Pumped storage power station reservoir characteristic water level scheme optimization method and system

By optimizing the characteristic water level of pumped storage power stations using the grey ideal solution method and entropy weight method, the problems of complex selection of characteristic water levels and insufficient applicability in existing technologies are solved, achieving efficient and accurate optimization of characteristic water levels, which is suitable for the planning and design of power stations with large head variations.

CN118964779APending Publication Date: 2024-11-15SHANDONG ELECTRIC POWER ENG CONSULTING INST CORP
View PDF 0 Cites 4 Cited by

Patent Information

Application Number
CN202410893318.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-04
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

Existing technologies cannot effectively solve the problem of selecting characteristic water levels for pumped storage power stations, especially in power stations with high head and large head variations. Existing methods are difficult to apply, resulting in significant human influence and complex selection.

Method used

By combining the grey ideal solution method and the entropy weight method, an evaluation index system is constructed to select the optimal characteristic water level model for pumped storage power stations. The grey relational ideal solution method is used to optimize the characteristic water level scheme. The calculation mode under different construction conditions, including the construction of new upper reservoir, lower reservoir and linkage mode, is combined to optimize the selection of characteristic water level.

Benefits of technology

A method for optimizing characteristic water levels in pumped storage power stations is provided. This method is simple and flexible, and can calculate the optimal characteristic water level scheme in a short time. It improves the calculation accuracy and applicability, reduces the influence of human factors, and meets the planning and design requirements of power stations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118964779A_ABST
    Figure CN118964779A_ABST
Patent Text Reader

Abstract

The invention belongs to the field of pumped storage power stations, and provides a pumped storage power station reservoir characteristic water level scheme optimization method and system. The pumped storage power station reservoir characteristic water level scheme optimization method comprises the following steps: screening corresponding characteristic water level scheme calculation modes according to pumped storage power station engineering related data and actual construction working conditions to obtain a plurality of to-be-selected characteristic water level schemes; the method comprises the following steps of: screening out preferable evaluation indexes of the characteristic water level of the pumped storage power station from preset key influence factors of operation characteristics of the pumped storage power station and characteristic water level selection in a planning and design stage of the pumped storage power station, quantifying qualitative indexes in the screened evaluation indexes, and constructing an evaluation scheme decision matrix; based on the evaluation scheme decision matrix, calculating objective weights of evaluation indexes by adopting an entropy weight method, and constructing an index weight matrix; and based on the index weight matrix, performing optimal selection from the to-be-selected characteristic water level schemes by using a grey correlation ideal solution to obtain an optimal characteristic water level scheme of the upper and lower reservoirs of the power station.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the field of pumped storage power stations, and in particular relates to a method and system for optimizing a characteristic water level scheme of a pumped storage power station reservoir. Background Art

[0002] The statements in this section merely provide background information related to the present invention and do not necessarily constitute prior art.

[0003] At present, the research on the selection of reservoir characteristic water level is mainly focused on the selection of characteristic water level of conventional hydropower stations. For example, a multi-objective variable fuzzy optimization method is used to optimize the characteristic water level of hydropower stations, and it is applied to the planning and design of the Altash Power Station in Xinjiang; and based on GIS and multi-subgroup genetic neural network model, the nonlinear problem in the optimization of normal water storage level schemes is solved, effectively reducing the problem of excessive influence of human subjective factors on decision-making results. However, the above methods are only applicable to conventional hydropower stations. The operating characteristics of pumped storage power stations are different from those of conventional hydropower stations, and the above methods cannot be simply applied to complete the optimization of the characteristic water level of pumped storage power stations.

[0004] The characteristic water level of a reservoir is a crucial parameter of a water conservancy project, which is used to reflect the operating status of a water conservancy project. In the planning and design of a pumped storage power station, the selection of the characteristic water level has a significant impact on the scale, investment, construction period, and economic benefits of the power station, and is one of the main tasks of the power station planning and design. For power stations with high heads, large head fluctuations, and general upper and lower reservoir conditions, the process of formulating characteristic water level ratio selection plans is more complicated. Summary of the invention

[0005] In order to solve the above technical problems, the present invention provides a method and system for optimizing the characteristic water level scheme of a pumped-storage power station reservoir, which can formulate and optimize the characteristic water level scheme of the pumped-storage power station according to the model, analyze and propose the characteristic water level and excavation scheme under different construction conditions of the pumped-storage power station, and use the grey ideal solution to determine the optimal characteristic water level scheme.

[0006] In order to achieve the above object, the present invention adopts the following technical solution:

[0007] A first aspect of the present invention provides a method for optimizing a characteristic water level scheme of a pumped storage power station reservoir.

[0008] In one or more embodiments, a method for optimizing a characteristic water level scheme of a pumped storage power station reservoir is provided, comprising:

[0009] Obtain data related to pumped storage power station projects;

[0010] According to the relevant data of the pumped storage power station project and the actual construction conditions, the corresponding characteristic water level scheme calculation mode is screened to obtain several candidate characteristic water level schemes; among them, the characteristic water level scheme calculation mode includes three calculation modes: new upper reservoir, new lower reservoir and upper and lower reservoir linkage;

[0011] From the preset key influencing factors of the pumped storage power station operation characteristics and the characteristic water level selection in the planning and design stage of the pumped storage power station, the preferred evaluation index of the characteristic water level of the pumped storage power station is screened out, and the qualitative indexes in the screened evaluation indexes are quantified, and the evaluation scheme decision matrix is ​​constructed and normalized;

[0012] Based on the evaluation scheme decision matrix, the entropy weight method is used to calculate the objective weights of the evaluation indicators, and then the indicator weight matrix is ​​constructed; based on the indicator weight matrix, the grey correlation ideal solution is used to select the optimal characteristic water level scheme from the candidate characteristic water level schemes, and the optimal characteristic water level schemes of the upper and lower reservoirs of the power station are obtained.

[0013] A second aspect of the present invention provides a system for optimizing characteristic water level schemes of a pumped storage power station reservoir.

[0014] In one or more embodiments, a pumped storage power station reservoir characteristic water level scheme optimization system includes:

[0015] A pumped storage power station project data acquisition module, which is used to obtain pumped storage power station project related data;

[0016] The module for calculating the characteristic water level scheme to be selected is used to select the corresponding characteristic water level scheme calculation mode according to the relevant data of the pumped storage power station project and the actual construction conditions, and obtain several characteristic water level schemes to be selected; among them, the characteristic water level scheme calculation mode includes three calculation modes: newly built upper reservoir, newly built lower reservoir and upper and lower reservoir linkage;

[0017] An evaluation scheme decision matrix construction module is used to select the preferred evaluation index of the characteristic water level of the pumped-storage power station from the preset key influencing factors of the operation characteristics of the pumped-storage power station and the characteristic water level selection in the planning and design stage of the pumped-storage power station, quantify the qualitative indicators in the selected evaluation indicators, construct the evaluation scheme decision matrix and normalize it;

[0018] The optimal characteristic water level scheme determination module is used to calculate the objective weights of the evaluation indicators based on the evaluation scheme decision matrix using the entropy weight method, and then construct an indicator weight matrix; based on the indicator weight matrix, the grey correlation ideal solution is used to select the optimal characteristic water level scheme from the candidate characteristic water level schemes to obtain the optimal characteristic water level schemes for the upper and lower reservoirs of the power station.

[0019] A third aspect of the present invention provides a computer-readable storage medium.

[0020] A computer-readable storage medium stores a computer program, which, when executed by a processor, implements the steps in the above-mentioned method for optimizing the characteristic water level scheme of a pumped-storage power station reservoir.

[0021] A fourth aspect of the present invention provides an electronic device.

[0022] An electronic device comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the steps in the method for optimizing the characteristic water level scheme of a pumped storage power station reservoir are implemented as described above.

[0023] Compared with the prior art, the present invention has the following beneficial effects:

[0024] (1) The method for optimizing the characteristic water level scheme of a pumped-storage power station reservoir of the present invention includes the formulation and optimization of the characteristic water level scheme (mainly the normal water storage level and the dead water level) of the pumped-storage power station, and has strong applicability, and can provide a technical reference for the selection of the characteristic water level in the planning and design stage of the pumped-storage power station; the principle is simple, the operation is concise and flexible, and it is easy to implement. It can rely on programming programs (such as Python programs) to analyze the basic data of a specific pumped-storage power station, calculate and formulate the characteristic water level scheme of the power station in a short time, and perform scheme optimization to obtain the optimal characteristic water level scheme.

[0025] (2) The present invention also proposes a method for calculating the power generation capacity of a pumped storage power station based on the energy conversion principle of the upper and lower reservoirs. This method assumes the water level at the end of a time period and iterates the power generation capacity in the order of the time period. Compared with the original method of estimating the power generation capacity using the average power generation head, the calculation result is more accurate and more in line with reality.

[0026] (3) The present invention establishes a characteristic water level scheme optimization model based on the grey correlation ideal solution, providing a method system for optimizing the characteristic water level of a pumped storage power station. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.

[0028] Figure 1 is a schematic diagram of an electronic device according to an embodiment of the present invention;

[0029] Figure 2 It is a flow chart of a method for optimizing a characteristic water level scheme of a pumped storage power station reservoir according to an embodiment of the present invention. DETAILED DESCRIPTION

[0030] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.

[0031] It should be noted that the following detailed descriptions are all illustrative and intended to provide further explanation of the present invention. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present invention belongs.

[0032] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit exemplary embodiments according to the present invention. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprising" and / or "including" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.

[0033] Figure 1 is a flow chart of a method for optimizing a characteristic water level scheme of a pumped storage power station reservoir in an embodiment of the present invention. Figure 1 The method for optimizing the characteristic water level scheme of the pumped storage power station reservoir in the present embodiment may include:

[0034] S101, obtaining data related to the pumped storage power station project.

[0035] In the specific implementation process, it is necessary to first analyze the main influencing factors of the characteristic water level scheme of the pumped storage power station, summarize the basic input data required for the characteristic water level scheme calculation model, and then process the original data of the pumped storage power station project, screen out the basic data required for the model, and eliminate other irrelevant data. After screening, the basic input of the characteristic water level scheme model can be basically obtained. It includes but is not limited to the upper and lower reservoir water level-reservoir capacity relationship curve, the elevation of the mountain in the reservoir area, the elevation of the top plate of the impermeable layer, the average sediment content of the dam site for many years, the average runoff of the dam site for many years, the evaporation increase and loss of the reservoir, the monthly leakage rate of the reservoir, and the average monthly temperature data of the coldest year in history.

[0036] After screening out the basic input data required for model calculation, it is necessary to process the missing values ​​and outliers. The processing strategy is: use manual completion for single missing values, and use linear interpolation method to supplement the missing values ​​of continuous data sequences; delete the obviously abnormal data such as mutation values ​​and excess values ​​and treat them as missing values.

[0037] S102, according to the relevant data of the pumped storage power station project and the actual construction conditions, the corresponding characteristic water level scheme calculation mode is screened to obtain several candidate characteristic water level schemes; among which, the characteristic water level scheme calculation mode includes three calculation modes: a new upper reservoir, a new lower reservoir and a linkage between the upper and lower reservoirs.

[0038] The steps for constructing the characteristic water level scheme calculation mode are as follows:

[0039] S102, based on the topographic and geological conditions of the upper and lower reservoirs, comprehensively evaluate the height of the ridges around the reservoirs, the height of the passes and the influencing factors related to reservoir leakage, and calculate the ultimate characteristic water level values ​​of the upper and lower reservoirs.

[0040] The specific calculation process of step S102 is as follows:

[0041] The limit characteristic water level mainly refers to the limit normal water storage level and the limit dead water level. The limit normal water storage level of the reservoir generally does not exceed the maximum elevation of the mountains around the reservoir, the minimum elevation of the top plate of the impermeable layer around the reservoir, and the lowest elevation of the watershed around the reservoir. The minimum value of the above three elevations is taken as the limit normal water storage level of the reservoir, that is:

[0042] z n =min{z m , z a , z s}

[0043] Among them, z nl is the limit normal water storage level; m is the maximum elevation of the Kuzhou mountain; a is the minimum elevation of the impermeable layer top plate around the reservoir; s It is the lowest elevation of the Kuzhou watershed.

[0044] The ultimate dead water level needs to be determined by comprehensively evaluating the siltation of the reservoir and the layout requirements of the inlet / outlet buildings. It is generally believed that the dead water level of the reservoir shall not be lower than the siltation elevation of the designed operating life of the power station. In addition, since the inlet / outlet of the pumped storage power station has high requirements for flow conditions, the water flow conditions must meet the two-way water flow conditions of power generation conditions and pumping conditions, and it must be ensured that no suction vortex is generated under various operating conditions. Therefore, when selecting the dead water level, the inlet / outlet of the upper and lower reservoirs must also meet certain conditions.

[0045] The calculation of sediment accumulation volume adopts the empirical formula method, which establishes the relationship between sediment accumulation volume and the multi-year average sediment content of the dam site, multi-year average runoff, porosity of sediment body, bulk density and other parameters. Considering that the amount of bed load sedimentation is 20% of the suspended load, the annual average sedimentation of the sediment body is calculated as follows:

[0046]

[0047] Among them, V0 is the average sediment volume over many years (m 3 / year); a is the ratio of bed load to suspended load volume, which is taken as 20% in this study; P0 is the average sediment content over many years (t / m 3 ); W0 is the multi-year average runoff (m 3 ), D is the sediment discharge rate of the reservoir, ρ is the porosity of the sediment, and γ is the dry bulk density of the sediment.

[0048] The total sedimentation storage capacity within the operating life of the power station is calculated by multiplying the annual sedimentation volume of the reservoir obtained by the empirical formula method by the operating life of the power station. Assuming that the sedimentation is spread flat in the reservoir, the sedimentation storage capacity value is converted into the corresponding sedimentation elevation based on the water level-storage capacity curve of the reservoir.

[0049] The requirements for the arrangement of inlets and outlets are mainly in the following two aspects: First, in order to prevent the inlet and outlet from generating suction vortices, the minimum submerged water depth requirement should be met, that is, the depth from the lower edge of the inlet and outlet top plate to the lowest water level that may be encountered should be greater than a certain value; secondly, according to the experience of pumped storage power station construction, the Froude number of the inlet and outlet that does not generate suction vortices should be less than 0.23, and the water depth above the inlet and outlet top plate should be no less than 2.0 m .

[0050] The formula for the submerged water depth to prevent the generation of suction vortex is estimated using the Gordon formula, which is specifically expressed as:

[0051]

[0052] Among them, v1 is the flow velocity of the gate hole section; d is the gate hole height; c is the coefficient related to the geometric shape of the inlet and outlet. When water is taken forward, c is 0.55, and when water is taken laterally, c is 0.73.

[0053] According to the condition that no suction vortex is generated, the calculation method of the Froude number Fr at the inlet / outlet is required to be:

[0054]

[0055] Wherein, v2 is the average flow velocity at the opening of the trash rack; g is the acceleration due to gravity; Δh is the minimum flooding depth at the opening of the trash rack.

[0056] S1022. Formulate several dead water level plans within the range of the upper and lower reservoir limit characteristic water level values.

[0057] Among them, the steps of formulating several dead water level schemes in step S1022 are:

[0058] After determining the ultimate dead water level, multiple sets of dead water level plans are formulated above this elevation. The dead water level plans are formulated using the exhaustive method, that is, within the range of the ultimate dead water level and the ultimate normal water level elevation of the upper reservoir, with a step length of 1m, several dead water level plans are obtained. These dead water level plans may not all meet the requirements. In the subsequent regulation of reservoir capacity calculation, the dead water level plans that do not meet the actual situation will be eliminated, and the plans that meet the conditions will be retained.

[0059] S1023, utilizing the energy conversion between the upper and lower reservoirs under pumping conditions or power generation conditions, adopting a trial algorithm to calculate the power generation storage capacity of each scheme, and eliminating the scheme that exceeds the upper and lower reservoir limit characteristic water levels.

[0060] The process of calculating the power generation storage capacity in step S1023 is as follows:

[0061] Calculate the power generation reservoir capacity corresponding to each dead water level scheme. In the initial state, the normal water level of the lower reservoir is known. Pumping starts from the normal water level of the lower reservoir, and the normal water level of the upper reservoir is obtained through the energy conversion calculation of the pumping condition; that is, it is known that the upper reservoir is empty in the initial state, the water level is the dead water level, and the lower reservoir is full, the water level is the normal water level; at the same time, according to the typical daily load diagram of the system, the pumping power of the power station in each period under the pumping condition is obtained, and the complete water level change process of the upper and lower reservoirs can be iterated through the trial algorithm.

[0062] In a certain period of time under pumping conditions, it is assumed that the water level of the reservoir rises to a certain elevation at the end of the period. (Here the * sign indicates that the variable is an assumed value, and there is a calculated value corresponding to it). Based on the water level and storage capacity curve of the upper reservoir, the storage capacity of the upper reservoir at the end of the period is At the same time, the water volume change during this period is obtained as follows:

[0063]

[0064] in, is the water volume change value during the period; V is the storage capacity corresponding to the upper reservoir water level at the end of the period; si-1 is the storage capacity corresponding to the water level of the upper reservoir at the beginning of the period. Furthermore, the amount of water added to the upper reservoir is the amount of water reduced in the lower reservoir during the period, from which the storage capacity of the lower reservoir at the end of the period can be obtained, that is:

[0065]

[0066] in, V is the storage capacity corresponding to the reservoir water level at the end of the period; xi-1 It is the storage capacity value corresponding to the reservoir water level at the beginning of the period.

[0067] The above calculation results are based on the assumed value of the reservoir water level at the end of the period. On this basis, it is necessary to verify its rationality through energy conversion calculation under pumping conditions. The specific method is as follows:

[0068] First, calculate the average pumping head ΔH for the period based on the calculation results of the above assumed values i , the calculation method is:

[0069]

[0070] Among them, Z si-1 With Z xi-1 are the upper and lower reservoir water levels at the beginning of the time period respectively; is the upper reservoir water level at the end of the assumed time period; is the water level value corresponding to the reservoir capacity at the end of the period, that is H lost The head loss in power generation conditions needs to be compensated under pumping conditions. The value needs to be determined based on the actual project conditions.

[0071] Then, the average pumping flow rate Q in a period can be calculated based on the average pumping head in the period i ,for:

[0072]

[0073] Among them, η p N is the comprehensive efficiency of the power station under pumping conditions; i It is the pumping power during the period.

[0074] Then, according to the average pumping flow rate during the period, the calculated values ​​of the upper and lower reservoir capacity and water level at the end of the period can be obtained as follows:

[0075] V si =V si-1 +Q i ΔT, Z si =f s (V si )

[0076] V xi =V xi-1 -Q i ΔT, Z xi =f x (V xi )

[0077] Where ΔT is the time period length; f s The function is the upper reservoir water level-storage capacity curve; f x The function is the lower reservoir water level-storage capacity curve. The upper reservoir water level calculated value Z at the end of the period si With the assumed value For comparison, the difference between the two satisfies (allowable error) indicates the reservoir water level at the end of the assumed period is reasonable, the calculation for this period is completed, otherwise it is necessary to re-assume the reservoir water level at the end of the period Repeat the above steps until the error meets the requirements. After the calculation of this period is completed, the water levels of the upper and lower reservoirs at the end of this period are used as the water levels of the upper and lower reservoirs at the beginning of the next period. This iteration is repeated until the pumping process is completed, and finally the power generation capacity, the water level elevation corresponding to the power generation capacity of the upper reservoir, and the elevation of the lower reservoir after the water level drops are obtained.

[0078] Since the dead water level scheme of the upper reservoir is obtained by exhaustively enumerating between the upper reservoir's ultimate dead water level and the ultimate normal water storage level, these dead water level schemes may produce the following two abnormal situations after the power generation capacity calculation: the water level corresponding to the power generation capacity of the upper reservoir is higher than the upper reservoir's ultimate normal water storage level; the water level of the lower reservoir after the water level is reduced is lower than the lower reservoir's ultimate dead water level. The schemes with the above abnormal situations need to be eliminated.

[0079] S1024, for pumped storage power stations located in freezing areas, calculate their frozen standby storage capacity requirements; at the same time, set the water loss standby storage capacity based on the designed low-water period upper and lower reservoir water inflow minus the evaporation and leakage water losses and upstream and downstream water use during the same period of normal operation, based on the cumulative maximum shortfall.

[0080] On the basis of the power generation capacity, the demand for standby capacity is further considered. The standby capacity of the pumped storage power station includes frozen standby capacity and water loss standby capacity. For some pumped storage power stations located in the winter freezing zone, the freezing of the power station reservoir in winter occupies a part of the regulating storage capacity, which may lead to insufficient water for power generation and may have different degrees of impact on the normal operation of the power station. Therefore, it is necessary to consider setting up a certain size of frozen standby capacity to make up for the part of the capacity occupied by the freezing in winter. The calculation method of the frozen standby capacity of the pumped storage power station is to take the product of the designed maximum ice thickness and the reservoir area corresponding to the normal water storage level as the frozen standby capacity of the pumped storage power station, that is, the size of the frozen standby capacity is:

[0081] V bd =δ·S z

[0082] Where δ is the designed maximum ice thickness; S z It is the reservoir area corresponding to the normal water storage level.

[0083] At the same time, it is necessary to set the water loss reserve storage capacity according to the water inflow into the upper and lower reservoirs during the designed low-water period, minus the evaporation and leakage water losses in the same period of normal operation and the upstream and downstream water use. The cumulative maximum deficit value, among which the leakage loss is obtained by multiplying the monthly leakage rate of the reservoir by the designed length of the low-water section.

[0084] In terms of evaporation loss, since the water level fluctuation cycle of the upper and lower reservoirs of the pumped-storage power station is one day, the daily evaporation area change process of the reservoir is the same, and the evaporation loss depth is a constant, it is believed that the daily evaporation amount within a month is constant. The specific calculation method for the evaporation loss of the reservoir in one day is: for pumped-storage power stations, due to the exchange of water between the upper and lower reservoirs, there is a conjugate relationship between the instantaneous reservoir surface area of ​​the upper reservoir and the instantaneous reservoir surface area of ​​the lower reservoir at each time point in a day. Taking hours as the calculation scale, it is simply assumed that the evaporation area of ​​the reservoir within one hour is a constant value, then the area corresponding to the average water level elevation of the reservoir within the time period can be used as the constant evaporation area of ​​the time period, and then the evaporation loss of the reservoir in each hour can be obtained, that is:

[0085] W i =S i ·h i

[0086] Among them, W i is the amount of water lost by evaporation from the reservoir in the i-th hour; S i is the evaporation area of ​​the reservoir in the i-th hour; h i is the evaporation depth of the reservoir in the i-th hour. The evaporation loss water volume in one day can be obtained by accumulating the evaporation loss water volume of the upper and lower reservoirs in each hour in one day. The evaporation loss water volume of the current month can be obtained by multiplying the daily evaporation loss water volume by the number of days in the current month, and then the total evaporation loss water volume of the designed dry period can be obtained.

[0087] S1025, by setting the ratio of the maximum pumping head to the minimum power generation head, the characteristic water levels of the upper and lower reservoirs are adjusted, thereby calculating the artificial excavation storage capacity of each scheme and obtaining the characteristic water level scheme after the expansion of the reservoir.

[0088] The power generation capacity, freezing reserve capacity and water loss reserve capacity of the upper and lower reservoirs of each dead water level scheme are added together to obtain the regulating capacity of the upper and lower reservoirs corresponding to each scheme. The water level corresponding to the sum of the dead storage capacity and the regulating storage capacity of the upper reservoir is the normal water storage level. The storage capacity corresponding to the dead water level is subtracted from the regulating storage capacity of the lower reservoir from the storage capacity corresponding to the normal water storage level of the lower reservoir, and the dead water level value of the lower reservoir is obtained by converting the water level-storage capacity curve of the lower reservoir.

[0089] Similarly, the normal water level of the upper reservoir and the dead water level of the lower reservoir obtained by each scheme may be abnormal: 1. The normal water level of the upper reservoir is higher than the upper reservoir's limit normal water level. 2. The dead water level of the lower reservoir is lower than the limit dead water level. The dead water level schemes with the above abnormalities still need to be eliminated, and the remaining schemes are used to formulate reservoir expansion excavation schemes.

[0090] When the characteristic water level of the lower reservoir has been determined, the normal water level and dead water level of the upper reservoir should not be too low. The lower the normal water level and dead water level of the upper reservoir, the greater the reservoir drawdown depth under the same regulation storage capacity, which in turn leads to a greater amplitude of change in the unit head. The amplitude of head change of the pumped storage unit is closely related to the stability of the unit. The greater the amplitude of head change, the greater the impact on the stability of the unit. Usually, in order to ensure the stable operation of the reversible unit, the ratio of the maximum pumping head to the minimum power generation head of the power station can be restricted during the planning and design stage to keep it as close to the ideal range as possible. For high-head pumped storage power stations (rated head 400-600m), the ideal range of the ratio K of the maximum pumping head to the minimum power generation head is 1.16-1.18, that is, 1.16≤K≤1.18. The calculation method of K value is as follows:

[0091]

[0092] Among them, H pmax is the maximum pumping lift, i.e. the normal water level of the upper reservoir Z sz and the dead water level Z of the lower reservoir xs The difference; H tmin is the minimum water head for power generation, i.e. the dead water level Z of the upper reservoir ss and the normal water level Z of the lower reservoir xx difference.

[0093] Moreover, the ratio K of the maximum pumping head to the minimum power generation head is negatively correlated with the normal water level and dead water level of the upper reservoir, that is, the higher the normal water level and dead water level of the upper reservoir, the smaller the K value, and vice versa. Therefore, when selecting the normal water level and dead water level of the upper reservoir, a higher value should be selected as much as possible so that the excavation expansion capacity is not too large, but it should not be too high. Too high normal water level and dead water level of the upper reservoir will increase the elevation of the upper reservoir dam, thereby increasing the construction cost.

[0094] Therefore, the specific method of expanding the upper reservoir is as follows: for the normal water storage level and dead water level of the upper reservoir under certain natural conditions, keep its normal water storage level unchanged, set the K value to 1.16 (increase excavation) and 1.18 (appropriate excavation), and use the adjusted K value to reversely calculate the dead water level of the upper reservoir after the expansion excavation, that is:

[0095]

[0096] Among them, Z′ ss is the dead water level of the upper reservoir after the expansion and excavation; K′ is the adjusted K value, which is taken as 1.16 and 1.18 here. As the K value decreases, the dead water level of the upper reservoir obtained by reverse calculation will inevitably rise, and the natural storage capacity between the normal water level cannot meet the demand for regulating storage capacity, so expansion and excavation are required. The size of the expanded storage capacity is the difference between the regulating storage capacity and the corresponding storage capacity of the dead water level and the normal water level.

[0097] In the specific implementation process, the three calculation modes of newly built upper reservoir, newly built lower reservoir and upper and lower reservoir linkage can all adopt the exhaustive method to initially propose dead water level schemes, that is, under the condition of newly built upper reservoir, all dead water level schemes can be listed with a step length of 1m between the upper reservoir's ultimate dead water level and the ultimate normal water storage level; under the condition of newly built lower reservoir, all dead water level schemes can be listed with a step length of 1m between the lower reservoir's ultimate dead water level and the ultimate normal water storage level; under the upper and lower reservoir linkage condition, since the characteristic water levels of the upper and lower reservoirs are variables, it is necessary to formulate a "normal water storage level of the upper reservoir~dead water level of the lower reservoir" scheme, that is, between the upper reservoir's ultimate dead water level and the upper reservoir's ultimate normal water storage level, with a step length of 1m, a series of upper reservoir normal water storage level values ​​are exhaustively obtained, and similarly, between the lower reservoir's ultimate dead water level and the lower reservoir's ultimate normal water storage level, a series of lower reservoir dead water level values ​​are exhaustively obtained, and the above two series are combined in pairs to form several schemes.

[0098] Specifically, in the new download mode, the specific calculation method is as follows:

[0099] (1) Calculate the ultimate characteristic water level elevations of the upper and lower reservoirs.

[0100] The specific process of this step is the same as the new upload mode.

[0101] (2) Formulate a dead water level plan

[0102] Similar to the newly built upper reservoir model, an exhaustive method is used to formulate multiple sets of dead water level plans above the ultimate dead water level elevation of the lower reservoir, that is, within the range of the ultimate dead water level and the ultimate normal water storage level elevation of the lower reservoir, with a step size of 1m. It is also necessary to eliminate the dead water level plans that do not meet the actual situation in the subsequent storage capacity adjustment calculation part, and retain the plans that meet the conditions.

[0103] (3) Calculation of power generation capacity

[0104] Different from the newly built upper reservoir mode, the newly built lower reservoir mode uses the energy conversion calculation of the power generation condition to obtain the power generation capacity of the upper and lower reservoirs. That is, it is known that the upper reservoir is empty in the initial state, the water level is the dead water level, and the lower reservoir is full, and the water level is the normal water storage level; at the same time, according to the typical daily load diagram of the system, the output process of each period under the power generation condition is known, and the complete water level change process of the upper and lower reservoirs can be iterated through the trial algorithm.

[0105] In a certain period of time under power generation conditions, it is assumed that the water level of the reservoir rises to a certain height at the end of the period. (Here the * sign indicates that the variable is an assumed value, and there is a calculated value corresponding to it). Based on the water level and storage capacity curve of the lower reservoir, the storage capacity of the lower reservoir at the end of the period is At the same time, the water volume change during this period is obtained as follows:

[0106]

[0107] in, is the water volume change value during the period; V is the storage capacity corresponding to the reservoir water level at the end of the period; xi-1 is the storage capacity corresponding to the water level of the lower reservoir at the beginning of the period. Furthermore, the increase in water volume in the lower reservoir is the decrease in water volume in the upper reservoir during the period, from which the storage capacity of the upper reservoir at the end of the period can be obtained, that is:

[0108]

[0109] in, V is the storage capacity corresponding to the reservoir water level at the end of the period; xi-1 It is the storage capacity value corresponding to the reservoir water level at the beginning of the period.

[0110] The above calculation results are based on the assumed value of reservoir water level at the end of the period. On this basis, it is necessary to verify its rationality through energy conversion calculation under power generation conditions. The specific method is as follows:

[0111] First, the average power generation head ΔH for the period is calculated based on the calculation results of the above assumed values. i , the calculation method is:

[0112]

[0113] Among them, Z si-1 With Z xi-1 are the upper and lower reservoir water levels at the beginning of the time period respectively; is the upper reservoir water level at the end of the assumed time period; is the water level value corresponding to the reservoir capacity at the end of the period, that is H lost The head loss in power generation conditions needs to be compensated under pumping conditions. The value needs to be determined based on the actual project conditions.

[0114] Then, the average power generation flow Q in the period can be calculated based on the average power generation head in the period i ,for:

[0115]

[0116] Among them, η t N is the comprehensive efficiency of the power station under power generation conditions; i The power generated during the time period.

[0117] Then, according to the average power generation flow in the period, the calculated values ​​of the upper and lower reservoir capacity and water level at the end of the period can be obtained as follows:

[0118] V si =V si-1 -Qi ΔT, Z si =f s (V si )

[0119] V xi =V xi-1 +Q i ΔT, Z xi =f x (V xi )

[0120] Where ΔT is the time period length; f s The function is the lower reservoir water level-storage capacity curve; f x The function is the lower reservoir water level-storage capacity curve. The lower reservoir water level calculated value Z at the end of the period xi With the assumed value For comparison, the difference between the two satisfies (allowable error) indicates the reservoir water level at the end of the assumed time period It is reasonable, and the calculation for this period is completed. Otherwise, it is necessary to re-assume the reservoir water level at the end of the period. Repeat the above steps until the error meets the requirements. After the calculation of this period is completed, the water levels of the upper and lower reservoirs at the end of this period are used as the water levels of the upper and lower reservoirs at the beginning of the next period. This iteration is repeated until the power generation process is completed, and finally the power generation capacity, the water level elevation corresponding to the power generation capacity of the lower reservoir, and the elevation after the water level of the upper reservoir decreases are obtained.

[0121] The dead water level scheme of the lower reservoir is obtained by exhaustively enumerating the dead water level and the normal water level of the lower reservoir. Therefore, the dead water level scheme may produce the following two abnormal situations after the power generation capacity calculation: 1. The water level corresponding to the power generation capacity of the lower reservoir is higher than the normal water level of the lower reservoir. 2. The water level of the upper reservoir after the water level is reduced is lower than the dead water level of the upper reservoir. The schemes with the above abnormal situations need to be eliminated.

[0122] (4) Calculation of freezing reserve storage capacity and water loss reserve storage capacity

[0123] The specific process of this step is the same as the new upload mode.

[0124] (5) Preparation of reservoir expansion excavation plan

[0125] Before formulating a plan for reservoir expansion and excavation, it is also necessary to eliminate dead water level plans that do not meet the actual situation. The method is the same as the new reservoir model.

[0126] Similar to the newly built upper reservoir mode, the dead water level of the lower reservoir after the expansion is reversed by setting the value of the ratio of the maximum pumping head to the minimum power generation head, that is:

[0127] Z′ xs=Z sz -(Z ss -Z XZ )·K′

[0128] Among them, Z′ xs is the dead water level of the lower reservoir after the expansion and excavation; K′ is the adjusted K value, which is taken as 1.16 (increase excavation) and 1.18 (appropriate excavation). As the K value decreases, the reversed dead water level of the lower reservoir will inevitably rise, and the natural storage capacity between the normal water level cannot meet the regulation storage capacity demand, so expansion and excavation are required. The size of the expanded storage capacity is the difference between the regulation storage capacity and the dead water level and the storage capacity corresponding to the normal water level.

[0129] In the upper and lower library linkage mode, the specific calculation method is as follows:

[0130] (1) Calculate the ultimate characteristic water level elevations of the upper and lower reservoirs.

[0131] The specific process of this step is the same as the new upload mode.

[0132] (2) Formulate a dead water level plan

[0133] In the linkage mode of the upper and lower reservoirs, the characteristic water levels of the upper and lower reservoirs, a total of four unknown variables, need to be solved. We can first formulate a "normal water level of the upper reservoir ~ dead water level of the lower reservoir" scheme, and calculate the upper reservoir dead water level and the normal water level of the lower reservoir corresponding to each scheme through the energy conversion calculation of the upper and lower reservoirs. When formulating the "normal water level of the upper reservoir ~ dead water level of the lower reservoir" scheme, between the upper reservoir limit dead water level and the upper reservoir limit normal water level, with a step length of 1m, a series of upper reservoir normal water level values ​​are exhaustively obtained. Similarly, between the lower reservoir limit dead water level and the lower reservoir limit normal water level, a series of lower reservoir dead water level values ​​are exhaustively obtained, and the above two series are combined into several schemes.

[0134] (3) Calculation of power generation capacity

[0135] The power generation reservoir capacity is calculated based on several "normal water level of the upper reservoir ~ dead water level of the lower reservoir" schemes prepared in the previous step. That is, in the initial state, the upper reservoir is full and the water level is the normal water level, while the lower reservoir is empty and the water level is the dead water level. The power generation reservoir capacity can be calculated using the energy conversion of the upper and lower reservoirs under power generation conditions, and the calculation method is the same as that of the newly built lower reservoir mode.

[0136] (4) Calculation of freezing reserve storage capacity and water loss reserve storage capacity

[0137] The specific process of this step is the same as the new upload mode.

[0138] (5) Preparation of reservoir expansion excavation plan

[0139] Before formulating a plan for reservoir expansion and excavation, it is also necessary to eliminate dead water level plans that do not meet the actual situation. The method is the same as the new reservoir model.

[0140] In the upper and lower reservoir linkage mode, both the upper and lower reservoirs need to be expanded and excavated to meet the storage capacity requirements and head change requirements. Similar to the new upper reservoir mode and the new lower reservoir mode, it is also divided into two situations: "increase excavation" and "appropriate excavation". The specific operation methods are as follows:

[0141] Set the ratio K of the maximum pumping head to the minimum power generation head to 1.165 (increase excavation) or 1.175 (appropriate excavation). Keep the normal water level of the upper and lower reservoirs unchanged after excavation, and the dead water level of the upper and lower reservoirs will rise to a certain value after the expansion excavation. In order to obtain the dead water level of the upper and lower reservoirs after the expansion excavation, the dead water level of the lower reservoir after the expansion excavation can be assumed first, and then the dead water level of the upper reservoir after the expansion excavation can be reversed using the K value calculation formula.

[0142] When assuming the dead water level after the lower reservoir is expanded, several values ​​can be assumed between the dead water level before the lower reservoir is excavated and the normal water level with a step length of 1m. The corresponding dead water level after the upper reservoir is expanded can be inversely calculated from these values, that is:

[0143]

[0144] The above method is used to calculate the dead water level after excavation of the upper reservoir corresponding to each assumed value of the lower reservoir dead water level. At the same time, the excavation capacity of the upper and lower reservoirs corresponding to several of these assumed values ​​are also obtained. The plan with the smallest sum of the excavation capacity of the upper and lower reservoirs is taken as the most reasonable excavation plan.

[0145] S103, selecting the optimal evaluation index of the characteristic water level of the pumped-storage power station from the preset key influencing factors of the operation characteristics of the pumped-storage power station and the characteristic water level selection in the planning and design stage of the pumped-storage power station, quantifying the qualitative indicators in the selected evaluation indicators, constructing the evaluation scheme decision matrix and normalizing it.

[0146] The specific steps of step S103 are:

[0147] S1031, analyze the key influencing factors of the operating characteristics of pumped-storage power stations and the selection of characteristic water levels in the planning and design stage of pumped-storage power stations, analyze from the aspects of water conservancy kinetic energy indicators, project construction conditions, impact of land acquisition and resettlement of immigrants for project construction, environmental impact, project investment, etc., select the optimal evaluation indicators of characteristic water levels of pumped-storage power stations, and establish an optimal evaluation indicator system for characteristic water levels of pumped-storage power stations.

[0148] S1032, for qualitative indicators, the evaluation criteria are divided into five levels: poor, relatively poor, fair, relatively good, and good, based on the construction and operation characteristics of pumped storage power stations and actual business needs. At the same time, a five-level degree of excellence is introduced to quantify the qualitative indicators:

[0149] For the qualitative indicators of the benefit type, the bigger the better, the quality of the qualitative indicators is positively correlated with the quantitative level:

[0150] R = {poor, relatively poor, average, relatively good, good}

[0151] ={(0, 0.2], (0.2, 0.4], (0.4, 0.6], (0.6, 0.8], (0.8, 1]}

[0152] For the smaller the better cost-type qualitative indicators, the quality of the qualitative indicators is negatively correlated with the quantitative level:

[0153] R = {poor, relatively poor, average, relatively good, good}

[0154] ={[1, 0.8), [0.8, 0.6), [0.6, 0.4), [0.4, 0.2), [0.2, 0)}

[0155] Then the quantitative indicators are normalized using the range transformation method. The specific calculation method is as follows:

[0156] For the larger the better benefit-oriented quantitative indicators: b ij =[x ij -x min (j)] / [x max (j)-x min (j)];

[0157] For the smaller the better cost-based quantitative indicators: b ij =[x max (j)-x ij ] / [x max (j)-x min (j)].

[0158] Among them, b ij is the characteristic value of the evaluation index x ij The standardized value of ij ≤1;x max (j), x min (j) is the maximum and minimum value of the jth indicator.

[0159] Assuming that the number of characteristic water level schemes of pumped storage power stations is m, and the number of evaluation indicators for each scheme is n, the dimensionless standardized matrix R = (r ij ) m×n :

[0160]

[0161] S104, based on the evaluation scheme decision matrix, the entropy weight method is used to calculate the objective weights of the evaluation indicators, and then the indicator weight matrix is ​​constructed; based on the indicator weight matrix, the grey correlation ideal solution is used to select the optimal characteristic water level scheme from the candidate characteristic water level schemes, and the optimal characteristic water level schemes of the upper and lower reservoirs of the power station are obtained.

[0162] Specifically, the specific steps of S104 are:

[0163] S1041, for the dimensionless normalization matrix R = (r ij ) m×n , the entropy weight method is used to solve the weight of each indicator, specifically:

[0164] First, calculate the weight of the i-th sample under the j-th index in the above matrix:

[0165]

[0166] Then the information entropy of the j-th indicator is:

[0167]

[0168] Then the weight of the jth indicator is:

[0169]

[0170] The entropy weight method is used to solve the weight of each indicator in the evaluation system, and finally the evaluation indicator weight matrix is ​​constructed as follows:

[0171] S1042, using the grey correlation ideal solution to solve the optimal characteristic water level scheme of the pumped storage power station, that is, introducing the concept of grey correlation degree in the grey correlation method into the ideal solution, constructing relative proximity to describe the degree of similarity between the characteristic water level selection scheme and the ideal solution, and judging the advantages and disadvantages of the characteristic water level selection scheme and the corresponding order of priority according to the relative proximity.

[0172] First, the indicator weight matrix w = (w1, w2, ..., w n ) T and the dimensionless normalized matrix R = (r ij ) m×n Perform weighted multiplication to obtain the weighted normalization matrix U = (u ij ) m×n :

[0173]

[0174] Then, determine the positive and negative ideal solutions. Positive ideal solution u+ and negative ideal solution u - The calculation method is

[0175]

[0176]

[0177] Among them, J + is a benefit-type indicator; J- is a cost-type indicator. It can be seen that the positive ideal solution consists of the maximum value of the benefit-type indicator and the minimum value of the cost-type indicator, and the negative ideal solution consists of the minimum value of the benefit-type indicator and the maximum value of the cost-type indicator.

[0178] Secondly, the Euclidean distance between the comparison scheme and the positive and negative ideal solutions is calculated. The Euclidean distance calculation formula between the i-th comparison scheme and the positive and negative ideal solutions is:

[0179]

[0180] For the jth indicator of the ith solution, u ij With positive ideal solution Grey correlation coefficient The calculation formula is:

[0181]

[0182] in, is the maximum difference between the two levels, and is the minimum difference between the two levels; ρ + ∈[0,1] is the resolution coefficient with the positive ideal solution, ρ + Generally, it is taken as 0.5. Then the grey correlation coefficient matrix between the comparison scheme and the positive ideal solution is:

[0183]

[0184] Then the grey correlation degree between the ith alternative and the positive ideal solution is:

[0185]

[0186] Similarly, the jth indicator u of the i-th solution ij With negative ideal solution Grey correlation coefficient The calculation formula is:

[0187]

[0188] Then the grey correlation coefficient matrix between the alternatives and the negative ideal solution is for:

[0189]

[0190] Then the grey correlation degree between the ith comparison scheme and the negative ideal solution is:

[0191]

[0192] S1043, after obtaining the Euclidean distance and grey correlation degree between each comparison scheme and the positive and negative ideal solutions, the two are coupled to obtain the relative proximity.

[0193] First, the Euclidean distance and grey correlation degree are dimensionless:

[0194]

[0195] in, The Euclidean distance between the solution and the positive and negative ideal solutions The dimensionless value of Grey correlation degree between the scheme and the positive and negative ideal solutions The dimensionless value of .

[0196] Secondly, calculate the degree of closeness between the selected solutions and the positive and negative ideal solutions. For the ith solution, if and The larger the Euclidean distance between the solution and the negative ideal solution, the higher the grey correlation with the positive ideal solution, that is, the closer the solution is to the positive ideal solution and the less likely it is to be the negative ideal solution; on the contrary, if its and The larger the value is, the greater the Euclidean distance between the solution and the positive ideal solution is, and the higher the grey correlation degree with the negative ideal solution is. and To combine Euclidean distance and grey correlation index information:

[0197]

[0198] Then the relative closeness of the ith solution to the positive ideal solution is:

[0199]

[0200] Calculate the relative closeness π of all solutions according to the above method i , relative proximity π i It reflects the closeness of the solution to the positive ideal solution. If π i The larger the value, the closer the solution is to the positive ideal solution and the better the solution is. Therefore, π i The alternative with the largest value is the optimal characteristic water level scheme for the pumped storage power station.

[0201] The present invention provides a method for optimizing characteristic water level schemes of pumped-storage power stations, and proposes a calculation model for formulating characteristic water level schemes of pumped-storage power stations under three different construction conditions. By setting an ideal value of the ratio of the maximum pumping head to the minimum power generation head, the calculation result of the corrected water level after reservoir excavation is reversed and the excavation storage capacity scheme is obtained at the same time. Then, the optimal characteristic water level scheme is obtained by using the grey correlation ideal solution, which provides a reference for the planning and design of pumped-storage power stations.

[0202] Taking a pumped storage power station project in a certain county as an example, the method for formulating and optimizing the characteristic water level scheme of the pumped storage power station described in the present invention is used to study the selection of the normal water storage level and dead water level of the pumped storage power station, and the effectiveness and rationality of the present invention are explained.

[0203] The pumped storage power station has a continuous full-power hour of 6 hours, an installed capacity of 1800MW, 6 units, a single unit capacity of 300MW, and a rated head of 425.00m. The catchment area above the reservoir dam site is 4.3km 2 , normal water level is 1326.00m, storage capacity below normal water level is 12.67 million m 3 , dead water level 1298.0m, dead reservoir capacity 1.06 million m 3 , regulating reservoir capacity 11.84 million m 3 The catchment area above the lower reservoir dam site is 25.31km 2 , normal water level is 902.00m, and the storage capacity below normal water level is 14.36 million m 3 , dead water level 865.00m, dead reservoir capacity 2.47 million m 3 , regulating reservoir capacity 11.9 million m 3 This project is a Class I Large (1) Project. The main buildings are designed as Class I buildings, the secondary buildings are designed as Class III buildings, and the temporary buildings are designed as Class IV buildings. The design service life of permanent main buildings is 100 years, and the design service life of permanent secondary buildings is 50 years.

[0204] (1) Calculation mode selection and basic data input for the model of characteristic water level scheme for pumped storage power station

[0205] Analysis of the basic information of the pumped-storage power station shows that the upper and lower reservoirs of the pumped-storage power station are constructed by excavating the natural reservoir basin, so the calculation mode of the scheme formulation model adopts the "upper and lower reservoir linkage" mode; at the same time, according to relevant meteorological data, the average daily temperature of the coldest month in the pumped-storage power station is -3℃, so there is no need to set up frozen standby storage capacity, and the regulating storage capacity is only composed of power generation capacity and water loss standby capacity.

[0206] The basic input data required by the model include the upper and lower reservoirs required by the extreme characteristic water level calculation module: water level-storage capacity curve, multi-year average flow at the dam site, multi-year average sediment content at the dam site, bulk density of silted sediment, porosity of silted body, and reservoir sediment discharge ratio; in addition, the upper and lower reservoirs required by the power generation capacity calculation module: continuous full-power hours, installed capacity, comprehensive power generation efficiency, and head loss; and the water loss standby capacity calculation module also includes: the designed monthly inflow of the power station in low-water years, the evaporation depth of large water bodies in representative years and months, and the monthly leakage coefficient.

[0207] The above basic input data are verified, and outliers and missing values ​​are processed: single missing values ​​are supplemented by manual completion, and missing values ​​of continuous data sequences are supplemented by forward and backward linear interpolation; outliers are deleted and treated as missing values.

[0208] (2) Calculation process of each module of the characteristic water level scheme model

[0209] First, the sediment storage capacity and the limit characteristic water level of the upper and lower reservoirs are obtained through the upper and lower reservoir limit characteristic water level calculation module, as shown in Table 1:

[0210] Table 1 Calculation results of limit characteristic water level

[0211]

[0212] Secondly, under the condition of the ultimate characteristic water level of the upper and lower reservoirs of the pumped-storage power station, different “upper reservoir normal water level ~ lower reservoir dead water level” schemes are formulated from the ultimate dead water levels of the upper and lower reservoirs and the ultimate normal water level of the upper reservoir. The power generation capacity module is used to calculate the storage capacity required for power generation in each scheme, and the calculation results of the water loss standby capacity module of the upper and lower reservoirs are superimposed to obtain the regulation storage capacity demand of the upper and lower reservoirs, eliminate the calculation results that exceed the ultimate characteristic water level, and retain the schemes that meet the conditions.

[0213] Calculate the ratio K value of the maximum pumping head and the minimum power generation head of each characteristic water level scheme. The calculation formula of K value is:

[0214]

[0215] Among them, H pmax is the maximum pumping lift, i.e. the normal water level of the upper reservoir Z sz and the dead water level Z of the lower reservoir xs The difference; H tmin is the minimum water head for power generation, i.e. the dead water level Z of the upper reservoir ss and the normal water level Z of the lower reservoir xz difference.

[0216] In the case that the upper and lower reservoirs are not excavated for expansion, the K value of each scheme is generally between 1.5 and 2.5. Since the pumped storage power station reservoir is a reservoir basin type reservoir, when the demand for regulating storage capacity remains unchanged, the lower the normal water storage level of the upper and lower reservoirs, the greater the head fluctuation, and the greater the K value; the higher the normal water storage level of the upper and lower reservoirs, the smaller the head fluctuation, and the smaller the K value. Too low a normal water storage level will result in a too large K value, and the amount of open excavation of earth and stone for excavation and expansion will be too large; too high a normal water storage level will lead to an increase in the maximum elevation of the dam body. Both of the above situations do not meet the economic requirements, so five schemes with K values ​​close to 1.18, 1.19, 1.20, 1.21, and 1.22 are selected, as shown in Table 2:

[0217] Table 2 Parameters of original characteristic water level scheme

[0218]

[0219]

[0220] The excavation schemes are calculated for each scheme in the above table, and the K value is set to "1.175" and "1.165" respectively. At the same time, the normal water storage levels of the upper and lower reservoirs are kept unchanged. By assuming a series of dead water level values ​​of the lower reservoir, the dead water level of the upper reservoir after excavation is reversed, and the scheme with the smallest excavation volume is taken as the final excavation scheme. The excavation schemes are shown in Table 3.

[0221] Table 3 Calculation results of characteristic water level excavation scheme

[0222]

[0223]

[0224] The grey correlation ideal solution method is used to optimize the above 10 proposed characteristic water level schemes. First, the optimization indicators of the characteristic water level of the pumped storage power station are determined as follows: the maximum dam height of the upper reservoir, the maximum dam height of the lower reservoir, the drawdown depth of the upper reservoir, the drawdown depth of the lower reservoir, and the total excavation volume. The above five indicators are all cost indicators.

[0225] The cost-based indicators are normalized using the following formula:

[0226] b ij =[x max (j)-x ij ] / [x max (j)-x min (j)]

[0227] Where i = 1, 2, ..., 10; j = 1, 2, ..., 5; b ij is the characteristic value of the evaluation index x ij The standardized value of ij≤1;x max (j), x min (j) is the maximum and minimum value of the jth index. The dimensionless standardized matrix obtained by normalization is shown in Table 4:

[0228] Table 4 Calculation table of normalized values ​​of characteristic water level comparison schemes

[0229]

[0230] The entropy weight method is used to calculate the indicator weights of the above indicators, and the calculation results are:

[0231] w=(0.3539, 0.1531, 0.1266, 0.1692, 0.1972)

[0232] Multiply the indicator weight matrix with the dimensionless standardized matrix to obtain the weighted standardized matrix, as shown in Table 5:

[0233] Table 5 Weighted standardization calculation results

[0234]

[0235] Then determine the positive and negative ideal solutions as follows:

[0236] u + =(0,0,0,0,0)

[0237] u - =(0.3539, 0.1531, 0.1266, 0.1692, 0.1972)

[0238] Calculate the Euclidean distance between each comparison scheme and the positive and negative ideal solutions. The calculation results are as follows:

[0239] S + =(0.2598, 0.2322, 0.2055, 0.1902, 0.2410, 0.2381,

[0240] 0.2511, 0.2661, 0.3805, 0.3883)

[0241] S - =(0.4059, 0.3962, 0.3880, 0.3870, 0.2452, 0.2555,

[0242] 0.2666, 0.3115, 0.2115, 0.2394)

[0243] Calculate the grey correlation between each comparison scheme and the positive and negative ideal solutions. The calculation results are as follows:

[0244] D +=(0.7968, 0.7676, 0.7448, 0.7280, 0.6599, 0.6567,

[0245] 0.6753, 0.7188, 0.6579, 0.6756)

[0246] D - =(0.6905, 0.6712, 0.6514, 0.6567, 0.6459, 0.6571,

[0247] 0.6669, 0.6979, 0.7308, 0.7534)

[0248] Then for the above S + , S - , D + , D - Perform dimensionless processing, and integrate Euclidean distance and grey relational evaluation information to construct relative proximity π i , i = 1, 2, ... 10, the calculation results are shown in Table 6:

[0249] Table 6 Relative proximity calculation results

[0250]

[0251] From Table 6, we can see that the scheme with the highest relative closeness to the positive ideal solution is Scheme 4, that is: the normal water level of the upper reservoir is 1327.00m, and the dead water level is 1301.00m; the normal water level of the lower reservoir is 907.00m, and the dead water level is 868.00m.

[0252] Judging from the calculation results, the above-mentioned characteristic water level optimization results are not much different from the actual characteristic water levels of the upper and lower reservoirs of the pumped-storage power station (the normal water level of the upper reservoir is 1326.00m, and the dead water level is 1298.00m; the normal water level of the lower reservoir is 902.00m, and the dead water level is 865.00m), and the calculation results are relatively reasonable; at the same time, from the calculation process, the above-mentioned calculation method is highly operational, the principle is relatively simple, and the calculation results have a certain degree of reliability, which can provide a reference for the selection of characteristic water levels in the planning and construction process of pumped-storage power stations.

[0253] Figure 2 Schematic diagram of the structure of a pumped storage power station reservoir characteristic water level scheme optimization system in an embodiment of the present invention. Figure 1 The optimization method of the characteristic water level scheme of the pumped storage power station reservoir corresponds to Figure 2 As shown, the pumped storage power station reservoir characteristic water level scheme optimization system in this embodiment may include:

[0254] The pumped storage power station project data acquisition module 201 is used to acquire pumped storage power station project related data.

[0255] Among them, in the pumped-storage power station project data acquisition module 201, the pumped-storage power station project related data include but are not limited to the upper and lower reservoir water level-storage capacity relationship curve, the reservoir area mountain elevation, the impermeable layer top elevation, the dam site's multi-year average sediment content, the dam site's multi-year average runoff, the reservoir's evaporation increase and loss, the reservoir's monthly leakage rate and the historical coldest year's average monthly temperature data.

[0256] The module 202 for calculating the characteristic water level scheme to be selected is used to screen the corresponding characteristic water level scheme calculation mode according to the relevant data of the pumped storage power station project and the actual construction conditions, and obtain several characteristic water level schemes to be selected; among which, the characteristic water level scheme calculation mode includes three calculation modes: a new upper reservoir, a new lower reservoir and the linkage between the upper and lower reservoirs.

[0257] In the characteristic water level scheme calculation module 202, the steps of constructing the characteristic water level scheme calculation mode are as follows:

[0258] According to the topographic and geological conditions of the upper and lower reservoirs, the height of the mountain ridges and the pass around the reservoirs, as well as the influencing factors related to reservoir leakage, are comprehensively evaluated to calculate the limit characteristic water level values ​​of the upper and lower reservoirs;

[0259] Formulate several dead water level plans within the range of the upper and lower reservoir limit characteristic water level values;

[0260] By utilizing the energy conversion between the upper and lower reservoirs under pumping or power generation conditions, a trial algorithm is used to calculate the power generation storage capacity of each scheme, and schemes that exceed the upper and lower reservoir limit characteristic water levels are eliminated;

[0261] For pumped storage power stations located in freezing areas, calculate their frozen reserve storage capacity requirements; at the same time, set the water loss reserve storage capacity based on the designed low-water period upper and lower reservoir water inflow minus the evaporation and leakage water loss and upstream and downstream water use during the same period of normal operation;

[0262] By setting the ratio of the maximum pumping head to the minimum power generation head, the characteristic water levels of the upper and lower reservoirs are adjusted, and the artificial excavation storage capacity of each scheme is calculated to obtain the characteristic water level scheme after the expansion of the reservoir.

[0263] Specifically, the three calculation modes of newly built upper reservoir, newly built lower reservoir and linkage between upper and lower reservoirs all adopt the exhaustive method to initially simulate the dead water level scheme to obtain the corresponding calculation mode model.

[0264] The evaluation scheme decision matrix construction module 203 is used to screen out the preferred evaluation indicators of the characteristic water level of the pumped-storage power station from the preset key influencing factors of the operating characteristics of the pumped-storage power station and the characteristic water level selection in the planning and design stage of the pumped-storage power station, quantify the qualitative indicators in the screened evaluation indicators, construct the evaluation scheme decision matrix and normalize it.

[0265] The optimal characteristic water level scheme determination module 204 is used to calculate the objective weights of the evaluation indicators based on the evaluation scheme decision matrix using the entropy weight method, and then construct an indicator weight matrix; based on the indicator weight matrix, the grey correlation ideal solution is used to select the optimal characteristic water level scheme from the candidate characteristic water level schemes to obtain the optimal characteristic water level schemes for the upper and lower reservoirs of the power station.

[0266] In the optimal characteristic water level scheme determination module 204, the steps of selecting the optimal characteristic water level scheme from the candidate characteristic water level schemes using the grey correlation ideal solution are as follows:

[0267] First, determine the positive and negative ideal solutions;

[0268] Then the Euclidean distances from each candidate characteristic water level scheme to the positive and negative ideal solutions are calculated, and the concept of grey correlation degree in grey system theory is introduced to calculate the grey correlation degree from each comparison scheme to the positive and negative ideal solutions;

[0269] Then, relative closeness is introduced to aggregate Euclidean distance and grey relational degree, and relative closeness is used to evaluate and rank the candidate characteristic water level schemes.

[0270] Figure 2 The specific implementation process of modules 201 to 204 in the pumped storage power station reservoir characteristic water level program optimization system is shown in FIG. Figure 1 The specific implementation process of steps S101 to 104 is the same as that of FIG. 1 and will not be described in detail here.

[0271] In one or more embodiments, an electronic device is also provided, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the following is achieved: Figure 1 The steps in the method for optimizing characteristic water level scheme of a pumped storage power station reservoir are shown.

[0272] In particular, according to an embodiment of the present application, the process described above with reference to the flowchart can be implemented as a computer software program. For example, an embodiment of the present application includes a computer program product, which includes a computer program carried on a computer readable medium, the computer program including a computer program for executing Figure 1In such an embodiment, the computer program can be downloaded and installed from a network through a communication part, and / or installed from a removable medium. When the computer program is executed by a central processing unit, various functions defined in the device of the present application are executed.

[0273] in, Figure 1 The computer program instructions corresponding to the method shown may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce a product including an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0274] A person skilled in the art can understand that all or part of the processes in the above-mentioned embodiments can be implemented by instructing the relevant hardware through a computer program, and the program can be stored in a computer-readable storage medium, and when the program is executed, it can include the processes of the embodiments of the above-mentioned methods. The storage medium can be a disk, an optical disk, a read-only memory (ROM) or a random access memory (RAM), etc.

[0275] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A method for optimizing characteristic water level scheme of a pumped storage power station reservoir. It is characterized in that include: Obtain data related to pumped storage power station projects; According to the relevant data of the pumped storage power station project and the actual construction conditions, the corresponding characteristic water level scheme calculation mode is screened to obtain several candidate characteristic water level schemes; Among them, the characteristic water level scheme calculation mode includes three calculation modes: new upper reservoir, new lower reservoir and upper and lower reservoir linkage; From the preset key influencing factors of the pumped storage power station operation characteristics and the characteristic water level selection in the planning and design stage of the pumped storage power station, the preferred evaluation index of the characteristic water level of the pumped storage power station is screened out, and the qualitative indexes in the screened evaluation indexes are quantified, and the evaluation scheme decision matrix is ​​constructed and normalized; Based on the evaluation scheme decision matrix, the entropy weight method is used to calculate the objective weights of the evaluation indicators, and then the indicator weight matrix is ​​constructed; based on the indicator weight matrix, the grey correlation ideal solution is used to select the optimal characteristic water level scheme from the candidate characteristic water level schemes, and the optimal characteristic water level schemes of the upper and lower reservoirs of the power station are obtained.

2. The method for optimizing the characteristic water level scheme of a pumped storage power station reservoir according to claim 1, It is characterized in that The steps for constructing the characteristic water level scheme calculation mode are as follows: According to the topographic and geological conditions of the upper and lower reservoirs, the height of the mountain ridges and the pass around the reservoirs, as well as the influencing factors related to reservoir leakage, are comprehensively evaluated to calculate the limit characteristic water level values ​​of the upper and lower reservoirs; Formulate several dead water level plans within the range of the upper and lower reservoir limit characteristic water level values; By utilizing the energy conversion between the upper and lower reservoirs under pumping or power generation conditions, a trial algorithm is used to calculate the power generation storage capacity of each scheme, and schemes that exceed the upper and lower reservoir limit characteristic water levels are eliminated; For pumped storage power stations located in freezing areas, calculate their frozen reserve storage capacity requirements; at the same time, set the water loss reserve storage capacity based on the designed low-water period upper and lower reservoir water inflow minus the evaporation and leakage water loss and upstream and downstream water use during the same period of normal operation; By setting the ratio of the maximum pumping head to the minimum power generation head, the characteristic water levels of the upper and lower reservoirs are adjusted, and the artificial excavation storage capacity of each scheme is calculated to obtain the characteristic water level scheme after the expansion of the reservoir.

3. The method for optimizing the characteristic water level scheme of a pumped storage power station reservoir according to claim 2, It is characterized in that The three calculation modes of newly built upper reservoir, newly built lower reservoir and linkage between upper and lower reservoirs all adopt the exhaustive method to initially simulate the dead water level scheme to obtain the corresponding calculation mode model.

4. The method for optimizing the characteristic water level scheme of a pumped storage power station reservoir according to claim 1, It is characterized in that The steps of selecting the optimal characteristic water level scheme from the candidate water level schemes using the grey correlation ideal solution are as follows: First, determine the positive and negative ideal solutions; Then the Euclidean distances from each candidate characteristic water level scheme to the positive and negative ideal solutions are calculated, and the concept of grey correlation degree in grey system theory is introduced to calculate the grey correlation degree from each comparison scheme to the positive and negative ideal solutions; Then, relative closeness is introduced to aggregate Euclidean distance and grey relational degree, and relative closeness is used to evaluate and rank the candidate characteristic water level schemes.

5. The method for optimizing the characteristic water level scheme of a pumped storage power station reservoir according to claim 1, It is characterized in that The relevant data of the pumped-storage power station project include the water level-storage capacity relationship curve of the upper and lower reservoirs, the elevation of the mountain in the reservoir area, the elevation of the top of the impermeable layer, the average sediment content of the dam site over many years, the average runoff of the dam site over many years, the evaporation increase and loss of the reservoir, the monthly leakage rate of the reservoir and the average monthly temperature data of the coldest year in history.

6. A pumped storage power station reservoir characteristic water level optimization system, It is characterized in that include: A pumped storage power station project data acquisition module, which is used to obtain pumped storage power station project related data; A candidate characteristic water level scheme calculation module is used to select corresponding characteristic water level scheme calculation modes according to relevant data of the pumped storage power station project and actual construction conditions, and obtain several candidate characteristic water level schemes; Among them, the characteristic water level scheme calculation mode includes three calculation modes: new upper reservoir, new lower reservoir and upper and lower reservoir linkage; An evaluation scheme decision matrix construction module is used to select the preferred evaluation index of the characteristic water level of the pumped-storage power station from the preset key influencing factors of the operation characteristics of the pumped-storage power station and the characteristic water level selection in the planning and design stage of the pumped-storage power station, quantify the qualitative indicators in the selected evaluation indicators, construct the evaluation scheme decision matrix and normalize it; The optimal characteristic water level scheme determination module is used to calculate the objective weights of the evaluation indicators based on the evaluation scheme decision matrix using the entropy weight method, and then construct an indicator weight matrix; based on the indicator weight matrix, the grey correlation ideal solution is used to select the optimal characteristic water level scheme from the candidate characteristic water level schemes to obtain the optimal characteristic water level schemes for the upper and lower reservoirs of the power station.

7. The pumped storage power station reservoir characteristic water level scheme optimization system according to claim 6, It is characterized in that In the characteristic water level scheme calculation module to be selected, the steps of constructing the characteristic water level scheme calculation mode are: According to the topographic and geological conditions of the upper and lower reservoirs, the height of the mountain ridges and the pass around the reservoirs, as well as the influencing factors related to reservoir leakage, are comprehensively evaluated to calculate the limit characteristic water level values ​​of the upper and lower reservoirs; Formulate several dead water level plans within the range of the upper and lower reservoir limit characteristic water level values; By utilizing the energy conversion between the upper and lower reservoirs under pumping or power generation conditions, a trial algorithm is used to calculate the power generation storage capacity of each scheme, and schemes that exceed the upper and lower reservoir limit characteristic water levels are eliminated; For pumped storage power stations located in freezing areas, calculate their frozen reserve storage capacity requirements; at the same time, set the water loss reserve storage capacity based on the designed low-water period upper and lower reservoir water inflow minus the evaporation and leakage water loss and upstream and downstream water use during the same period of normal operation; By setting the ratio of the maximum pumping head to the minimum power generation head, the characteristic water levels of the upper and lower reservoirs are adjusted, and the artificial excavation storage capacity of each scheme is calculated to obtain the characteristic water level scheme after the expansion of the reservoir.

8. The pumped storage power station reservoir characteristic water level scheme optimization system according to claim 7, It is characterized in that In the calculation module of the candidate characteristic water level scheme, the three calculation modes of newly-built upper reservoir, newly-built lower reservoir and linkage between upper and lower reservoirs all adopt the exhaustive method to initially simulate the dead water level scheme to obtain the corresponding calculation mode model.

9. A computer-readable storage medium having a computer program stored thereon, It is characterized in that When the program is executed by a processor, the steps in the method for optimizing the characteristic water level scheme of a pumped storage power station reservoir are implemented as described in any one of claims 1 to 5.

10. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, It is characterized in that When the processor executes the program, the steps in the method for optimizing the characteristic water level scheme of a pumped storage power station reservoir are implemented as described in any one of claims 1-5.

Citation Information

Cited By

  • Pumped storage power station development potential evaluation system based on reservoir geographic characteristics

    CN119831265A

  • Method and device for calculating hydraulic energy parameters of pumped storage power station based on machine learning

    CN120805746A

  • Machine learning based pumped storage power plant water energy parameter calculation method and device

    CN120805746B

  • Pumped storage power station parameter optimization method based on social emotion optimization algorithm

    CN121389732A