Building material carrying device and carrying method thereof
By designing a building material handling device including ropes, handling boxes and sealing plates, the problem of automatic unloading of steel pipes after lifting is solved, the safety and automatic unloading of steel pipes are achieved, and construction safety is improved.
Patent Information
- Application Number
- CN202411402539.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-09
- Publication Date
- 2024-11-15
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Existing construction equipment can easily cause the steel pipe to fall when lifting the steel pipe to a high place and unloading it, which poses safety risks. Because the lack of an automatic unloading structure, workers need to operate manually, resulting in changes in the center of gravity of the steel pipe and the risk of falling.
A building material handling device is designed, including ropes, handling boxes, sealing plates, slide rods and pushing structures. Through the self-weight effect of the sealing plate and the return spring drive, the function of steel pipes automatically unloading to the platform at the highest point is avoided by manual labor. operate.
The automatic unloading of steel pipes is realized, which improves safety, avoids the risk of steel pipes falling, simplifies the operation process, and enhances construction safety.
Smart Images

Figure CN118958711A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building material handling, and in particular relates to a building material handling device and a handling method thereof. Background Art
[0002] Steel pipes of various lengths are used in construction. They have the following uses in construction: 1. Support and temporary structures; 2. Steel pipes are used as supports and formwork supports during concrete pouring; 3. They are used in the piping system in the building; 4. They are part of columns, beams and trusses; 5. They are used as materials for safety railings and guardrails. Therefore, construction often encounters situations where steel pipes need to be transported to high places.
[0003] The equipment used for steel pipe lifting in existing construction includes the following components: a crane, a lifting chain, a hook and an operating system; the crane can lift the steel pipe in the vertical direction, and the steel pipe is connected to the crane through a lifting chain. The hook is connected to the lifting chain and the steel pipe respectively, and is used to directly mount the steel pipe. When lifting the steel pipe, the hook is connected to the center or both ends of the steel pipe for lifting. The operating system includes an electronic control system, an operating panel and a remote control device, which are used to accurately control the lifting operation.
[0004] The existing steel pipe lifting equipment does not have a structure for automatically unloading the steel pipe. After the steel pipe is lifted to a suitable height, the staff needs to separate the hook from the steel pipe. The center of gravity of the steel pipe will change during the separation process. Therefore, the steel pipe is likely to fall during this process, posing a safety hazard. Summary of the invention
[0005] The purpose of the present invention is to provide a construction material handling device, which solves the problem that the steel pipes are easy to fall off when unloading after being lifted to a high place in the prior art.
[0006] The technical solution adopted by the present invention is a construction material handling device, comprising:
[0007] Two ropes are provided, and the upper ends of the two ropes are connected to the lifting structure;
[0008] The transport structure comprises a transport box, a sealing plate, a sliding rod, a positioning block and a protruding plate, two opposite sides of the transport box are respectively connected to the lower ends of the ropes, one side of the transport box is an open structure, the sliding rod is horizontally arranged on the open side of the transport box and is slidably connected to the transport box, the sliding rod can slide in a vertical direction, the upper side of the sealing plate is hinged to the sliding rod, the positioning block is slidably arranged at the bottom of the transport box and the positioning block contacts the lower side of the sealing plate in the initial position, and the protruding plate is fixedly connected to the middle part of the bottom side of the sealing plate;
[0009] The sealing plate pushing structure includes a pushing slider, a reset spring and a reset plate. The pushing slider is slidably arranged at the bottom of the transport box, the reset plate is fixed to the bottom of the transport box and on a side away from the sealing plate, the reset spring is located between the pushing slider and the reset plate, and the pushing slider can push out the lower side of the sealing plate when it slides toward the direction close to the sealing plate.
[0010] The sliding rod comprises a middle round rod and square rods fixedly connected at both ends thereof, the square rods at both ends are slidably connected with the opening side of the transport box, and the upper side of the sealing plate is hinged with the round rod.
[0011] The side of the positioning block facing the building is an inclined surface. There are two positioning blocks, which are respectively located on both sides of the pushing slider. A wedge block corresponding to each positioning block is also provided on the top side of the building, and the inclined surface on the wedge block is arranged corresponding to the inclined surface on the positioning block.
[0012] Two vertical partitions and a horizontal plate are arranged in the transport box. The two vertical partitions are respectively arranged at the two ends of the transport box and correspond to each rope respectively. The horizontal plate is fixedly connected to the lower ends of the two vertical partitions. The two vertical partitions and the horizontal plate divide the interior of the transport box into a steel pipe storage area in the middle and a transmission area on the outside. A first gear corresponding to each positioning block is arranged in the transmission area. The lower side of the first gear passes through the bottom surface of the transmission area. The top two sides of the positioning block are slidably connected with the bottom surface of the transmission area. A first rack meshing with the first gear is arranged in the top center of the positioning block. A first support shaft supporting the rotation of the first gear is arranged in each transmission area.
[0013] The first supporting shaft is also provided with a second gear for driving the sealing plate to move, and the sealing plate is provided with a second rack meshing with the second gear.
[0014] A second support shaft parallel to the first support shaft is also provided in each transmission area, a transmission gear set is provided between the first support shaft and the second support shaft, and a third gear for driving the push slider is also provided on the second support shaft. The lower side of the third gear passes through the bottom of the transmission area, and a third rack meshing with the third gear is also provided on the top of the push slider.
[0015] A first limiting wedge block is arranged on the side of each positioning block facing the pushing slider, and a second limiting wedge block corresponding to each first limiting wedge block is arranged on the pushing slider, the inclined surface on the first limiting wedge block is arranged corresponding to the inclined surface on the second limiting wedge block, and the second limiting wedge block is slidably connected to the pushing slider and can slide in the direction approaching and away from the first limiting wedge block.
[0016] The lifting structure adopts a winding drum, and the upper ends of the two ropes are wound on the corresponding winding drums. A fixed pulley is also provided on the lower side of the winding drum. The ropes are suspended downward after passing around the fixed pulley.
[0017] A third limiting wedge block is arranged at the bottom of the sealing plate, a fourth wedge-shaped limiting block corresponding to the third limiting wedge block is arranged on the top surface of the positioning block, and the inclined surface on the third limiting wedge block faces the building and is arranged corresponding to the inclined surface on the fourth wedge-shaped limiting block.
[0018] Another technical solution adopted by the present invention is a construction material handling method, based on the construction material handling device as described above, specifically comprising the following steps:
[0019] When the transport box is at the lowest point, place the steel pipe to be transported in the transport box;
[0020] Lift the transport box and the steel pipes inside upwards;
[0021] The positioning block is slid away from the building, and then the sealing plate is slid downward, and at the same time, the slider is pushed out to push the lower end of the sealing plate onto the building platform, and then the steel pipe automatically slides down along with the inclined sealing plate.
[0022] The beneficial effects of the present invention are:
[0023] When the material is unloaded, the worker only needs to control the positioning block arranged at the bottom of the sealing plate to move in the direction away from the building. After that, when the positioning block leaves the bottom of the sealing plate, the sealing plate starts to slide downward under the action of its own weight, and because the sealing plate is hinged to the opening side of the carrying box through the sliding rod, after the sealing plate is separated from the limiting effect of the positioning block, it starts to push the sealing plate to rotate a certain angle under the action of the return spring, and finally makes the upper end of the sealing plate hinged to the carrying box, and the lower end of the sealing plate overlaps the platform at the top of the building. At this time, the inclined sealing plate acts as a bridge, and the steel pipe in the carrying box also rolls onto the platform along the sealing plate. In this process, the unloading of the steel pipe can be automatically completed without the need for workers to unload, thereby avoiding the problem of safety hazards in unloading the steel pipe. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a structural schematic diagram of a construction material handling device of the present invention;
[0025] Figure 2 It is a schematic diagram of the installation of a positioning block on a building material handling device of the present invention;
[0026] Figure 3 It is a schematic diagram of a lifting structure on a construction material handling device of the present invention;
[0027] Figure 4 It is a schematic diagram of the installation of a push slider on a building material handling device of the present invention;
[0028] Figure 5 This is a structural schematic diagram of an upper slide bar of a building material handling device of the present invention.
[0029] Figure 6 This is a transmission schematic diagram of a sliding block on a building material handling device of the present invention.
[0030] Figure 7 The present invention is a schematic diagram of the position limiting of a sealing plate on a building material handling device.
[0031] In the figure, 1. winding drum, 2. rope, 3. fixed pulley, 4. carrying box, 5. sealing plate, 6. slide rod, 7. positioning block, 8. pushing slider, 9. reset spring, 10. reset plate, 11. protruding plate, 12. round rod, 13. square rod, 14. wedge block, 15. first limiting wedge block, 16. second limiting wedge block, 17. first gear, 18. first support shaft, 19. second gear, 20. second rack, 21. first rack, 22. second support shaft, 23. third gear, 24. third rack, 25. third limiting wedge block, 26, fourth limiting wedge block. DETAILED DESCRIPTION
[0032] The present invention is described in detail below in conjunction with the accompanying drawings and specific implementation methods. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and cannot be used to limit the protection solution of the present invention.
[0033] Steel pipes of various lengths are used in construction. They have the following uses in construction: 1. Support and temporary structures; 2. Steel pipes are used as supports and formwork supports during concrete pouring; 3. They are used in the piping system in the building; 4. They are part of columns, beams and trusses; 5. They are used as materials for safety railings and guardrails. Therefore, construction often encounters situations where steel pipes need to be transported to high places.
[0034] The equipment used for steel pipe lifting in existing construction includes the following components: a crane, a lifting chain, a hook and an operating system; the crane can lift the steel pipe in the vertical direction, connect the steel pipe to the crane through the lifting chain, and the hook is connected to the lifting chain and the steel pipe respectively, so as to directly mount the steel pipe, and when lifting the steel pipe, the hook is connected to the center or both ends of the steel pipe for lifting; when the center lifting point is used, it is required to set the lifting point at the center of the steel pipe as much as possible to evenly distribute the weight and avoid the steel pipe from tilting or bending during the lifting process. For longer steel pipes, it is usually necessary to set a lifting point at each end to ensure the stability of the steel pipe during the lifting process.
[0035] The existing steel pipe lifting equipment does not have a structure for automatically unloading the steel pipe. After the steel pipe is lifted to a suitable height, the staff needs to separate the hook from the steel pipe. The center of gravity of the steel pipe will change during the separation process. Therefore, the steel pipe is likely to fall during this process, posing a safety hazard.
[0036] The present invention discloses a construction material handling device, such as Figure 1-Figure 3 As shown, it includes: a rope 2, a transport structure and a sealing plate pushing structure; two ropes are provided, and the upper ends of the two ropes are connected to a lifting structure; the transport structure includes a transport box 4, a sealing plate 5, a slide bar 6, a positioning block 7 and a protruding plate 11, two opposite sides of the transport box 4 are respectively connected to the lower ends of the rope 2, one side of the transport box 4 is an open structure, the slide bar 6 is horizontally arranged on the open side of the transport box 4 and is slidably connected to the transport box 4, the slide bar 6 can slide in the vertical direction, the upper side of the sealing plate 5 is hinged to the slide bar 6, and the positioning block 7 slides The positioning block 7 is movably arranged at the bottom of the transport box 4 and in the initial position, it contacts the lower side of the sealing plate 5, and the protruding plate 11 is fixedly connected to the middle part of the bottom side of the sealing plate 5; the sealing plate pushing structure includes a pushing slider 8, a reset spring 9 and a reset plate 10, the pushing slider 8 is slidably arranged at the bottom of the transport box 4, the reset plate 10 is fixed at the bottom of the transport box 4 and away from the side of the sealing plate 5, the reset spring 9 is located between the pushing slider 8 and the reset plate 10, and the pushing slider 8 can push out the lower side of the sealing plate 5 when it slides in the direction close to the sealing plate 5.
[0037] When the construction material handling device disclosed in the present invention handles steel pipes for construction, the steel pipes to be handled are placed in the handling box 4, and then one side of the handling box 4 is sealed by the sealing plate 5, and then the handling box 4 and the steel pipes inside it are carried upward. When they are carried to the highest point and need to be unloaded to the platform, there is no need for workers to manually unload. During unloading, it is only necessary to control the positioning block 7 set at the bottom of the sealing plate 5 to move in the direction away from the building. After that, when the positioning block 7 leaves the bottom of the sealing plate 5, the sealing plate 5 starts to slide downward under the action of its own weight, and because the sealing plate The plate 5 is hinged to the open side of the transport box 4 through the sliding rod 6. Therefore, after the sealing plate 5 is separated from the limiting effect of the positioning block 7, the sealing plate 5 begins to be pushed to rotate a certain angle under the action of the return spring 9, and finally the upper end of the sealing plate 5 is hinged to the transport box, and the lower end of the sealing plate 5 overlaps the platform on the top of the building. At this time, the inclined sealing plate 5 acts as a bridge, and the steel pipes in the transport box 4 also roll down to the platform along the sealing plate 5. In this process, the unloading of the steel pipes can be completed automatically without the need for workers to unload, thereby avoiding the current safety hazards when unloading steel pipes.
[0038] like Figure 5As shown, in order to allow the sealing plate 5 to slide freely on the opening side of the transport box 4 and to rotate a certain angle, the slide bar 6 disclosed in this embodiment includes a middle round bar 12 and square bars 13 fixedly connected at both ends thereof, the square bars 13 at both ends are slidably connected to the opening side of the transport box 4, and the upper side of the sealing plate 5 is hinged to the round bar 12. In this way, the square bars 13 at both ends of the slide bar 6 are slidably connected to the opening side because the sealing plate can be driven to slide freely in the vertical direction of the opening side, and because the upper side of the sealing plate 5 is also hinged to the round bar 12, the sealing plate 5 can rotate a certain angle under the action of the return spring 9.
[0039] In order to enable the positioning block 7 to automatically slide away from the building when the transport box 4 is transported to the highest point, the positioning block 7 disclosed in this embodiment has an inclined surface on the side facing the building, and two positioning blocks 7 are provided. The two positioning blocks 7 are respectively located on both sides of the push slider 8. A wedge block 14 corresponding to each positioning block 7 is also provided on the side of the top of the building, and the inclined surface on the wedge block 14 is arranged corresponding to the inclined surface on the positioning block 7. Therefore, when the positioning block 7 slides to a certain height with the transport box 4, the positioning block 7 contacts the wedge block 14 and the inclined surfaces of the two generate thrust against each other, because the wedge block 14 is connected to the valley bottom of the side of the building, and because the positioning block 7 continues to move upward with the transport box 4, the positioning block 7 will start to slide away from the building under the squeezing action of the wedge block 14.
[0040] Furthermore, two vertical partitions and a horizontal plate are provided in the transport box 4. The two vertical partitions are respectively arranged at the two ends of the transport box 4 and respectively correspond to each rope 2. The horizontal plate is fixedly connected to the lower ends of the two vertical partitions. The two vertical partitions and the horizontal plate divide the interior of the transport box 4 into a steel pipe storage area in the middle and a transmission area on the outside. A first gear 17 corresponding to each positioning block 7 is provided in the transmission area. The lower side of the first gear 17 passes through the bottom surface of the transmission area. The top two sides of the positioning block 7 are slidably connected to the bottom surface of the transmission area. A first rack 21 meshing with the first gear 17 is provided in the top center of the positioning block 7. A first support shaft 18 supporting the rotation of the first gear 17 is provided in each transmission area. Therefore, when the positioning block 7 starts to slide in the direction away from the building, it can drive the first gear 17 and the first support shaft 18 to rotate; at the same time, the first support shaft 18 is also provided with a second gear 19 for driving the sealing plate 5 to move, and the sealing plate 5 is provided with a second rack 20 meshing with the second gear 19; therefore, as the first support shaft 18 rotates, it can act on the sealing plate 5 through the second gear 19, so that the sealing plate slides downward, and therefore, under the action of the sealing plate's own weight, the second gear 19 drives the sealing plate 5 to slide downward, thereby making the stability of the entire handling device higher.
[0041] like Figure 6As shown, a second support shaft 22 parallel to the first support shaft 18 is also provided in each transmission area, and a transmission gear set is provided between the first support shaft 18 and the second support shaft 22. Under the action of the transmission gear set, the first support shaft 18 and the second support shaft 22 rotate in opposite directions. A third gear 23 for driving the push slider 8 to move is also provided on the second support shaft 22. The lower side of the third gear 23 passes through the bottom of the transmission area, and a third rack 24 meshing with the third gear 23 is also provided on the top of the push slider 8. In this way, the second support shaft can drive the push slider 8 to slide at the bottom of the transport box through the mutually meshing third gear 23 and the third rack 24 while rotating with the first support shaft 18, and the sliding direction of the push slider 8 is opposite to the sliding direction of the positioning block 7. Therefore, the push slider 8 can lift the lower side of the sealing plate when the sealing plate 5 falls and make its end overlap with the platform of the building, thereby facilitating the unloading of the steel pipe.
[0042] like Figure 4 As shown, during the hanging process, in order to overcome the elastic force of the return spring 9 and keep the pushing slider 8 stationary, each positioning block 7 disclosed in this embodiment is provided with a first limiting wedge block 15 on the side facing the pushing slider 8, and the pushing slider 8 is provided with a second limiting wedge block 16 corresponding to each first limiting wedge block 15, and the inclined surface on the first limiting wedge block 15 is arranged corresponding to the inclined surface on the second limiting wedge block 16, and the second limiting wedge block 16 is slidably connected to the pushing slider 8 and can slide in the direction of approaching and moving away from the first limiting wedge block 15. Therefore, during the hanging process, the positioning block 7 only slides in the vertical direction with the transport box 4 but not in the horizontal direction. At this time, the first limiting wedge block 15 on the positioning block 7 interacts with the second limiting wedge block 16 on the pushing slider 8, so that the pushing slider 8 can overcome the elastic force of the return spring 9 and cannot slide in the direction close to the building. After the positioning block 7 slides in the direction away from the building under the action of the wedge block 14, the first limiting wedge block 15 on the positioning block 7 acts on the second limiting wedge block 16 on the pushing slider 8, so that the second limiting wedge block 16 slides in the direction away from the first limiting wedge block 15. At this time, the first limiting wedge block 15 will no longer restrict the second limiting wedge block 16. At this time, under the action of the return spring 9, the pushing slider 8 starts to slide and pushes the lower end of the sealing plate out.
[0043] like Figure 7As shown, in order to meet the requirements of normal suspension, that is, the sealing plate will not rotate arbitrarily during the suspension process, a third limiting wedge block 25 is arranged at the bottom of the sealing plate 5 disclosed in this embodiment, and a fourth wedge limiting block 26 corresponding to the third limiting wedge block 25 is arranged on the top surface of the positioning block 7. The inclined surface on the third limiting wedge block 25 faces the building and is arranged corresponding to the inclined surface on the fourth wedge limiting block 26. Therefore, during the hanging process, the fourth wedge limiting block 26 limits the third limiting wedge block 25 and the sealing plate 5, so that the sealing plate 5 does not rotate arbitrarily. When the positioning block 7 slides in the horizontal direction, the third limiting wedge block 25 will be squeezed under the action of the fourth wedge limiting block 26 and the sealing plate 5 will be driven to slide upward for a short distance. Finally, after the positioning block 7 slides over, the sealing plate 5 starts to slide downward.
[0044] The present invention also discloses a construction material handling method, based on the construction material handling device as described above, characterized in that it specifically comprises the following steps:
[0045] When the transport box 4 is at the lowest point, the steel pipe to be transported is placed in the transport box 4;
[0046] Lift the transport box 4 and the steel pipe inside upwards;
[0047] The positioning block 7 is slid away from the building, and then the sealing plate 5 slides downward, and at the same time, the pushing slider 8 slides out to push the lower end of the sealing plate 5 onto the building platform, and then the steel pipe automatically slides down along with the inclined sealing plate 5.
[0048] The embodiments described above are only preferred specific implementation methods of the present invention, and the protection scope of the present invention is not limited thereto. Any simple changes or equivalent replacements of the technical solutions that can be obviously obtained by any technician familiar with the field within the technical scope disclosed in the present invention belong to the protection scope of the present invention.
Claims
1. A construction material handling device, characterized in that: include: Two ropes (2) are provided, and the upper ends of the two ropes (2) are connected to a lifting structure; A transport structure, comprising a transport box (4), a sealing plate (5), a sliding rod (6), a positioning block (7) and a protruding plate (11), wherein two opposite side surfaces of the transport box (4) are respectively connected to the lower end of the rope (2), one side of the transport box (4) is an open structure, the sliding rod (6) is horizontally arranged on the open side of the transport box (4) and is slidably connected to the transport box (4), the sliding rod (6) can slide in a vertical direction, the upper side of the sealing plate (5) is hinged to the sliding rod (6), the positioning block (7) is slidably arranged at the bottom of the transport box (4) and in an initial position, the positioning block (7) contacts the lower side of the sealing plate (5), and the protruding plate (11) is fixedly connected to the middle part of the bottom side of the sealing plate (5); The sealing plate pushing structure comprises a pushing slider (8), a reset spring (9) and a reset plate (10), wherein the pushing slider (8) is slidably arranged at the bottom of a transport box (4), the reset plate (10) is fixed at the bottom of the transport box (4) and at a side away from the sealing plate (5), the reset spring (9) is located between the pushing slider (8) and the reset plate (10), and the pushing slider (8) can push out the lower side of the sealing plate (5) when sliding in a direction close to the sealing plate (5).
2. A construction material handling device according to claim 1, characterized in that: The sliding rod (6) comprises a middle round rod (12) and square rods (13) fixedly connected at both ends thereof, the square rods (13) at both ends are slidably connected to the opening side of the transport box (4), and the upper side of the sealing plate (5) is hinged to the round rod (12).
3. A construction material handling device according to claim 1, characterized in that: The side of the positioning block (7) facing the building is an inclined surface. Two positioning blocks (7) are provided. The two positioning blocks (7) are respectively located on both sides of the pushing slider (8). A wedge block (14) corresponding to each positioning block (7) is also provided on the top side of the building. The inclined surface on the wedge block (14) is arranged corresponding to the inclined surface on the positioning block (7).
4. A construction material handling device according to claim 3, characterized in that: Two vertical partitions and a horizontal plate are arranged in the transport box (4). The two vertical partitions are respectively arranged at the two ends of the transport box (4) and are respectively arranged corresponding to each of the ropes (2). The horizontal plate is fixedly connected to the lower ends of the two vertical partitions. The two vertical partitions and the horizontal plate divide the interior of the transport box (4) into a steel pipe storage area in the middle and a transmission area on the outside. The transmission area is provided with a first gear (17) corresponding to each of the positioning blocks (7). The lower side of the first gear (17) passes through the bottom surface of the transmission area. The top two sides of the positioning block (7) are slidably connected to the bottom surface of the transmission area. A first rack (21) meshing with the first gear (17) is arranged in the center of the top of the positioning block (7). Each of the transmission areas is provided with a first support shaft (18) supporting the rotation of the first gear (17).
5. A construction material handling device according to claim 4, characterized in that: The first support shaft (18) is also provided with a second gear (19) for driving the sealing plate (5) to move, and the sealing plate (5) is provided with a second rack (20) meshing with the second gear (19).
6. A construction material handling device according to claim 4, characterized in that: A second support shaft (22) parallel to the first support shaft (18) is also provided in each transmission area, a transmission gear set is provided between the first support shaft (18) and the second support shaft (22), a third gear (23) for driving the pushing slider (8) to move is also provided on the second support shaft (22), the lower side of the third gear (23) passes through the bottom of the transmission area, and a third rack (24) meshing with the third gear (23) is also provided on the top of the pushing slider (8).
7. A construction material handling device according to claim 4, characterized in that: A first limiting wedge block (15) is arranged on the side of each positioning block (7) facing the pushing sliding block (8), and a second limiting wedge block (16) corresponding to each first limiting wedge block (15) is arranged on the pushing sliding block (8), the inclined surface on the first limiting wedge block (15) is arranged corresponding to the inclined surface on the second limiting wedge block (16), and the second limiting wedge block (16) is slidably connected to the pushing sliding block (8) and can slide in a direction approaching and away from the first limiting wedge block (15).
8. A construction material handling device according to claim 1, characterized in that: The lifting structure adopts a winding drum (1), the upper ends of the two ropes (2) are wound on the corresponding winding drum (1), and a fixed pulley (3) is also arranged on the lower side of the winding drum (1). The rope (2) is suspended downward after passing through the fixed pulley (3).
9. A construction material handling device according to claim 1, characterized in that: A third limiting wedge block (25) is arranged at the bottom of the sealing plate (5), and a fourth wedge-shaped limiting block (26) corresponding to the third limiting wedge block (25) is arranged on the top surface of the positioning block (7), and the inclined surface on the third limiting wedge block (25) faces the building and is arranged corresponding to the inclined surface on the fourth wedge-shaped limiting block (26).
10. A method for transporting construction materials, based on the construction material transporting device as claimed in claim 1, characterized in that: The specific steps include: When the transport box (4) is at the lowest position, placing the steel pipe to be transported in the transport box (4); Lift the transport box (4) and the steel pipe inside upwards; The positioning block (7) is slid in a direction away from the building, and then the sealing plate (5) slides downward, and at the same time, the pushing slider (8) slides out to push the lower end of the sealing plate (5) onto the building platform, and then the steel pipe automatically slides down along with the inclined sealing plate (5).