Building construction path optimization method based on ant colony algorithm

The construction path optimization method based on the ant colony algorithm solves the shortcomings of existing technology in dealing with complex environments and unpredictable factors, achieves dynamic adjustment of construction paths and resource optimization, improves construction efficiency and safety, and provides data driven decision support.

CN118798459AInactive Publication Date: 2024-10-18SHAOXING MINGDING DECORATION ENG CO LTD
View PDF 0 Cites 5 Cited by

Patent Information

Application Number
CN202410895918.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-05
Publication Date
2024-10-18
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Existing building construction path optimization methods have shortcomings in dealing with complex environments and unpredictable factors, lack of dynamic adjustment capabilities, ignore environmental factors and human factors, and insufficient technology integration and data processing capabilities, resulting in low efficiency and safety risks.

Method used

The construction path optimization method based on the ant colony algorithm is adopted. By defining the construction optimization goals, the construction site is abstracted into a graph model, the ant colony algorithm is customized, the volatilization speed and intensity of the pheromone are adjusted, real-time monitoring data and environmental factors are integrated, and multiple Goal optimization, dynamically adjusting path selection, and using machine learning methods to adjust algorithm parameters.

Benefits of technology

Significantly improves the efficiency and safety of construction management, can dynamically adjust paths to adapt to environmental changes, optimize resource allocation, reduce costs and delays, improve construction site safety, provide a data-driven decision support system, and enhance the accuracy and accuracy of decision-making. effectiveness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118798459A_ABST
    Figure CN118798459A_ABST
Patent Text Reader

Abstract

The invention relates to a building construction path optimization method, in particular to a building construction path optimization method based on an ant colony algorithm. Firstly, a construction optimization target is defined, a building construction site is abstracted into a graph model, each construction point serves as a node, a route for connecting the nodes serves as an edge, each edge is endowed with a weight, and the weight is distance, cost, time or risk; then customizing an optimized ant colony algorithm, adapting to the change of a construction environment by adjusting the volatilization speed and intensity of pheromones and a heuristic function, implementing multi-objective optimization, and synthesizing cost, time and safety factors; the system further comprises a dynamic adjustment mechanism for path selection, and integrates real-time monitoring system data and external environment factors, including weather and emergency situations, so as to dynamically adjust a path selection strategy. Algorithm parameters are adjusted by using a machine learning method, the path calculation efficiency is improved, and the requirements of different construction scenes are met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to a construction path optimization method, in particular to a construction path optimization method based on an ant colony algorithm. Background Art

[0002] In modern construction management, path optimization is a key link, which directly affects the efficiency, cost, safety and completion time of engineering projects. Although existing construction path optimization methods have made progress in some aspects, these methods still have shortcomings and drawbacks, especially in dealing with complex environments and unpredictable factors. The shortcomings of existing methods are elaborated in detail below. First, traditional path optimization methods often rely on simplified or idealized assumptions. For example, many methods assume that all resources are available at any time, ignoring the uncertainty in the supply chain, the real-time availability of resources and their dynamic changes. This assumption may work in theory, but in reality, the resource allocation on the construction site is affected by many factors, such as weather conditions, the reliability of suppliers, and delays in other construction activities. When these external variables change, the original optimization model may not be able to adapt, resulting in inefficiency in actual operation. Secondly, the lack of dynamic adjustment capabilities is an important shortcoming of traditional methods. Many path optimization models are designed and fixed before the project starts, and it is difficult to adapt to changes that occur during project execution. For example, if an unexpected underground pipeline appears, the construction path may need to be adjusted immediately, but traditional models often lack this immediate response capability and cannot dynamically adjust the plan to reduce delays and additional costs. Furthermore, insufficient consideration of environmental factors is also a problem. In construction, environmental factors such as weather conditions and terrain features have a significant impact on construction progress and safety. However, most existing optimization models do not effectively integrate these factors. For example, strong winds or rainy days may affect the safety and feasibility of certain construction activities, and traditional methods may not be able to predict such effects, leading to safety risks and construction delays. In addition, the challenge of technology integration cannot be ignored. Although technological advances have provided new possibilities for path optimization, such as the application of technologies such as the Internet of Things (IoT) and artificial intelligence (AI), the integration and implementation of these advanced technologies is a challenge in itself. Technology integration requires a large initial investment and also requires the construction team to have relevant technical knowledge, which is a considerable threshold for many construction companies. More importantly, the limitation of data processing and analysis capabilities is also a key weakness of existing methods. Optimizing construction paths requires processing a large amount of complex data and extracting useful information from it. This requires not only strong data processing capabilities, but also advanced analytical methods to understand the patterns behind the data. Although some modern methods have begun to use data-driven decision support systems, the effectiveness of these systems depends largely on the quality of the data and the advancement of the analytical methods.

[0003] In addition, human factors and management issues are also issues that cannot be ignored. Construction path optimization is not only a technical issue, but also a management challenge. In actual operation, the effectiveness of construction management is affected by teamwork, communication, and personal experience and judgment. Traditional optimization methods often ignore these human factors, which may lead to poor optimization results in practical applications. Summary of the invention

[0004] The purpose of the present invention is to provide a construction path optimization method based on ant colony algorithm, so as to solve some of the drawbacks and shortcomings pointed out in the background technology.

[0005] The present invention solves the above-mentioned technical problems by adopting the following technical solutions: firstly, by defining the construction optimization target and abstracting the construction site into a graph model, each construction point is a node, the route connecting the nodes is an edge, and a weight is assigned to each edge, the weight being distance, cost, time or risk;

[0006] Then, a customized optimized ant colony algorithm was used to adapt to changes in the construction environment by adjusting the evaporation speed and intensity of pheromones and heuristic functions, and to implement multi-objective optimization while integrating cost, time and safety factors;

[0007] further including a dynamic adjustment mechanism for route selection that integrates real-time monitoring system data and external environmental factors, including weather and emergency situations, to dynamically adjust the route selection strategy;

[0008] By using machine learning methods to adjust algorithm parameters, the efficiency of path calculation can be improved and adapted to the needs of different construction scenarios.

[0009] Furthermore, the definition of construction optimization objectives includes:

[0010] S1. First, set the construction optimization goal as:

[0011]

[0012] Where S(t) is the function of safety over time, C, T and R represent the total cost, total time and risk assessment respectively, a 1 ,a 2 ,a 3 ,a 4 and λ are coefficients that adjust the relative importance of these factors;

[0013] S2, then build a graph G(V,E) where each edge e ij The weight of is given by the formula:

[0014]

[0015] Calculate, where dij ,c ij ,t ij ,r ij They represent the distance, cost, time and risk of the edge respectively. The fidelity of the calculation is enhanced by introducing nonlinear parameters and trigonometric functions.

[0016] S3. The final formula for dynamic weight adjustment is:

[0017] w′ ij =w ij ·(1+k·sin(2πf env ))

[0018] Where k is the adjustment factor, f env It is a function calculated based on environmental variables, including the influencing factors of weather and emergency situations, using a sine function to simulate the periodicity and volatility of environmental factors and allowing dynamic adjustment of weights.

[0019] Furthermore, the custom optimized ant colony algorithm construction includes:

[0020] First, the pheromone volatilization speed and intensity are dynamically adjusted to respond to real-time construction environment changes, including weather conditions, construction progress and emergencies;

[0021] Secondly, a customized heuristic function is used to configure different priorities for various paths based on the cost or length of the path, and to comprehensively consider time and safety evaluation, so as to balance the cost and potential safety risks while finding the shortest path;

[0022] Finally, a multi-objective optimization framework was implemented to simultaneously consider multiple key construction indicators such as cost minimization, time optimization and high safety assurance.

[0023] Furthermore, the method for dynamically adjusting pheromones includes:

[0024] S1. First, the pheromone adjustment algorithm is used to dynamically adjust the pheromone volatilization speed and intensity according to the real-time data collected at the construction site. The adjustment of the pheromone volatilization speed is based on the formula:

[0025]

[0026] Indicates that, where φ 0 is the initial pheromone intensity, v represents the environmental factor variables including temperature, humidity, and wind speed, t represents the time variable, and α and β are adjustment coefficients;

[0027] S2. Secondly, develop an environmental sensitivity model to predict the impact on the construction path through real-time data. The prediction formula is:

[0028]

[0029] Where e represents the environmental impact factor, s(t) represents the construction status function within the time period, γ, δ, and ∈ are model parameters, and T is the total time considered;

[0030] S3. Finally, an adaptive feedback system is used to adjust the parameters of pheromones according to the monitoring results. The adjustment formula is:

[0031]

[0032] where θ 0 is the baseline pheromone parameter, p represents the real-time monitoring parameter obtained from the environmental sensor, and κ, ω, and η are adjustment factors.

[0033] Furthermore, the customized heuristic function construction includes:

[0034] First, create a multi-factor heuristic scoring function H(v), which is defined as:

[0035]

[0036] Where l(v), c(v), t(v), s(v) represent the length, cost, estimated time and safety risk of path v respectively; λ 1 ,λ 2 ,λ 3 ,λ 4 is the weight coefficient, α 1 , α 2 , α 3 , α 4 It is a nonlinear parameter that adjusts the influence of various factors;

[0037] Secondly, the real-time monitoring data is integrated into the heuristic function to dynamically adjust the weight coefficient λ i and the nonlinear parameter α i , in order to reflect the changes in the environment and emergencies at the construction site in real time, by adaptively adjusting the formula:

[0038] λ′ i =λ i ·(1+κ i sin(ω i Δ i ))

[0039] and

[0040] α′ i =α i ·(1+η i cos(μ i Δ i ))

[0041] where κi ,ω i , η i , μ i is the adjustment factor, Δ i Indicates the real-time monitoring parameter changes obtained from environmental sensors.

[0042] Furthermore, the implementation of the multi-objective optimization framework method includes:

[0043] S1. First, define the comprehensive optimization function F(x), which combines the weighted sum of cost C(x), time T(x), and security S(x). The specific form is:

[0044]

[0045] Where x represents the predicted construction path or plan, ω C ,ω T ,ω S is the weight of each goal;

[0046] S2. Secondly, a genetic algorithm is used to solve the optimization problem, effectively searching for the optimal solution in the multidimensional solution space, while considering multiple construction objectives. The fitness function used in the algorithm is Φ(x)=1 / F(x), which is used to evaluate the fitness of each solution;

[0047] S3. Finally, a real-time data feedback mechanism is introduced to dynamically adjust the parameters in the optimization model according to the real-time data of the construction site, and adjust the weight coefficient: ω C ,ω T ,ω S By formula:

[0048] ω′ i =ω i +κ i sin(ω i Δt i )

[0049] where κ i is the adjustment coefficient, Δt i It is the increment of time variable to reflect the changes of environment and emergencies at the construction site in real time.

[0050] Furthermore, the method for constructing the dynamic adjustment mechanism of the path selection is as follows:

[0051] First, IoT technology is used to collect data on the construction site and its surrounding environment, including data on weather conditions and emergencies. The data is integrated through functions:

[0052]

[0053] to describe, where t represents time, ai and b i is the adjustment coefficient, which is used to quantify the impact of different types of sensor data;

[0054] Secondly, a deep learning algorithm is used to analyze real-time data and predict its potential impact on the construction path. The prediction model is expressed as:

[0055]

[0056] where x j represents the characteristics of data collected from the monitoring system, c j is the learned weight;

[0057] Finally, a dynamic path adjustment algorithm is implemented to adjust the path according to the output of the prediction model. The adjustment mechanism is implemented through the function:

[0058]

[0059] Expression, where w 0 is the original path weight, d k ,ω k and Δw k They are the adjustment amplitude, frequency, and amount of change detected.

[0060] Furthermore, the algorithm parameters are adjusted using the machine learning method: first, historical and real-time data are collected, including successful cases, failed cases, environmental change data and construction progress updates of the construction path, and the data is preprocessed and feature extracted, through the function:

[0061]

[0062] Indicates that D represents the data set, d i (t) is the data after feature extraction, a i is the adjustment coefficient, T is the time frame;

[0063] Next, we select a machine learning model to predict the optimal algorithm parameter settings based on the input construction scenario parameters including terrain, weather, and construction stage, through the function:

[0064]

[0065] Indicates that x j is the input feature, β j and γ j are model parameters;

[0066] Finally, the key parameters of the path calculation algorithm are dynamically adjusted according to the current construction scenario through the online learning system. The adjustment mechanism is based on the formula:

[0067]

[0068] Indicates that, where θ 0 is the baseline parameter, δ k ,ω k and φ k They adjust the amplitude, frequency and phase respectively, which are used to adjust the algorithm parameters in real time.

[0069] The present invention has multiple beneficial effects, significantly improving the efficiency and safety of construction management, including:

[0070] 1. By simulating the behavior of ants in search of food, this method can effectively identify the best construction path, reduce unnecessary movement and resource allocation time, and thus reduce the overall construction time. The introduction of real-time monitoring data and environmental change feedback enables the path selection to be dynamically adjusted to adapt to emergencies and unforeseen environmental changes, ensuring the continuity and flexibility of the construction plan.

[0071] 2. By optimizing the construction path, human and mechanical resources can be arranged more reasonably, reducing idle time and overuse, thereby reducing construction costs. Effective path planning helps prevent resource waste and indirectly reduces the risk of overspending by reducing resource use and optimizing time management.

[0072] 3. This method can significantly improve the safety of construction sites by considering potential risks in the construction path, such as avoiding high-risk areas. It can adjust construction operations based on environmental data (such as weather conditions) to reduce accidents and delays caused by environmental factors.

[0073] 4. Using real-time and historical data from the site to support the decision-making process, a data-driven decision support system is provided to enhance the accuracy and effectiveness of decision-making. The introduction of machine learning and deep learning methods allows the prediction of problems that may be encountered during the construction process and the formulation of response strategies in advance, reducing the cost and time loss caused by emergency handling. BRIEF DESCRIPTION OF THE DRAWINGS

[0074] Figure 1 This is a flow chart of the construction path optimization method based on the ant colony algorithm of the present invention.

[0075] Figure 2 A flow chart of the ant colony algorithm customized and optimized for the present invention is constructed. DETAILED DESCRIPTION

[0076] The specific implementation modes of the present invention will be described in detail below in conjunction with the accompanying drawings.

[0077] Combined with Figure 1In step S1, the construction path optimization method based on ant colony algorithm first involves defining the construction optimization objectives, such as minimizing cost, time, distance or risk, and abstracting the construction site into a graph model, where each important construction point is regarded as a node, and these nodes are connected by paths, which are represented as edges in the graph. Each edge is assigned a weight according to the actual construction needs, and these weights can be calculated based on the distance, cost, time required or risk associated with the path. Such modeling allows the use of ant colony algorithm, an algorithm that imitates the path of ants finding food in nature, to find the optimal path by simulating the behavior of ants releasing and following pheromones.

[0078] Combined with Figure 1 Step S2 in the method further involves a custom optimized ant colony algorithm that adapts to changes in the construction environment by adjusting the evaporation rate and intensity of pheromones and heuristic functions. The adjustment of the evaporation rate and intensity of pheromones allows the algorithm to quickly adapt to dynamic changes in the construction site, such as unexpected events or plan adjustments, ensuring that the ant colony algorithm can continue to effectively find the optimized path. The adjustment of the heuristic function optimizes the search behavior of ants according to the specific characteristics of the path (such as distance, cost, or safety risk) to increase the probability of finding the best path. In addition, the method also implements multi-objective optimization, allowing multiple key factors such as cost minimization, time minimization, and maximum safety to be considered simultaneously, ensuring that the selected path is not only cost-effective, but also meets the project schedule and safety standards. In this way, the ant colony algorithm is not only optimized according to a single goal (such as cost or time), but all important factors are considered comprehensively, providing a more comprehensive and adaptable path optimization solution for construction management.

[0079] Combined with Figure 1 The S3 step in the algorithm further includes a dynamic adjustment mechanism for path selection, which integrates real-time monitoring system data and external environmental factors such as weather and emergencies to dynamically adjust the path selection strategy. This integration enables the algorithm to respond to changes and external influences on the construction site in real time, thereby optimizing path decisions instantly. Data provided by the real-time monitoring system, such as real-time video of the construction area, sensor data (such as temperature, humidity, wind speed), and other relevant information (such as unexpected events or human resource distribution) are used to evaluate the current state of the construction environment. These data are analyzed by advanced data processing technology so that the algorithm can adjust the distribution and volatility of pheromones according to weather changes, delayed material supply, or other emergency situations. For example, if severe weather is predicted, the algorithm will adjust the path to avoid high-risk areas, or re-plan the path in the event of an emergency such as equipment failure.

[0080] Combined with Figure 1The S4 step in the algorithm also includes adjusting the algorithm parameters by using machine learning methods to improve the efficiency of path calculation and adapt to the needs of different construction scenarios. This process involves using machine learning techniques to dynamically adjust key parameters in the ant colony algorithm, such as pheromone intensity, evaporation rate, and weights of heuristic functions. By collecting historical construction data, real-time performance feedback, and relevant information about the construction environment, the machine learning model can learn and predict the optimal algorithm parameter settings under specific construction conditions. For example, the model identifies that higher pheromone evaporation rates in high-density urban environments lead to more efficient path searches, while lower evaporation rates are sufficient in open and infrequently changing construction environments. By updating and adjusting these parameters in real time, the algorithm can adapt to the current construction scenario more accurately, thereby optimizing the path selection process, reducing unnecessary detours and delays, and improving the efficiency and safety of overall construction.

[0081] Embodiment 1:

[0082] A high-rise office building is being built in a metropolitan area. The project manager uses an ant colony algorithm-based construction path optimization method to determine resource allocation and construction path optimization. The construction optimization goals here include safety, cost efficiency, project completion time, and risk minimization.

[0083] To set the construction optimization goal, the project manager defined the following optimization objective function:

[0084]

[0085] Among them, S(t) represents the function of safety changing over time, which is inversely proportional to the number of safety accidents on the construction site every day; C represents the total cost, including the cost of materials, labor and machinery and equipment; T is the expected completion time; R represents the overall risk associated with the project, including legal risks and environmental risks during construction. Adjustment coefficient a 1 ,a 2 ,a 3 ,a 4 and λ are used to balance the relative importance of these factors.

[0086] For example, suppose that in a particular month, the safety record of the construction site is poor, and S(t) is the inverse of the number of accidents that occur each day. For mathematical simplicity, assume that the average number of accidents in a day is 2, then S(t) can be simplified to 1 / 2. Safety factor a 1 Set to 0.5 to emphasize the importance of safety. If the total cost of the project C is $10,000,000, and λ is set to 0.0001, the cost coefficient a 2 It can be set to 0.3. The project is expected to take 450 days to complete, and the time coefficient a 3Set to 0.2. If the risk assessment R is 5 (on a scale where higher numbers indicate higher risk), the risk factor a 4 Set to 0.1.

[0087] Substituting these values ​​into the optimization objective function:

[0088]

[0089] set up It is calculated on a daily basis, and for a 30-day month, the integral is 15. Therefore, it can be further simplified and calculated:

[0090]

[0091] O=7.5+0.3·0+0.2·6.11+0.1·2.236

[0092] O=7.5+0+1.222+0.224

[0093] O=8.946

[0094] This calculation shows how to dynamically calculate optimization goals based on preset weights and project-specific data. By continuously updating this data (such as improving safety performance or adjusting estimated costs), project managers can use ant colony algorithms to optimize resource allocation and construction paths to achieve optimal construction efficiency and safety, ensuring that the project is completed on time and on budget.

[0095] The next step of this embodiment is to construct a graph model G(V, E) to represent the nodes (construction points) at the construction site and the connections (paths) between them. ij The weight is calculated using the following formula to ensure that the optimization of path selection can integrate multiple key factors:

[0096]

[0097] Here, d ij 、c ij ,t ij and r ij Represent the distance, cost, time and risk of the edge respectively. For example, for an edge from the supply area (node ​​i) to the construction point (node ​​j), the distance d ij For 200 meters, the cost is c ij is $500, and the estimated time is t ij For 30 minutes, the risk ij is 0.3 (on a scale for quantifying risk, lower numbers indicate lower risk).

[0098] Take b 1 =0.5, b2 =0.3, b 3 =0.1, b 4 = 0.1 as an example, the weight of this edge can be calculated:

[0099]

[0100]

[0101] w ij =0.5·1+75000+0.1·(-1)+0.1·0.295 / / Assuminge -200 ≈0

[0102] w ij =0.5+75000-0.1+0.0295

[0103] w ij =75000.4295

[0104] This calculation result shows that the weight of this path is extremely high considering the high cost, indicating that it is not a cost-effective option. By introducing nonlinear parameters and trigonometric functions, the calculation is more realistic and can better reflect the complexity and uncertainty of the real world. In practical applications, this calculation method can help project managers make more informed decisions, optimize resource allocation and path selection, thereby minimizing costs and time while ensuring safety.

[0105] In the next step of this embodiment, the project manager introduces a dynamic adjustment mechanism for the weights. This mechanism allows the path selection to be adjusted according to environmental variables such as weather conditions and sudden emergencies. This adjustment not only improves the response efficiency, but also increases the accuracy of decision-making, ensuring that construction can continue to proceed efficiently under different conditions.

[0106] The specific implementation method is to use the following dynamic adjustment formula to calculate the path weight:

[0107] w′ ij =w ij ·(1+k·sin(2πf env ))

[0108] Among them, w ij is the static weight calculated based on the previous steps, k is the adjustment factor, and f env It is a function calculated from environmental variables, reflecting the impact of weather and emergency situations.

[0109] On a construction day, the predicted weather conditions change, causing f envThe evaluation is 0.75 (indicating poor weather conditions), and the value of the adjustment factor k is selected to be 0.2. This value is selected after evaluation, usually in the range of 0.1 to 0.3, to ensure that the adjustment does not affect the weights extremely, thereby avoiding overreaction.

[0110] With the previously calculated w ij Taking 75000.4295 as an example, apply the dynamic adjustment formula:

[0111] w′ ij =75000.4295·(1+0.2·sin(2π·0.75))

[0112] w′ ij =75000.4295·(1+0.2·sin(1.5π))

[0113] w′ ij =75000.4295·(1-0.2) / / because sin(1.5π)=-1

[0114] w′ ij =75000.4295·0.8

[0115] w′ ij =60000.3436

[0116] This calculation shows that the weight of a path decreases under adverse weather conditions, meaning that the path is less optional in bad weather, encouraging project managers to choose other safer or more feasible paths.

[0117] Embodiment 2:

[0118] The key step of this embodiment is to achieve dynamic adjustment of pheromones to cope with real-time construction environment changes, such as weather conditions, construction progress and emergencies. This adjustment is completed through a precise pheromone adjustment algorithm, which uses real-time environmental data to dynamically adjust the evaporation speed and intensity of pheromones, ensuring that the ant colony algorithm can respond to environmental changes in real time and optimize path selection.

[0119] A specific example is the construction of a new commercial area in the summer. The main challenges faced by summer construction include high temperatures, high humidity, and occasional strong winds, which affect construction progress and safety. To adapt to these challenges, the pheromone adjustment algorithm dynamically adjusts the parameters of pheromones based on environmental data collected in real time.

[0120] The formula for dynamically adjusting pheromones is as follows:

[0121]

[0122] In this formula, φ 0is the initial pheromone intensity, which can be set to 1.0 as a standard value; v and t represent environmental factors (such as temperature, humidity, wind speed) and time variables respectively; α and β are adjustment coefficients, which are set according to the specific construction environment and empirical data. α = 0.05 and β = 0.1 are set to meet the needs of most standard urban construction environments.

[0123] Assume that in the afternoon of a certain day, the temperature is 35°C (high), the humidity is 80%, and the wind speed is 20 km / h. Converting these values ​​into a comprehensive environmental impact index v can be simplified to v = 35 + 80 + 20 = 135. If we consider that the construction has entered the t = 60th day:

[0124]

[0125] φ(135,60)=1.0·e -0.05·5.13·log(7) / / Simplify calculation

[0126] φ(135,60)=1.0·e -0.05·5.13·1.946

[0127] φ(135,60)=1.0·e -0.499

[0128] φ(135,60)≈0.607

[0129] The calculation results show that as environmental conditions deteriorate and the project progresses, the volatilization rate of pheromones accelerates, thereby reducing the duration of pheromones under adverse conditions and prompting the ant colony to update its path selection more frequently.

[0130] In this example, the project manager introduced an environmentally sensitive model. This model aims to use real-time data to predict the potential impact of environmental changes on the construction path, helping to adjust construction plans and path decisions. This model is particularly important because it can identify potential problems in advance and quickly adjust strategies to avoid delays or other negative effects.

[0131] The specific implementation of the environmentally sensitive model involves the following prediction formula:

[0132]

[0133] In this formula, e represents environmental influencing factors, such as weather conditions, rainfall, temperature changes, etc.; s(t) represents the construction status in different time periods, including the number of workers, equipment utilization, material supply, etc.; γ, δ, and ∈ are parameters for adjusting the model response; T is the total consideration time, which is the length of a day's work or the duration of the entire project.

[0134] The specific value ranges of the setting parameters are: γ = 0.5 to 1.5, δ = 0.01 to 0.05, ∈ = 0.1 to 0.5. These value ranges are determined based on actual project data and historical performance analysis to ensure that the model is both sensitive and does not over-respond to small changes.

[0135] Assume that you are working in a hot and dusty environment, the environmental impact factor e is high, and the impact factor s(t) on the construction status increases significantly during high temperature periods, such as the afternoon temperature causing an increase in equipment failure rate. Assuming that in a typical working day, the function of s(t) over time is the increased equipment failure rate due to high temperature, set s(t) = 0.02t, if T = 8 hours (a day's working time), the output of the model can be calculated:

[0136]

[0137] This integral requires a numerical method to solve, but it will give a value that represents the overall impact of environmental factors on the construction schedule. If this value is relatively high, the project manager needs to adjust the construction plan, such as deploying more resources on cooler mornings or adjusting the timing of certain key operations.

[0138] In the next step of this embodiment, the project manager introduced an adaptive feedback system to adjust the parameters of the pheromone according to the real-time monitoring results to more accurately adapt to the changes in the real-time environment and construction status. This adaptive system can ensure that the algorithm is continuously optimized during the construction process, reflecting the changes in the environment and actual working conditions, thereby improving the effectiveness of path selection and the efficiency of resource use.

[0139] The adaptive feedback system uses the following formula to adjust the pheromone parameters:

[0140]

[0141] Among them, θ 0 is the baseline pheromone parameter, representing the pheromone setting without any external influence. p is the real-time monitoring parameter obtained from environmental sensors (such as temperature, humidity, wind speed, or other construction-related sensors). κ, ω, and η are adjustment factors used to control the sensitivity and range of pheromone parameter adjustment.

[0142] The specific value range of the adjustment factor is set as follows: κ = 0.1 to 0.5, which allows the adjustment amplitude to range from mild to strong; ω = 0.1 to 1.0, which controls the adjustment frequency; η = 0.01 to 0.1, which helps balance the adjustment baseline.

[0143] It is assumed that on a typical construction day, the temperature value monitored by the environmental sensor is p = 35 (degrees Celsius), which is a relatively high temperature that will affect the efficiency of workers and material performance. Set the baseline pheromone parameter θ 0=1.0, select κ=0.3, ω=0.5, and η=0.05 to calculate:

[0144]

[0145] Use math software or a calculator to find:

[0146] sin(17.5)≈0.304

[0147] cos(17.5)≈0.953

[0148] therefore:

[0149]

[0150] θ(35)=1.0(1+0.3×0.303)

[0151] θ(35)=1.0(1+0.091)

[0152] θ(35)=1.091

[0153] This result shows that under high temperature conditions, the intensity of pheromones should be moderately increased to adapt to the challenges brought by the environment, thereby helping the ant colony algorithm to optimize the path more effectively and avoid the decrease in work efficiency due to high temperature.

[0154] Embodiment 3:

[0155] In this embodiment, it is very important to consider the multi-dimensional factors of the path (such as length, cost, time, and safety) in the construction project, so the use of customized heuristic functions can help the project management team make more comprehensive decisions when selecting the construction path. The construction path optimization method based on the ant colony algorithm of the present invention uses a multi-factor heuristic scoring function H(v) to configure priorities for different paths. This function not only considers the actual attributes of the path, but also combines the specific needs and priorities of the project.

[0156] The specific heuristic function is defined as follows:

[0157]

[0158] In this formula, l(v), c(v), t(v), and s(v) represent the length, cost, estimated time, and safety risk of path v, respectively. 1 , 2 , 3 and λ 4 are the weight coefficients of these factors, and α 1 , α 2 , α 3 and α 4It is a nonlinear parameter that adjusts the influence of various factors.

[0159] In order to actually apply this model, the parameter value range is set as follows:

[0160] λ 1 =0.5,λ 2 =0.3,λ 3 =0.15,λ 4 = 0.05. The assignment of these weights reflects the importance that the project places on different factors. For example, paying more attention to cost control will increase λ 2 The value of .

[0161] α 1 = 0.01 to 0.1, α 2 =1 to 10, α 3 =1 to 2, α 4 =0.01 to 0.1, these parameters are set based on historical data and the experience of the project manager.

[0162] Assume a specific path v, whose properties are as follows:

[0163] l(v)=1000m

[0164] c(v)=5000

[0165] t(v)=3 hours

[0166] s(v) = 0.2 (on the safety risk scale)

[0167] Substitute into the heuristic function for calculation:

[0168] H(v)=0.5·e -0.01·1000 +0.3·log(1+10·5000)+0.15·(3) 1.5 +0.05·(1-e -0.05·0.2 )

[0169] H(v)=0.5·e -10 +0.3·log(50001)+0.15·5.196+0.05·(1-e -0.01 )

[0170] H(v)=0.5·0.000045+0.3·10.82+0.15·5.196+0.05·0.00995

[0171] H(v)=0.0000225+3.246+0.7794+0.000498

[0172] H(v)=4.0264

[0173] The calculated result H(v)=4.0264 can be used to compare the H(v) values ​​of other paths to determine which path is better after comprehensively considering cost, time, length and safety.

[0174] In this embodiment, it is crucial to improve the adaptability and real-time performance of path decision making. In order to ensure that path selection can adapt to changes in the construction site environment and emergencies, the project management team introduced a mechanism to integrate real-time monitoring data into the heuristic function and dynamically adjust the relevant weight coefficient λ i and the nonlinear parameter α i This integration enables the heuristic function to reflect the current status of the construction site in real time, thereby optimizing the path selection.

[0175] A specific implementation includes using the following adaptive adjustment formula:

[0176] λ i ′=λ i ·(1+κ i sin(ω i Δ i ))

[0177] α i ′=α i ·(1+η i cos(μ i Δ i ))

[0178] Here, κ i ,ω i ,η i , and μ i is the adjustment factor, used to control the magnitude and rate of adjustment, Δ i Represents the amount of change in real-time monitored parameters obtained from environmental sensors, such as temperature changes, humidity increases, or noise level increases.

[0179] The value range of the adjustment factor is set as follows:

[0180] κ i = 0.05 to 0.2, used to control the adjustment range of the weight coefficient,

[0181] ω i =1.0 to 2.0, control adjustment frequency,

[0182] η i = 0.05 to 0.2,

[0183] μ i =1.0 to 2.0, controls the adjustment amplitude and frequency of nonlinear parameters.

[0184] Assume that at a certain construction stage, a sudden rise in temperature is detected, causing quality problems in construction materials (Δ i is 10℃), the original weight coefficient λ 2 and the nonlinear parameter α 2 are 0.3 and 10 respectively. 2 =0.1,ω 2 =1.5,η 2 =0.1,μ 2 =1.5 to adjust:

[0185] λ′ 2 =0.3·(1+0.1sin(1.5×10))

[0186] λ′ 2 =0.3·(1+0.1sin(15))

[0187] λ′ 2 =0.3·1+0.1×0.650=0.3·1.065=0.3195

[0188] α′ 2 =10·(1+0.1cos(1.5×10))

[0189] α′ 2 =10·(1+0.1cos(15))

[0190] α′ 2 =10·1+0.1×0.965=10·1.0965=10.965

[0191] This calculation result shows that after the temperature rises, the cost-related weight coefficients and parameters increase appropriately to reflect the increase in cost and the higher demand for safety and quality control.

[0192] Embodiment 4:

[0193] This embodiment is implemented through a comprehensive optimization function F(x), which considers the weighted sum of cost, time, and safety, allowing the project management team to comprehensively evaluate the advantages and disadvantages of each predicted construction path or plan.

[0194] The specific multi-objective optimization function is defined as follows:

[0195]

[0196] Where x represents a specific construction path or plan. C(x), T(x), and S(x) represent the cost, estimated time, and safety risk of the path, respectively. C ,ω T and ω SIt is the weight coefficient of these factors, which is used to adjust the influence of each factor in the overall evaluation.

[0197] The value range of the weight coefficient is as follows:

[0198] ω C =0.3 to 0.5: High weight reflects the importance of cost in construction decision-making.

[0199] ω T = 0.2 to 0.4: Time management is critical to adhering to project schedules.

[0200] ω S =0.3 to 0.5: Safety is the primary consideration in construction projects.

[0201] In an actual construction project, the cost C(x) of path x is estimated to be $5000, the estimated time T(x) is 200 hours, and the safety risk S(x) is assessed to be 0.1. The formula and specific parameter settings (set ω_C = 0.4, ω_T = 0.3, ω_S = 0.3) are used for calculation:

[0202]

[0203] F(x)=0.4·1+0.3·(0-e -200 )+0.3·0.995

[0204] F(x)=0.4+0.3·0+0.3·0.995

[0205] F(x)=0.4+0+0.2985

[0206] F(x)=0.6985

[0207] The next step of implementing the genetic algorithm in this embodiment is as follows:

[0208] In the genetic algorithm, the fitness function Φ(x) = 1 / F(x) is used to evaluate the fitness of each solution, where F(x) is the aforementioned comprehensive optimization function, which includes the weighted sum of cost C(x), time T(x), and safety S(x). The fitness function is designed to optimize the construction path to minimize cost, shorten time, and maximize safety.

[0209] A set of randomly generated construction paths is selected as the initial population. Each path or solution represents a potential construction plan. The best solution is selected for reproduction based on the result of the fitness function, and solutions with high fitness have a higher chance of being selected.

[0210] New solutions are generated through crossover and mutation operations, where crossover ensures the diversity of solutions and mutation introduces new features to avoid local optimality. The selection, crossover and mutation operations are repeated until the stopping condition is met, such as reaching the preset number of iterations or the fitness reaching a certain threshold.

[0211] For a specific example, the initial parameters of the construction project are set as follows:

[0212] Cost C(x) = 5000

[0213] Time T(x) = 200 hours

[0214] Safety risk S(x) = 0.1

[0215] The weight coefficient range is ω C =0.3,ω T =0.3,ω S =0.4

[0216] Calculate the initial fitness using the comprehensive optimization function defined previously:

[0217]

[0218] Φ(x)=1 / F(x)

[0219] Assuming the calculated F(x) is 0.6985 (as in the previous example), then:

[0220] Φ(x)=1 / 0.6985=1.432

[0221] The fitness value Φ(x) = 1.432 is used to evaluate the quality of the solution. Through the iteration of the genetic algorithm, this value can be continuously optimized to search for a construction path with lower cost, shorter time and higher safety.

[0222] In the next step of this embodiment, the project team introduced a real-time data feedback mechanism, which can dynamically adjust the parameters in the optimization model according to the real-time data of the construction site. This real-time adjustment ensures that the construction path decision can respond immediately to changes on site, such as weather changes, material delays, emergency safety incidents, etc., thereby effectively optimizing resource allocation and construction progress.

[0223] The key to implementing this strategy is to dynamically adjust the weight coefficient ω C (cost),ω T (time),ω S (Safety), use the following formula to adjust:

[0224] ω i ′=ω i +κ i sin(ω i Δti )

[0225] In this formula, ω i is the original weight coefficient, κ i is the adjustment coefficient, which determines the magnitude of the adjustment, Δt i is the increment of the time variable, representing the time that has passed since the last adjustment.

[0226] Setting adjustment coefficient κ i The specific value range of is 0.05 to 0.15. This range allows for gentle to moderate adjustments in the weight coefficients to avoid overreaction while ensuring sufficient responsiveness to cope with real-time changes.

[0227] At the beginning of the project, the weight coefficient is set to ω C =0.4,ω T =0.3,ω S =0.3. If a major safety incident occurs during the project, it is necessary to immediately increase the attention to safety measures and set a safety factor ω S The adjustment is urgent, choose κ S =0.1 for adjustment. The increment of the time variable Δt S It can be set to 1 hour after the event occurs (the time unit is self-defined, depending on the project's response time and update frequency). S =1.0 is the baseline for adjusting frequency.

[0228] Apply the adjustment formula:

[0229] ω′ S =0.3+0.1sin(1.0×1)

[0230] ω′ S =0.3+0.1sin(1)

[0231] ω′ S =0.3+0.1×0.8415

[0232] ω′ S =0.3+0.08415

[0233] ω′ S =0.38415

[0234] This calculation result shows that after the emergency occurs, the safety weight is adjusted from the original 0.3 to about 0.384, reflecting the higher demand for safety.

[0235] Embodiment 5:

[0236] In this example, the project team used the Internet of Things (IoT) technology to collect key data on the construction site and its surrounding environment. This strategy allows the project to monitor and respond to key factors such as weather conditions, construction progress changes, and emergencies in real time, thereby effectively adjusting the construction path and resource allocation.

[0237] Various sensors, such as temperature, humidity, anemometer, rain gauge, and safety monitoring equipment, are used to collect real-time data about the construction site. These sensors are deployed at key locations on the construction site and upload data to the central monitoring system in real time.

[0238] Use function To integrate the collected data, where t represents time, a i and b i is the adjustment coefficient, which represents the weight of each type of sensor data and the data decay rate. This data integration method allows the project team to understand how environmental factors change over time and the potential impact of these changes on the construction path.

[0239] The setting range of the adjustment coefficient is: a i (Data weight) The value range is usually set from 0.1 to 1.0 and is adjusted according to the importance of the sensor data to the construction; b i (Data decay rate) The value range is set to 0.01 to 0.1, reflecting the timeliness and change rate of the data.

[0240] During construction, especially in hot summer, high temperatures affect the performance of construction materials and the health of workers. The temperature data monitored by the sensor is t i is 35℃, the corresponding adjustment coefficient is set to a i =0.8 (taking into account the high impact of high temperature on construction), b i =0.05 (reflecting the need for rapid response to temperature changes).

[0241] Apply this data to the data integration function:

[0242] D(t)=0.8·e -0.05·35

[0243] D(t)=0.8·e -1.75

[0244] D(t)=0.8·0.1738

[0245] D(t)=0.13904

[0246] This calculation result shows that the impact of high temperature on construction will gradually decrease over time. If this situation persists, the construction plan will need to be adjusted, such as adjusting working hours, arranging work during cooler periods or increasing heat prevention measures.

[0247] In this example, the project team then introduced a deep learning algorithm to analyze the real-time data collected from the monitoring system at the construction site and predict the potential impact of this data on the construction path.

[0248] The construction and implementation of a deep learning prediction model consists of the following steps:

[0249] 1. Data collection: Various sensors (such as temperature, humidity, wind speed, pressure, etc.) deployed at the construction site using IoT technology collect real-time data, which will serve as input features for the deep learning model.

[0250] 2. Feature processing: The collected data is preprocessed, including normalization and missing value processing, to ensure the quality and consistency of the data and make it suitable for deep learning models.

[0251] 3. Model training: Use annotated historical data to train the deep learning model. These historical data include previous construction path selection, cost records, time records, and safety incident records. During the training process, the model will learn the relationship between these input data and construction results.

[0252] 4. Prediction model: Apply the trained model using the formula:

[0253]

[0254] To predict the potential impact of the newly collected data on the construction path. j represents the input feature, i.e. real-time monitoring data; c j It is the weight learned in the model, which indicates the contribution of each feature to the prediction result.

[0255] In a specific construction project, the data monitored by the sensor include temperature x 1 =30℃, humidity x 2 =80%, wind speed x 3 =15km / h, and the previous model training process has determined the corresponding weight c 1 =0.3, c 2 =0.2, c 3 =0.5.

[0256] Substituting this data into the prediction model:

[0257]

[0258] P(x)≈0.99993

[0259] This result shows that under the current environmental conditions, the prediction model indicates extremely high potential risks or the need for adjustment. The project team can consider adjusting the construction plan or taking additional safety measures, such as reducing high-altitude work under high wind speed and high humidity conditions, to ensure construction safety and optimize progress.

[0260] This embodiment then introduces a dynamic path adjustment algorithm to cope with real-time environmental changes and the output of the prediction model. This algorithm allows the path selection to be not only based on the initial settings, but also adjusted according to the real-time data of the environment and the construction site, ensuring real-time optimization of the construction path and maximizing efficiency.

[0261] The implementation steps and mechanisms of the dynamic path adjustment algorithm include:

[0262] 1. Original path weight (w 0 ): This is the path weight set based on initial data and project plan without the influence of external changes.

[0263] 2. Adjust the formula: Use the formula:

[0264]

[0265] To adjust the path weight, where:

[0266] d k is the adjustment amplitude, which defines the weight adjustment intensity of each factor. k It is the adjustment frequency, which determines the periodicity or frequency of adjustment. k It is the amount of detected changes, such as changes in environmental data, safety events, or other key construction parameters.

[0267] The range of adjustment coefficient: d k Typically set in the range 0.1 to 0.5, this allows for significant but not extreme adjustments to the path weights ω k The value range can be 1.0 to 2.0 to adapt to different change rates and response requirements. k It is set according to the actual monitored data changes, such as a temperature increase of 10°C or a wind speed increase of 5km / h.

[0268] Assume that in a construction project, due to sudden high temperatures and increased wind speeds, the weight of the construction path needs to be adjusted to ensure safety and efficiency. Set the original path weight w 0 =1.0, and adjust considering two factors: temperature and wind speed:

[0269] Temperature (d 1 =0.3,ω 1 =1.5,Δw 1 =10℃)

[0270] Wind speed (d 2 =0.2,ω 2 =1.0,Δw 2 =5km / h)

[0271] Apply the dynamic path adjustment formula:

[0272] A(w)=1.0+0.3·sin(1.5·10)+0.2·sin(1.0·5)

[0273] A(w)=1.0+0.3·sin(15)+0.2·sin(5)

[0274] A(w)=1.0+0.3·0.650+0.2·(-0.958)

[0275] A(w)=1.0+0.195-0.192

[0276] A(w)≈1.003

[0277] This calculation shows that despite changes in environmental conditions, the path weights remain close to their original settings after appropriate adjustments, indicating that the system makes subtle adjustments to adapt to environmental changes rather than overreacting.

[0278] Embodiment 6:

[0279] The use of machine learning methods to adjust algorithm parameters in this embodiment is an innovative step aimed at improving the adaptability and efficiency of the algorithm. This process involves collecting historical and real-time data from multidimensional data sources, preprocessing this data, extracting key features, and using machine learning models to learn how to dynamically adjust the path selection strategy based on environmental and schedule changes.

[0280] The implementation steps are detailed as follows:

[0281] First, historical data and real-time data are collected, including successful cases, failed cases, environmental change data (such as weather conditions, temperature, humidity changes, etc.) of the construction path, and real-time updates of the construction progress. These data come from various sensors and monitoring systems at the construction site, as well as records in the project management system.

[0282] The collected data is preprocessed, including data cleaning (removing outliers and filling missing values), normalization (standardizing the data range), and feature extraction. The purpose of feature extraction is to transform the raw data into a form that is more meaningful to the machine learning model, for example, converting time series data into statistical features or window-based aggregate values.

[0283] The extracted features are used to train a machine learning model, for example, a regression model, decision tree, support vector machine, or deep learning network can be used. The goal of the model is to predict the optimal parameters of the construction path based on the input features (i.e., environmental and schedule features).

[0284] Mathematical model for algorithm parameter adjustment:

[0285] Use the function:

[0286]

[0287] To integrate and apply the output of the machine learning model. This function can be understood as an integrated decision model, where D represents the dataset and d i (t) is the data after feature extraction, a i is the adjustment factor, and T is the time frame considered. i The value range can be set from 0.1 to 1.0, and can be adjusted according to the importance of the feature and its impact on the model.

[0288] In a specific project, the construction team needs to consider the impact of temperature and humidity on the construction progress. Through feature extraction, the feature data of average temperature and humidity per day are obtained. 1 (t) and d 2 (t), adjustment coefficient a 1 =0.5, a 2 =0.3.

[0289] If T is set to 30 days (months), the comprehensive impact of this month can be calculated:

[0290]

[0291] Setting 1 (t) = 28 °C and d 2 (t) = 75%, calculation example when t = 15 in a day:

[0292]

[0293] φ(D)=3065.238

[0294] This result can help the team evaluate the impact of temperature and humidity on the construction progress throughout the month, thereby making more precise construction path and plan adjustments to ensure the continuity and efficiency of construction.

[0295] This embodiment then introduces a machine learning model to further optimize the selection of algorithm parameters. This model aims to predict the algorithm parameter settings that best suit the current conditions based on different parameters of the specific construction scenario, such as terrain, weather conditions, and construction stage. Through the prediction of the machine learning model, dynamic adjustment of algorithm parameters can be achieved, thereby ensuring that the construction path selection remains optimal in a constantly changing environment.

[0296] First determine the input feature x of the model j ,These characteristics include the complexity of the terrain, the current weather conditions (such as temperature, humidity, rainfall), and the specific needs of the construction phase (such as foundation phase, structure construction phase, etc.). These characteristics are collected from various data sources at the construction site, such as sensor data, weather forecast services, and construction progress reports.

[0297] For each feature x j Define two model parameters, β j and γ j Here, β j represents the weight of the feature in the prediction, and γ j Adjust the influence strength of the feature, that is, how it affects the predicted algorithm parameters.

[0298] Prediction function:

[0299]

[0300] This function predicts the algorithm parameters by combining the weighted logarithmic transformations of all important features. This form allows the model to take into account nonlinear effects while avoiding prediction instability caused by direct input of extreme values.

[0301] Train the model using historical construction data to find the optimal β j and γ j This process involves cross-validation and hyperparameter optimization to ensure that the model provides reliable predictions under different construction scenarios.

[0302] Parameter value range:

[0303] β j Typically in the range of 0.1 to 1.0, depending on the importance of the feature in the prediction.

[0304] γ j The value range is 0.01 to 10, and is adjusted according to the sensitivity of the feature to the algorithm parameters.

[0305] Example application:

[0306] The construction project is located in a mountainous area with a changeable climate, and the complexity of the terrain needs to be considered. 1= 0.8 (higher), humidity of current weather conditions x 2 =80%, and in the structural construction stage x 3 =0.5. Set the model parameter β 1 =0.7,γ 1 =1.0;β 2 =0.3,γ 2 =0.05; β 3 =1.0,γ 3 =5:

[0307] Ψ(x)=0.7·log(1+1.0×0.8)+0.3·log(1+0.05×80)+1.0·log(1+5×0.5)

[0308] Ψ(x)=0.7·log(1.8)+0.3·log(5)+1.0·log(3.5)

[0309] Ψ(x)=0.7·0.5878+0.3·1.6094+1.0·1.2528

[0310] Ψ(x)=0.4115+0.4828+1.2528

[0311] Ψ(x)=2.1471

[0312] This prediction result can be used to dynamically adjust the parameters of the construction path algorithm, such as adjusting the release rate and evaporation rate of pheromones to adapt to complex terrain and high humidity environments, ensuring safety and efficiency during the structure construction phase. In this way, the machine learning model directly supports the decision-making process of the construction path, improving the adaptability and efficiency of the project.

[0313] This embodiment further introduces an online learning system to adjust key parameters of the path calculation algorithm in real time. This online learning system can dynamically adjust the algorithm settings according to real-time data and construction progress to maximize construction efficiency and safety.

[0314] The steps to implement an online learning system are as follows:

[0315] This is the default setting of the algorithm in an ideal situation without any external interference. The baseline parameters include pheromone intensity, evaporation rate, path selection weight, etc.

[0316] Dynamic adjustment mechanism:

[0317] Use the function:

[0318]

[0319] Make parameter adjustments.

[0320] Among them, p k Represents real-time monitoring parameters obtained from environmental sensors, such as temperature, humidity, wind speed, etc.

[0321] δ k It is the adjustment amplitude, which controls the intensity of the change of the adjustment parameter.

[0322] ω k It is the adjustment frequency, which determines the periodicity of parameter adjustment.

[0323] φ k is the phase, which determines the starting angle of the adjustment function.

[0324] Parameter value range:

[0325] θ 0 The value of δ depends on the specific algorithm parameters. For example, if the pheromone intensity is considered, the baseline value is between 0.1 and 1.0. k Typically set between 0.01 and 0.1, allowing for subtle to significant adjustments. k The value range of can be from 0.5 to 2.0, which is selected according to the frequency of change of real-time data. k It is generally between 0 and 2π (i.e. 0 to 360 degrees).

[0326] Assume that the construction project is experiencing an unusually hot summer, and temperature changes have a significant impact on construction efficiency and material quality. Set the baseline parameter θ 0 = 0.5 (pheromone intensity), considering temperature as the key environmental parameter p 1 , set the adjustment parameters as follows:

[0327] δ 1 =0.05

[0328] ω 1 =1.0

[0329] φ 1 =π / 4 (i.e. 45 degrees)

[0330] If the current temperature changes:

[0331] Δt 1 =10℃:

[0332] Θ(p)=0.5+0.05·sin(1.0×10+π / 4)

[0333] Θ(p)=0.5+0.05·sin(10+0.785)

[0334] Θ(p)=0.5+0.05·sin(10.785)

[0335] Θ(p)=0.5+0.05·0.981

[0336] Θ(p)=0.5+0.04905

[0337] Θ(p)≈0.54905

[0338] This result shows that under high temperature conditions, the pheromone intensity was increased by about 0.049 by dynamically adjusting to adapt to environmental changes and reduce the negative impact of high temperature on construction progress and material properties.

[0339] The above shows and describes the basic principles, main features and advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. The construction path optimization method based on ant colony algorithm is characterized by The following steps are involved: First, the construction optimization goal is defined and the construction site is abstracted into a graph model, where each construction point is a node, the route connecting the nodes is an edge, and each edge is given a weight, which is distance, cost, time or risk. Then, a customized optimized ant colony algorithm was used to adapt to changes in the construction environment by adjusting the evaporation speed and intensity of pheromones and heuristic functions, and to implement multi-objective optimization while integrating cost, time and safety factors; further including a dynamic adjustment mechanism for route selection that integrates real-time monitoring system data and external environmental factors, including weather and emergency situations, to dynamically adjust the route selection strategy; By using machine learning methods to adjust algorithm parameters, the efficiency of path calculation can be improved and adapted to the needs of different construction scenarios.

2. The construction path optimization method based on ant colony algorithm according to claim 1 is characterized in that The construction optimization objectives are defined as follows: S1. First, set the construction optimization goal as: Where S(t) is the function of safety over time, C, T and R represent total cost, total time and risk assessment respectively, and a1, a2, a3, a4 and λ are coefficients that adjust the relative importance of these factors; S2, then build a graph G(V, E) where each edge e ij The weight of is given by the formula: Calculate, where d ij , c ij , t ij , r ij They represent the distance, cost, time and risk of the edge respectively. The fidelity of the calculation is enhanced by introducing nonlinear parameters and trigonometric functions. S3. The final formula for dynamic weight adjustment is: w′ ij =w ij ·(1+k·sin(2πf env )) Where k is the adjustment factor, f env It is a function calculated based on environmental variables, including the influencing factors of weather and emergency situations, using a sine function to simulate the periodicity and volatility of environmental factors and allowing dynamic adjustment of weights.

3. The construction path optimization method based on ant colony algorithm according to claim 1 is characterized in that The custom optimized ant colony algorithm construction includes: First, the pheromone volatilization speed and intensity are dynamically adjusted to respond to real-time construction environment changes, including weather conditions, construction progress and emergencies; Secondly, a customized heuristic function is used to configure different priorities for various paths based on the cost or length of the path, and to comprehensively consider time and safety evaluation, so as to balance the cost and potential safety risks while finding the shortest path; Finally, a multi-objective optimization framework was implemented to simultaneously consider multiple key construction indicators such as cost minimization, time optimization and high safety assurance.

4. The construction path optimization method based on ant colony algorithm according to claim 3 is characterized in that The method for dynamically adjusting pheromones comprises: S1. First, the pheromone adjustment algorithm is used to dynamically adjust the pheromone volatilization speed and intensity according to the real-time data collected at the construction site. The adjustment of the pheromone volatilization speed is based on the formula: Indicates, where φ0 is the initial pheromone intensity, v represents the environmental factor variables including temperature, humidity, and wind speed, t represents the time variable, and α and β are adjustment coefficients; S2. Secondly, develop an environmental sensitivity model to predict the impact on the construction path through real-time data. The prediction formula is: Where e represents the environmental impact factor, s(t) represents the construction status function within the time period, γ, δ, and ∈ are model parameters, and T is the total time considered; S3. Finally, an adaptive feedback system is used to adjust the parameters of pheromones according to the monitoring results. The adjustment formula is: where θ0 is the baseline pheromone parameter, p represents the real-time monitoring parameter obtained from the environmental sensor, and K, ω, and ηη are adjustment factors.

5. The construction path optimization method based on ant colony algorithm according to claim 3 is characterized in that The customized heuristic function construction includes: First, create a multi-factor heuristic scoring function H(v), which is defined as: Where l(v), c(v), t(v), s(v) represent the length, cost, expected time and safety risk of path v respectively; λ1, λ2, λ3, λ4 are weight coefficients, α1, α2, α3, α4 are nonlinear parameters that adjust the influence of each factor; Secondly, the real-time monitoring data is integrated into the heuristic function to dynamically adjust the weight coefficient λ i and the nonlinear parameter α i , in order to reflect the changes in the environment and emergencies at the construction site in real time, by adaptively adjusting the formula: λ′ i =λ i ·(1+k i sin(ω i D i )) and a' i =a i ·(1+n i cos(μ i D i )) where κ i ,ω i , η i , μ i is the adjustment factor, Δ i Indicates the real-time monitoring parameter changes obtained from environmental sensors.

6. The construction path optimization method based on ant colony algorithm according to claim 3 is characterized in that The method for implementing the multi-objective optimization framework includes: S1. First, define the comprehensive optimization function F(x), which combines the weighted sum of cost C(x), time T(x), and security S(x). The specific form is: Where x represents the predicted construction path or plan, ω C ,ω T ,ω S is the weight of each goal; S2. Secondly, a genetic algorithm is used to solve the optimization problem, effectively searching for the optimal solution in the multidimensional solution space, while considering multiple construction objectives. The fitness function used in the algorithm is Φ(x)=1 / F(x), which is used to evaluate the fitness of each solution; S3. Finally, a real-time data feedback mechanism is introduced to dynamically adjust the parameters in the optimization model according to the real-time data of the construction site, and adjust the weight coefficient: ω C ,ω T ,ω S By formula: oh' i =ω i +k i sin(ω i Δt i ) where κ i is the adjustment coefficient, Δt i It is the increment of time variable to reflect the changes of environment and emergencies at the construction site in real time.

7. The construction path optimization method based on ant colony algorithm according to claim 1 is characterized in that The method for constructing the dynamic adjustment mechanism of the path selection: First, IoT technology is used to collect data on the construction site and its surrounding environment, including data on weather conditions and emergencies. The data is integrated through functions: to describe, where t represents time, a i and b i is the adjustment coefficient, which is used to quantify the impact of different types of sensor data; Secondly, a deep learning algorithm is used to analyze real-time data and predict its potential impact on the construction path. The prediction model is expressed as: where x j represents the characteristics of data collected from the monitoring system, c j is the learned weight; Finally, a dynamic path adjustment algorithm is implemented to adjust the path according to the output of the prediction model. The adjustment mechanism is implemented through the function: Expression, where w0 is the original path weight, d k ,ω k and Δw k They are the adjustment amplitude, frequency, and amount of change detected.

8. The construction path optimization method based on ant colony algorithm according to claim 1 is characterized in that The machine learning method is used to adjust the algorithm parameters: first collect historical and real-time data, including successful cases, failed cases, environmental change data and construction progress updates of the construction path, pre-process the data and perform feature extraction, through the function: Indicates that D represents the data set, d i (t) is the data after feature extraction, a i is the adjustment coefficient, T is the time frame; Next, we select a machine learning model to predict the optimal algorithm parameter settings based on the input construction scenario parameters including terrain, weather, and construction stage, through the function: Indicates that x j is the input feature, β j and γ j are model parameters; Finally, the key parameters of the path calculation algorithm are dynamically adjusted according to the current construction scenario through the online learning system. The adjustment mechanism is based on the formula: Denotes, where θ0 is the baseline parameter, δ k ,ω k and φ k They adjust the amplitude, frequency and phase respectively, which are used to adjust the algorithm parameters in real time.

Citation Information

Cited By

  • Intelligent construction site data acquisition and visual management method based on Internet of Things

    CN119359043A

  • Monitoring video transmission method and system based on wireless communication

    CN119421008A

  • Material scheduling method and device based on intelligent storage and construction site linkage

    CN120235408A

  • Path planning method and device for construction site, computer equipment and storage medium

    CN121540173A

  • Intelligent optimization and monitoring management platform for old structure breaking construction scheme

    CN122693930A