicular to each other, and their connecting nodes are welded in the factory, so as to ensure that the main frame 1 is a stable space frame. The main frame 1 can be used to locate the pre-installation position of the prefabricated column 6, and the positioning steel plate 4 can be installed with the connecting anchor bolts 7 for locating and connecting the prefabricated column 6, and the connecting anchor bolts 7 can be accurately embedded. The fine-adjusting mechanism 2 is used to adjust and support the main frame 1 in the vertical, horizontal and longitudinal directions, and cooperates with the anchoring mechanism 3 to temporarily fix the entire anchor bolt positioning tooling structure after the fine-adjustment is completed, so that the anchor bolt positioning tooling structure is stable and not easily disturbed during the positioning process.
[0053] The present invention is used for accurately positioning the prefabricated column 6, connecting the anchor bolt 7 and the installation base platform, and can realize accurate positioning of the prefabricated column 6 before installation, and ensure that the prefabricated column 6 and the rail meet the relevant rail acceptance standards after installation. The arrangement of the anchor bolt positioning tooling structure can reduce the weight as much as possible while meeting the positioning accuracy, so that the movement is more labor-saving and the work efficiency is higher in the actual use of the whole project, which saves manpower consumption, saves materials, and reduces costs.
[0054] Anchor bolt connection holes 401 are opened at the four corners of the inner walls of all the positioning steel plates 4, and all the anchor bolt connection holes 401 are connected with connection anchor bolts 7 for positioning and connecting the prefabricated columns 6. The connection anchor bolts 7 connected to all the positioning steel plates 4 correspond to the multiple groups of reserved holes 11, and all the connection anchor bolts 7 are threadedly connected with two nuts.
[0055] A column foot steel plate 10 is provided at the bottom of all prefabricated columns 6 , and column positioning holes for connecting and fixing with all connecting anchor bolts 7 are opened at the four corners of the bottom of all column foot steel plates 10 .
[0056] All longitudinal beams 101 are provided with prism mounting bases 104 matching the total station, each prism mounting base 104 is mounted with a measuring prism, and the longitudinal centers of the prism mounting base 104 and the positioning steel plate 4 are located on the same axis.
[0057] The positioning steel plate 4 is welded to the bottom of the connection node between the longitudinal beam 101 and the cross beam 102, and the connecting anchor bolt 7 is detachably connected to the positioning steel plate 4 through the anchor bolt connecting hole 401; the positioning steel plates 4 of the anchor bolt positioning tooling structure are arranged in pairs, and can be arranged in two pairs, three pairs, four pairs, etc. according to the construction conditions. Since the connecting anchor bolt 7 is connected to the positioning steel plate 4, and the positioning steel plate 4 is fixedly installed at the bottom of the main frame 1, their relative position relationship is fixed, and the measuring prism is installed on the prism mounting base 104 on the main frame 1, which can accurately reflect the installation position of the connecting anchor bolt 7.
[0058] Before installing the prefabricated columns 6, the present invention needs to first complete the pouring of the cast-in-place base plate 8, and then accurately pre-embed four connecting anchor bolts 7 at the foundation position for installing each prefabricated column 6 on the cast-in-place base plate 8, and pour grouting material to complete the positioning of the prefabricated columns 6. Therefore, when the anchor bolt positioning tooling structure of the present invention is used, first connect the positioning steel plate 4 with the connecting anchor bolt 7 through the anchor bolt connecting hole 401, and fix each connecting anchor bolt 7 to the positioning steel plate 4 through the upper and lower two nuts, connect the four lifting ears 103 on the main frame 1 with a hanger through a rope, and move the anchor bolt positioning tooling structure to the corresponding connection reserved with the cast-in-place base plate 8 The reserved hole 11 of the connecting anchor bolt 7 corresponds to the approximate position, and then the connecting anchor bolt 7 is placed in the reserved hole 11 on the cast-in-place bottom plate 8. The diameter of the reserved hole 11 on the cast-in-place bottom plate 8 is larger than that of the connecting anchor bolt 7, which can match the fine adjustment range of the anchor bolt positioning tooling structure; before fine-tuning the connecting anchor bolt 7 using the fine adjustment mechanism 2, a measuring prism is installed on all prism mounting bases 104, and the coordinates and elevation of the measuring prism on the prism mounting base 104 installed on the main frame 1 are measured using the total station arranged in the measurement system, so as to accurately reflect the offset amount that needs to be adjusted in the horizontal, vertical and longitudinal directions of the connecting anchor bolt 7. Then, the position of the main frame 1 is adjusted by the fine adjustment mechanism 2, thereby adjusting the positions of several pairs of positioning steel plates 4, and realizing the position adjustment of several pairs of connecting anchor bolts 7 corresponding thereto.
[0059] The structures of all fine-adjusting mechanisms 2 are the same. The fine-adjusting mechanism 2 includes a supporting base, a connecting plate 201, a height adjustment screw 202, a lateral adjustment moving assembly 203 and a longitudinal adjustment moving assembly 204. The connecting plate 201 is fixed to the side wall of the longitudinal beam 101, the height adjustment screw 202 passes through the connecting plate 201 and is threadedly connected to the connecting plate 201, the lateral adjustment moving assembly 203 is installed at the bottom end of the height adjustment screw 202, the longitudinal adjustment moving assembly 204 is installed at the bottom end of the lateral adjustment moving assembly 203, and the supporting base is installed at the bottom of the longitudinal adjustment moving assembly 204.
[0060] The support base is used to support the entire fine-adjustment mechanism 2 and the main frame 1, and before fine-adjustment, the main frame 1 is placed on the cast-in-place base plate 8. When fine-adjusting, the height adjustment screws 202 on multiple fine-adjustment mechanisms 2 are adjusted respectively, so that the height positions of all fine-adjustment mechanisms 2 can be adjusted. Since all fine-adjustment mechanisms 2 are connected to the main frame 1, the height of the main frame 1 can also be adjusted synchronously to achieve the adjustment of the vertical offset of all connecting anchor bolts 7; by adjusting the lateral adjustment moving groups on all fine-adjustment mechanisms 2 Component 203 can adjust the lateral movement position of the fine-adjusting mechanism 2. Since all the fine-adjusting mechanisms 2 are connected to the main frame body 1, the main frame body 1 can also move laterally, thereby realizing the adjustment of the lateral offset of the connecting anchor bolt 7; by adjusting the longitudinal adjustment movement on all the fine-adjusting mechanisms 2, the longitudinal movement position of the fine-adjusting mechanism 2 can be adjusted. Since all the fine-adjusting mechanisms 2 are connected to the main frame body 1, the main frame body 1 can move longitudinally accordingly, thereby realizing the adjustment of the longitudinal offset of all the connecting anchor bolts 7 installed on the main frame body 1.
[0061] When the height and lateral position of the connecting anchor bolts 7 of the main frame 1 are adjusted by using the four fine adjustment mechanisms 2, four operators synchronously rotate the height adjustment screws 202, the lateral adjustment moving assembly 203 and the longitudinal adjustment moving assembly 204 on the four fine adjustment mechanisms 2 clockwise or counterclockwise to adjust the positions of the main frame 1 and all the connecting anchor bolts 7 on the main frame 1 in four directions: lateral, vertical and longitudinal. This achieves adjustment of the offset of all the connecting anchor bolts 7 on the anchor bolt positioning tooling structure in the lateral, vertical and longitudinal directions, ensuring the balance of the adjusted offset.
[0062] All anchoring mechanisms 3 have the same structure. The anchoring mechanisms 3 include a screw rod 301 and a locking nut 302 . The screw rod 301 is threadedly connected to the longitudinal beam 101 , and the locking nut 302 is threadedly connected to the screw rod 301 .
[0063] When the positions of the main frame 1 and the connecting anchor bolts 7 are accurately adjusted, the anchor mechanism 3 is placed directly below the cast-in-place base plate 8, and a hole is drilled using an electric drill. The screw rod 301 on the anchor mechanism 3 is then rotated to screw the bottom of the anchor mechanism 3 into the drilled hole, and the temporary anchoring of the anchor bolt positioning tooling structure is completed through the enlarged head on the top of the anchor mechanism 3.
[0064] The cross-sectional shape of all longitudinal beams 101 is I-shaped, and two longitudinal beams 101 are fixedly connected with fixing columns 105, and the fixing columns 105 are respectively located at the center of the connection points of all longitudinal beams 101 and the positioning steel plates 4. Grouting holes 106 are opened in all fixing columns 105, and the upper and lower ends of the grouting holes 106 pass through and connect the longitudinal beams 101 and the positioning steel plates 4 respectively.
[0065] After the main frame 1 and all the connecting anchor bolts 7 are positioned and temporarily fixed, the gaps between all the positioning steel plates 4 and the cast-in-place bottom plate 8 are enclosed by templates, and then grouting material is injected into the grouting holes 106 in the middle of the positioning steel plates 4. The grouting material enters the space enclosed by the templates on the cast-in-place bottom plate 8 through the grouting holes 106, and is diverted to the reserved holes 11 around it, filling the reserved holes 11 of the connecting anchor bolts 7 on the cast-in-place bottom plate 8 and the gaps at the bottom of the positioning steel plates 4. After the grouting material reaches the strength, the connecting anchor bolts 7 can be reliably connected to the cast-in-place bottom plate 8. At the same time, the top surface of the grouting material can form a column support surface, and the nuts used to temporarily fix the connecting anchor bolts 7 above the anchor bolt connection holes 401 in the positioning steel plates 4 are removed, and the movable anchor bolt positioning tooling structure can be disassembled and moved to other sections of the line for construction.
[0066] After completing the precise positioning and pre-embedding of all the connecting anchor bolts 7, the installation of the prefabricated column 6 can be carried out. The installation of the prefabricated column 6 can be completed by matching the four anchor bolt connection holes 401 on the column foot steel plate 10 at the bottom of the prefabricated column 6 with the connecting anchor bolts 7 on the cast-in-place bottom plate 8 one by one and then connecting and fixing them through nuts. The present invention adopts an assembled structure with fast installation speed, high precision, saving construction period, fast work efficiency and safe construction. The setting of the anchor bolt positioning tooling structure enables the connecting anchor bolt 7 and the top surface of the grouting material to be accurately positioned, realizing the positioning and installation of the prefabricated column 6. The connection method is safe and convenient, greatly simplifies the construction steps, simplifies the construction equipment, and realizes the real assembled structure from the installation of prefabricated components to the assembly construction; it is convenient for flow operation, improves the safety, convenience and work efficiency of construction; and cancels the two ground beams of the traditional inspection pit, reduces the depth of the ditch, reduces the amount of masonry, and saves the cost; and adopts a sophisticated temporary support, which can conveniently and quickly adjust the connecting anchor bolt 7, and solve the problem of difficult control of the accuracy of the embedded foundation.
[0067] The above embodiments are only exemplary embodiments of the present application and are not intended to limit the present application. The protection scope of the present application is defined by the claims. Those skilled in the art may make various modifications or equivalent substitutions to the present application within the essence and protection scope of the present application, and such modifications or equivalent substitutions shall also be deemed to fall within the protection scope of the present application.
Claims
1. A construction method for an assembled track structure, characterized in that: The following steps are involved: S100, after the foundation construction under the civil engineering line is completed, the pouring of the pit floor is checked to form a cast-in-place floor (8), and a corrugated sleeve is pre-buried before pouring the concrete of the inspection pit floor, so that two rows of reserved holes (11) are reserved on both sides of the top of the cast-in-place floor (8) after pouring, and each row of reserved holes (11) is divided into a plurality of groups, each group has four holes, and the four reserved holes (11) are arranged diagonally; S200, after the corrugated sleeve is pre-embedded, the base plate concrete is poured, and at the same time, steel bars for the subsequent installation of the retaining wall are reserved on the cast-in-place base plate (8). After the civil construction completes the above steps, the elevation of the cast-in-place base plate (8), the positioning of the pre-embedded corrugated sleeve, and whether the inner wall of the corrugated sleeve is blocked or has water accumulation are re-measured; S300, placing a template around the periphery of each group of reserved holes (11), placing a connecting anchor bolt (7) in each reserved hole (11), and positioning and adjusting the positions of all the connecting anchor bolts (7); In S300, positioning and adjusting the position and height of the connecting anchor bolt (7) specifically includes the following steps: S301, hoisting the prefabricated anchor bolt positioning tooling structure to a position at one end of the inspection pit for installing the prefabricated column (6), and connecting the anchor bolt positioning tooling structure to the connecting anchor bolt (7); S302, according to the measurement and setting out, adjust the height, left and right, front and back of the anchor bolt positioning tooling structure to a preset position; S303, after the adjustment is completed, the connecting anchor bolt (7) is fixed by a nut, and the template installation begins; The invention comprises an anchor bolt positioning fixture structure arranged on the cast-in-place base plate (8) in the step S301, wherein the anchor bolt positioning fixture structure comprises a main frame (1), a plurality of anchoring mechanisms (3) and a plurality of fine adjustment mechanisms (2) for adjusting and supporting the main frame (1) in the vertical, horizontal and longitudinal directions, wherein the main frame (1) is detachably mounted on the top of the cast-in-place base plate (8), wherein the main frame (1) comprises two longitudinal beams (101) and a plurality of cross beams (102), wherein the two longitudinal beams (101) are symmetrically arranged on the cast-in-place base plate (8), and the plurality of cross beams (102) are evenly arranged between the two longitudinal beams (101), and both ends of all the cross beams (102) are respectively fixed to the two longitudinal beams (101). The plurality of positioning steel plates (4) are evenly arranged at the bottom of each longitudinal beam (101) along its length direction, and the plurality of positioning steel plates (4) are respectively connected to the two ends of the bottom of the plurality of cross beams (102); the plurality of anchoring mechanisms (3) are symmetrically arranged at the top of the two longitudinal beams (101), and two adjacent anchoring mechanisms (3) on each longitudinal beam (101) are respectively located between the two positioning steel plates (4); the plurality of fine adjustment mechanisms (2) are symmetrically arranged at opposite sides of the two longitudinal beams (101), and all the fine adjustment mechanisms (2) are located between the two cross beams (102); and the tops of the two cross beams (102) are both provided with lifting ears (103); All of the fine adjustment mechanisms (2) have the same structure. The fine adjustment mechanisms (2) comprise a support base, a connecting plate (201), a height adjustment screw (202), a lateral adjustment moving assembly (203) and a longitudinal adjustment moving assembly (204), wherein the connecting plate (201) is fixed to the side wall of the longitudinal beam (101), the height adjustment screw (202) passes through the connecting plate (201) and is threadedly connected to the connecting plate (201), the lateral adjustment moving assembly (203) is mounted at the bottom end of the height adjustment screw (202), the longitudinal adjustment moving assembly (204) is mounted at the bottom end of the lateral adjustment moving assembly (203), and the support base is mounted at the bottom of the longitudinal adjustment moving assembly (204); S400, after the adjustment is completed, the cement-based grouting material is mixed according to the material requirements, and the grout is poured into the formwork so that the grout fills the formwork and flows from the formwork to the inside of all the reserved holes (11). After the grouting is completed, the formwork is removed after the grout is filled and reaches a preset strength; S500, after the grouting material is cured, the prefabricated column (6) is transported to the installation site, the prefabricated column (6) is hoisted, the prefabricated column (6) is accurately positioned and connected with the pre-buried connecting anchor bolts (7), and then the four connecting anchor bolts (7) on the prefabricated column (6) are fixed with double nuts; S600, after the prefabricated column (6) is installed, the iron pad of the fastener is fixed on the top of the prefabricated column (6) and tightened, a pad is placed on the iron pad, the rail is installed on the iron pad on the top of the prefabricated column (6) and the fastener is installed to complete the installation of the track system (5).
2. The construction method of a prefabricated track structure according to claim 1, characterized in that: All of the positioning steel plates (4) have anchor connection holes (401) at the four corners of the inner walls, and all of the anchor connection holes (401) are connected with connection anchors (7) for positioning and connecting prefabricated columns (6). The connection anchors (7) connected to all of the positioning steel plates (4) correspond to the multiple groups of reserved holes (11), and all of the connection anchors (7) are threadedly connected with two nuts.
3. The construction method of a prefabricated track structure according to claim 1, characterized in that: A column base steel plate (10) is provided at the bottom of all the prefabricated columns (6), and column positioning holes for connecting and fixing with all the connecting anchor bolts (7) are provided at the four corners of the bottom of all the column base steel plates (10).
4. The construction method of a prefabricated track structure according to claim 1, characterized in that: All of the anchoring mechanisms (3) have the same structure. The anchoring mechanisms (3) comprise a screw rod (301) and a locking nut (302). The screw rod (301) is threadedly connected to the longitudinal beam (101), and the locking nut (302) is threadedly connected to the screw rod (301).
5. The construction method of an assembled track structure according to claim 1, characterized in that: All the longitudinal beams (101) are provided with a prism mounting base (104) matching the total station, a measuring prism can be mounted on each of the prism mounting bases (104), and the longitudinal centers of the prism mounting bases (104) and the positioning steel plate (4) are located on the same axis.
6. The construction method of a prefabricated track structure according to claim 1, characterized in that: The cross-sectional shape of all the longitudinal beams (101) is an I-shape, and two longitudinal beams (101) are fixedly connected with fixing columns (105) inside, and the fixing columns (105) are respectively located at the center position of the connection point between all the longitudinal beams (101) and the positioning steel plate (4), and all the fixing columns (105) are provided with grouting holes (106) inside, and the upper and lower ends of the grouting holes (106) respectively penetrate and connect the longitudinal beam (101) and the positioning steel plate (4).
7. An assembled track structure, characterized in that: Obtained by the construction method described in any one of claims 1-6.
Citation Information
Patent Citations
Fabricated maintenance stand column, train maintenance platform and construction method of train maintenance platform
CN110512922A
Subway prefabricated stand column type inspection pit structure and construction method
CN112240111A
Assembly type prefabricated stand column inspection pit structure capable of being constructed in forward direction and construction method
CN117005729A
Precast concrete track stand column of stand column type inspection pit
CN213953148U
Column foot bolted prefabricated hollow square column type inspection pit capable of being constructed in forward direction
CN219864319U